Knowledge (XXG)

Northern Suburbs Transit System

Source đź“ť

825:. The Government's lawyers considered that Westpac would have reasonable recourse against the Government, and its Consolidated Revenue Fund, in the event that a default occurred. One solution proposed by Clayton Utz was to enjoin the Minister for Transport as a party to the financing facility contract. However, after further significant problems arose with proposed changes by Westpac to the funding arrangements, its contract for the finance facility was terminated in August 1992. 919:
noted that this was supported by the fact that Warwick and Whitfords were at the time the busiest stations on NSTS, attracting a combined 18,000 passenger movements on weekdays. 60% of those passengers did not arrive or depart by bus, but arrived by car or by walking about 55 metres (180 ft) across the Mitchell Freeway. Passenger modelling found that the relocation to the station would have no effect on project passenger boardings.
778:, then responsible for the provision and management of metropolitan rail transport for Transperth, would not have enough rolling stock to operate the new line. Further to that, the funding available to Westrail would not permit the purchase of rolling stock from current or future operating funds. On 20 November 1989, the State Cabinet allowed Westrail to pursue an operating lease to permit the acquisition of the required 22 2-car 754:
suburbs. Due to the need to construct a rail tunnel under Roe Street, it was considered unsafe and impractical to retain the existing level crossing, because it would be situated very near the tunnel entrance, and so make impossible for train drivers to see any vehicles on the crossing and take evasive action. That led to the construction of the Fitzgerald Street Bus Bridge.
507:, in which car-like vehicles travelled automatically, suspended from an overhead beam. The vehicles were then used as electronically driven cars on the road once having reached the end of the track network. Proctor claimed that the system had been selected for use in connecting two shopping centres and other local infrastructure in 802:, to minimise withholding tax liabilities from the Japanese and Australian taxation agencies. Allco refused to release specific information on the proposed structure, due to its policy prohibiting the release of specific details of this financing arrangement until it had secured a mandate for their services. 945:
That was in addition to the construction of a further 240 car parking bays at Whitfords Station, costing $ 780,000 in 2000, on the southern side of the station. Construction of a multi-story parking structure at Warwick was not considered as an option due to a number of social and environmental concerns.
362:
were faster journeys, and lower capital costs. However, those who preferred the electric railway option cited greater comfort, less crowding, and less pollution as important factors in their preference. In addition, quite a number of respondents liked the railway idea due to it being "forward thinking".
905:
The supply of additional rolling stock was critical to the completion of the project, particularly in the context of the future planned rail needs for Perth. Existing rolling stock was being utilised to capacity, and based on future projections, that included the operation of a fifth railway line and
797:
were around 16-17%, placing a significant burden on companies in their business dealings. To work around this, Allco proposed a financing structure that involved a cross-border financing arrangement in Japan. It also required the establishment of a special purposes lessor company, incorporated in the
159:
The participants from both sub-groups all held similar views in relation to the public transport; that of bus overcrowding, poor connections, poor timing, and poor route design impacted negatively on their perceptions and opinions of public transport. Over 43% of the participants described the public
935:
While Nowergup was selected as the final site for the planned railway depot, Neerabup was suggested as the original site. However, as the new railway depot would require some 300 metres (330 yd) of space in the middle of the freeway reserve, it would have a significantly larger footprint in the
918:
The committee took these factors into account in its final report, and noted that the relocation was seen as having major environmental and social benefits. Improved frequency, journey speed, and reliability would be more significant factors than an additional 60-metre (200 ft) walk. The report
644:
Related to the project was the realignment of the Mitchell Freeway between Loftus and McDonald Streets. At the time, the northbound and southbound carriages of the freeway in this section were constructed next to each other. To allow for the rail corridor down the middle of the freeway, that section
765:
However the planned flyover was abandoned in favour of moving the existing level crossing some 250 metres to the west of its original position underneath the Hamilton Interchange approaches. In 2008 construction began on the Perth Arena Bus Bridge, crossing Roes Street, which would offer a similar
361:
During the study, various surveys were undertaken to establish public attitudes towards the transport options that were being considered. In order of preference respondents selected electric railway (41%), bus expressway (34.4%), guided busway (19.3%). The most important factors making a selection
944:
One of the other major problems noted in the report was the availability of parking at stations along the line. One of the key features of the Greenwood Station was to be additional parking, which would remove any need to construct a multi-story parking facility at Whitfords and Warwick Stations.
914:
At the time of the project's proposal, there was significant community discussion relating to the relocation of the Currambine Station into the middle of the freeway reserve. In the 1989 master plan, the location of the station was designed to reduce the 'transfer penalty' in moving from train to
817:
However, the establishment of the funding facility was not without significant incident. Substantial argument between the Western Australian Government and Westpac ensued, in respect of liability if Westrail defaulted on payments. Of concern was the recourse Westpac would have against the Western
155:
The focus groups consisted of two sub-groups of participants, one consisting of public transport users residing within established suburbs, and the other of public transport users from newer and developing suburbs. Combined within these sub-groups were subsets of both regular and irregular users,
753:
Already in existence prior to the planning for the line was a level crossing at the intersection of Fitzgerald and Roe streets in central Perth. The crossing allowed buses coming from Wellington Street Bus Station to connect with Fitzgerald Street and then run to the northern and north-eastern
369:
noted the recommendation by the consultants for the implementation of a bus-based system using an exclusive right-of-way in the median of the Mitchell Freeway. However, he noted that further detailed evaluation of a rail-based option was still being carried out. The report noted that while its
176:
The study was commenced in early 1988 under the auspices of the then Minister for Transport and Small Business, after receiving Cabinet approval 10 November 1987. Due to the budget position of the then Department of Transport, it was not possible to fund the nine-month project from within its
103:
by the then Office of the Director General of Transport. The report looked at Perth's transport needs into the 21st century and beyond, at a broad strategic level. It provided some strategic travel forecasts, and made a limited evaluation of rapid transit options for the northern corridor.
645:
of road required realignment. While necessary bridges and some associated works for the realignment were included as part of the project cost, the rebuilding of the section of road in the realigned section was funded separately from the project, using regular road funding sources.
188:
was completed in September 1988 by consulting firms Travers Morgan, Pack Poy and Kneebone, Blackwell and Associated, and Uloth and Associates. It evaluated a number of rapid transport options for Perth's northern corridor as well as garnering public feedback on those options.
373:
During the public debate over the future of public transportation in the northern corridor, Transport Minister Pearce claimed that the NSTS would never be built under a Liberal coalition government. Opposition Leader Barry MacKinnon stated that charge was "totally untrue".
569:
The project was estimated to cost $ 220 million (1989), including $ 130 million (1989) for infrastructure including earthworks, bridges, and stations. A further $ 90 million (1989) would be spent on the purchase of a 22 additional two-car electric trains,now known as the
114:
The government of the day, after a strong political push, decided to plan and construct a rail service, to known as the Northern Suburbs Rapid Transit System. It was aimed at restructuring the bus network for the northern corridor, while going some way to reduce
922:
The relocation would also help retain consistency with rest of the line and the future SWMR. It was further supported in surveys and opinion polls undertaken in Glen Iris, South Lakes and Atwell and with commercial business as part of SWMR planning processes.
