Knowledge (XXG)

Burbo Bank Offshore Wind Farm

Source 📝

572: 39: 585: 738: 3106: 752: 381: 724: 3094: 3118: 1411: 480:; to the south and to the west, reducing potential impact on recreational sailing activities and on certain species of sea bird, and due to potential conflicts with ship anchoring sites; also reducing the visual impact from land. In April 2010 the Crown Estate awarded an area of 40 km (15 sq mi) for lease. 2278: 1420: 537:
Initial expectations were for construction to start in early 2015, and be complete by early 2017, subject to final specifications; neither foundation nor turbine type was specified, an offshore substation to step up the inter turbine voltage (either 33 or 66 kV) to an export voltage of either 132 or
2222: 891:
EDF Energies Nouvelles' offshore ambitions are closer to fruition in Britain, where work should start next year on the 90 MW Burbo Offshore plant in Liverpool Bay. The project is being developed by Seascape Energy Ltd, owned jointly by EDF Energies Nouvelles and Danish electricity company Elsam,
483:
Water depths in the area are between 6 and 13 metres (20 and 43 ft). The sea bed consisted primarily of sand. The underlying geology is sand overlaying clay overlaying mudstone. Samples within the turbine area showed sand followed by clay down to around 30m before weak mudstone was found.
348:
coastline) was selected due to shallow water depths (0.5 to 8m at low tide), high wind speeds ~7 m/s (23 ft/s), and a generally favourable location including proximity to an electrical grid connection. Initial expectations were for a 30 × 3 MW turbine wind farm, with
2307: 2249: 2289: 2231: 604:
was the preferred model for the development, and made preliminary agreements to buy 32 units in August 2014. The order for 32 turbines was confirmed in December 2014, the first series production of the type. The nacelles are to be produced at the former
427:
The facility began generating power in July 2007, and the wind farm was officially inaugurated on 18 October 2007, and the facility was commercially operational by the end of 2007; the capital cost of developing the wind farm was €181 million. Its
471:
identified Burbo Bank as a potential site and began consultation on a ~90 km (35 sq mi) extension westwards of the original wind farm. Between 2009 and 2010 the area of the site was reduced to the north increase clearance from the
2318: 353:
on a site of approximately 10 km (3.9 sq mi). An electrical connection to the mainland grid was to be made by a seabed cable running southeast to Wirral, followed by a ~3.5 km underground cable to a substation at
2260: 3164: 1210: 1568:
State aid SA.38758 (2014/N), SA.38759 (2014/N), SA.38761 (2014/N), SA.38763 (2014/N) & SA.38812 (2014/N) – United Kingdom - Support for five Offshore Wind Farms: Walney, Dudgeon, Hornsea, Burbo Bank and
419:
The contractor for the substation was EDF Energy Contracting, cable installation was by McNicholas Construction Services Ltd. (onshore) and Submarine Cable & Pipe (offshore), with cables supplied by
2201: 1631: 1041: 2005:
Aldersey-Williams, John; Broadbent, Ian; Strachan, Peter (2019). "Better estimates of LCOE from audited accounts – A new methodology with examples from United Kingdom offshore wind and CCGT".
2383: 1149: 2071: 1133: 443:. During summer 2010 Siemens decided to change the blade bearings on all 25 turbines as a pre-emptive measure after corrosion was found in blade bearings found on other sites. 487:
The initial cable export route and grid connection identified was one making landfall near to the existing Burbo Bank land connection, and connected to a 275 kV substation in
2423: 2102: 571: 3067: 2766: 1334: 772: 1218: 3174: 2491: 1586: 1070: 2376: 3144: 1316: 2207: 1247:
Aldersey-Williams, John (2019). "Better estimates of LCOE from audited accounts – A new methodology with examples from United Kingdom offshore wind and CCGT".
710:
After around 20–25 years of operation the wind farm would be expected to be decommissioned, including removal off all offshore components above seabed level.
1639: 777: 439:
was between 32 and 35%. In 2009 the whole wind farm was put out of action for 4 weeks due to a failure in the underground electrical cable connecting to the
1049: 1413:
Summary of Geotechnical Investigations for the Burbo Bank Extension Project and Comparison of These to Preliminary Geophysical Survey and Interpretation
1103: 3110: 2413: 2369: 3121: 2169: 869:
Enxco - a subsidiary of French energy company EdF, bought out the interests of small developer Wind Prospect in their joint development at Burbo Bank
2806: 3169: 1957: 3154: 336:
In September 2002 SeaScape Energy ( Zilkha Renewable Energy, enXco A/S, Wind Prospect Ltd. joint venture.) submitted an application to develop a
1157: 2408: 275: 1012: 2082: 3159: 424:. Inter turbine and grid connection to the substation was at 33 kV, with voltage step up to 132 kV at the substation for grid connection. 1830: 2901: 1848: 1783: 1736: 373:
was selected as the turbine supplier, with 25 3.6 MW turbines ordered at a cost of over €90 million. In December 2005 Dong Energy (now
649: 647:
obtained the contract to construct wind turbine foundations and structures, with transition pieces to be manufactured by Bladt/EEW jv
2851: 2816: 2108: 1895: 1537: 504: 88: 328:
3.6 MW turbines was constructed from 2005, and officially opened in 2007. A further 32 8 MW turbines were constructed in 2016–17.
38: 3027: 2836: 2392: 1695: 1913: 2721: 1342: 1613: 959: 361:
In 2003 EDF subsidiary enXco bought the interests of Wind Prospect in the project, the project became a joint venture between
3149: 2921: 2861: 523: 345: 1765: 2666: 508: 440: 1592: 1079: 527: 2403: 1715: 688:'s two 200 tonne transformers were delivered by Collett & Sons Ltd to the onshore substation via 550 Tonne capacity 514:
The planned export cable route crossed a number of pre-existing cables and pipelines: a set of pipelines related to the
926: 2896: 2521: 1301: 767: 553:
of £150 per MWh (2012 prices). DONG made the decision to proceed with construction of the wind farm in December 2014.
464: 1877: 538:
275 kV, connection to the National Grid would be made at 400 kV, stepped up at an onshore substation at Bodelwyddan.
