Knowledge (XXG)

Natick Center station

Source đź“ť

593: 613:
completion would be delayed to early 2024 due to supply chain issues and soil conditions requiring modification of a retaining wall design. By December 2022, construction was 45% complete, with the east ramps nearly finished. By that time, expected completion was further delayed to fall 2024. The east ramps were put into service on February 13, 2023, to access temporary platforms east of Washington Street, allowing the old platforms to be demolished and the new permanent platforms built. The Walnut Street footbridge was closed on March 2, 2023. By November 2023, construction was 70% complete and expected to finish in September 2024. By June 2024, work was still 70% complete, with completion expected in December 2024.
510: 478: 565: 35: 576:; the low platforms do not support level boarding, and passage to street level is via staircases only. Inbound ridership in 2018 was 736 passengers, making Natick Center the second-busiest non-accessible station on the MBTA Commuter Rail system. Flooding of the inbound track and platform during heavy rains is a recurrent problem. In January 2013, the Town of Natick formed a formal committee to advise the town on developing plans for a rebuilt station. 133: 489:, extending outwards from Boston, was completed Natick in August 1834. The line was double tracked through Natick in 1839, by which time a station had been established. Two other stations were located in Natick: Lake Crossing (at Bacon Street on the border with Wellesley to the east) and Walkerville (at Speen Street to the west). Neither lasted long into the 20th century. 254: 588:
for cost and operational reasons, with a third track (to allow freight trains and express passenger trains to pass stopped local trains) able to fit into the wide existing trench as well. The proposal would provide better integration of the station with the surrounding streets, including a deck over
550:
The line was reduced to two tracks through Natick in 1962. Around that time, a large building was built over the 1897 station, with the old station becoming the wine cellar of a liquor store. The original inbound canopy remained for use by the public, though the only station facilities were two bare
608:
After further MBTA review, the island platform design was replaced with two side platforms in 2017. The third center track will not be added as part of initial construction, but space will be left between the two main tracks to add it in the future. The estimated $ 36.5 million contract was put out
612:
In July 2020, the state awarded $ 125,000 for design of the final 1,300-foot (400 m) segment of the Cochituate Rail Trail, including the connection with the new station. Construction in 2021 included platform supports, drainage, and a retaining wall. In February 2022, the MBTA indicated that
521:
to Lake Crossing in 1894, and through Natick in 1896. During that construction, the line was realigned north (primarily to eliminate a sharp curve west of downtown) and lowered into a wide cut through downtown Natick to eliminate grade crossings with a number of streets. (Middlesex Avenue and the
555:
in 1982 to provide additional parking. In October 1997, Natick was identified as a possible site for a parking garage. The MBTA planned a three-story, 300-space garage on town-owned land. The plan was cancelled because of concerns over the financial viability of the garage.
542:
The lightly used Saxonville Branch never saw more than three daily round trips; passenger service was discontinued effective February 17, 1936. A "bus" – the Saxonville station agent's car – ran to Saxonville until 1943. Freight service continued until the 1980s; the
496:
section of Framingham on July 4, 1846, with through trains to Boston. Although branch ridership was never high, these trains were timed to allow commuting from Natick for the first time. Stations on the branch included Felchville (at Fisher Street), Cochituate (at
609:
to bid in August 2019. A $ 36.1 million contract was awarded on November 4, 2019. The 30-month construction period began in March 2020. Demolition of the canopy took place in May 2020. A temporary platform on the south side was installed later in the year.
600:
In July 2014, the MBTA agreed to the town's request to change the station's name as part of a larger rebranding of the Natick Center area. Online maps were changed shortly thereafter, and on January 12, 2015, the station was officially renamed as
589:
parts of the trench between Washington Street and Main Street. One option with the new station and a pedestrian-only deck was projected to cost $ 26.0 million, while a deck incorporating a bus loop would add $ 17 million more.
579:
In June 2014, conceptual plans were unveiled for upgrades to make the station fully handicapped accessible with high-level platforms and accessible routes from street level. The rebuilt station was to replace the existing
1444: 551:
platforms. The inbound side of the station is supported by the rear wall of the liquor store, decorated with a colorful mural of the Downtown Natick area. A second station serving the town opened at
1449: 616:
In June 2021, the MBTA issued a $ 28 million design contract for a project to add a third track from Weston to Framingham, including through Natick Center, with projected completion in 2030.