833:
In 2000, the Department of Transport released the report from the Urban Rail Planning and Implementation Steering Committee outlining plans for the extension of the line from Currambine to Clarkson, and its continuation to a new railway depot to be located at
482:
The study predicted that by 2001, the line would have 13,000 passenger boardings during peak hour. Over 12,000 of these passengers were predicted to board the services prior to reaching the maximum load point, defined by the report as Scarborough Beach Road.
757:
Estimated in 1991 to cost $ 2.88 million, the bridge was designed as a flyover from Roe Street, accommodating two bus lanes, and a shared use path for pedestrian and cycle movements. To construct the bridge, a significant amount of land then occupied by a
648:
The transit system was designed to provide for a rapid service, allowing rail cars using the line to operate at speeds of 110 km/h (68 mph), which would allow a journey from Perth to Joondalup to be completed in approximately 20 minutes.
926:
If the railway station and subsequent rail reserve had remained on the western side of the freeway, there would have been significantly increased expenditure because of the need for additional noise reduction measures and other engineering works.
845:
Government that it would extend the Joondalup Line from Currambine to Clarkson during its term of government. The report was initiated following the completion of the South West Metropolitan Railway (SWMR) Master Plan, which was the basis of the
523:
would be ideal for use along the Mitchell Freeway. He said that the proposed rail line in the middle of the freeway would be an eyesore, and claimed that skytrain systems installed in Vancouver, Toronto, and Boston had been quite successful.
238:
It is almost beyond belief that the Government would contemplate spending $ 41 million on another new arterial route in the northern suburbs when the Mitchell Freeway is clearly inadequate to serve peak-hour needs of the northern suburbs
127:
As part of research into community attitudes on public transport within the northern corridor, Donovan Research was engaged during 1987 to undertake focus group and telephone research to determine information on the following key points:
326:
The majority of these options were rejected on the basis that introducing another mode of public transport to the city would serve little or no purpose, considering the existing modes of bus and rail functioned effectively.
67:
The need for the project arose from the rapid and sustained growth of the northern suburbs of Perth during the 1970s and 1980s, which had placed a considerable strain on infrastructure, including the bus system and the
813:
be accepted. Her recommendation was subsequently approved by Cabinet on 20 May 1991. The final financial facility provided by Westpac was valued in 1991 at over $ 160 million, to be paid off over a period of 20 years.
2179: 936:
Neerabup National Park. The environmental assessment recommended that the depot be relocated to a site in Nowergup to lower the environmental impact while retaining larger areas of the park in pristine condition.
72:. However, prior to the opening of the railway, the proposal was controversial as many in the community believed that upgrading the Mitchell Freeway or providing a guided busway would be better solutions. 2030: 491:
A number of theoretically innovative ideas for possible transport systems were put forward by various people within the Western Australian business and transport communities, but ultimately rejected.
782:. On 30 November 1989, the contract to construct the trains was awarded to Walkers-ABB despite a funding deal not being in place. Westrail sought out a financing arrangement to enable the purchase. 111:, along with major arterial routes servicing the northern corridor, were constantly clogged during peak hour, with the community at large dissatisfied with the bus services provided for the region. 2866: 1013:
Construction of the extension commenced in 2011, with the opening of services planned for late 2014. By early 2014, works were running early, leading to a revised opening date of September 2014.
1010:
already constructed as a two track reserve. That was in addition to the planning for that section recognising the need to further extend the railway to areas further north, beyond the depot.
857:
The amendment of the Metropolitan Region Scheme to excise 202 hectares of land from the adjoining Neerabup National Park, while returning some 572 hectares to the park in the same adjustment;
511:, but the Acting Deputy Director General was not impressed with the concept having shifted a number of times in conversation and there still not a working prototype in place for evaluation. 2144: 793:. One of the more interesting notes to the Allco proposal was the nature of the financing arrangements it was proposing. At the time of the proposed financing deal, interest rates in 479:. However, this idea was rejected by both the project coordinators and the public at large due to the significant cost, lack of identifiable benefits, and environmental impact. 2559: 382:
As part of the analysis of a rail service in Perth's northern corridor, a comprehensive study was undertaken in 1989 to establish the best route and potential station options.
267:
Roads and public transport are the two biggest single concerns represented to our association and this new $ 41 million highway will do nothing to resolve any of these concerns
1021:
In the 2017 WA state budget, $ 441 million was allocated to build the extension, with preparation works starting in January 2020 and bulk earthworks to start by April 2020.
889:
Construction of the rail reserve and four kilometres of railway track from Burns Beach Road to Nowgerup, along with associated works including communications and signalling;
2062: 2171: 899:
The plan also recommended a delay in the construction of Greenwood Station, because it could not be adequately serviced until additional rolling stock had been delivered.
532:
State Cabinet gave in-principle support for the construction of a railway and the enabling legislation passed parliament and was assented to on 15 January 1989. The first
177:
existing budget, which necessitated a request to Treasury for additional funds. The Minister for Budget Management approved the request for additional funding, allocating
148:
Obtain specific information as to the various aspects of suggested operation of the committee, such as communications channels used, method of community participation; and
370:
preference was to construct a bus expressway, the extension of such a busway beyond Warwick would provide little or no benefits in terms of speed, time, and economics.
2297: 1006:
Some of the groundwork for the works had been laid during construction of the Clarkson to Currambine extension, with the rail surface necessary to allow access to the
1091: 2632: 2353: 2315: 2118: 2088: 1452: 1000: 2040: 2535: 255:
This was a view also supported by the then president of the Greenwood, Kingsley, Warwick, and Woodvale Citizens' Association, Cheryl Edwardes (later the
818:
Australian Government Consolidated Revenue Fund, particularly in the context of the Crown Suits Act of 1889 and 1947, if such a default event occurred.
581:, and designed to closely link the new rail infrastructure with bus services through the construction of several interchange stations along the route. 1410: 1343: 1320: 1283: 1249: 1222: 1177: 1069: 230:
called on the state government to put plans to construct a new northern suburbs highway on hold, and redirect funds to upgrading and extending the
1643:
File 02957 SC V2; Finance: Rail Infrastructure Funding Scheme: Northern Suburbs Railway (Perth to Joondalup): Financial Arrangements with Westpac
987:
In 2008, the state government announced a further 7.5 kilometres (4.7 mi) extension to the line, taking it as far as the northern suburb of
1032:. When opened, a journey time of 49 minutes is envisioned from Yanchep to the CBD, with up to 13,500 people expected to use the line every day. 2693: 2345: 2231: 1562:
Letter from Rawlinsons WA to Bruechle Gilcrist and Evans Pty Ltd, Northern Suburbs Transit System: Fitzgerald Street Bus Bridge: Interim Report
863:
The construction of a new Currambine Station to a location in the middle of the Mitchell Freeway reserve, along with associated approach works;
2148: 2209: 2290: 1587: 2498: 2122: 2084: 1448: 2478: 2473: 2261:
Johnstone, Peter (1989). The Northern Suburbs Railway (Report 332). Perth: Department of Transport, Government of Western Australia.