2957: 2926: 2801: 703:
The first 8MW turbine was installed in September 2016. The wind farm extension was commissioned in April 2017. Its
584: 628:; DONG Energy having agreed to a long-term supply arrangement for inter array cabling with Nexans in August 2014. 2856: 2811: 2781: 1566: 860: 881: 2967: 2826: 2791: 2731: 2711: 2631: 2551: 2546: 632: 988: 3072: 2998: 2706: 2671: 2641: 2541: 2526: 2123: 1111: 757: 542: 317:. It consists of an original 90 MW wind farm commissioned in 2007 and a 258 MW extension completed in 2017. 2346: 3077: 3003: 2891: 2686: 2656: 2636: 2601: 2175: 1661: 366: 2158: 842: 3008: 2942: 2716: 2651: 2616: 2596: 2581: 2556: 606: 492: 128: 3049: 17: 1812: 409: 2886: 2701: 2691: 2571: 2536: 1317:"EXCLUSIVE: Burbo Bank wind farm off Wirral shore out of action for four weeks after cabling failure" 654: 320:
The wind farm was developed in the 2000s by SeaScape Energy, which was acquired by DONG Energy (now
2871: 2747: 2696: 2661: 2531: 2516: 2511: 2506: 2446: 1020: 737: 557: 374: 350: 321: 150: 3042: 2906: 2786: 2726: 2606: 2032: 1676: 1274: 905: 370: 325: 241: 173: 1292: 522:
to landfall were crossed in the Mid-Hoyle channel the export cable route also ran close to the
446:
At the end of the windfarm's operational life (25 years) the wind farm will be decommissioned.
3098: 3035: 2952: 2947: 2876: 2866: 531: 477: 358:. SeaScape received a capital grant of £10 million in 2003 to aid development of the project. 337: 1856: 1791: 636: 2962: 2916: 2911: 2752: 2621: 2022: 2014: 1744: 1264: 1256: 640: 639:
for the Burbo 2 extension Dynamic Reactive Compensation electrical equipment (STATCOM); and
397: 341: 2841: 2831: 2626: 2576: 2566: 2471: 2140: 519: 436: 257: 1545: 624:
was awarded the contract to supply export cables. Suppliers for inter array cabling was
2988: 2821: 2611: 2586: 2466: 2461: 1973: 743: 729: 704: 546: 429: 389: 231: 2224:
Burbo Bank Extension offshore wind farm Environmental Impact Assessment Scoping Report
906:"Elsam og EDF Energie Nouvelle, køber offshore møller hos Siemens til engelsk projekt" 340:
farm site. The site, located on Burbo Flats in Liverpool bay (~7 km northwest of
3138: 2676: 2561: 2481: 2451: 2036: 1700: 1278: 693: 610: 515: 473: 310: 68: 2993: 2972: 2846: 2361: 967: 689: 550: 496: 460: 72: 491:; subsequently a potential grid connection at the 400 kV Deeside substation (near 1294:
UK Renewable Energy Data - Monthly Generation Statistics, April 2002 – March 2010
2646: 2317:, vol. 1, DONG Energy Burbo Extension (UK) Ltd., March 2013, archived from 2288:, vol. 2, DONG Energy Burbo Extension (UK) Ltd., March 2013, archived from 2018: 1991: 1260: 1214: 1135:
North Sea construction: Installing monopiles for the Dutch Q7 offshore wind farm
751: 685: 601: 593: 568:
holding company) and Danish pension fund PKA for £660 million in February 2016.
468: 388:
Construction began in June 2006. Contractor for the foundation installation was
380: 3013: 2881: 2681: 2591: 2431: 719: 697: 677: 658: 561: 488: 405: 76: 103: 90: 421: 314: 306: 165: 3093: 1588:
DONG Energy skal opføre Burbo Bank Extension Havmøllepark i Storbritannien
1337:[Corrosion forces Siemens to replace bearings in Wind Turbines], 681: 355: 1932: 284: 2436: 2159:"Burbo Offshore Wind Farm, River Mersey, Liverpool Bay, United Kingdom" 666: 662: 614: 393: 2027: 1269: 2476: 2441: 2279:"Chapter 23: (5.1.2.23) Other Infrastructure and Licensed Activities" 1896:"Van Oord signs contract for Burbo Bank Extension offshore wind farm" 1186:
Burbo Offshore Wind Farm, River Mersey, Liverpool Bay, United Kingdom
625: 597: 1234:
Offshore Wind Energy Cost Modeling: Installation and Decommissioning
2081:, vol. 1, SeaScape Energy Ltd., September 2002, archived from 1831:"A2SEA's 'SEA CHALLENGER' to Install Burbo Bank Extension Turbines" 673: 583: 570: 379: 362: 495:, Wales) was identified; and later a connection with landfall at 369:
in 2004 with Elsam taking 50% of the projecty. In September 2005
2354: 1696:"Nu indleder Vestas serieproduktion af verdens største havmølle" 565: 2365: 1335:"Korrosion tvinger Siemens til skift af vingelejer i havmøller" 700:
to be used as a base during the construction of the wind farm.
3165:
Buildings and structures in the Metropolitan Borough of Wirral
2456: 680:
contracted to install the offshore export cable. In June 2015
644: 621: 401: 186:
0.5 to 13 m (1 ft 8 in to 42 ft 8 in)
1591:(Press release) (in Danish), 19 December 2014, archived from 1211:"Inauguration of DONG Energy's Burbo Bank offshore wind farm" 684:
were contracted for foundation installation. In October 2015
575:
Svanen, lifting ship, Burbo Banks Offshore Windfarm Extension
1575:, European Commission, 23 July 2014, Table 2, pp.4-5c; § 29 1169: 1167: 396:, Smulders supplied the WTG foundations, turbine towers by 1959:
DONG Energy secures construction base for latest wind farm
465:
extensions to their Round 1 or Round 2 offshore wind farms
1677:"Nu starter Vestas produktion af gigantisk havvindmølle" 1042:"Arklow Bank & Burbo Bank Offshore Windfarms Towers" 511:
to use to a connection near the Bodelwyddan substation.
