234: 215:
On 10 November 2014, the National Green Tribunal cancelled the Environmental Clearance for the project, on the grounds that the project had not conducted a proper cumulative impact assessment of the project. It ordered "a fresh review of the environmental clearance on the basis of a fresh cumulative
204:
of China said it had signed a $ 2.4 billion contract to build the second phase of the coal-fired power complex. IL&FS said it would import coal from Indonesia, Australia and South Africa to fuel the plant. It said it had acquired a mine in Indonesia to supply the generators. IL&FS plans to
208:
The project faced delays due to an order by National Green Tribunal in June 2012 for a flue gas desulphurisation unit. Due to this, the two units are proposed to come up by December 2014 and February 2015, respectively, at a cost of Rs 9,500 crore.
196:
The project received environmental clearance in 2010 as a 3,600 MW thermal power project to be developed in phases, with Phase-I comprising 2 x 600 MW units and Phase-II comprising the remaining 2,400 MW (3X800 MW).
63: 749: 351: 703: 800: 834: 819: 744: 829: 344: 295: 556: 546: 439: 793: 337: 693: 839: 698: 409: 723: 713: 561: 404: 499: 469: 222:
With no forward progress more than two years after receiving environmental clearance, Phase II appears to be shelved or abandoned.
786: 571: 282: 414: 479: 718: 525: 454: 434: 399: 474: 688: 464: 459: 424: 394: 389: 205:
sell the power from the project to state-run distribution companies on a long-term basis as well as in the open market.
824: 739: 708: 652: 551: 530: 504: 484: 509: 419: 489: 444: 185: 494: 449: 364: 270: 320: 257: 616: 103: 668: 631: 601: 611: 606: 329: 159: 770: 621: 596: 576: 360: 813: 581: 239: 626: 591: 636: 586: 566: 368: 229: 51: 78: 65: 233: 47: 321:"Monthly Report on Broad Status of Thermal Power Projects in the Country," 171: 212:
In February 2014 the project was amended to be 2X600 MW and 3X660 MW.
201: 219:
Unit 1 was commissioned in September 2015 and unit 2 in March 2016.
131: 333: 30:
Location of the Cuddalore IL&FS Thermal Power Station
774: 750:
Indian states ranking by households having electricity
732: 681: 661: 645: 539: 518: 382: 375: 158: 137: 127: 122: 114: 102: 94: 57: 43: 35: 23: 704:Tamil Nadu Generation and Distribution Corporation 323:Government of India Ministry of Power, March 2016 271:"China power giant inks $ 2.4 bln India project," 769:This article about an Indian power station is a 500:Ennore SEZ Super Critical Thermal Power Project 296:"NGT quashes eco nod for Cuddalore power plant" 470:Pillaiperumalnallur Combined Cycle Power Plant 794: 345: 8: 258:"IL&FS Cuddalore power project delayed," 745:States of India by installed power capacity 801: 787: 379: 352: 338: 330: 20: 430:Cuddalore IL&FS Thermal Power Station 24:Cuddalore IL&FS Thermal Power Station 480:Valantharavai Combined Cycle Power Plant 835:Energy infrastructure completed in 2015 820:Coal-fired power stations in Tamil Nadu 455:Thirumakottai Gas Turbine Power Station 247: 557:Bhavani Kattalai Hydroelectric Project 440:Basin Bridge Gas Turbine Power Station 7: 766: 764: 694:Tamil Nadu Energy Development Agency 253: 251: 699:Tamil Nadu Transmission