2054: 2658: 2283: 2036: 2008: 1975: 1936: 1906: 1876: 1839: 1809: 1779: 1749: 1719: 1689: 1650: 1513: 1434: 1378: 1314: 1216: 1171: 1063: 995:, the Planning and Infrastructure Minister, had announced that funds of $ 2.1 million (2007) had been set aside in the 2007-08 853:
Estimated in 2001 to cost $ 81 million, the report recommended the undertaking of the following works to complete the project:
667: 453: 84: 31: 2266: 673: 434: 256: 508: 1313:: Travers Morgan, Pack Poy and Kneebone, Blackwell and Associated, Uloth and Associates for the Department of Transport, 1170:: Travers Morgan, Pack Poy and Kneebone, Blackwell and Associated, Uloth and Associates for the Department of Transport, 1099: 2685: 2589: 2555: 537: 428: 205: 99:
The transport needs of Perth's northern corridor were evaluated as far back as 1982, with the preparation of the report
835: 821:
The position of Westpac's lawyers was in direct conflict with that of the Government's legal advisors on the project,
729: 661: 468: 462: 424: 216: 197: 75:
The Northern Suburbs Transit System name has been used subsequently for additions to the original line, including the
2393: 1024:
Construction commenced in 2020 to extend the line by 14.5 km (9.0 mi) to service growing suburbs including
2819: 2642: 1025: 842: 710: 476: 389: 212: 76: 866:
Demolition of the existing Currambine Station, including associated sidings and rolling-stock cleaning facilities;
2514: 2442: 2437: 2432: 988: 779: 742: 736: 691: 685: 679: 593: 571: 417: 411: 405: 399: 334: 193: 80: 839: 396:
space, due to limitations at Joondalup, and rail storage, as well as providing for further extension northward);
2018: 2004: 1985: 1971: 1946: 1932: 1916: 1902: 1886: 1872: 1849: 1835: 1819: 1805: 1789: 1775: 1759: 1745: 1729: 1715: 1699: 1685: 1660: 1646: 1575: 1565: 1549: 1539: 1523: 1509: 1430: 1414: 1388: 1374: 1347: 1324: 1310: 1287: 1253: 1226: 1212: 1181: 1167: 1144: 1134: 1073: 1059: 822: 252:
He also commented that northern suburbs residents faced road journeys of up to an hour to reach the Perth CBD.
201: 42: 574:. The remaining cost of the trains was to be funded from a financing package being drafted by the government. 519:
Retired engineering design consultant, John Stephens, told the Wanneroo Times that a skytrain system using a
2732: 953:
In addition to Greenwood and Clarkson, the project outlined several additional future stations, which were:
174:"A study will be conducted on the most appropriate form of rapid transit service for the northern suburbs." 2519: 1007: 976: 883: 631: 606: 520: 169: 88: 53: 475:
At the time, a possible deviation of the rail alignment was considered to directly service the suburb of
2871: 2824: 2803: 847: 589: 1307:
Public Transport for Perth's Northern Suburbs - A summary of the Northern Suburbs Rapid Transit System
1164:
Public Transport for Perth's Northern Suburbs - A summary of the Northern Suburbs Rapid Transit System
2768: 2758: 892:
Lengthening existing station platforms along the line to 144 metres to accommodate 6-car trains; and
60:(then known as the Joondalup line) and linked bus services, which have been a core component of the 2399: 2372: 1337: 1243: 790: 555:, all subsequent projects involving additions or upgrades to the line have carried the same name. 2793: 2773: 2763: 2201: 2014: 1981: 1942: 1912: 1882: 1845: 1815: 1785: 1755: 1725: 1695: 1656: 1571: 1545: 1519: 1384: 1140: 1095: 992: 759: 20: 838:, within the future Mitchell Freeway reserve. This was the result of a commitment from the then 208:, along with previous respondents to a survey initiated through local papers in December 1987. 2737: 2330: 2262: 996: 500: 46: 2114: 139:
Determine major perceived issues of importance related to public transport within the region;
2092: 1456: 873: 578: 339: 231: 219:
Coalition Opposition, and local community groups, rallied against what they claimed was the
108: 69: 50: 902:
The project was to be funded from government borrowings over four years from 2001 to 2004.
2550: 624: 613: 355: 227: 192:
Amongst the methods used to collect data for the report were surveys sent to residents of
1506:
Northern Suburbs Transit System; Perth to Joondalup Railway; Progress Summary - June 1991
1035:
Construction has been completed, and the line commenced revenue service on 14 July 2024.
330:
A number of routes were examined for use as part of the eventual system, which included:
156:
with regular users being defined as those using public transport at least once per week.
2798: 2722: 2717: 2574: 2468: 2463: 2458: 2382: 1594: 1277: 906:
passenger numbers modelling, the size of the existing fleet would not be able to cope.
799: 716:
The second stage of the project was expected to be in operation by the middle of 1993.
273: 245: 116: 38: 2035:. Urban Rail Planning and Implementation Steering Committee, Department of Transport, 2007:: Urban Rail Planning and Implementation Steering Committee, Department of Transport, 1974:: Urban Rail Planning and Implementation Steering Committee, Department of Transport, 1935:: Urban Rail Planning and Implementation Steering Committee, Department of Transport, 1905:: Urban Rail Planning and Implementation Steering Committee, Department of Transport, 1875:: Urban Rail Planning and Implementation Steering Committee, Department of Transport, 1838:: Urban Rail Planning and Implementation Steering Committee, Department of Transport, 1808:: Urban Rail Planning and Implementation Steering Committee, Department of Transport, 1778:: Urban Rail Planning and Implementation Steering Committee, Department of Transport, 1748:: Urban Rail Planning and Implementation Steering Committee, Department of Transport, 1718:: Urban Rail Planning and Implementation Steering Committee, Department of Transport, 1688:: Urban Rail Planning and Implementation Steering Committee, Department of Transport, 637:
Construction of new western concourse at Perth station and appropriate facilities; and
2860: 2545: 2404: 2387: 2377: 965: 958: 540: 393: 350: 291: 260: 2032:
Northern Suburbs Transit System, Currambine to Butler Extension, Interim Master Plan
2001:
Northern Suburbs Transit System, Currambine to Butler Extension, Interim Master Plan
1968:
Northern Suburbs Transit System, Currambine to Butler Extension, Interim Master Plan
1929:
Northern Suburbs Transit System, Currambine to Butler Extension, Interim Master Plan
1899:
Northern Suburbs Transit System, Currambine to Butler Extension, Interim Master Plan
1869:
Northern Suburbs Transit System, Currambine to Butler Extension, Interim Master Plan
1832:
Northern Suburbs Transit System, Currambine to Butler Extension, Interim Master Plan
1802:
Northern Suburbs Transit System, Currambine to Butler Extension, Interim Master Plan
1772:
Northern Suburbs Transit System, Currambine to Butler Extension, Interim Master Plan
1742:
Northern Suburbs Transit System, Currambine to Butler Extension, Interim Master Plan
1712:
Northern Suburbs Transit System, Currambine to Butler Extension, Interim Master Plan
1682:
Northern Suburbs Transit System, Currambine to Butler Extension, Interim Master Plan
2727: 2605: 2597: 2409: 620: 441: 320: 57: 1056:
Transport 2000 – A Perth Study, Northern Suburbs Rapid Transit Study (File 8722/1)
785:
In the end, options for the financing of the purchase came down to two companies,
627:, Collier Pass, Joondalup Drive/Shenton Avenue (Double Segment), and Moore Drive; 2637: 2613: 895:
The purchase and delivery of new rolling stock at a cost of $ 23 million (2000).