1766:"DONG Energy, Nexans Ink Offshore Wind Cable Deal (UK)" 1486:(5.1.2.23) Other Infrastructure and Licensed Activities 1471:(5.1.2.23) Other Infrastructure and Licensed Activities 1456:(5.1.2.23) Other Infrastructure and Licensed Activities 2308:"Chapter 5: (5.1.1.5) Site Selection and Alternatives" 1914:"Van Oord to Install Burbo Bank Extension Foundations" 1614:"DONG Sells Half of Burbo Bank Extension to PKA, LEGO" 507:. In 2011 the developer reached an agreement with the 549:
funding from the UK government in April 2014, with a
499:, (nr. Prestatyn, Wales) to an extension of the new 3060: 3026: 2981: 2935: 2774: 2765: 2740: 2499: 2490: 2422: 1813:"A2SEA SIGNS CONTRACT FOR BURBO BANK EXTENSION OWF" 463:announced that wind farm operators could apply for 271: 266: 256: 240: 204: 190: 182: 164: 159: 143: 127: 119: 82: 63: 49: 31: 1716:"ABB's Cables for Dong's Burbo Bank Extension OWF" 1398: 1386: 665:(Denmark) with monopiles made at EEW's factory in 3068:List of offshore wind farms in the United Kingdom 773:List of offshore wind farms in the United Kingdom 692:. In early 2016 DONG Energy acquired a lease on 676:was contracted to for turbine installations, and 1154:International Cranes & Specialised Transport 2353:(official website), Dong Energy, archived from 1632:"Dong Taps Vestas for Burbo Bank Offshore Wind" 892:which bought a 50% stake of the project in 2004 530:, as well as the planned route of the 2000 MW 2377: 1962:(press release), Dong Energy, 27 January 2016 503:400 kV substation under construction for the 8: 1878:"Jan De Nul Wins Burbo Bank Extension Wires" 927:"Siemens' first turbine order for UK waters" 778:List of offshore wind farms in the Irish Sea 400:, monopiles and transition pieces were from 2206:, The Planning Inspectorate, archived from 1419:, Dong Energy, 26 July 2013, archived from 1197: 1173: 324:) in 2005. A 25 turbine installation using 2771: 2496: 2384: 2370: 2362: 2250:"Chapter 6: (5.1.1.6) Project Description" 560:) sold half of the wind farm extension to 384:The logo of Orsted who owns the wind farm. 28: 2414:Offshore wind power in the United Kingdom 2026: 1444:(5.1.1.5) Site Selection and Alternatives 1375:(5.1.1.5) Site Selection and Alternatives 1268: 2807:European Offshore Wind Deployment Centre 1446:(Dong) sec. 5.3.15-5.3.30, fig. 5.3, 5.4 861:"British consents for four in North Sea" 3175:Energy infrastructure completed in 2007 2203:Burbo Bank Extension offshore wind farm 1731: 1729: 1694:Bredsdorff, Magnus (22 December 2014), 1232:Kaiser, Mark J.; Snyder, Brian (2012), 882:"Nuclear utility with a wind portfolio" 788: 609:, while the blades are made at Vestas' 276:Related media on Commons 18:Burbo Bank Extension offshore wind farm 2409:Renewable energy in the United Kingdom 1488:(Dong) sec.23.6.25-23.6.26, fig.23.6 1377:(Dong) sec.5.3.3-5.3.14, fig.5.1, 5.2 915:(in Danish), Elsam, 21 September 2005 526:export cable; and crossed the 500 MW 7: 3145:Offshore wind farms in the Irish Sea 3117: 1784:"EEW, Bladt win Burbo 2 foundations" 1148:Verrinder, James (1 December 2006), 832:(SeaScape Energy, 2002) pp. 2–4 810: 808: 806: 804: 377:) became sole owner of the project. 2093:Vestergaard, Søren (October 2007), 1933:"Transforming Burbo Bank Wind Farm" 1660:Snieckus, Darius (21 August 2014), 313:on the west coast of the UK in the 1849:"A2Sea to tackle Burbo 8MW giants" 1737:"Chinese land Burbo 2 electricals" 1638:, 24 February 2014, archived from 1490:Telecommunication and power cables 1475:Telecommunication and power cables 1221:from the original on 7 April 2008. 650:Offshore Structures (Britain) Ltd. 518:oil and gas field, connecting the 25: 2141:"Burbo Bank 1 Offshore Wind Farm" 1790:, 27 January 2015, archived from 1365:(SeaScape Energy, 2002) p. 4 798:(SeaScape Energy, 2002) p. 2 541:The wind farm extension received 412:supplying lifting barge platform 3116: 3105: 3104: 3092: 2393:Wind power in the United Kingdom 1743:, 8 January 2015, archived from 1333:Godske, Bjørn (24 August 2010), 1315:Dunn, Justin (16 October 2009), 1104:"Reference Projects -Burbo Bank" 750: 736: 722: 707:has been estimated at £147/MWh. 37: 2347:"Burbo Bank Offshore Wind Farm" 1974:"First 8MW giant up at Burbo 2" 1855:, 24 April 2015, archived from 1544:, 23 April 2014, archived from 1538:"UK awards contracts for 4.5GW" 989:"Burbo Bank offshore wind farm" 960:"Burbo Bank Offshore Wind Farm" 815:Burbo Bank 1 Offshore Wind Farm 432:has been estimated as £87/MWh. 392:: the foundation design was by 3170:2007 establishments