1454: 1198: 1439: 1230: 1419: 1124: 993: 1248: 67: 592: 1012: 257: 253: 1389: 272: 1191: 1319: 938:"Independent State Auditor's Report on Certain Activities of the Massachusetts Bay Transportation Authority: July 1, 1996 to July 31, 2001" 136: 937: 1034: 523: 492:
Improvements to the station building were made around 1845. The 3.87-mile (6.23 km) Saxonville Branch opened from Natick to the
920: 896: 850: 665: 1215: 1147: 1101: 1082: 1390:"MBTA Contract No. C72PS01: Worcester Line Track and Stations Accessibility Improvements (P0261) Design and Engineering Services" 1173: 345: 1336: 1132: 699: 1354: 486: 1371: 605:. In March 2016, $ 4 million for completing design of the station was included in a draft 2017–2021 MBTA capital plan. 1360:. Massachusetts Bay Transportation Authority Department of System-Wide Accessibility. November 27, 2023. p. 6. 1302: 353: 1325:. Massachusetts Bay Transportation Authority Department of System-Wide Accessibility. December 6, 2022. p. 6. 1267: 1414: 1252: 531: 493: 449: 330: 280: 102: 817: 518: 363: 287: 1020: 464:
station on the system, it is undergoing a major accessibility renovation and modernization from 2020 to 2024.
716: 509: 498: 477: 453: 1083:"Natick Center MBTA Commuter Rail Station: Feasibility Study and Conceptual Design for Upgrades (Draft)" 544: 445: 381: 376: 55: 34: 564: 1056: 522:
Middlesex Path now lie on the original alignment.) A new granite and brownstone station designed by
552: 267: 1284: 1231:"Long-awaited $ 40 million reconstruction of the Natick Center commuter rail station is underway" 978: 970: 782: 766: 750: 441: 340: 1273:. Massachusetts Bay Transportation Authority Department of System-Wide Accessibility. p. 7. 944: 1038: 892: 846: 695: 661: 866: 585: 527: 1109: 1086: 913: 637: 457: 1433: 1340: 581: 573: 368: 292: 113: 530:(who had designed nine stations for the B&A in the 1880s), opened in 1897. The 1106:
Natick Center MBTA Commuter Rail Station Improvements Implementation Plan (Draft)
798: 732: 452:. The station, located below grade in a wide cut adjacent to North Main Street ( 1218:(Press release). Massachusetts Bay Transportation Authority. November 4, 2019. 461: 1409: 82: 69: 1339:. Massachusetts Bay Transportation Authority. March 21, 2023. Archived from 140: 1216:"FMCB Approves Contract for Major Improvements at Natick Center Station" 843:
A Field Guide to Southern New England Railroad Depots and Freight Houses
1377:. Massachusetts Bay Transportation Authority. June 25, 2024. p. 6. 1251:. Massachusetts Bay Transportation Authority. June 2020. Archived from 481:
Early station and Saxonville Branch engine house on an 1877 aerial map
825:
HAER No. MA-108: Boston & Albany Railroad: Marion Street Bridge
1420:
Natick Center station from North Avenue on Google Maps Street View
591: 563: 508: 476: 1197:. Massachusetts Bay Transportation Authority. August 30, 2019. 1445:
MBTA Commuter Rail stations in Middlesex County, Massachusetts
827:. Historic American Engineering Record, National Park Service. 1415:
MBTA – Natick Center Accessibility Improvements Project Page
943:. Auditor of the Commonwealth. April 3, 2002. Archived from 784:
Report of the Directors of the Boston and Worcester Railroad
768:
