79:. Increased power demand necessitated a second generating station, SAB 2, to be constructed in 1954. SAB 2 derives its water supply from two diversion tunnels, each about 9 kilometres (5.6 mi) in length. In 1958, a reservoir and the SAB Pump Station were constructed in order to make better use of available water by storing it during periods of low demand and using it in periods of greater demand in order to maximize the efficiency of the stations in regards to electricity supply and demand. 292: 126: 264:(OPG) and the Ontario Government officially placed the new Niagara tunnel into service with a formal opening ceremony and tour. The OPG reported that the project will be financially rewarding despite being completed four years later than planned and about $ 500M over its originally estimated cost. OPG's president and CEO Tom Mitchell stated: "This was a large, complex project that will serve Ontario for more than 100 years". 19: 320: 306: 101:
The new 10.2 kilometres (6.3 mi) long tunnel is 12.7 metres (42 ft) in diameter, or about four storeys in height, and allows an additional diversion of a distant part of the Niagara River to reach the SAB plant complex at a rate of about 500 cubic metres (18,000 cu ft) of water
267:
The tunnel project was completed at a total cost $ 100 million lower than its revised $ 1.6 billion budget, and with an in-service date of 9 March 2013. The operational start-of-service date was nine months sooner than the project's revised schedule that was drawn up in 2009 due to unexpected and
149:
to the SAB complex. The bored tunnel was subsequently lined with an impervious membrane and a concrete lining, pre-stressed by high pressure grouting. The massive undertaking created about 1.6 million cubic metres of rock and debris, and was designed for a minimum 90-year life span.
102:
per second, a flow rate that can fill an Olympic-sized swimming pool in seconds. The Ontario Government considers the Niagara Tunnel Project and the Sir Adam Beck complex as integral to its efforts to close all of the province's coal-fired generating plants as part of its
157:, and was the world's largest hard-rock tunnel boring machine as of 2006. The TBM operated as deep as 140 metres (460 ft) below ground level to avoid the machine's vibrations being felt at surface level. The design-build contractor for the project was the 251:
Due to slower than projected boring progress caused by constant tunnel roof over-breaks, the project completion date was extended to at least December 2013, with a revised total projected cost of $ 1.6 billion.
171: 59:
The project's new 12.7 metres (42 ft) diameter, 10.2 kilometres (6.3 mi) long tunnel was officially placed into service on 21 March 2013, helping to increase the generating complex's
211: 472: 622: 602: 94:. Water delivered through the new Niagara Tunnel Project complements the SAB 2 upgrade, and results in an overall increase to the efficient use of the Niagara River's 75:
First constructed in 1922, the initial Sir Adam Beck power generating station, now abbreviated as SAB 1, derived its water supply from a hydro canal connected to the
49: 117:, stated that "This project is a source of pride as an engineering feat and as a practical solution for meeting Ontario's energy needs through clean sources". 31: 617: 278:
The Niagara Tunnel Project was selected by International Water Power & Dam Construction as the North American Project of the Year for 2013.
515: 531: 275:
The new tunnel will provide enough additional water to the Sir Adam Beck generating complex to produce power for approximately 160,000 homes.
153:
The HP 471-316 TBM was driven by 15 electric motors totaling about 4.7 megawatts of power (6,375 horsepower), built by the Robbins Company of
86:(OPG), which owns and operates the SAB complex, completed a series of major upgrades at the SAB 2 plant, increasing its potential generating 627: 563: 607: 141:. The TBM machine bored a tunnel about 10.2 kilometres (6.3 mi) long and about 14.4 metres (47 feet) in diameter under the 345: 612: 459: 114: 551: 460:
Water Now Flowing Through Newly Completed Niagara Tunnel Project will generate 100 plus years of renewable electricity
546: 168:
Boring by the Hatch Mott MacDonald Engineering Company started on 15 September 2006 at the north end, located at
355: 261: 83: 325: 496: 142: 38: 350: 134: 103: 501: 269: 22:
The Niagara Tunnel Project's intake point (near Upper Rapids Boulevard) under construction in 2010.
