Knowledge (XXG)

Bözberg Rail Tunnel

Source 📝

400:, the maximum tonnage of trains on the route is around 1,600 tonnes. However, during the 2010s, the original tunnel's loading gauge was deemed to be insufficient and that work would be necessary in order to realise ambitions for this corridor to provide a headroom of 4 metres (13 ft) throughout its length, allowing for the haulage of taller freight trains, resulting in a reduction in the numbers of lorries traversing the road network. Addressing the non-compliant Bözberg Tunnel has been referred to as the most major undertaking of the initiative; a further 20 tunnels also required enlargement work for the initiative, along with numerous platforms, overpasses, signalling systems, and electrical infrastructure. 420: 27: 641:, where it was subsequently used in restoration work at the Oberegg limestone quarry. Considerable care was paid in minimising the risks involved in working close to the original tunnel, which remained active throughout the boring process; accordingly, a series of continuous monitoring systems were active onsite at all times, along with emergency evacuation preparations. For extra protection during the last 60 meters of the TBM's boring, a temporary protection wall was deployed in the original tunnel. 260: 404:
gained favour instead. The new Bözberg Tunnel shall replace the old one. Following the completion of the new tunnel, the original bore shall be retained but be modified for access use to the new bore, which is intended for both service and rescue purposes in a safe manner. The modification work, which is planned to be completed during 2022, shall involve the construction of five cross-shafts for access between the new and old tunnels.
985: 973: 645:
required full waterproofing measures; the inner lining was heavily reinforced to withstand swelling by the surrounding ground in addition to water pressure. On 29 November 2017, the TBM achieved breakthrough in the new bore. During November 2019, work begun on laying the track, which is supported by slab-type
331:
During March 2016, construction commenced on the new Bözberg Tunnel, which runs roughly parallel to its predecessor. It is a considerably wider and longer tunnel, being able to accommodate trains up to a height of 4 metres (13 ft). The reason for its construction is to better accommodate larger
403:
Studies were conducted into proposed remedial work to expand the loading gauge, which found that such efforts would involve a six-year timeframe that would heavily impact existing traffic operations throughout; an alternative approach of constructing a larger second tunnel alongside the original
644:
Progress within the tunnel was relatively steady, despite varying geology along its path; the rate of advance was sometimes as high as 40 meters per day, achieve by crews working in two shifts of eight hours each per workday. The lining of the tunnel differs along its length, as only some areas
328:. The original tunnel was opened during 1875; it is set to be closed to rail traffic during 2020-2021 following the commissioning of its replacement, after which it shall be converted and retained for service and rescue purposes in respect to its successor. 637:(TBM); use of the TBM commenced during May 2017 following seven months of conventional excavation work. The excavated spoil was removed from the tunnel by rail, using three trains per day to transfer a daily average rate of 1,800 tonnes of material to 750: 889: 649:. On 6 February 2020, the final sleeper was laid, marking a major milestone in the tunnel's fitting-out process. Railway operations using the new tunnel are anticipated to begin during October 2020. 881: 923: 858: 995: 777: 796: 626:
350m. The new tunnel's northern portal is located at Effingen and the southern portal at Schinznach-Dorf. During July 2015, a contract was awarded to
466: 81: 1015: 633:
On 9 March 2016, construction of the new Bözberg Tunnel commenced. The majority of the excavation was conducted from the southern portal using a
697: 622:
The Swiss Federal Office of Transport permitted the construction of a new Bözberg railway tunnel, to parallel the existing one, at a cost of
718: 1020: 989: 977: 630:
to perform the construction of the new tunnel itself as well as any associated works. Preparatory work begun during October 2015.
850: 723: 1010: 816: 459: 74: 390: 419: 835: 26: 940: 438: 341: 309: 229: 53: 370:) tracks underground along a distance of 2,526 metres (8,287 ft). These tracks are electrified at 15 k 580: 540: 530: 386: 313: 188: 148: 137: 955: 924:"The new Bözberg Tunnel (Switzerland) – risk management and auxiliary measures for the TBM break-through" 634: 267:
Parts of this article (those related to old tunnel was replaced by new one in November 2020) need to be
374: 242: 332:
and heavier freight trains. The second Bözberg Rail Tunnel is scheduled to be opened during 2020.