Report of the Directors of the Boston and Worcester Railroad
752:
Report of the Directors of the Boston and Worcester Railroad
1424: 873:. February 15, 1936. p. 3 – via Newspapers.com. 787:. Boston and Worcester Railroad. June 7, 1847. p. 13. 771:. Boston and Worcester Railroad. June 1, 1846. p. 10. 755:. Boston and Worcester Railroad. June 2, 1845. p. 10. 1125:"MBTA Commuter Rail Station Now 'Natick Center Station'" 39:
Natick Center station in 2023 during reconstruction work
994:"Heavy rains cause commuter rail delays, snarl commute" 1287:. Commonwealth of Massachusetts. July 2020. p. 6. 891:. Boston Street Railway Association. pp. 39, 61. 460:
serving the line's two tracks. The second-busiest non-
1355:"System-Wide Accessibility Initiatives—November 2023" 1320:"System-Wide Accessibility Initiatives—December 2022" 1268:"System-Wide Accessibility Initiatives—November 2020" 660:. Boston Street Railway Association. pp. 21–25. 329: 251: 1450:
Railway stations in the United States opened in 1834
1013:"Storm causes flooding on MBTA Commuter Rail tracks" 887:Humphrey, Thomas J. & Clark, Norton D. (1986). 656:Humphrey, Thomas J. & Clark, Norton D. (1985). 420: 239: 223: 214: 206: 191: 178: 173: 165: 160: 152: 147: 127: 119: 108: 98: 61: 49: 44: 21: 1303:"Natick Center Station Accessibility Improvements" 1249:"Natick Center Station Accessibility Improvements" 1148:"MBTA eyes money for Natick Center station design" 805:. F.W. Beers & Co. 1875 – via Ward Maps. 739:. F.W. Beers & Co. 1875 – via Ward Maps. 517:The B&A extended third and fourth tracks from 501:on the Natick/Framingham border), and Saxonville. 1455:Buildings and structures in Natick, Massachusetts 971:"Parking scarcity makes commuting by train tough" 914:"Changes to Transit Service in the MBTA district" 1174:"Natick Center train station design progressing" 882: 880: 992:Rosen, Andy; Roberts, Sarah (August 21, 2015). 1057:"MBTA backs Natick Center station name change" 636:Central Transportation Planning Staff (2019). 1395:. Massachusetts Bay Transportation Authority. 1308:. Massachusetts Bay Transportation Authority. 640:. Massachusetts Bay Transportation Authority. 8: 658:Boston's Commuter Rail: The First 150 Years 568:Natick Center station before reconstruction 1440:Former Boston and Albany Railroad stations 1296: 1294: 1050: 1048: 651: 649: 647: 631: 629: 417: 323: 312: 245: 33: 18: 16:Train station in Natick, Massachusetts, US 836: 834: 818:"WRITTEN HISTORICAL AND DESCRIPTIVE DATA" 334: 326: 261: 248: 1100:McMahon Associates; URS (18 June 2014). 1081:McMahon Associates; URS (15 June 2014). 932: 930: 513:Early postcard of the 1897-built station 1204:from the original on September 6, 2019. 1123:Arsenault, Charlene (12 January 2015). 867:"Bus to Take Place of Saxonville Train" 803:County Atlas of Middlesex Massachusetts 737:County Atlas of Middlesex Massachusetts 694:. Branch Line Press. pp. 278–283. 625: 1266:Brelsford, Laura (November 30, 2020). 1011:Henrich, Michael (30 September 2015). 889:Boston's Commuter Rail: Second Section 845:. Branch Line Press. pp. 302–03. 692:The Rail Lines of Southern New England 1372:"Accessibility Initiatives—June 2024" 685: 683: 681: 679: 677: 132: 7: 718:The Boston Almanac for the Year 1838 547:has been built on the right-of-way. 1337:"Alerts: Framingham/Worcester Line" 1229:Malachowski, Jeff (April 8, 2020). 