in England 2230:, October 2010, archived from 1819:(press release), 24 April 2014 1663:MHI Vestas 8MW gets Burbo deal 1527:(Dong) sec.6.8.3, 6.8.23, 6.10 1188:(www.renewable-technology.com) 843:"More offshore plant go ahead" 613:. Assembly will take place in 588:Turbines viewed from the shore 524:North Hoyle Offshore Wind Farm 505:Gwynt y Môr Offshore Wind Farm 309:located on the Burbo Flats in 1: 2259:, vol. 1, archived from 2174:, 4C Offshore, archived from 2125:Burbo Bank Offshore Wind Farm 2050:(5.1.1.6) Project Description 1902:(press release), 25 June 2015 1683:(in Danish), 22 December 2014 1525:(5.1.1.6) Project Description 1513:(5.1.1.6) Project Description 1501:(5.1.1.6) Project Description 1473:(Dong) sec.23.6.21, fig.23.6 1458:(Dong) sec.23.6.13, fig.23.5 1304:, August 2010, pp. 95–96 1132:de Vries, Eize (1 May 2007), 303:Burbo Bank Offshore Wind Farm 32:Burbo Bank Offshore Wind Farm 2404:Energy in the United Kingdom 1485: 1470: 1455: 1236:, Springer, Table 8.1, p.138 819:Timeline & Track records 455:Planning, funding and design 3160:Round 1 offshore wind farms 3155:Ørsted (company) wind farms 2019:10.1016/j.enpol.2018.12.044 1341:(in Danish), archived from 1302:Renewable Energy Foundation 1261:10.1016/j.enpol.2018.12.044 948:Developers/Owners/Operators 768:List of offshore wind farms 435:Between 2008 and 2010, the 344:and ~6 km west of the 3191: 1460:Oil and gas infrastructure 1443: 1374: 1185: 1072:References - Offshore Wind 183:Max. water depth 3086: 2399: 2049: 1524: 1512: 1500: 814: 637:design and build contract 633:Rongxin Power Engineering 281: 213: 209: 45: 36: 2968:Sofia Offshore Wind Farm 2163:renewable-technology.com 2079:Burbo Offshore Wind Farm 1362: 829: 795: 611:Isle of Wight facilities 528:East–West Interconnector 228:Make and model 197:107 m (351 ft) 3073:North Sea Offshore Grid 2315:Environmental Statement 2286:Environmental Statement 2257:Environmental Statement 2072:"Non-Technical Summary" 1399:EIA Scoping report 2010 1387:EIA Scoping report 2010 943: 758:Renewable energy portal 661:, UK), and by Bladt at 543:contract for difference 242:Nameplate capacity 71:at the entrance to the 3078:Wind power in Scotland 2852:Lynn and Inner Dowsing 2104:The Burbo Bank Project 631:In January 2015 RXPE ( 589: 576: 385: 367:EDF Energies Nouvelles 236:Vestas V164-8.0MW (32) 218:Units operational 3150:Wind farms in England 3099:Wind power portal 1992:"Showtime at Burbo 2" 1363:Non-Technical Summary 1078:, Sif, archived from 830:Non-Technical Summary 796:Non-Technical Summary 607:Odense Steel Shipyard 587: 574: 493:Deeside Power Station 404:; piling was done by 383: 338:Round 1 offshore wind 305:is a 348 MW offshore 205:Power generation 3028:Installation vessels 2922:West of Duddon Sands 2194:Burbo Bank Extension 2178:on 26 September 2010 1017:smulders-hoboken.com 931:windpowermonthly.com 888:, 1 September 2005, 886:windpowermonthly.com 865:windpowermonthly.com 847:windpowermonthly.com 655:TAG Energy Solutions 351:monopile foundations 332:Initial Construction 258:Capacity factor 129:Commission date 2767:Offshore wind farms 2667:Little Cheyne Court 2357:on 24 February 2016 2295:on 23 February 2016 2237:on 23 February 2016 1859:on 23 February 2016 1794:on 23 February 2016 1770:subseaworldnews.com 1720:subseaworldnews.com 1548:on 20 February 2016 1515:(Dong) sec.6.6, 6.7 1426:on 23 February 2016 1217:. 18 October 2007. 867:, 1 November 2003, 602:V164 8.0 MW turbine 596:announced that the 267:External links 191:Rotor diameter 100: /  2492:Onshore wind farms 1980:, 8 September 2016 1937:Collett & Sons 1747:on 12 January 2015 1620:, 11 February 2016 635:) was awarded the 590: 577: 386: 371:Siemens Wind Power 326:Siemens Wind Power 104:53.4833°N 3.1667°W 3132: 3131: 3022: 3021: 2761: 2760: 2522:Askam and Ireleth 1345:on 27 August 2010 1321:wirralglobe.co.uk 1213:(Press release). 849:, 1 December 2003 556:DONG Energy (now 532:Western HVDC Link 478:Port of Liverpool 292: 291: 16:(Redirected from 3182: 3120: 3119: 3108: 3107: 3097: 3096: 2963:Neart Na Gaoithe 2927:Westermost Rough 2902:Sheringham Shoal 2772: 2497: 2386: 2379: 2372: 2363: 2358: 2332: 2331: 2329: 2324:on 24 April 2014 2323: 2312: 2303: 2302: 2300: 2294: 2283: 2274: 2273: 2271: 2266:on 24 April 2014 2265: 2254: 2245: 2244: 2242: 2236: 2229: 2218: 2217: 2215: 2210:on 24 April 2014 2186: 2185: 2183: 2165: 2154: 2153: 2151: 2136: 2135: 2133: 2119: 2118: 2116: 2107:, archived from 2098: 2089: 2088:on 24 April 2014 2087: 2076: 2053: 2047: 2041: 2040: 2030: 2002: 1996: 1995: 1994:. 