102:
28:
81:
drains from sewer lines, built separate storm sewers in some locations, diverted surface streams away from the combined sewers, and added sumps and other devices to control surges of stormwater. These relatively low-cost efforts reduced the stormwater entering the system by more than 2 billion US gallons (7.6
121:
that was 300 feet (91 m) long and had a cutting head that was 25 feet (7.6 m) in diameter. In addition to the tunnel and the pipe, the project involved building seven access shafts, connecting pipelines, and the
Portsmouth Forcemain, which carries sewage from the Swan Island Pump Station to
55:
system of pipes, sumps, drains, pumps, and other infrastructure that transports sewage and stormwater run-off to the city's
Columbia Boulevard Wastewater Treatment Plant. The East Side Big Pipe project, begun in 2006 and finished in 2011, was the largest of a 20-year series of projects designed to
132:
Costs associated with the CSO projects, which totaled about $ 1.4 billion, included $ 450 million for the East Side CSO Tunnel and $ 70 million for the
Portsmouth Forcemain. Most of the financing for the projects is coming from sewer ratepayers and almost none from state or Federal
80:
Over the next 20 years, the city took a series of steps to reach its goals: a 99 percent reduction in CSOs into the
Columbia Slough by the year 2000 and a 94 percent reduction in CSOs into the river by December 2011. As first steps, the city helped property owners disconnect their roof
109:
Work on the East Side Big Pipe began in 2006 and was completed in late 2011. Its tunnel is almost 6 miles (9.7 km) long. It lies at an average of 150 feet (46 m) below the surface along the east bank of the
Willamette River from the intersection of Southeast 17th Avenue and McLoughlin
72:
From the mid-19th century until the mid-20th century, Portland's combined sewer system poured untreated sewage into the
Willamette River and the Columbia Slough. In 1952, the city built its first plant to treat wastewater, which included stormwater run-off as well as raw sewage. However, the
141:
The route parallels the east side of the
Willamette River mostly within a few blocks. Six vertical shafts were built to manage and facilitate tunnel construction. These are listed in reverse flow direction, or North to South.
204:
88:
By 2000, the city completed a more complicated project, the 3.5-mile (5.6 km) Columbia Slough
Consolidation Conduit. A separate project completed in 2006 centered on construction of the 3.5-mile (5.6 km)
296:
250:
480:
434:
388:
342:
73:
existing sewer pipes were often overwhelmed by surges of stormwater from big storms, and the resulting CSOs continued to pollute the river and the slough. In 1991, the city signed an agreement with the
93:
and the Swan Island Pump
Station. By late 2011, the city finished the largest of the CSO projects, the East Side Big Pipe. The combined projects were completed on schedule and met the intended goals.
680:
675:
117:
The East Side tunnel was the largest sewer construction project ever undertaken by the City of
Portland. A contractor, Kiewit-Bilfinger Berger (KBB), used a
125:
The Portsmouth Forcemain, 3 miles (4.8 km) long and 66 inches (170 cm) in diameter, runs north from the pump station across Swan Island and under
64:. The combined projects were completed on time, and they reduced CSOs into the river by 94 percent and into the slough by more than 99 percent.
74:
129:
and North Willamette Boulevard. There it meets the pre-existing Portsmouth Tunnel, which conveys combined sewage by gravity to the treatment plant.
690:
700:
695:
150:
685:
17:
177:
118:
172:
111:
90:
167:
57:
40:
61:
545:
52:
624:
31:
Looking down the main construction shaft to the East Side Big Pipe during construction
669:
650:
584:
162:
651:"Combined Sewer Overflow CSO Abatement Program: Final Report, 1991–2011"
126:
44:
496:
482:
450:
436:
404:
390:
358:
344:
312:
298:
266:
252:
220:
206:
82:
114:. The pipe in the tunnel has an inside diameter of 22 feet (6.7 m).
546:"Sewer Repair Portland OR - Trenchless Sewer Line & Drain Cleaning"
101:
27:
48:
100:
26:
56:
nearly eliminate combined sewer overflows (CSO)s into the
653:. Portland Bureau of Environmental Services. January 2012
122:the Columbia Boulevard Wastewater Treatment Plant.
579:
577:
18:Columbia Boulevard Wastewater Treatment Plant
8:
681:Sewerage infrastructure in the United States
676:Buildings and structures in Portland, Oregon
587:. Portland Bureau of Environmental Services
187:
75:Oregon Department of Environmental Quality
567:
565:
528:
105:East Side Big Pipe under construction
7:
39:is a large sewer line and tunnel in
25:
77:to nearly eliminate these CSOs.