697:
The first stage of the project was expected to be operation by the end of 1992.
809:, made a recommendation to State Cabinet that the financing package offered by 2845: 2840: 2320: 533: 366: 302: 297: 287: 221:
lack of the then government's commitment to transport in the northern corridor
133: 61: 1536:
Northern Suburbs Transit System: Fitzgerald Street Bus Bridge: Interim Report
762:
car park, and a number of buildings, would have to be compulsorily acquired.
132:
Determine people's overall beliefs and attitudes about and expectations from
2742: 2275: 806: 794: 35: 657:
Stations to be constructed as part of the first stage of the project were:
64:
transport network since the line's opening to passengers on 21 March 1993.
2712: 775: 315: 142:
Ascertain attitudes towards the concept of a transport liaison committee;
805:
On 29 April 1991, after much deliberation, then Minister for Transport,
1029: 1003:
to undertake preparation of the master plan for that segment of works.
810: 786: 860:
Acquisition of relevant lands, funded from the 2000/2001 state budget;
705:
A station to be constructed as part of the projects second stage was:
605:
Construction of three road and railway bridges at Vincent, Powis, and
280:
Preliminary studies evaluated a number of possible options including:
2055:"Carpenter promises to extend the Northern Suburbs Railway to Butler" 160:
transport system as it currently stood as either poor or very poor.
602:
New footbridges at Oxford Street, Britannia Road and Leeder Street;
56:
government in the late 1980s, and its main feature project was the
551:
While the original project to construct the line was known as the
308: 16:
Rail service for the northern suburbs of Perth, Western Australia
2279: 964:
Merriwa, a "walk on" (no parking, no bus transfers) station at
1131:
Liaison Committee Research: North West Corridor Research Phase
915:
bus/car, and to better integrate with the surrounding suburb.
30:
is the name given to the project initiated and funded by the
2085:"Preparations for Clarkson-Jindalee rail extension steps up" 178: 151:
To obtain specific demographic information from respondents.
869:
Construction of the Clarkson Station and associated works;
577:
The proposed rail line would run along the centre of the
565:
Northern Suburbs Transit System § Railcar financing
2172:"$ 441m commitment to make Yanchep rail line a reality" 2061:. Australian Broadcasting Corporation. 13 August 2008. 1371:
Northern Suburbs Transit System: Transport Study Report
423:
Dunwood (named for its location between the suburbs of
1094:. Institute for Sustainability and Technology Policy, 145:
Measure interest in participation in such a committee;
1158: 1156: 1154: 1152: 630:
Replacement of existing pedestrian level crossing at
536:
for the line was driven on 14 November 1989, by then
2867:
Passenger rail transport in Perth, Western Australia
1637: 1635: 1633: 1631: 1092:"Perth And Fremantle, A Hesitant Start in Australia" 2833: 2812: 2786: 2751: 2705: 2678: 2671: 2651: 2625: 2582: 2573: 2528: 2507: 2491: 2451: 2425: 2418: 2365: 2338: 2329: 1995: 1993: 1629: 1627: 1625: 1623: 1621: 1619: 1617: 1615: 1613: 1611: 1863: 1861: 1859: 1857: 1209:Northern Suburbs Rapid Transit Study (File 8722/1) 385:The locations of possible station sites included: 41:services to the northern corridor of metropolitan 1377:: Urban Rail Electrification Steering Committee, 1050: 1048: 774:When the project commenced, it was believed that 766:route to the abandoned Fitzgerald Street option. 1962: 1960: 1958: 1956: 1954: 879:Construction of a road bridge at Hester Avenue; 724:Other possible future stations sites included: 265: 236: 1676: 1674: 1672: 1670: 1668: 1203: 1201: 1199: 1197: 1195: 1193: 1191: 1189: 971:Butler, a bus transfer station at Lukin Drive. 2291: 1085: 1083: 1081: 709:North Joondalup, which later became known as 365:In his response, then Minister for Transport 186:Public Transport for Perth’s Northern Suburbs 164:Public Transport for Perth’s Northern Suburbs 23:, also known as the Northern Suburbs Railway. 8: 2043:on 28 August 2007 – via New MetroRail. 1568:: Bruechle Gilcrist and Evans Pty Ltd. 1988. 1542:: Bruechle Gilcrist and Evans Pty Ltd. 1988. 1512:: The Urban Rail Electrification Committee, 1365: 1363: 1361: 1359: 1357: 1355: 168:In its 1986 election campaign platform, the 1500: 1498: 1496: 1494: 1398: 1396: 728:Oxford Street (which later became known as 2675: 2579: 2422: 2335: 2298: 2284: 2276: 1649:: Western Australian Government Railways, 1492: 1490: 1488: 1486: 1484: 1482: 1480: 1478: 1476: 1474: 1411:State Records Office of Western Australia 1344:State Records Office of Western Australia 1321:State Records Office of Western Australia 1284:State Records Office of Western Australia 1250:State Records Office of Western Australia 1223:State Records Office of Western Australia 1178:State Records Office of Western Australia 1125: 1123: 1121: 1119: 1117: 1070:State Records Office of Western Australia 584:The proposed project initially included: 440:Northern Perimeter Highway (now known as 1301: 1299: 1297: 1295: 588:29.2 km of electric rail line from 503:of Modular Commuting Systems, was for a 2039:. June 2000. p. 73. Archived from 1267: 1265: 1263: 1261: 1238:Nicholson, Brendan (5 