27 April 2017. 1988: 1982: 1981: 1970: 1964: 1963: 1954: 1948: 1947: 1945: 1943: 1928: 1922: 1921: 1918:offshorewind.biz 1910: 1904: 1903: 1892: 1886: 1885: 1882:offshorewind.biz 1874: 1868: 1867: 1866: 1864: 1845: 1839: 1838: 1835:offshorewind.biz 1827: 1821: 1820: 1809: 1803: 1802: 1801: 1799: 1780: 1774: 1773: 1772:, 27 August 2014 1762: 1756: 1755: 1754: 1752: 1733: 1724: 1723: 1722:, 13 August 2014 1712: 1706: 1705: 1691: 1685: 1684: 1673: 1667: 1666: 1657: 1651: 1650: 1649: 1647: 1642:on 24 April 2014 1628: 1622: 1621: 1618:offshorewind.biz 1610: 1604: 1603: 1602: 1600: 1595:on 24 March 2017 1583: 1577: 1576: 1574: 1563: 1557: 1556: 1555: 1553: 1534: 1528: 1522: 1516: 1510: 1504: 1498: 1492: 1483: 1477: 1468: 1462: 1453: 1447: 1441: 1435: 1434: 1433: 1431: 1425: 1418: 1408: 1402: 1396: 1390: 1389:, §2.3, 3.2.2.1. 1384: 1378: 1372: 1366: 1360: 1354: 1353: 1352: 1350: 1330: 1324: 1323: 1312: 1306: 1305: 1299: 1289: 1283: 1282: 1272: 1244: 1238: 1237: 1229: 1223: 1222: 1207: 1201: 1198:Vestergaard 2007 1195: 1189: 1183: 1177: 1174:Vestergaard 2007 1171: 1162: 1161: 1160:on 24 April 2014 1156:, archived from 1145: 1139: 1138: 1129: 1123: 1122: 1121: 1119: 1114:on 24 April 2014 1110:, archived from 1100: 1094: 1093: 1092: 1090: 1085:on 24 April 2014 1084: 1077: 1067: 1061: 1060: 1059: 1057: 1052:on 24 April 2014 1048:, archived from 1046:stateofgreen.com 1038: 1032: 1031: 1030: 1028: 1023:on 24 April 2014 1019:, archived from 1009: 1003: 1002: 1001: 999: 985: 979: 978: 977: 975: 970:on 24 April 2014 966:, archived from 956: 950: 941: 935: 934: 933:, 1 October 2005 923: 917: 916: 910: 902: 896: 895: 878: 872: 871: 857: 851: 850: 839: 833: 827: 821: 812: 799: 793: 760: 755: 754: 746: 741: 740: 732: 727: 726: 725: 641:Bladt Industries 410:Mammoet Van Oord 398:Bladt Industries 296:Wind farm layout 285:edit on Wikidata 234:SWT-3.6-107 (25) 221:25 × 3.6 MW 115: 114: 112: 111: 110: 109:53.4833; -3.1667 105: 101: 98: 97: 96: 93: 41: 29: 21: 3190: 3189: 3185: 3184: 3183: 3181: 3180: 3179: 3135: 3134: 3133: 3128: 3091: 3082: 3056: 3018: 2977: 2931: 2832:Hywind Scotland 2812:Greater Gabbard 2757: 2736: 2627:Goonhilly Downs 2486: 2472:Talisman Energy 2418: 2395: 2390: 2351:burbobank.co.uk 2345: 2342: 2337: 2327: 2325: 2321: 2310: 2306: 2298: 2296: 2292: 2281: 2277: 2269: 2267: 2263: 2252: 2248: 2240: 2238: 2234: 2227: 2221: 2213: 2211: 2200: 2196: 2191: 2181: 2179: 2168: 2157: 2149: 2147: 2139: 2131: 2129: 2122: 2114: 2112: 2111:on 12 June 2009 2101: 2092: 2085: 2074: 2070: 2067: 2061: 2056: 2052:(Dong) sec.6.14 2048: 2044: 2004: 2003: 1999: 1990: 1989: 1985: 1972: 1971: 1967: 1956: 1955: 1951: 1941: 1939: 1931:Walker, Shell. 1930: 1929: 1925: 1912: 1911: 1907: 1894: 1893: 1889: 1884:, 21 April 2015 1876: 1875: 1871: 1862: 1860: 1847: 1846: 1842: 1837:, 24 April 2015 1829: 1828: 1824: 1811: 1810: 1806: 1797: 1795: 1782: 1781: 1777: 1764: 1763: 1759: 1750: 1748: 1735: 1734: 1727: 1714: 1713: 1709: 1693: 1692: 1688: 1675: 1674: 1670: 1659: 1658: 1654: 1645: 1643: 1630: 1629: 1625: 1612: 1611: 1607: 1598: 1596: 1585: 1584: 1580: 1572: 1565: 1564: 1560: 1551: 1549: 1536: 1535: 1531: 1523: 1519: 1511: 1507: 1499: 1495: 1484: 1480: 1469: 1465: 1454: 1450: 1442: 1438: 1429: 1427: 1423: 1416: 1410: 1409: 1405: 1397: 1393: 1385: 1381: 1373: 1369: 1361: 1357: 1348: 1346: 1332: 1331: 1327: 1314: 1313: 1309: 1297: 1291: 1290: 1286: 1246: 1245: 1241: 1231: 1230: 1226: 1209: 1208: 1204: 1196: 1192: 1184: 1180: 1172: 1165: 1147: 1146: 1142: 1131: 1130: 1126: 1117: 1115: 1102: 1101: 1097: 1088: 1086: 1082: 1075: 1069: 1068: 1064: 1055: 1053: 1040: 1039: 1035: 1026: 1024: 1013:"Burbo Project" 1011: 1010: 1006: 997: 995: 987: 986: 982: 973: 971: 958: 957: 953: 942: 938: 925: 924: 920: 908: 904: 903: 899: 880: 879: 875: 859: 858: 854: 841: 840: 836: 828: 824: 813: 802: 794: 790: 786: 764: 763: 756: 749: 742: 735: 728: 723: 721: 716: 620:In August 2014 592:In early 2014, 582: 520:Douglas Complex 457: 452: 437:capacity factor 334: 299: 298: 297: 288: 252: 235: 222: 200: 178: 160:Wind farm 155: 139: 108: 106: 102: 99: 94: 91: 89: 87: 86: 67:Burbo Flats in 59: 23: 22: 15: 12: 11: 5: 3188: 3186: 3178: 3177: 3172: 3167: 3162: 3157: 3152: 3147: 3137: 3136: 3130: 3129: 3127: 3126: 3114: 3102: 3087: 3084: 3083: 3081: 3080: 3075: 3070: 3064: 3062: 3058: 3057: 3055: 3054: 3047: 3044:MPI Resolution 3040: 3032: 3030: 3024: 3023: 3020: 3019: 3017: 3016: 3011: 3006: 3001: 2996: 2991: 2989:Atlantic Array 2985: 2983: 2979: 2978: 2976: 2975: 