87: 60: 416: 403: 542:
Hatch Ltd, Owners Engineering Team with Hatch Mott MacDonald for Ontario Power Generation
125: 335: 18: 384: 596: 297: 165:, a large construction group with extensive experience in large tunnel construction. 146: 138: 110: 76: 53: 34: 311: 473:
Niagara Tunnel Completion Important Piece for Ontario's Hydroelectric Power Supply
319: 154: 95: 340: 287: 578: 565: 442: 429: 227: 213: 187: 173: 360: 305: 91: 64: 48:
Water delivered by the major new tunnel complements other upgrades to the
557:, Season 8, Episode 17, 15 March 2011. Retrieved from the CBC.ca website 406:, Ontario Power Generation website, March 2013. Retrieved 11 April 2013. 67:, with the extra power produced enough for approximately 160,000 homes. 162: 158: 42: 124: 17: 491: 489: 547:
Morrison Hershfield Lead Consulting Engineer for outside works
516:
North American Project of the Year – Niagara tunnel project
380: 378: 376: 268:
difficult geological conditions encountered in the soft
208:
and ended on 31 March 2011 at the south end, located at
541: 536: 455: 453: 451: 387:, NiagaraFrontier.com website, updated November 2012. 137:(TBM), affectionately named "Big Becky" in honour of 514:International Water Power & Dam Construction – 109:Upon the project's formal opening the Honourable 50:Sir Adam Beck Hydroelectric Generating Stations 30:was part of a series of major additions to the 399: 397: 395: 393: 8: 417:Niagara Tunnel Now In-Service, 21 March 2013 404:21 March 2013: Niagara Tunnel Now In-Service 133:The Niagara Tunnel was constructed using a 52:, resulting in more efficient use of the 462:, OPG News Release, 21 March 2013 (PDF). 430:"NIAGARA TUNNEL PROJECT - Niagara Falls" 623:Energy infrastructure completed in 2013 603:Hydroelectric power stations in Ontario 372: 385:Niagara Tunnel Project Technical Facts 7: 262:Ontario Power Generation Corporation 443:Niagara Tunnel Project (2005-2013) 272:during the tunnel boring process. 14: 537:Ontario Power Generation website 532:Official Niagara Tunnel web page 351:Ontario Green Energy Act of 2009 318: 304: 290: 346:List of energy storage projects 618:2013 establishments in Ontario 552:Niagara Tunnel Project on the 445:, NiagaraFrontier.com website. 143:City of Niagara Falls, Ontario 104:clean and green energy program 1: 497:Big Becky's running late: OPG 256:Completion and commissioning 518:. Retrieved September 2013. 419:. Retrieved September 2013. 415:Ontario Power Generation – 644: 628:Tunnels completed in 2013 579:43.0696444°N 79.0593806°W 270:Queenston Shale Formation 228:43.0696444°N 79.0593806°W 129:Construction work in 2010 608:Ontario Power Generation 477:RenewableEnergyWorld.com 356:Ontario Power Generation 239:Niagara Tunnel south end 199:Niagara Tunnel north end 84:Ontario Power Generation 584:43.0696444; -79.0593806 326:Renewable energy portal 233:43.0696444; -79.0593806 188:43.140333°N 79.062278°W 82:Between 1996 and 2005, 130: 39:Niagara Falls, Ontario 37:generation complex in 28:Niagara Tunnel Project 23: 260:On 21 March 2013 the 193:43.140333; -79.062278 161:construction company 135:Tunnel Boring Machine 128: 21: 613:Engineering projects 502:Niagara Falls Review 479:in association with 113:, M.P.P., Ontario's 575: /  505:, 26 November 2008. 223: /  183: /  554:Rick Mercer Report 131: 115:Minister of Energy 88:nameplate capacity 61:nameplate capacity 24: 495:Larocque, Corey. 