693: 382: 234: 638: 448: 305: 63: 396:
The tunnel has become a key structure on the Gotthard freight corridor route, according to
646: 325: 317: 273:
Please help update this article to reflect recent events or newly available information.
345: 1004: 882:"SBB Bözberg railway tunnel contract delivers boost to transalpine rail freight" 623: 590: 452: 302: 198: 67: 713: 481: 468: 96: 83: 397: 984: 972: 627: 321: 295: 298: 665: 378: 371: 246: 239: 817:"Construction begins on Switzerland's new Bözberg railway tunnel" 385:. The alignment of the tunnel runs roughly parallel to the later 797:"New Bözberg Rail Tunnel: Start of Construction in Spring 2016" 778:"SBB Cargo removes excavated material Bözberg tunnel by train" 253: 996:
Geological longitudinal section of the Bözberg Rail Tunnel
810: 808: 806: 830: 828: 826: 751:"New Bözberg tunnel (1) – more freight carried by rail" 791: 789: 787: 589: 575: 567: 562: 554: 546: 536: 526: 518: 510: 505: 497: 458: 444: 434: 429: 228: 197: 183: 175: 170: 162: 154: 144: 133: 125: 117: 112: 73: 59: 49: 41: 36: 917: 915: 913: 911: 909: 907: 772: 770: 768: 424:New tunnel is built next to the old one (ca. 2017) 836:"Ground Breaking on Switzerland's Bözberg Tunnel" 692:. Verlag Schweers + Wall GmbH. 2012. p. 11. 8: 745: 743: 741: 412: 19: 16:Railway tunnel in the Swiss canton of Aargau 411: 18: 941:"Slab track in the Bözberg Tunnel stands" 657: 956:"Final sleeper laid in Bözberg tunnel" 922:M. Ramoni; R. Gallus; R. Iten (2019). 340:The tunnel forms a key element of the 838:. tunnelingonline.com. 11 March 2016. 7: 892:from the original on 15 October 2015 861:from the original on 15 October 2015 726:from the original on 15 October 2015 719:Historical Dictionary of Switzerland 857:. Simmons-Boardman Publishing Inc. 14: 954:Green, Anitra (5 February 2020). 851:"SBB to start work on new tunnel" 983: 971: 849:Green, Anitra (9 October 2015). 799:. tunnel-online.info. June 2015. 418: 258: 25: 815:Foley, Amanda (10 March 2016). 780:. railfreight.com. 31 May 2018. 1016:Railway tunnels in Switzerland 888:. Russell Publishing Limited. 880:Sadler, Katie (17 July 2015). 722:(in French). 14 October 2004. 576: 184: 140:, previous: Bötzbergbahn (BöB) 1: 929:. Taylor & Francis Group. 855:International Railway Journal 571:2,693 metres (8,835 ft) 179:2,526 metres (1.570 mi) 1037: 670:(Map). Swiss Confederation 1021:Tunnels completed in 1875 943:. Rhomberg. 6 March 2020. 417: 24: 819:. tunnellingjournal.com. 886:European Railway Review 413:New Bözberg Rail Tunnel 20:Old Bözberg Rail Tunnel 690:Eisenbahnatlas Schweiz 541:Swiss Federal Railways 531:Swiss Federal Railways 314:Swiss Federal Railways 149:Swiss Federal Railways 138:Swiss Federal Railways 635:tunnel boring machine 558:Passenger and freight 344:, carrying a pair of 166:Passenger and freight 992:at Wikimedia Commons 990:Bözberg Tunnel (new) 980:at Wikimedia