Corporation 632:Suruliyar Hydroelectric Power Plant 475:Karuppur Combined Cycle Power Plant 410:North Chennai Thermal Power Station 269:Charlie Zhu and Sanjeev Choudhary, 773:. You can help Knowledge (XXG) by 724:Power System Operation Corporation 714:Nuclear Power Corporation of India 617:Parsons Valley Hydro Power Station 465:Valuthur Gas Turbine Power Station 460:Kuttalam Gas Turbine Power Station 405:Neyveli Zero Lignite Power Station 16:Power station in Tamil Nadu, India 14: 830:2015 establishments in Tamil Nadu 260:Projects Today, 20 November 2013. 182:Cuddalore IL&FS Power Station 637:Pykara Hydroelectric Power Plant 562:Lower Mettur Barrage Power House 232: 123:Thermal power station 485:Samalpatti Diesel Power Station 415:Tuticorin Thermal Power Station 719:PowerGrid Corporation of India 526:Kudankulam Nuclear Power Plant 510:Udangudi Thermal Power Project 1: 602:Kadambari Hydro Power Station 435:GMR Vasavi Diesel Power Plant 400:Neyveli Thermal Power Station 689:Tamil Nadu Electricity Board 627:Solaiyar Hydro Power Station 425:Vallur Thermal Power Station 395:Mettur Thermal Power Station 390:Ennore Thermal Power Station 740:Electricity sector in India 709:Neyveli Lignite Corporation 653:Kamuthi Solar Power Project 622:Periyar Hydro Power Station 607:Kodayar Hydro Power Station 552:Kateri hydroelectric system 531:Madras Atomic Power Station 505:Uppur Thermal Power Project 490:Narimanam Gas Power Station 445:Thirumakottai Power Station 856: 840:Indian power station stubs 763: 597:Aliyar Hydro Power Station 567:Mettur Hydro Power Station 420:NTPL Thermal Power Station 216:impact assessment study." 184:is a 1,200-megawatt (MW) 168: 146: 142: 28: 450:Kuttalam Power Stations 186:coal-fired power station 547:Maravakandy Power House 495:Sarkarpathy Power House 273:Reuters, 13 April 2012. 160:Nameplate capacity 79:11.521611°N 79.751833°E 188:in Tamil Nadu, India. 151:Units operational 108:Unit 1: September 2015 285:NGT, 10 November 2014 283:"Appeal no. 50/2012," 138:Power generation 104:Commission date 84:11.521611; 79.751833 669:Muppandal Wind Farm 192:Background on plant 75: /  825:Cuddalore district 612:Kundah Power House 302:. 12 November 2014 200:On 13 April 2012, 110:Unit 2: March 2016 782: 781: 758: 757: 677: 676: 572:Moyar Power House 179: 178: 128:Primary fuel 847: 803: 796: 789: 765: 380: 354: 347: 340: 331: 324: 318: 312: 311: 309: 307: 292: 286: 280: 274: 267: 261: 255: 242: 237: 236: 172:edit on Wikidata 90: 89: 87: 86: 85: 80: 76: 73: 72: 71: 68: 21: 855: 854: 850: 849: 848: 846: 845: 844: 810: 809: 808: 807: 761: 759: 754: 728: 673: 657: 641: 535: 514: 371: 358: 328: 327: 319: 315: 305: 303: 294: 293: 289: 281: 277: 268: 264: 256: 249: 238: 231: 228: 194: 175: 154:2 X 600 MW 109: 83: 81: 77: 74: 69: 66: 64: 62: 61: 31: 17: 12: 11: 5: 853: 851: 843: 842: 837: 832: 827: 822: 812: 811: 806: 805: 798: 791: 783: 780: 779: 756: 755: 753: 752: 747: 742: 736: 734: 733:Related topics 730: 729: 727: 726: 721: 716: 711: 706: 701: 696: 691: 685: 683: 679: 678: 675: 674: 672: 671: 665: 663: 659: 658: 656: 655: 649: 647: 643: 642: 640: 639: 634: 629: 624: 619: 614: 609: 604: 599: 594: 589: 584: 579: 577:Perunchani Dam 574: 569: 564: 559: 554: 