June 1988). "New 1044: 619:Construction of tunnels at Roe Street, 2346:Western Australian Government Railways 2145:"Butler Station construction complete" 564: 2212:from the original on 26 February 2021 2147:. WA State Government. Archived from 612:Construction of a new road bridge at 244:Opposition Leader Barry MacKinnon to 7: 2125:from the original on 6 December 2010 2065:from the original on 13 January 2015 882:Construction of a new rail depot at 505:"Personal Vehicle Fast Track System" 259:and Environment Minister during the 83:extension which was built as far as 2499:List of Transperth railway stations 599:The construction of seven stations; 49:. The project was commenced by the 1754:Pg. 55-56, 65, 67-71, Accessed at 1427:Perth - Joondalup Railway Act 1989 515:Linear induction-based rail system 495:Personal Vehicle Fast Track System 14: 2238:. Government of Western Australia 1403:"Raise rail, says Kingsley man". 872:Construction of a rail bridge at 609:Roads within the freeway reserve; 211:At the time, members of the then 2182:from the original on 14 May 2020 2170:Pond, Laura (7 September 2017). 1449:"History at a Glance, 1976-2000" 961:-only station at Wishart Street; 910:Relocation of Currambine Station 829:Currambine to Clarkson Extension 499:One proposal, from Tom Proctor, 2659:List of Transperth bus stations 2541:Northern Suburbs Transit System 2037:Government of Western Australia 2009:Government of Western Australia 1976:Government of Western Australia 1937:Government of Western Australia 1907:Government of Western Australia 1877:Government of Western Australia 1840:Government of Western Australia 1810:Government of Western Australia 1780:Government of Western Australia 1750:Government of Western Australia 1720:Government of Western Australia 1690:Government of Western Australia 1651:Government of Western Australia 1514:Government of Western Australia 1435:Government of Western Australia 1379:Government of Western Australia 1315:Government of Western Australia 1217:Government of Western Australia 1172:Government of Western Australia 1064:Government of Western Australia 553:Northern Suburbs Transit System 32:Government of Western Australia 28:Northern Suburbs Transit System 2232:"Yanchep Line Officially Open" 321:Automated people mover systems 181:150,000 (1987) for the study. 101:Transport 2000 – A Perth Study 1: 2633:List of Transperth bus routes 2178:. Community Newspaper Group. 2091:. 22 May 2007. Archived from 640:Passenger Information Systems 509:Campbelltown, New South Wales 2686:Metropolitan Transport Trust 2590:Metropolitan Transport Trust 983:Clarkson to Butler extension 749:Fitzgerald Street Bus Bridge 347:east of the Mitchell Freeway 344:west of the Mitchell Freeway 1215:: Department of Transport, 1090:Prof. Peter Newman (2000). 1062:: Department of Transport, 1017:Butler to Yanchep extension 284:Buses on a separate roadway 257:Liberal Member for Kingsley 2888: 2643:Perth Central Area Transit 2354:Public Transport Authority 2316:Public Transport Authority 2119:Public Transport Authority 2089:Public Transport Authority 1453:Public Transport Authority 1336:"Liberals against train". 1001:Public Transport Authority 562: 18: 2311: 2306:Public transport in Perth 1137:: Donovan Research. 1987. 634:with a Pedestrian Bridge; 87:in 2004, and extended to 2202:"Yanchep Rail Extension" 2005:Perth, Western Australia 1972:Perth, Western Australia 1933:Perth, Western Australia 1903:Perth, Western Australia 1873:Perth, Western Australia 1836:Perth, Western Australia 1806:Perth, Western Australia 1776:Perth, Western Australia 1746:Perth, Western Australia 1716:Perth, Western Australia 1686:Perth, Western Australia 1647:Perth, Western Australia 1588:"Perth Arena Bus Bridge" 1566:Perth, Western Australia 1540:Perth, Western Australia 1510:Perth, Western Australia 1431:Perth, Western Australia 1375:Perth, Western Australia 1311:Perth, Western Australia 1213:Perth, Western Australia 1168:Perth, Western Australia 1135:Perth, Western Australia 1060:Perth, Western Australia 949:Further station planning 823:Mallesons Stephen Jaques 19:Not to be confused with 2560:Level Crossing Removals 1433:: State Law Publisher, 107:By the late 1980s, the 2536:Fremantle line closure 2208:. MetroNET Taskforce. 1008:Nowergup railway depot 979:has been constructed. 940:Parking and Facilities 850:and associated works. 720:Future Station options 521:linear induction motor 463:Scarborough Beach Road 278: 250: 170:Australian Labor Party 45:, the capital city of 34:to provide high-speed 2825:Rockingham Light Rail 2804:Trolleybuses in Perth 1242:plan for city link". 975:As of 2023, only the 848:Mandurah railway line 735:Near Wishart Street, 563:Further information: 487:Alternate suggestions 2733:Shelley Taylor-Smith 2694:Captain Cook Cruises 2013:Pg. 37, Accessed at 1980:Pg. 39, Accessed at 1941:Pg. 40, Accessed at 1911:Pg. 10, Accessed at 1784:Pg. 74, Accessed at 1724:Pg. 89, Accessed at 528:Enabling legislation 378:1989 Transport Study 1881:Pg. 9, Accessed at 1844:Pg. 3, Accessed at 1814:Pg. 4, Accessed at 1694:Pg. 1, Accessed at 1338:The West Australian 1244:The West Australian 1139:Pg. 1, Accessed at 435:Warwick Bus Station 272:Cheryl Edwardes to 184:The study entitled 2820:Metro Area Express 2794:Trams in Fremantle 2115:"Media Statements" 2015:J S Battye Library 1982:J S Battye Library 1943:J S Battye Library 1913:J S Battye Library 1883:J S Battye Library 1846:J S Battye Library 1816:J S Battye Library 1786:J S Battye Library 1756:J S Battye Library 1726:J S Battye Library 1696:J S Battye Library 1657:J S Battye Library 1572:J S Battye Library 1546:J S Battye Library 1520:J S Battye Library 1385:J S Battye Library 1340:. 