Commons 978:Bözberg Tunnel (old) 342:Bözberg railway line 310:Bözberg railway line 97:47.46528°N 8.11694°E 31:South portal in 1875 1011:Transport in Aargau 478: /  414: 387:Bözberg Road Tunnel 292:Bözberg Rail Tunnel 93: /  21: 753:. amberggroup.com/ 482:47.4649°N 8.1164°E 129:2020 (rail tunnel) 42:Other name(s) 988:Media related to 976:Media related to 699:978-3-89494-130-7 620: 619: 383:overhead catenary 288: 287: 252: 251: 235:Overhead catenary 102:47.46528; 8.11694 1028: 987: 975: 960: 959: 951: 945: 944: 937: 931: 930: 928: 919: 902: 901: 899: 897: 877: 871: 870: 868: 866: 846: 840: 839: 832: 821: 820: 812: 801: 800: 793: 782: 781: 774: 763: 762: 760: 758: 747: 736: 735: 733: 731: 710: 704: 703: 686: 680: 679: 677: 675: 667:map.geo.admin.ch 662: 615: 613: 612: 608: 605: 597: 578: 493: 492: 490: 489: 488: 483: 479: 476: 475: 474: 471: 422: 415: 369: 367: 366: 362: 359: 351: 306:canton of Aargau 283: 280: 274: 262: 261: 254: 223: 221: 220: 216: 213: 205: 186: 108: 107: 105: 104: 103: 98: 94: 91: 90: 89: 86: 29: 22: 1036: 1035: 1031: 1030: 1029: 1027: 1026: 1025: 1001: 1000: 968: 963: 953: 952: 948: 939: 938: 934: 926: 921: 920: 905: 895: 893: 879: 878: 874: 864: 862: 848: 847: 843: 834: 833: 824: 814: 813: 804: 795: 794: 785: 776: 775: 766: 756: 754: 749: 748: 739: 729: 727: 714:"Bözberg (col)" 712: 711: 707: 700: 688: 687: 683: 673: 671: 664: 663: 659: 655: 610: 606: 603: 601: 600:4 ft  599: 595: 487:47.4649; 8.1164 486: 484: 480: 477: 472: 469: 467: 465: 464: 425: 410: 364: 360: 357: 355: 354:4 ft  353: 349: 338: 326:Schinznach-Dorf 308:. It takes the 284: 278: 275: 272: 263: 259: 237: 218: 214: 211: 209: 208:4 ft  207: 203: 101: 99: 95: 92: 87: 84: 82: 80: 79: 32: 17: 12: 11: 5: 1034: 1032: 1024: 1023: 1018: 1013: 1003: 1002: 999: 998: 993: 981: 967: 966:External links 964: 962: 961: 946: 932: 903: 872: 841: 822: 802: 783: 764: 737: 705: 698: 681: 656: 654: 651: 618: 617: 593: 587: 586: 583: 573: 572: 569: 565: 564: 560: 559: 556: 552: 551: 548: 544: 543: 538: 534: 533: 528: 524: 523: 520: 516: 515: 512: 508: 507: 503: 502: 499: 495: 494: 462: 456: 455: 446: 442: 441: 436: 432: 431: 427: 426: 423: 409: 406: 346:standard gauge 337: 334: 286: 285: 266: 264: 257: 250: 249: 232: 226: 225: 201: 195: 194: 191: 181: 180: 177: 173: 172: 168: 167: 164: 160: 159: 156: 152: 151: 146: 142: 141: 135: 131: 130: 127: 123: 122: 119: 115: 114: 110: 109: 77: 71: 70: 61: 57: 56: 51: 47: 46: 43: 39: 38: 34: 33: 30: 15: 13: 10: 9: 6: 4: 3: 2: 1033: 1022: 1019: 1017: 1014: 1012: 1009: 1008: 1006: 997: 994: 991: 986: 982: 979: 974: 970: 969: 965: 957: 950: 947: 942: 936: 933: 925: 918: 916: 914: 912: 910: 908: 904: 891: 887: 883: 876: 873: 860: 856: 852: 845: 842: 837: 831: 829: 827: 823: 818: 811: 809: 807: 803: 798: 792: 790: 788: 784: 779: 773: 771: 769: 765: 752: 746: 744: 742: 738: 725: 721: 720: 715: 709: 706: 701: 695: 691: 