1172:Benson, Brian (December 17, 2017). 139:: 10, 11, Natick Commuter Shuttle, 524:Alexander Wadsworth Longfellow Jr. 14: 1035:"MBTA Station Advisory Committee" 921:Boston Street Railway Association 1388:Kelly, Maribel (June 21, 2021). 1108:. Town of Natick. Archived from 1085:. Town of Natick. Archived from 1037:. Town of Natick. Archived from 969:Gregg, John (November 1, 1998). 252: 156:71 spaces (town permit required) 131: 1301:Doherty, John (February 2022). 1146:Benson, Brian (26 March 2016). 1055:Benson, Brian (4 August 2014). 596:Construction work in March 2022 487:Boston & Worcester Railroad 227:736 (weekday average boardings) 210:Natick (until January 12, 2015) 1285:"2020 MassTrails Grant Awards" 1: 572:Natick Center station is not 196: 182: 816:Healey, John (August 1990). 981:– via Newspapers.com. 638:"2018 Commuter Rail Counts" 534:acquired the line in 1900. 1471: 1102:"Implementation Framework" 690:Karr, Ronald Dale (1995). 354:Boston and Albany Railroad 281:Framingham/​Worcester Line 841:Roy, John H. Jr. (2007). 532:New York Central Railroad 450:Framingham/Worcester Line 427: 416: 412: 408: 331:New York Central Railroad 311: 307: 303: 244: 235: 231: 219: 32: 715:Dickinson, S.N. (1838). 597: 569: 514: 482: 1425:Cochituate Rail Trail 1135:on 30 September 2015. 1112:on 30 September 2015. 1089:on 30 September 2015. 1041:on 30 September 2015. 1023:on 30 September 2015. 595: 567: 545:Cochituate Rail Trail 512: 480: 446:Natick, Massachusetts 438:Natick Center station 56:Natick, Massachusetts 1410:MBTA – Natick Center 1235:Metrowest Daily News 1178:Metrowest Daily News 1152:Metrowest Daily News 1061:MetroWest Daily News 1192:"Notice to Bidders" 977:. pp. West 1, 912:Belcher, Jonathan. 103:Worcester Main Line 83:42.2858°N 71.3472°W 79: /  45:General information 1343:on March 21, 2023. 598: 570: 515: 505:Longfellow station 483: 442:MBTA Commuter Rail 389:Saxonville Branch 335:Following station 327:Preceding station 262:Following station 249:Preceding station 1255:on June 24, 2020. 499:Commonwealth Road 435: 434: 431: 430: 404: 403: 400: 399: 299: 298: 161:Other information 88:42.2858; -71.3472 1462: 1397: 1396: 1394: 1385: 1379: 1378: 1376: 1368: 1362: 1361: 1359: 1351: 1345: 1344: 1333: 1327: 1326: 1324: 1316: 1310: 1309: 1307: 1298: 1289: 1288: 1281: 1275: 1274: 1272: 1263: 1257: 1256: 1245: 1239: 1238: 1226: 1220: 1219: 1212: 1206: 1205: 1203: 1196: 1188: 1182: 1181: 1169: 1163: 1162: 1160: 1158: 1143: 1137: 1136: 1131:. Archived from 1120: 1114: 1113: 1097: 1091: 1090: 1078: 1072: 1071: 1069: 1067: 1052: 1043: 1042: 1031: 1025: 1024: 1019:. Archived from 1008: 1002: 1001: 989: 983: 982: 975:The Boston Globe 966: 960: 959: 957: 955: 949: 942: 934: 925: 924: 918: 909: 903: 902: 884: 875: 874: 863: 857: 856: 838: 829: 828: 822: 813: 807: 806: 795: 789: 788: 779: 773: 772: 763: 757: 756: 747: 741: 740: 729: 723: 722: 712: 706: 705: 687: 672: 671: 653: 642: 641: 633: 418: 324: 313: 288:Wellesley Square 256: 246: 201: 198: 187: 184: 135: 134: 94: 93: 91: 90: 89: 84: 80: 77: 76: 75: 72: 37: 19: 1470: 1469: 1465: 1464: 1463: 