2970: 2965: 2960: 2955: 2950: 2945: 2939: 2937: 2933: 2932: 2930: 2929: 2924: 2919: 2914: 2909: 2904: 2899: 2894: 2889: 2884: 2879: 2874: 2869: 2864: 2859: 2854: 2849: 2844: 2839: 2834: 2829: 2827:Humber Gateway 2824: 2819: 2817:Gunfleet Sands 2814: 2809: 2804: 2799: 2794: 2789: 2784: 2778: 2776: 2769: 2763: 2762: 2759: 2758: 2756: 2755: 2750: 2744: 2742: 2738: 2737: 2735: 2734: 2732:Winscales Moor 2729: 2724: 2719: 2714: 2712:Trimdon Grange 2709: 2704: 2699: 2694: 2689: 2684: 2679: 2674: 2669: 2664: 2659: 2654: 2649: 2644: 2639: 2634: 2632:Great Eppleton 2629: 2624: 2619: 2614: 2609: 2604: 2599: 2594: 2589: 2587:Cold Northcott 2584: 2579: 2574: 2569: 2564: 2559: 2554: 2552:Brechfa Forest 2549: 2547:Braes of Doune 2544: 2539: 2534: 2529: 2527:Beinn an Tuirc 2524: 2519: 2514: 2509: 2503: 2501: 2494: 2488: 2487: 2485: 2484: 2479: 2474: 2469: 2467:SSE Renewables 2464: 2462:Siemens Gamesa 2459: 2454: 2449: 2444: 2439: 2434: 2428: 2426: 2420: 2419: 2417: 2416: 2411: 2406: 2400: 2397: 2396: 2391: 2389: 2388: 2381: 2374: 2366: 2360: 2359: 2341: 2340:External links 2338: 2336: 2335: 2334: 2333: 2304: 2275: 2246: 2197: 2195: 2192: 2190: 2189: 2188: 2187: 2155: 2137: 2120: 2099: 2090: 2066: 2063: 2062: 2060: 2057: 2055: 2054: 2042: 1997: 1983: 1965: 1949: 1923: 1920:, 24 June 2015 1905: 1887: 1869: 1840: 1822: 1804: 1775: 1757: 1725: 1707: 1686: 1668: 1652: 1623: 1605: 1578: 1558: 1529: 1517: 1505: 1503:(Dong) sec.6.3 1493: 1478: 1463: 1448: 1436: 1403: 1391: 1379: 1367: 1355: 1325: 1307: 1284: 1239: 1224: 1202: 1190: 1178: 1163: 1140: 1124: 1095: 1062: 1033: 1004: 980: 951: 946:(4C Offshore) 936: 918: 897: 873: 852: 834: 822: 800: 787: 785: 782: 781: 780: 775: 770: 762: 761: 747: 744:Weather portal 733: 730:England portal 718: 717: 715: 712: 705:levelised cost 672:In April 2015 581: 578: 547:energy subsidy 474:shipping lanes 456: 453: 451: 448: 430:levelised cost 333: 330: 295: 294: 293: 290: 289: 282: 279: 278: 273: 269: 268: 264: 263: 260: 254: 253: 251: 250: 246: 244: 238: 237: 232:Siemens Gamesa 229: 225: 224: 223:32 × 8 MW 219: 215: 214: 211: 210: 207: 206: 202: 201: 199: 198: 194: 192: 188: 187: 184: 180: 179: 177: 176: 170: 168: 162: 161: 157: 156: 154: 153: 147: 145: 141: 140: 138: 137: 133: 131: 125: 124: 121: 117: 116: 84: 80: 79: 65: 61: 60: 58: 57: 56:United Kingdom 53: 51: 47: 46: 43: 42: 34: 33: 24: 14: 13: 10: 9: 6: 4: 3: 2: 3187: 3176: 3173: 3171: 3168: 3166: 3163: 3161: 3158: 3156: 3153: 3151: 3148: 3146: 3143: 3142: 3140: 3125: 3124: 3115: 3113: 3112: 3103: 3101: 3100: 3095: 3089: 3088: 3085: 3079: 3076: 3074: 3071: 3069: 3066: 3065: 3063: 3059: 3053: 3052: 3051:MPI Discovery 3048: 3046: 3045: 3041: 3039: 3038: 3037:MPI Adventure 3034: 3033: 3031: 3029: 3025: 3015: 3012: 3010: 3007: 3005: 3002: 3000: 2999:Docking Shoal 2997: 2995: 2992: 2990: 2987: 2986: 2984: 2980: 2974: 2971: 2969: 2966: 2964: 2961: 2959: 2956: 2954: 2951: 2949: 2946: 2944: 2941: 2940: 2938: 2934: 2928: 2925: 2923: 2920: 2918: 2915: 2913: 2910: 2908: 2905: 2903: 2900: 2898: 2895: 2893: 2890: 2888: 2885: 2883: 2880: 2878: 2875: 2873: 2870: 2868: 2865: 2863: 2860: 2858: 2855: 2853: 2850: 2848: 2845: 2843: 2840: 2838: 2837:Kentish Flats 2835: 2833: 2830: 2828: 2825: 2823: 2820: 2818: 2815: 2813: 2810: 2808: 2805: 2803: 2800: 2798: 2795: 2793: 2790: 2788: 2785: 2783: 2780: 2779: 2777: 2773: 2770: 2768: 2764: 2754: 2751: 2749: 2746: 2745: 2743: 2739: 2733: 2730: 2728: 2725: 2723: 2720: 2718: 2715: 2713: 2710: 2708: 2707:Slieve Rushen 2705: 2703: 2700: 2698: 2695: 2693: 2690: 2688: 2685: 2683: 2680: 2678: 2677:Moel Maelogan 2675: 2673: 2672:Milton Keynes 2670: 2668: 2665: 2663: 2660: 2658: 2655: 2653: 2650: 2648: 2645: 2643: 2642:Holmside Hall 2640: 2638: 2635: 2633: 2630: 2628: 2625: 2623: 2620: 2618: 2615: 2613: 2610: 2608: 2605: 2603: 2600: 2598: 2595: 2593: 2590: 2588: 2585: 2583: 2580: 2578: 2575: 2573: 2570: 2568: 2565: 2563: 2562:Carland Cross 2560: 2558: 2555: 2553: 2550: 2548: 2545: 2543: 2542:Blyth Harbour 2540: 2538: 2535: 2533: 2530: 2528: 2525: 2523: 2520: 2518: 2515: 2513: 2510: 2508: 2505: 2504: 2502: 2498: 2495: 2493: 2489: 2483: 2482:ScottishPower 2480: 2478: 2475: 2473: 2470: 2468: 2465: 2463: 2460: 2458: 2455: 2453: 2452:REG WindPower 2450: 2448: 2445: 2443: 2440: 2438: 2435: 2433: 2430: 2429: 2427: 2425: 2421: 2415: 2412: 2410: 2407: 2405: 2402: 2401: 2398: 2394: 2387: 2382: 2380: 2375: 2373: 2368: 2367: 2364: 2356: 2352: 2348: 2344: 2343: 2339: 2320: 2316: 2309: 2305: 2291: 2287: 2280: 2276: 2262: 2258: 2251: 2247: 2233: 2226: 