23 January 1989. 1280:. 2 February 1988. 1141:J S Battye Library 1096:Murdoch University 993:Alannah MacTiernan 760:Perth City Council 701:Stage Two Stations 653:Stage One Stations 335:West Coast Highway 292:O-bahn in Adelaide 226:Opposition Leader 21:Riverline (Hobart) 2854: 2853: 2782: 2781: 2667: 2666: 2569: 2568: 2487: 2486: 2394:Morley–Ellenbrook 2095:on 31 August 2007 1317:. September 1989. 1174:. September 1989. 931:New Railway Depot 770:Railcar financing 607:Scarborough Beach 594:Joondalup Station 501:Managing Director 123:The case for rail 47:Western Australia 2879: 2698: 2690: 2676: 2618: 2610: 2602: 2594: 2580: 2423: 2358: 2350: 2336: 2300: 2293: 2286: 2277: 2272: 2248: 2247: 2245: 2243: 2228: 2222: 2221: 2219: 2217: 2198: 2192: 2191: 2189: 2187: 2167: 2161: 2160: 2158: 2156: 2141: 2135: 2134: 2132: 2130: 2111: 2105: 2104: 2102: 2100: 2081: 2075: 2074: 2072: 2070: 2051: 2045: 2044: 2027: 2021: 2012: 1997: 1988: 1979: 1964: 1949: 1940: 1925: 1919: 1910: 1895: 1889: 1880: 1865: 1852: 1843: 1828: 1822: 1813: 1798: 1792: 1783: 1768: 1762: 1753: 1738: 1732: 1723: 1708: 1702: 1693: 1678: 1663: 1654: 1639: 1606: 1605: 1603: 1601: 1592: 1584: 1578: 1569: 1558: 1552: 1543: 1532: 1526: 1517: 1502: 1469: 1468: 1466: 1464: 1459:on 30 April 2007 1455:. Archived from 1445: 1439: 1438: 1423: 1417: 1408: 1400: 1391: 1382: 1367: 1350: 1341: 1333: 1327: 1318: 1303: 1290: 1281: 1269: 1256: 1247: 1235: 1229: 1220: 1205: 1184: 1175: 1160: 1147: 1138: 1127: 1112: 1111: 1109: 1107: 1098:. Archived from 1087: 1076: 1067: 1052: 874:Burns Beach Road 579:Mitchell Freeway 559:Original Project 459:McDonald Street; 412:Whitfords Avenue 390:Burns Beach Road 340:Mitchell Freeway 290:(similar to the 276: 248: 232:Mitchell Freeway 109:Mitchell Freeway 70:Mitchell Freeway 2887: 2886: 2882: 2881: 2880: 2878: 2877: 2876: 2857: 2856: 2855: 2850: 2829: 2808: 2787:Former services 2778: 2747: 2701: 2696: 2688: 2663: 2647: 2621: 2616: 2608: 2600: 2592: 2565: 2551:Perth City Link 2524: 2503: 2483: 2447: 2414: 2361: 2356: 2348: 2325: 2307: 2304: 2269: 2260: 2257: 2255:Further reading 2252: 2251: 2241: 2239: 2230: 2229: 2225: 2215: 2213: 2200: 2199: 2195: 2185: 2183: 2169: 2168: 2164: 2154: 2152: 2143: 2142: 2138: 2128: 2126: 2113: 2112: 2108: 2098: 2096: 2083: 2082: 2078: 2068: 2066: 2053: 2052: 2048: 2029: 2028: 2024: 1999: 1998: 1991: 1966: 1965: 1952: 1927: 1926: 1922: 1897: 1896: 1892: 1867: 1866: 1855: 1830: 1829: 1825: 1800: 1799: 1795: 1770: 1769: 1765: 1740: 1739: 1735: 1710: 1709: 1705: 1680: 1679: 1666: 1641: 1640: 1609: 1599: 1597: 1590: 1586: 1585: 1581: 1560: 1559: 1555: 1534: 1533: 1529: 1504: 1503: 1472: 1462: 1460: 1447: 1446: 1442: 1425: 1424: 1420: 1402: 1401: 1394: 1369: 1368: 1353: 1335: 1334: 1330: 1305: 1304: 1293: 1274:a $ 41m mistake 1271: 1270: 1259: 1237: 1236: 1232: 1207: 1206: 1187: 1162: 1161: 1150: 1129: 1128: 1115: 1105: 1103: 1102:on 16 June 2007 1089: 1088: 1079: 1054: 1053: 1046: 1041: 1028:, Eglinton and 1019: 985: 951: 942: 933: 912: 831: 780:A-series trains 772: 751: 722: 703: 655: 632:Milligan Street 625:Joondalup Drive 614:Ocean Reef Road 567: 561: 549: 530: 517: 497: 489: 450:Wishart Street; 406:Ocean Reef Road 380: 356:Alexander Drive 277: 271: 249: 243: 228:Barry MacKinnon 166: 125: 97: 24: 17: 12: 11: 5: 2885: 2883: 2875: 2874: 2869: 2859: 2858: 2852: 2851: 2849: 2848: 2843: 2837: 2835: 2831: 2830: 2828: 2827: 2822: 2816: 2814: 2810: 2809: 2807: 2806: 2801: 2799:Trams in Perth 2796: 2790: 2788: 2784: 2783: 2780: 2779: 2777: 2776: 2771: 2769:Elizabeth Quay 2766: 2761: 2759:Barrack Street 2755: 2753: 2749: 2748: 2746: 2745: 2740: 2738:Phillip Pendal 2735: 2730: 2725: 2720: 2715: 2709: 2707: 2703: 2702: 2700: 2699: 2697:(1995–present) 2691: 2682: 2680: 2673: 2669: 2668: 2665: 2664: 2662: 2661: 2655: 2653: 2649: 2648: 2646: 2645: 2640: 2635: 2629: 2627: 2623: 2622: 2620: 2619: 2617:(1996–present) 2611: 2609:(1996–present) 2603: 2601:(1996–present) 2595: 2586: 2584: 2577: 2571: 2570: 2567: 2566: 2564: 2563: 2553: 2548: 2543: 2538: 2532: 2530: 2529:Infrastructure 2526: 2525: 2523: 2522: 2517: 2511: 2509: 2505: 2504: 2502: 2501: 2495: 2493: 2489: 2488: 2485: 2484: 2482: 2481: 2476: 2471: 2466: 2461: 2455: 2453: 2449: 2448: 2446: 2445: 2440: 2435: 2429: 2427: 2420: 2416: 2415: 2413: 2412: 2407: 2402: 2397: 2390: 2385: 2380: 2375: 2369: 2367: 2363: 2362: 2360: 2359: 2357:(2003–present) 2351: 2342: 2340: 2333: 2327: 2326: 2324: 2323: 2318: 2312: 2309: 2308: 2305: 2303: 2302: 2295: 2288: 2280: 2274: 2273: 2267: 2256: 2253: 2250: 2249: 2223: 2193: 2162: 2136: 2106: 2076: 2046: 2022: 1989: 1950: 1920: 1890: 1853: 1823: 1793: 1763: 1733: 1703: 1664: 1607: 1595:Georgiou Group 1579: 1553: 1527: 1470: 1440: 1418: 1407:. 25 May 1989. 