471:Harris, Michael. 635: 590: 589: 587: 586: 585: 580: 576: 573: 572: 571: 568: 519: 512: 506: 493: 484: 469: 463: 457: 446: 440: 434: 433: 426: 420: 413: 407: 401: 388: 382: 328: 323: 322: 314: 309: 308: 300: 295: 294: 293: 247: 246: 244: 243: 242: 240: 235: 234: 229: 224: 221: 220: 219: 216: 207: 206: 204: 203: 202: 200: 195: 194: 189: 184: 181: 180: 179: 176: 56:'s hydro power. 643: 642: 638: 637: 636: 634: 633: 632: 593: 592: 583: 581: 577: 574: 569: 566: 564: 562: 561: 528: 523: 522: 513: 509: 494: 487: 483:, 9 April 2013. 470: 466: 458: 449: 441: 437: 428: 427: 423: 414: 410: 402: 391: 383: 374: 369: 332: 331: 324: 317: 310: 303: 296: 291: 289: 284: 258: 238: 236: 232: 230: 226: 225: 222: 217: 214: 212: 210: 209: 198: 196: 192: 190: 186: 185: 182: 177: 174: 172: 170: 169: 123: 73: 12: 11: 5: 641: 639: 631: 630: 625: 620: 615: 610: 605: 595: 594: 559: 558: 549: 544: 539: 534: 527: 526:External links 524: 521: 520: 507: 485: 481:HydroWorld.com 464: 447: 435: 421: 408: 389: 371: 370: 368: 365: 364: 363: 358: 353: 348: 343: 338: 336:Energy storage 330: 329: 315: 301: 286: 285: 283: 280: 257: 254: 122: 119: 72: 69: 13: 10: 9: 6: 4: 3: 2: 640: 629: 626: 624: 621: 619: 616: 614: 611: 609: 606: 604: 601: 600: 598: 591: 588: 570:79°03′33.77″W 567:43°04′10.72″N 556: 555: 550: 548: 545: 543: 540: 538: 535: 533: 530: 529: 525: 517: 511: 508: 504: 503: 498: 492: 490: 486: 482: 478: 474: 468: 465: 461: 456: 454: 452: 448: 444: 439: 436: 431: 425: 422: 418: 412: 409: 405: 400: 398: 396: 394: 390: 386: 381: 379: 377: 373: 366: 362: 361:Sir Adam Beck 359: 357: 354: 352: 349: 347: 344: 342: 339: 337: 334: 333: 327: 321: 316: 313: 307: 302: 299: 298:Canada portal 288: 281: 279: 276: 273: 271: 265: 263: 255: 253: 249: 245: 218:79°03′33.77″W 215:43°04′10.72″N 205: 166: 164: 160: 156: 151: 148: 147:Niagara River 144: 140: 139:Sir Adam Beck 136: 127: 120: 118: 116: 112: 111:Bob Chiarelli 107: 105: 99: 97: 93: 89: 85: 80: 78: 77:Welland River 70: 68: 66: 62: 57: 55: 54:Niagara River 51: 46: 44: 40: 36: 35:hydroelectric 33: 32:Sir Adam Beck 29: 20: 16: 560: 553: 510: 500: 480: 476: 467: 438: 424: 411: 312:Water portal 277: 274: 266: 259: 250: 178:79°03′44.2″W 175:43°08′25.2″N 167: 152: 132: 121:Construction 108: 100: 81: 74: 58: 47: 27: 25: 15: 582: / 231: / 191: / 155:Solon, Ohio 145:, from the 96:hydro power 597:Categories 367:References 341:Hydropower 237: ( 197: ( 163:Strabag AG 71:Background 92:megawatts 65:megawatts 282:See also 159:Austrian 90:by 194 63:by 150 43:Canada 26:The 599:: 499:, 488:^ 475:, 450:^ 392:^ 375:^ 248:. 106:. 98:. 45:. 41:, 432:. 241:) 201:)

Index


Sir Adam Beck
hydroelectric
Niagara Falls, Ontario
Canada
Sir Adam Beck Hydroelectric Generating Stations
Niagara River
nameplate capacity
megawatts
Welland River
Ontario Power Generation
nameplate capacity
megawatts
hydro power
clean and green energy program
Bob Chiarelli
Minister of Energy

Tunnel Boring Machine
Sir Adam Beck
City of Niagara Falls, Ontario
Niagara River
Solon, Ohio
Austrian
Strabag AG
43°08′25.2″N 79°03′44.2″W / 43.140333°N 79.062278°W / 43.140333; -79.062278 (Niagara Tunnel north end)
43°04′10.72″N 79°03′33.77″W / 43.0696444°N 79.0593806°W / 43.0696444; -79.0593806 (Niagara Tunnel south end)
Ontario Power Generation Corporation
Queenston Shale Formation
Canada portal

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.