1461: 1460: 1459: 1430: 1429: 1406: 1401: 1400: 1392: 1387: 1386: 1382: 1374: 1370: 1369: 1365: 1357: 1353: 1352: 1348: 1335: 1334: 1330: 1322: 1318: 1317: 1313: 1305: 1300: 1299: 1292: 1283: 1282: 1278: 1270: 1265: 1264: 1260: 1247: 1246: 1242: 1228: 1227: 1223: 1214: 1213: 1209: 1201: 1194: 1190: 1189: 1185: 1171: 1170: 1166: 1156: 1154: 1145: 1144: 1140: 1122: 1121: 1117: 1099: 1098: 1094: 1080: 1079: 1075: 1065: 1063: 1054: 1053: 1046: 1033: 1032: 1028: 1010: 1009: 1005: 991: 990: 986: 968: 967: 963: 953: 951: 950:on June 8, 2017 947: 940: 936: 935: 928: 916: 911: 910: 906: 899: 886: 885: 878: 865: 864: 860: 853: 840: 839: 832: 820: 815: 814: 810: 797: 796: 792: 781: 780: 776: 765: 764: 760: 749: 748: 744: 731: 730: 726: 714: 713: 709: 702: 689: 688: 675: 668: 655: 654: 645: 635: 634: 627: 622: 586:island platform 562: 540: 528:H.H. Richardson 526:, a student of 507: 475: 470: 423: 384: 371: 358: 348: 318: 317:Former services 295: 275: 199: 185: 143:Express Shuttle 87: 85: 81: 78: 73: 70: 68: 66: 65: 54: 53:1 Walnut Street 40: 28: 27: 26: 17: 12: 11: 5: 1468: 1466: 1458: 1457: 1452: 1447: 1442: 1432: 1431: 1428: 1427: 1422: 1417: 1412: 1405: 1404:External links 1402: 1399: 1398: 1380: 1363: 1346: 1328: 1311: 1290: 1276: 1258: 1240: 1221: 1207: 1183: 1164: 1138: 1115: 1092: 1073: 1044: 1026: 1003: 984: 961: 926: 904: 897: 876: 858: 851: 830: 808: 790: 774: 758: 742: 724: 707: 700: 673: 666: 643: 624: 623: 621: 618: 582:side platforms 561: 560:Reconstruction 558: 539: 536: 506: 503: 474: 471: 469: 466: 458:side platforms 448:served by the 433: 432: 429: 428: 425: 424: 421: 414: 413: 410: 409: 406: 405: 402: 401: 398: 397: 392: 390: 387: 385: 379: 373: 372: 366: 361: 359: 356: 351: 349: 343: 337: 336: 333: 328: 320: 319: 316: 309: 308: 305: 304: 301: 300: 297: 296: 290: 285: 283: 278: 276: 270: 264: 263: 260: 250: 242: 241: 237: 236: 233: 232: 229: 228: 225: 221: 220: 217: 216: 212: 211: 208: 207:Previous names 204: 203: 193: 189: 188: 180: 176: 175: 171: 170: 167: 163: 162: 158: 157: 154: 150: 149: 145: 144: 129: 125: 124: 121: 117: 116: 114:side platforms 110: 106: 105: 100: 96: 95: 63: 59: 58: 51: 47: 46: 42: 41: 38: 30: 29: 24: 23: 22: 15: 13: 10: 9: 6: 4: 3: 2: 1467: 1456: 1453: 1451: 1448: 1446: 1443: 1441: 1438: 1437: 1435: 1426: 1423: 1421: 1418: 1416: 1413: 1411: 1408: 1407: 1403: 1391: 1384: 1381: 1373: 1367: 1364: 1356: 1350: 1347: 1342: 1338: 1332: 1329: 1321: 1315: 1312: 1304: 1297: 1295: 1291: 1286: 1280: 1277: 1269: 1262: 1259: 1254: 1250: 1244: 1241: 1236: 1232: 1225: 1222: 1217: 1211: 1208: 1200: 1193: 1187: 1184: 1179: 1175: 1168: 1165: 1153: 1149: 1142: 1139: 1134: 1130: 1126: 1119: 1116: 1111: 1107: 1103: 1096: 1093: 1088: 1084: 1077: 1074: 1062: 1058: 1051: 1049: 1045: 1040: 1036: 1030: 1027: 1022: 1018: 1014: 1007: 1004: 999: 995: 988: 985: 980: 976: 972: 965: 962: 946: 939: 933: 931: 927: 922: 915: 908: 905: 900: 898:9780938315025 894: 890: 883: 881: 877: 872: 868: 862: 859: 854: 852:9780942147087 848: 844: 837: 835: 831: 826: 819: 812: 809: 804: 800: 794: 791: 786: 785: 778: 775: 770: 769: 762: 759: 754: 753: 746: 743: 738: 734: 728: 725: 721:. p. 50. 