685: 682: 669: 668: 661: 658: 652: 650: 648: 642: 640: 636: 631: 629: 625: 596:1,435 mm 594: 592: 588: 584: 582: 574: 570: 566: 561: 557: 553: 549: 545: 542: 539: 535: 532: 529: 525: 522:November 2020 521: 517: 513: 509: 504: 500: 496: 491: 463: 461: 457: 454: 450: 447: 443: 440: 437: 433: 428: 421: 416: 407: 405: 401: 399: 394: 392: 388: 384: 380: 376: 373: 350:1,435 mm 347: 343: 335: 333: 329: 327: 323: 319: 315: 311: 307: 304: 300: 297: 293: 282: 279:November 2022 270: 265: 256: 255: 248: 244: 241: 236: 233: 231: 227: 204:1,435 mm 202: 200: 196: 192: 190: 182: 178: 174: 169: 165: 161: 157: 153: 150: 147: 143: 139: 136: 132: 128: 124: 120: 116: 111: 106: 78: 76: 72: 69: 65: 62: 58: 55: 52: 48: 45:Bözbergtunnel 44: 40: 35: 28: 23: 949: 935: 894:. Retrieved 885: 875: 863:. Retrieved 854: 844: 755:. Retrieved 728:. Retrieved 717: 708: 689: 684: 672:. Retrieved 666: 660: 643: 632: 621: 402: 395: 339: 330: 318:Bözberg Pass 291: 289: 276: 268: 591:Track gauge 485: / 460:Coordinates 453:Switzerland 408:2020 tunnel 391:A3 motorway 336:1875 tunnel 230:Electrified 199:Track gauge 100: / 75:Coordinates 68:Switzerland 1005:Categories 896:14 October 865:14 October 730:14 October 674:14 October 653:References 511:Work begun 470:47°27′54″N 316:under the 85:47°27′55″N 563:Technical 555:Character 506:Operation 473:8°06′59″E 398:SBB Cargo 171:Technical 163:Character 113:Operation 890:Archived 859:Archived 724:Archived 647:sleepers 628:Implenia 614: in 537:Operator 445:Location 430:Overview 368: in 322:Effingen 320:between 222: in 145:Operator 60:Location 37:Overview 639:Wildegg 609:⁄ 547:Traffic 439:Bözberg 389:on the 377:16 2/3 363:⁄ 312:of the 301:in the 296:railway 269:updated 245:16 2/3 217:⁄ 155:Traffic 88:8°7′1″E 54:Bözberg 757:1 July 696:  581:tracks 568:Length 519:Opened 501:Active 498:Status 449:Aargau 381:using 299:tunnel 189:tracks 176:Length 126:Closed 118:Opened 64:Aargau 927:(PDF) 527:Owner 303:Swiss 294:is a 134:Owner 898:2015 867:2015 759:2020 732:2015 694:ISBN 676:2015 550:Rail 514:2016 435:Line 324:and 290:The 238:15 k 158:Rail 121:1875 50:Line 624:SFr 579:of 577:No. 352:or 187:of 185:No. 1007:: 906:^ 884:. 853:. 825:^ 805:^ 786:^ 767:^ 740:^ 716:. 451:, 393:. 379:Hz 375:AC 247:Hz 243:AC 66:, 958:. 900:. 869:. 761:. 734:. 702:. 678:. 616:) 611:2 607:1 604:+ 602:8 598:( 585:2 372:V 365:2 361:1 358:+ 356:8 348:( 281:) 277:( 271:. 240:V 224:) 219:2 215:1 212:+ 210:8 206:( 193:2

Index


Bözberg
Aargau
Switzerland
Coordinates
47°27′55″N 8°7′1″E / 47.46528°N 8.11694°E / 47.46528; 8.11694
Swiss Federal Railways
Swiss Federal Railways
tracks
Track gauge
Electrified
Overhead catenary
V
AC
Hz
railway
tunnel
Swiss
canton of Aargau
Bözberg railway line
Swiss Federal Railways
Bözberg Pass
Effingen
Schinznach-Dorf
Bözberg railway line
standard gauge
V
AC
Hz
overhead catenary

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.