1405:Wanneroo Times 1392: 1351: 1328: 1291: 1278:The Australian 1257: 1230: 1185: 1148: 1113: 1077: 1043: 1042: 1040: 1037: 1018: 1015: 991:. Previously, 984: 981: 977:Butler Station 973: 972: 969: 962: 950: 947: 941: 938: 932: 929: 911: 908: 897: 896: 893: 890: 887: 880: 877: 870: 867: 864: 861: 858: 830: 827: 800:Cayman Islands 771: 768: 750: 747: 746: 745: 740: 733: 721: 718: 714: 713: 702: 699: 695: 694: 689: 683: 677: 671: 665: 654: 651: 642: 641: 638: 635: 628: 617: 610: 603: 600: 597: 572:A-series train 560: 557: 548: 545: 529: 526: 516: 513: 496: 493: 488: 485: 473: 472: 466: 460: 457: 451: 448: 447:Erindale Road; 445: 438: 432: 421: 418:Hepburn Avenue 415: 409: 403: 397: 379: 376: 359: 358: 353: 348: 345: 342: 337: 324: 323: 318: 314:High-capacity 312: 305: 300: 295: 285: 274:The Australian 269: 246:The Australian 241: 165: 162: 153: 152: 149: 146: 143: 140: 137: 124: 121: 117:car dependence 96: 93: 15: 13: 10: 9: 6: 4: 3: 2: 2884: 2873: 2870: 2868: 2865: 2864: 2862: 2847: 2844: 2842: 2839: 2838: 2836: 2832: 2826: 2823: 2821: 2818: 2817: 2815: 2811: 2805: 2802: 2800: 2797: 2795: 2792: 2791: 2789: 2785: 2775: 2772: 2770: 2767: 2765: 2762: 2760: 2757: 2756: 2754: 2750: 2744: 2741: 2739: 2736: 2734: 2731: 2729: 2726: 2724: 2721: 2719: 2716: 2714: 2711: 2710: 2708: 2704: 2695: 2692: 2687: 2684: 2683: 2681: 2677: 2674: 2670: 2660: 2657: 2656: 2654: 2650: 2644: 2641: 2639: 2636: 2634: 2631: 2630: 2628: 2624: 2615: 2612: 2607: 2604: 2599: 2596: 2591: 2588: 2587: 2585: 2581: 2578: 2576: 2572: 2561: 2557: 2554: 2552: 2549: 2547: 2546:New MetroRail 2544: 2542: 2539: 2537: 2534: 2533: 2531: 2527: 2521: 2518: 2516: 2513: 2512: 2510: 2506: 2500: 2497: 2496: 2494: 2490: 2480: 2479:ADL/ADC class 2477: 2475: 2474:ADK/ADB class 2472: 2470: 2467: 2465: 2462: 2460: 2457: 2456: 2454: 2450: 2444: 2441: 2439: 2436: 2434: 2431: 2430: 2428: 2424: 2421: 2419:Rolling stock 2417: 2411: 2408: 2406: 2403: 2401: 2398: 2396: 2395: 2391: 2389: 2386: 2384: 2381: 2379: 2376: 2374: 2371: 2370: 2368: 2364: 2355: 2352: 2347: 2344: 2343: 2341: 2337: 2334: 2332: 2328: 2322: 2319: 2317: 2314: 2313: 2310: 2301: 2296: 2294: 2289: 2287: 2282: 2281: 2278: 2270: 2264: 2259: 2258: 2254: 2237: 2233: 2227: 2224: 2211: 2207: 2203: 2197: 2194: 2181: 2177: 2173: 2166: 2163: 2151:on 7 May 2014 2150: 2146: 2140: 2137: 2124: 2120: 2116: 2110: 2107: 2094: 2090: 2086: 2080: 2077: 2064: 2060: 2056: 2050: 2047: 2042: 2038: 2034: 2033: 2026: 2023: 2020: 2016: 2010: 2006: 2002: 1996: 1994: 1990: 1987: 1983: 1977: 1973: 1969: 1963: 1961: 1959: 1957: 1955: 1951: 1948: 1944: 1938: 1934: 1930: 1924: 1921: 1918: 1914: 1908: 1904: 1900: 1894: 1891: 1888: 1884: 1878: 1874: 1870: 1864: 1862: 1860: 1858: 1854: 1851: 1847: 1841: 1837: 1833: 1827: 1824: 1821: 1817: 1811: 1807: 1803: 1797: 1794: 1791: 1787: 1781: 1777: 1773: 1767: 1764: 1761: 1757: 1751: 1747: 1743: 1737: 1734: 1731: 1727: 1721: 1717: 1713: 1707: 1704: 1701: 1697: 1691: 1687: 1683: 1677: 1675: 1673: 1671: 1669: 1665: 1662: 1658: 1652: 1648: 1644: 1638: 1636: 1634: 1632: 1630: 1628: 1626: 1624: 1622: 1620: 1618: 1616: 1614: 1612: 1608: 1596: 1589: 1583: 1580: 1577: 1573: 1567: 1563: 1557: 1554: 1551: 1547: 1541: 1537: 1531: 1528: 1525: 1521: 1515: 1511: 1507: 1501: 1499: 1497: 1495: 1493: 1491: 1489: 1487: 1485: 1483: 1481: 1479: 1477: 1475: 1471: 1458: 1454: 1450: 1444: 1441: 1436: 1432: 1428: 1422: 1419: 1416: 1412: 1406: 1399: 1397: 1393: 1390: 1386: 1380: 1376: 1372: 1366: 1364: 1362: 1360: 1358: 1356: 1352: 1349: 1345: 1339: 1332: 1329: 1326: 1322: 1316: 1312: 1308: 1302: 1300: 1298: 1296: 1292: 1289: 1285: 1279: 1275: 1268: 1266: 1264: 1262: 1258: 1255: 1251: 1245: 1241: 1234: 1231: 1228: 1224: 1218: 1214: 1210: 1204: 1202: 1200: 1198: 1196: 1194: 1192: 1190: 1186: 1183: 1179: 1173: 1169: 1165: 1159: 1157: 1155: 1153: 1149: 1146: 1142: 1136: 1132: 1126: 1124: 1122: 1120: 1118: 1114: 1101: 1097: 1093: 1086: 1084: 1082: 1078: 1075: 1071: 1065: 1061: 1057: 1051: 1049: 1045: 1038: 1036: 1033: 1031: 1027: 1022: 1016: 1014: 1011: 1009: 1004: 1002: 998: 994: 990: 982: 980: 978: 970: 967: 966:Hester Avenue 963: 960: 959:park-and-ride 956: 955: 954: 948: 946: 939: 937: 930: 928: 924: 920: 916: 909: 907: 903: 900: 894: 891: 888: 885: 881: 878: 875: 871: 868: 865: 862: 859: 856: 855: 854: 851: 849: 844: 841: 837: 828: 826: 824: 819: 815: 812: 808: 803: 801: 796: 792: 791:Allco Leasing 788: 783: 781: 777: 769: 767: 763: 761: 755: 748: 744: 741: 738: 734: 731: 727: 726: 725: 719: 717: 712: 708: 707: 706: 700: 698: 693: 690: 687: 684: 681: 678: 675: 672: 669: 666: 663: 660: 659: 658: 652: 650: 646: 639: 636: 633: 629: 626: 622: 618: 615: 611: 608: 604: 601: 598: 595: 591: 590:Perth Station 587: 586: 585: 582: 580: 575: 573: 566: 558: 556: 554: 547:Project Scope 546: 544: 542: 541:Peter Dowding 539: 535: 527: 525: 522: 514: 512: 510: 506: 502: 494: 492: 486: 484: 480: 478: 470: 469:Oxford Street 467: 464: 461: 458: 455: 454:Cedric Street 452: 449: 446: 443: 439: 436: 433: 430: 426: 422: 419: 416: 413: 410: 407: 404: 401: 398: 395: 394:park-and-ride 391: 388: 387: 386: 383: 377: 375: 371: 368: 363: 357: 354: 352: 351:Wanneroo Road 349: 346: 343: 341: 338: 336: 333: 332: 331: 328: 322: 319: 317: 313: 311:on a guideway 310: 306: 304: 301: 299: 296: 293: 289: 288:Guided busway 286: 283: 282: 281: 275: 268: 264: 263:Government). 