605:"Final Report", pp. 18–20
614:"Final Report, pp. 26–27
1:
691:2011 establishments in Oregon
535:"Final Report", pp. 4–5
585:"East Side Big Pipe Project"
178:GPX (secondary coordinates)
717:
701:Southeast Portland, Oregon
696:Northeast Portland, Oregon
173:GPX (primary coordinates)
148:Map all coordinates using
156:Download coordinates as:
625:"East Side CSO Shafts"
497:45.48651°N 122.64755°W
451:45.50271°N 122.66139°W
405:45.50619°N 122.66278°W
359:45.51773°N 122.66250°W
313:45.52936°N 122.66649°W
267:45.53670°N 122.67524°W
221:45.55302°N 122.69564°W
106:
32:
168:GPX (all coordinates)
119:tunnel boring machine
104:
30:
571:"Final Report", p. 6
502:45.48651; -122.64755
456:45.50271; -122.66139
410:45.50619; -122.66278
364:45.51773; -122.66250
318:45.52936; -122.66649
272:45.53670; -122.67524
226:45.55302; -122.69564
91:West Side CSO Tunnel
492: /
446: /
400: /
354: /
308: /
262: /
216: /
627:. City of Portland
324:Steel Bridge shaft
291:Steel Bridge shaft
278:River Street shaft
245:River Street shaft
107:
51:. It is part of a
37:East Side Big Pipe
33:
686:Tunnels in Oregon
550:NWHomeServicesLLC
520:
519:
232:Port Center shaft
199:Port Center shaft
97:Technical details
16:(Redirected from
708:
662:
660:
658:
637:
636:
634:
632:
621:
615:
612:
606:
603:
597:
596:
594:
592:
581:
572:
569:
560:
559:
557:
556:
542:
536:
533:
516:
515:
513:
512:
511:
509:
508:McLoughlin shaft
504:
503:
498:
493:
490:
489:
488:
485:
475:McLoughlin shaft
470:
469:
467:
466:
465:
463:
458:
457:
452:
447:
444:
443:
442:
439:
424:
423:
421:
420:
419:
417:
412:
411:
406:
401:
398:
397:
396:
393:
378:
377:
375:
374:
373:
371:
366:
365:
360:
355:
352:
351:
350:
347:
332:
331:
329:
328:
327:
325:
320:
319:
314:
309:
306:
305:
304:
301:
286:
285:
283:
282:
281:
279:
274:
273:
268:
263:
260:
259:
258:
255:
240:
239:
237:
236:
235:
233:
228:
227:
222:
217:
214:
213:
212:
209:
188:
58:Willamette River
21:
716:
715:
711:
710:
709:
707:
706:
705:
666:
665:
656:
654:
649:
646:
641:
640:
630:
628:
623:
622:
618:
613:
609:
604:
600:
590:
588:
583:
582:
575:
570:
563:
554:
552:
544:
543:
539:
534:
530:
525:
507:
505:
501:
499:
495:
494:
491:
486:
483:
481:
479:
478:
461:
459:
455:
453:
449:
448:
445:
440:
437:
435:
433:
432:
415:
413:
409:
407:
403:
402:
399:
394:
391:
389:
387:
386:
369:
367:
363:
361:
357:
356:
353:
348:
345:
343:
341:
340:
323:
321:
317:
315:
311:
310:
307:
302:
299:
297:
295:
294:
277:
275:
271:
269:
265:
264:
261:
256:
253:
251:
249:
248:
231:
229:
225:
223:
219:
218:
215:
210:
207:
205:
203:
202:
186:
185:
184:
183:
182:
139:
99:
70:
62:Columbia Slough
23:
22:
15:
12:
11:
5:
714:
712:
704:
703:
698:
693:
688:
683:
678:
668:
667:
664:
663:
645:
642:
639:
638:
616:
607:
598:
573:
561:
537:
527:
526:
524:
521:
518:
517:
476:
472:
471:
430:
426:
425:
384:
380:
379:
338:
334:
333:
292:
288:
287:
246:
242:
241:
200:
196:
195:
192:
181:
180:
175:
170:
165:
159:
153:
146:
145:
144:
138:
135:
98:
95:
69:
66:
53:combined sewer
24:
14:
13:
10:
9:
6:
4:
3:
2:
713:
702:
699:
697:
694:
692:
689:
687:
684:
682:
679:
677:
674:
673:
671:
652:
648:
647:
643:
626:
620:
617:
611:
608:
602:
599:
586:
580:
578:
574:
568:
566:
562:
551:
547:
541:
538:
532:
529:
522:
514:
477:
474:
473:
468:
462:Taggart shaft
431:
429:Taggart shaft
428:
427:
422:
385:
382:
381:
376:
339:
336:
335:
330:
293:
290:
289:
284:
247:
244:
243:
238:
201:
198:
197:
193:
191:Location name
190:
189:
179:
176:
174:
171:
169:
166:
164:
161:
160:
158:
157:
152:
151:OpenStreetMap
149:
143:
136:
134:
133:governments.
130:
128:
123:
120:
115:
113:
110:Boulevard to
103:
96:
94:
92:
86:
84:
78:
76:
67:
65:
63:
59:
54:
50:
46:
42:
38:
29:
19:
655:. Retrieved
629:. Retrieved
619:
610:
601:
589:. Retrieved
553:. Retrieved
549:
540:
531:
155:
154:
147:
140:
131:
124:
116:
108:
87:
79:
71:
36:
34:
644:Works cited
631:October 15,
500: /
487:122°38′51″W
454: /
441:122°39′41″W
416:Opera shaft
408: /
395:122°39′46″W
383:Opera shaft
370:Alder Shaft
362: /
349:122°39′45″W
337:Alder Shaft
316: /
303:122°39′59″W
270: /
257:122°40′31″W
224: /
211:122°41′44″W
194:Coordinate
112:Swan Island
670:Categories
657:August 28,
591:August 28,
555:2022-09-16
523:References
506: (
484:45°29′11″N
460: (
438:45°30′10″N
414: (
392:45°30′22″N
368: (
346:45°31′04″N
322: (
300:45°31′46″N
276: (
254:45°32′12″N
230: (
208:45°33′11″N
127:Waud Bluff
85:) a year.
45:U.S. state
60:and the
41:Portland
68:History
43:in the
49:Oregon
137:Route
659:2013
633:2013
593:2013
35:The
163:KML
47:of
672::
576:^
564:^
548:.
83:Gl
661:.
635:.
595:.
558:.
510:)
464:)
418:)
372:)
326:)
280:)
234:)
20:)
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.