549: 543: 541: 537: 536: 534: 533: 528: 522: 520: 516: 515: 513: 512: 507: 502: 497: 492: 487: 482: 477: 472: 467: 462: 457: 452: 447: 442: 437: 432: 427: 422: 417: 412: 407: 402: 397: 392: 386: 384: 377: 376:Power stations 373: 372: 361:Power stations 359: 357: 356: 349: 342: 334: 326: 325: 313: 287: 275: 262: 246: 245: 244: 243: 227: 224: 193: 190: 177: 176: 169: 166: 165: 162: 156: 155: 152: 148: 147: 144: 143: 140: 139: 135: 134: 129: 125: 124: 120: 119: 116: 112: 111: 106: 100: 99: 96: 92: 91: 59: 55: 54: 45: 41: 40: 37: 33: 32: 29: 26: 25: 15: 13: 10: 9: 6: 4: 3: 2: 852: 841: 838: 836: 833: 831: 828: 826: 823: 821: 818: 817: 815: 804: 799: 797: 792: 790: 785: 784: 778: 776: 772: 767: 762: 751: 748: 746: 743: 741: 738: 737: 735: 731: 725: 722: 720: 717: 715: 712: 710: 707: 705: 702: 700: 697: 695: 692: 690: 687: 686: 684: 682:Organizations 680: 670: 667: 666: 664: 660: 654: 651: 650: 648: 644: 638: 635: 633: 630: 628: 625: 623: 620: 618: 615: 613: 610: 608: 605: 603: 600: 598: 595: 593: 590: 588: 585: 583: 582:Papanasam Dam 580: 578: 575: 573: 570: 568: 565: 563: 560: 558: 555: 553: 550: 548: 545: 544: 542: 540:Hydroelectric 538: 532: 529: 527: 524: 523: 521: 517: 511: 508: 506: 503: 501: 498: 496: 493: 491: 488: 486: 483: 481: 478: 476: 473: 471: 468: 466: 463: 461: 458: 456: 453: 451: 448: 446: 443: 441: 438: 436: 433: 431: 428: 426: 423: 421: 418: 416: 413: 411: 408: 406: 403: 401: 398: 396: 393: 391: 388: 387: 385: 381: 378: 374: 370: 366: 365:organizations 362: 355: 350: 348: 343: 341: 336: 335: 332: 322: 317: 314: 301: 297: 291: 288: 284: 279: 276: 272: 266: 263: 259: 254: 252: 248: 241: 240:Energy portal 235: 230: 225: 223: 220: 217: 213: 210: 206: 203: 198: 191: 189: 187: 183: 173: 167: 163: 161: 157: 153: 150: 149: 145: 141: 136: 133: 130: 126: 121: 118:IL&FS Ltd 117: 113: 107: 105: 101: 97: 93: 88: 60: 56: 53: 49: 46: 42: 38: 34: 27: 22: 19: 775:expanding it 768: 760: 592:Servalar dam 429: 316: 304:. Retrieved 299: 290: 278: 265: 221: 218: 214: 211: 207: 199: 195: 181: 180: 70:79°45′06.6″E 67:11°31′17.8″N 18: 306:17 December 115:Operator(s) 98:Operational 82: / 58:Coordinates 814:Categories 587:Vaigai Dam 369:Tamil Nadu 226:References 52:Tamil Nadu 300:The Hindu 48:Cuddalore 44:Location 519:Nuclear 383:Thermal 164:1200 MW 36:Country 202:SEPCO3 95:Status 646:Solar 170:[ 39:India 771:stub 662:Wind 363:and 308:2019 132:Coal 367:of 816:: 298:. 250:^ 50:, 802:e 795:t 788:v 777:. 353:e 346:t 339:v 310:. 174:]

Index

Cuddalore
Tamil Nadu
11°31′17.8″N 79°45′06.6″E / 11.521611°N 79.751833°E / 11.521611; 79.751833
Commission date
Coal
Nameplate capacity
edit on Wikidata
coal-fired power station
SEPCO3
icon
Energy portal


"IL&FS Cuddalore power project delayed,"
"China power giant inks $ 2.4 bln India project,"
"Appeal no. 50/2012,"
"NGT quashes eco nod for Cuddalore power plant"
"Monthly Report on Broad Status of Thermal Power Projects in the Country,"
v
t
e
Power stations
organizations
Tamil Nadu
Ennore Thermal Power Station
Mettur Thermal Power Station
Neyveli Thermal Power Station
Neyveli Zero Lignite Power Station
North Chennai Thermal Power Station
Tuticorin Thermal Power Station

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.