2225: 2220: 2219: 2209: 2205: 2204: 2199: 2198: 2193: 2177: 2173: 2172: 2167: 2166: 2164: 2160: 2156: 2146: 2142: 2138: 2127: 2126: 2121: 2110: 2106: 2105: 2100: 2097:, DONG Energy 2096: 2091: 2084: 2080: 2073: 2069: 2068: 2064: 2058: 2051: 2046: 2043: 2038: 2034: 2029: 2024: 2020: 2016: 2012: 2008: 2007:Energy Policy 2001: 1998: 1993: 1987: 1984: 1979: 1975: 1969: 1966: 1961: 1960: 1953: 1950: 1938: 1934: 1927: 1924: 1919: 1915: 1909: 1906: 1901: 1897: 1891: 1888: 1883: 1879: 1873: 1870: 1858: 1854: 1850: 1844: 1841: 1836: 1832: 1826: 1823: 1818: 1814: 1808: 1805: 1793: 1789: 1785: 1779: 1776: 1771: 1767: 1761: 1758: 1746: 1742: 1738: 1732: 1730: 1726: 1721: 1717: 1711: 1708: 1703: 1702: 1697: 1690: 1687: 1682: 1678: 1672: 1669: 1665: 1664: 1656: 1653: 1641: 1637: 1636:breakbulk.com 1633: 1627: 1624: 1619: 1615: 1609: 1606: 1594: 1590: 1589: 1582: 1579: 1571: 1570: 1562: 1559: 1547: 1543: 1539: 1533: 1530: 1526: 1521: 1518: 1514: 1509: 1506: 1502: 1497: 1494: 1491: 1487: 1482: 1479: 1476: 1472: 1467: 1464: 1461: 1457: 1452: 1449: 1445: 1440: 1437: 1422: 1415: 1414: 1407: 1404: 1400: 1395: 1392: 1388: 1383: 1380: 1376: 1371: 1368: 1364: 1359: 1356: 1344: 1340: 1336: 1329: 1326: 1322: 1318: 1311: 1308: 1303: 1296: 1295: 1288: 1285: 1280: 1276: 1271: 1266: 1262: 1258: 1254: 1250: 1249:Energy Policy 1243: 1240: 1235: 1228: 1225: 1220: 1216: 1212: 1206: 1203: 1199: 1194: 1191: 1187: 1182: 1179: 1175: 1170: 1168: 1164: 1159: 1155: 1151: 1144: 1141: 1137: 1136: 1128: 1125: 1113: 1109: 1105: 1099: 1096: 1081: 1074: 1073: 1066: 1063: 1051: 1047: 1043: 1037: 1034: 1022: 1018: 1014: 1008: 1005: 994: 993:ramboll.co.uk 990: 984: 981: 969: 965: 961: 955: 952: 949: 945: 940: 937: 932: 928: 922: 919: 914: 913:Press release 907: 901: 898: 894: 893: 887: 883: 877: 874: 870: 866: 862: 856: 853: 848: 844: 838: 835: 831: 826: 823: 820: 816: 811: 809: 807: 805: 801: 797: 792: 789: 783: 779: 776: 774: 771: 769: 766: 765: 759: 753: 748: 745: 739: 734: 731: 720: 713: 711: 708: 706: 701: 699: 695: 694:Cammell Laird 691: 690:girder bridge 687: 683: 679: 675: 670: 668: 664: 660: 656: 652: 651: 646: 642: 638: 634: 629: 627: 623: 618: 616: 612: 608: 603: 599: 595: 586: 579: 573: 569: 567: 563: 559: 554: 552: 548: 544: 539: 535: 533: 529: 525: 521: 517: 516:Liverpool Bay 512: 510: 509:National Grid 506: 502: 498: 494: 490: 485: 481: 479: 475: 470: 466: 462: 454: 449: 447: 444: 442: 441:National Grid 438: 433: 431: 425: 423: 417: 415: 411: 407: 403: 399: 395: 391: 382: 378: 376: 372: 368: 364: 359: 357: 352: 347: 343: 339: 331: 329: 327: 323: 318: 316: 312: 311:Liverpool Bay 308: 304: 286: 280: 277: 274: 270: 265: 261: 259: 255: 248: 247: 245: 243: 239: 233: 230: 227: 226: 220: 217: 216: 212: 208: 203: 196: 195: 193: 189: 185: 181: 175: 172: 171: 169: 167: 163: 158: 152: 149: 148: 146: 142: 135: 134: 132: 130: 126: 122: 118: 113: 85: 81: 78: 74: 70: 69:Liverpool Bay 66: 62: 55: 54: 52: 48: 44: 40: 35: 30: 27: 19: 3122: 3109: 3090: 3050: 3043: 3036: 3004:First Flight 2994:Celtic Array 2973:Triton Knoll 2892:Scroby Sands 2847:London Array 2796: 2687:Ovenden Moor 2657:Langley Park 2637:Hadyard Hill 2355:the original 2350: 2326:, retrieved 2319:the original 2314: 2297:, retrieved 2290:the original 2285: 2268:, retrieved 2261:the original 2256: 2239:, retrieved 2232:the original 2223: 2212:, retrieved 2208:the original 2202: 2180:, retrieved 2176:the original 2170: 2162: 2148:, retrieved 2144: 2130:, retrieved 2124: 2113:, retrieved 2109:the original 2103: 2094: 2083:the original 2078: 2045: 2010: 2006: 2000: 1986: 1977: 1968: 1958: 1952: 1940:. Retrieved 1936: 1926: 1917: 1908: 1899: 1890: 1881: 1872: 1861:, retrieved 1857:the original 1852: 1843: 1834: 1825: 1816: 1807: 1796:, retrieved 1792:the original 1787: 1778: 1769: 1760: 1749:, retrieved 1745:the original 1740: 1719: 1710: 1699: 1689: 1680: 1671: 1662: 1655: 1644:, retrieved 1640:the original 1635: 1626: 1617: 1608: 1597:, retrieved 1593:the original 1587: 1581: 1567: 1561: 1550:, retrieved 1546:the original 1541: 1532: 1520: 1508: 1496: 1489: 1481: 1474: 1466: 1459: 1451: 1439: 1428:, retrieved 1421:the original 1412: 1406: 1394: 1382: 1370: 1358: 1347:, retrieved 1343:the original 1338: 1328: 1320: 1310: 1293: 1287: 1252: 1248: 1242: 1233: 1227: 1205: 1200:, p. 6. 1193: 1181: 1176:, p. 5. 