720: 719: 711: 708: 703: 697: 693: 686: 684: 682: 680: 678: 674: 669: 667:9780685412947 663: 659: 652: 650: 648: 644: 639: 632: 630: 626: 619: 617: 614: 610: 606: 604: 603:Natick Center 594: 590: 587: 583: 577: 575: 566: 559: 557: 554: 548: 546: 537: 535: 533: 529: 525: 520: 511: 504: 502: 500: 495: 490: 488: 479: 473:Early history 472: 467: 465: 463: 459: 455: 451: 447: 443: 439: 426: 419: 415: 411: 407: 396: 393: 391: 388: 386: 383: 378: 375: 374: 370: 365: 362: 360: 355: 352: 350: 347: 342: 339: 338: 332: 325: 322: 321: 315: 314: 310: 306: 302: 294: 293:South Station 289: 286: 284: 282: 279: 277: 274: 269: 266: 265: 259: 255: 247: 243: 238: 234: 230: 226: 222: 218: 213: 209: 205: 194: 190: 181: 177: 172: 168: 164: 159: 155: 151: 146: 142: 138: 130: 126: 122: 118: 115: 111: 107: 104: 101: 97: 92: 64: 60: 57: 52: 48: 43: 36: 31: 25:Natick Center 20: 1383: 1366: 1349: 1341:the original 1331: 1314: 1279: 1261: 1253:the original 1243: 1234: 1224: 1210: 1186: 1177: 1167: 1155:. Retrieved 1151: 1141: 1133:the original 1129:Natick Patch 1128: 1118: 1110:the original 1105: 1095: 1087:the original 1076: 1064:. Retrieved 1060: 1039:the original 1029: 1021:the original 1017:FOX25 Boston 1016: 1006: 998:Boston Globe 997: 987: 974: 964: 952:. Retrieved 945:the original 907: 888: 871:Boston Globe 870: 861: 842: 824: 811: 802: 799:"Felchville" 793: 783: 777: 767: 761: 751: 745: 736: 727: 717: 710: 691: 657: 615: 611: 607: 602: 599: 578: 571: 549: 541: 516: 491: 484: 437: 436: 394: 148:Construction 954:October 24, 553:West Natick 456:), has two 444:station in 268:West Natick 202:, 2020–2024 200: 1962 186: 1839 128:Connections 86: / 62:Coordinates 1434:Categories 1066:12 January 701:0942147022 620:References 574:accessible 494:Saxonville 462:accessible 382:Saxonville 377:Felchville 341:Framingham 215:Passengers 74:71°20′50″W 71:42°17′09″N 519:Riverside 364:Wellesley 357:Main Line 273:Worcester 166:Fare zone 141:MathWorks 109:Platforms 1199:Archived 1157:26 March 733:"Natick" 584:with an 454:Route 27 422:Location 395:Terminus 240:Services 50:Location 538:Decline 468:History 380:toward 367:toward 344:toward 291:toward 271:toward 192:Rebuilt 174:History 153:Parking 99:Line(s) 895:  849:  698:  664:  440:is an 369:Boston 346:Albany 195:1897, 179:Opened 120:Tracks 1393:(PDF) 1375:(PDF) 1358:(PDF) 1323:(PDF) 1306:(PDF) 1271:(PDF) 1202:(PDF) 1195:(PDF) 948:(PDF) 941:(PDF) 917:(PDF) 821:(PDF) 137:MWRTA 1159:2016 1068:2015 956:2019 893:ISBN 847:ISBN 696:ISBN 662:ISBN 485:The 258:MBTA 224:2018 1436:: 1293:^ 1233:. 1176:. 1150:. 1127:. 1104:. 1059:. 1047:^ 1015:. 996:. 979:11 973:. 929:^ 919:. 879:^ 869:. 833:^ 823:. 801:. 735:. 676:^ 646:^ 628:^ 197:c. 183:c. 112:2 1237:. 1180:. 1161:. 1070:. 1000:. 958:. 923:. 901:. 855:. 704:. 670:. 169:4 123:2

Index


Natick, Massachusetts
42°17′09″N 71°20′50″W / 42.2858°N 71.3472°W / 42.2858; -71.3472
Worcester Main Line
side platforms
MWRTA
MathWorks

MBTA
West Natick
Worcester
Framingham/​Worcester Line
Wellesley Square
South Station
New York Central Railroad
Framingham
Albany
Boston and Albany Railroad
Wellesley
Boston
Felchville
Saxonville
MBTA Commuter Rail
Natick, Massachusetts
Framingham/Worcester Line
Route 27
side platforms
accessible

Boston & Worcester Railroad

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.

↑