262: 258: 253: 247: 240: 235: 233: 229: 224: 222: 218: 214: 209: 207: 203: 199: 195: 190: 187: 182: 180: 175: 171: 163: 161: 157: 150: 147: 144: 141: 138: 135: 131: 130: 129: 122: 120: 118: 112: 110: 105: 102: 94: 92: 90: 86: 82: 78: 73: 71: 65: 63: 59: 55: 52: 48: 44: 40: 37: 33: 29: 22: 2872:Yanchep line 2774:Mends Street 2764:Coode Street 2606:Swan Transit 2598:Path Transit 2540: 2392: 2240:. Retrieved 2235: 2226: 2214:. Retrieved 2205: 2196: 2184:. Retrieved 2175: 2165: 2153:. Retrieved 2149:the original 2139: 2127:. Retrieved 2109: 2097:. Retrieved 2093:the original 2079: 2067:. Retrieved 2058: 2049: 2041:the original 2031: 2025: 2000: 1967: 1928: 1923: 1898: 1893: 1868: 1831: 1826: 1801: 1796: 1771: 1766: 1741: 1736: 1711: 1706: 1681: 1655:Accessed at 1642: 1598:. Retrieved 1582: 1570:Accessed at 1561: 1556: 1544:Accessed at 1535: 1530: 1518:Accessed at 1505: 1461:. Retrieved 1457:the original 1443: 1426: 1421: 1409:Accessed at 1404: 1383:Accessed at 1370: 1342:Accessed at 1331: 1319:Accessed at 1306: 1282:Accessed at 1273: 1248:Accessed at 1239: 1233: 1221:Accessed at 1208: 1176:Accessed at 1163: 1130: 1104:. Retrieved 1100:the original 1068:Accessed at 1055: 1034: 1023: 1020: 1012: 1005: 997:state budget 986: 974: 952: 943: 934: 925: 921: 917: 913: 904: 901: 898: 852: 832: 820: 816: 804: 784: 773: 764: 756: 752: 723: 715: 704: 696: 656: 647: 643: 621:Hodges Drive 583: 576: 568: 552: 550: 531: 518: 504: 498: 490: 481: 474: 442:Reid Highway 392:(to include 384: 381: 372: 364: 360: 329: 325: 279: 266: 254: 251: 237: 225: 220: 210: 191: 185: 183: 173: 172:stated that 167: 158: 154: 126: 113: 106: 100: 98: 74: 66: 58:Yanchep line 27: 25: 2723:Princess II 2718:Countess II 2689:(1960–1995) 2638:CircleRoute 2614:Transdev WA 2593:(1958–1998) 2515:Claisebrook 2349:(1890–2003) 2242:7 September 2216:17 February 2186:7 September 2129:29 November 2069:23 December 1240:super buses 730:Leederville 662:Glendalough 2861:Categories 2846:SmartRider 2841:MultiRider 2321:Transperth 2268:0646011480 1600:4 February 1039:References 957:Gwelup, a 711:Currambine 367:Bob Pearce 307:Automated 303:Heavy rail 298:Light rail 239:residents. 134:Transperth 119:in Perth. 77:Currambine 62:Transperth 2834:Ticketing 2813:Proposals 2728:Georgette 2679:Operators 2583:Operators 2469:ADX class 2464:ADG class 2459:ASA class 2383:Fremantle 2339:Operators 2176:Perth Now 1272:"Highway 807:Pam Beggs 795:Australia 743:Greenwood 692:Joondalup 686:Edgewater 680:Whitfords 429:Greenwood 400:Joondalup 234:instead. 206:Karrinyup 91:in 2014. 36:passenger 2652:Stations 2626:Services 2556:Metronet 2520:Nowergup 2492:Stations 2443:C-series 2438:B-series 2433:A-series 2405:Thornlie 2388:Mandurah 2378:Armadale 2236:Metronet 2210:Archived 2206:MetroNET 2180:Archived 2123:Archived 2063:Archived 2059:ABC News 1106:15 April 999:for the 884:Nowergup 836:Nowergup 776:Westrail 668:Stirling 425:Duncraig 316:monorail 270:—  242:—  217:National 198:Duncraig 85:Clarkson 2752:Jetties 2706:Vessels 2426:Current 2410:Yanchep 2400:Midland 2373:Airport 2011:. 2000. 1978:. 2000. 1939:. 2000. 1909:. 2000. 1879:. 2000. 1842:. 2000. 1812:. 2000. 1782:. 2000. 1752:. 2000. 1722:. 2000. 1692:. 2000. 1653:. 1989. 1516:. 1991. 1437:. 1989. 1381:. 1989. 1219:. 1987. 1066:. 1987. 1030:Yanchep 1026:Alkimos 843:Liberal 811:Westpac 787:Westpac 674:Warwick 538:Premier 477:Innaloo 213:Liberal 95:History 51:Dowding 2743:Tricia 2508:Depots 2452:Former 2265:  2099:7 July 1463:5 June 989:Butler 737:Gwelup 309:trains 204:, and 194:Beldon 89:Butler 81:Butler 2713:Perth 2672:Ferry 2366:Lines 2331:Train 2155:7 May 2019:Perth 1986:Perth 1947:Perth 1917:Perth 1887:Perth 1850:Perth 1820:Perth 1790:Perth 1760:Perth 1730:Perth 1700:Perth 1661:Perth 1591:(PDF) 1576:Perth 1550:Perth 1524:Perth 1415:Perth 1389:Perth 1348:Perth 1325:Perth 1288:Perth 1254:Perth 1227:Perth 1182:Perth 1145:Perth 1074:Perth 968:; and 840:Court 739:; and 688:; and 534:spike 465:; and 261:Court 202:Balga 54:Labor 43:Perth 2263:ISBN 2244:2024 2218:2021 2188:2017 2157:2014 2131:2009 2101:2007 2071:2014 1602:2009 1465:2007 1108:2007 789:and 427:and 39:rail 26:The 2575:Bus 1276:". 592:to 179:A$ 79:to 2863:: 2234:. 2204:. 2174:. 2121:. 2117:. 2087:. 2057:. 2017:, 2003:. 1992:^ 1984:, 1970:. 1953:^ 1945:, 1931:. 1915:, 1901:. 1885:, 1871:. 1856:^ 1848:, 1834:. 1818:, 1804:. 1788:, 1774:. 1758:, 1744:. 1728:, 1714:. 1698:, 1684:. 1667:^ 1659:, 1645:. 1610:^ 1593:. 1574:, 1564:. 1548:, 1538:. 1522:, 1508:. 1473:^ 1451:. 1429:. 1413:, 1395:^ 1387:, 1373:. 1354:^ 1346:, 1323:, 1309:. 1294:^ 1286:, 1260:^ 1252:, 1225:, 1211:. 1188:^ 1180:, 1166:. 1151:^ 1143:, 1133:. 1116:^ 1080:^ 1072:, 1058:. 1047:^ 732:); 543:. 444:); 431:); 223:. 200:, 196:, 2562:) 2558:( 2299:e 2292:t 2285:v 2271:. 2246:. 2220:. 2190:. 2159:. 2133:. 2103:. 2073:. 1604:. 1467:. 1246:. 1110:. 886:; 876:; 682:; 676:; 670:; 664:; 623:/ 616:; 596:; 471:. 456:; 437:; 420:; 414:; 408:; 402:; 294:) 215:- 136:;

Index

Riverline (Hobart)
Government of Western Australia
passenger
rail
Perth
Western Australia
Dowding
Labor
Yanchep line
Transperth
Mitchell Freeway
Currambine
Butler
Clarkson
Butler
Mitchell Freeway
car dependence
Transperth
Australian Labor Party
A$
Beldon
Duncraig
Balga
Karrinyup
Liberal
National
Barry MacKinnon
Mitchell Freeway
The Australian
Liberal Member for Kingsley

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.

↑