1158:the original 1153: 1150:"Wind it on" 1143: 1134: 1127: 1116:, retrieved 1112:the original 1107: 1098: 1087:, retrieved 1080:the original 1071: 1065: 1054:, retrieved 1050:the original 1045: 1036: 1025:, retrieved 1021:the original 1016: 1007: 996:, retrieved 992: 983: 972:, retrieved 968:the original 963: 954: 947: 939: 930: 921: 912: 900: 890: 889: 885: 876: 868: 864: 855: 846: 837: 825: 818: 791: 709: 702: 671: 648: 630: 619: 591: 580:Construction 555: 551:strike price 540: 536: 513: 500: 497:Ffrith Beach 486: 482: 461:Crown Estate 459:In 2009 the 458: 445: 434: 426: 418: 414:Jumping Jack 413: 387: 360: 335: 319: 302: 300: 73:River Mersey 26: 3009:Navitus Bay 2948:East Anglia 2943:Dogger Bank 2862:North Hoyle 2822:Gwynt y Môr 2717:West Durham 2652:Knabs Ridge 2647:Kilgallioch 2617:Fraisthorpe 2597:Crystal Rig 2582:Coal Clough 2557:Burton Wold 2299:15 February 2241:15 February 1942:12 February 1900:vanoord.com 1863:15 February 1798:15 February 1704:(in Danish) 1599:24 December 1552:15 February 1430:15 February 1401:, §3.2.2.2. 1215:DONG Energy 696:'s yard in 686:DONG Energy 669:(Germany). 594:DONG Energy 501:Bodelwyddan 469:DONG Energy 390:MT Højgaard 249:348 MW 123:Operational 107: / 83:Coordinates 3139:Categories 3014:Shell Flat 2958:Moray East 2887:Robin Rigg 2882:Rhyl Flats 2797:Burbo Bank 2702:Scout Moor 2692:Pates Hill 2682:Out Newton 2592:Conisholme 2572:Cefn Croes 2537:Blood Hill 2432:Ecotricity 2171:Burbo Bank 2095:Burbo Bank 2065:Burbo Bank 2028:10059/3298 1978:renews.biz 1853:renews.biz 1788:renews.biz 1741:renews.biz 1701:Ingeniøren 1542:renews.biz 1270:10059/3298 944:Burbo Bank 784:References 698:Birkenhead 678:Jan De Nul 659:Billingham 562:KIRKBI A/S 545:renewable 489:Birkenhead 92:53°29′00″N 77:Merseyside 2982:Cancelled 2872:Race Bank 2748:Den Brook 2697:Royd Moor 2662:Lindhurst 2532:Black Law 2517:Arecleoch 2512:Ardrossan 2507:Alltwalis 2424:Companies 2128:, Ramboll 2037:158158724 2013:: 25–35. 1817:a2sea.com 1751:8 January 1349:25 August 1279:158158724 1255:: 25–35. 1108:menck.com 657:plant in 450:Extension 422:ABB Group 315:Irish Sea 307:wind farm 95:3°10′00″W 3111:Category 2936:Proposed 2907:Teesside 2897:Seagreen 2787:Beatrice 2741:Proposed 2727:Whitelee 2722:Westmill 2607:Delabole 2602:Dagenham 2328:23 April 2270:23 April 2214:23 April 2182:24 April 2150:24 April 2132:24 April 2115:24 April 1646:23 April 1569:Beatrice 1219:Archived 1118:24 April 1089:23 April 1056:24 April 1027:24 April 998:24 April 974:24 April 714:See also 682:Van Oord 653:(former 356:Wallasey 174:Offshore 144:Owner(s) 64:Location 3123:Commons 2953:Hornsea 2877:Rampion 2867:Ormonde 2802:Dudgeon 2437:Equinor 2145:lorc.dk 2059:Sources 964:mth.com 817:(Lorc) 667:Rostock 663:Aalborg 615:Belfast 476:to the 408:, with 394:Ramboll 272:Commons 50:Country 2917:Walney 2912:Thanet 2857:Methil 2782:Barrow 2775:Active 2753:Viking 2622:Garves 2500:Active 2477:Vestas 2447:Ørsted 2442:Innogy 2035:  1681:Børsen 1339:Ing.dk 1277:  626:Nexans 598:Vestas 558:Ørsted 375:Ørsted 346:Sefton 342:Wirral 322:Ørsted 151:Ørsted 120:Status 3061:Other 2842:Lincs 2792:Blyth 2577:Clyde 2567:Carno 2322:(PDF) 2311:(PDF) 2293:(PDF) 2282:(PDF) 2264:(PDF) 2253:(PDF) 2235:(PDF) 2228:(PDF) 2086:(PDF) 2075:(PDF) 2033:S2CID 1573:(PDF) 1424:(PDF) 1417:(PDF) 1298:(PDF) 1275:S2CID 1083:(PDF) 1076:(PDF) 909:(PDF) 674:A2SEA 406:Menck 363:Elsam 283:[ 2612:Farr 2330:2014 2301:2016 2272:2014 2243:2016 2216:2014 2184:2014 2152:2014 2134:2014 2117:2014 1944:2019 1865:2016 1800:2016 1753:2015 1648:2014 1601:2014 1554:2016 1432:2016 1351:2010 1120:2014 1091:2014 1058:2014 1029:2014 1000:2014 976:2014 643:and 566:Lego 365:and 301:The 262:~30% 166:Type 136:2007 2457:RWE 2023:hdl 2015:doi 2011:128 1265:hdl 1257:doi 1253:128 645:EEW 622:ABB 402:Sif 3141:: 2349:, 2313:, 2284:, 2255:, 2161:, 2143:, 2077:, 2031:. 2021:. 2009:. 1976:, 1935:. 1916:, 1898:, 1880:, 1851:, 1833:, 1815:, 1786:, 1768:, 1739:, 1728:^ 1718:, 1698:, 1679:, 1634:, 1616:, 1540:, 1319:, 1300:, 1273:. 1263:. 1251:. 1166:^ 1152:, 1106:, 1044:, 1015:, 991:, 962:, 929:, 911:, 884:, 863:, 845:, 803:^ 617:. 600:' 534:. 467:; 416:. 75:, 2385:e 2378:t 2371:v 2039:. 2025:: 2017:: 1946:. 1281:. 1267:: 1259:: 564:( 287:] 20:)

Index

Burbo Bank Extension offshore wind farm

Liverpool Bay
River Mersey
Merseyside
53°29′00″N 3°10′00″W / 53.4833°N 3.1667°W / 53.4833; -3.1667
Commission date
Ørsted
Type
Offshore
Siemens Gamesa
Nameplate capacity
Capacity factor
Related media on Commons
edit on Wikidata
wind farm
Liverpool Bay
Irish Sea
Ørsted
Siemens Wind Power
Round 1 offshore wind
Wirral
Sefton
monopile foundations
Wallasey
Elsam
EDF Energies Nouvelles
Siemens Wind Power
Ørsted

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.