Knowledge

East Side Big Pipe

Source 📝

102: 28: 81:
drains from sewer lines, built separate storm sewers in some locations, diverted surface streams away from the combined sewers, and added sumps and other devices to control surges of stormwater. These relatively low-cost efforts reduced the stormwater entering the system by more than 2 billion US gallons (7.6 
121:
that was 300 feet (91 m) long and had a cutting head that was 25 feet (7.6 m) in diameter. In addition to the tunnel and the pipe, the project involved building seven access shafts, connecting pipelines, and the Portsmouth Forcemain, which carries sewage from the Swan Island Pump Station to
55:
system of pipes, sumps, drains, pumps, and other infrastructure that transports sewage and stormwater run-off to the city's Columbia Boulevard Wastewater Treatment Plant. The East Side Big Pipe project, begun in 2006 and finished in 2011, was the largest of a 20-year series of projects designed to
132:
Costs associated with the CSO projects, which totaled about $ 1.4 billion, included $ 450 million for the East Side CSO Tunnel and $ 70 million for the Portsmouth Forcemain. Most of the financing for the projects is coming from sewer ratepayers and almost none from state or Federal
80:
Over the next 20 years, the city took a series of steps to reach its goals: a 99 percent reduction in CSOs into the Columbia Slough by the year 2000 and a 94 percent reduction in CSOs into the river by December 2011. As first steps, the city helped property owners disconnect their roof
109:
Work on the East Side Big Pipe began in 2006 and was completed in late 2011. Its tunnel is almost 6 miles (9.7 km) long. It lies at an average of 150 feet (46 m) below the surface along the east bank of the Willamette River from the intersection of Southeast 17th Avenue and McLoughlin
72:
From the mid-19th century until the mid-20th century, Portland's combined sewer system poured untreated sewage into the Willamette River and the Columbia Slough. In 1952, the city built its first plant to treat wastewater, which included stormwater run-off as well as raw sewage. However, the
141:
The route parallels the east side of the Willamette River mostly within a few blocks. Six vertical shafts were built to manage and facilitate tunnel construction. These are listed in reverse flow direction, or North to South.
204: 88:
By 2000, the city completed a more complicated project, the 3.5-mile (5.6 km) Columbia Slough Consolidation Conduit. A separate project completed in 2006 centered on construction of the 3.5-mile (5.6 km)
296: 250: 480: 434: 388: 342: 73:
existing sewer pipes were often overwhelmed by surges of stormwater from big storms, and the resulting CSOs continued to pollute the river and the slough. In 1991, the city signed an agreement with the
93:
and the Swan Island Pump Station. By late 2011, the city finished the largest of the CSO projects, the East Side Big Pipe. The combined projects were completed on schedule and met the intended goals.
680: 675: 117:
The East Side tunnel was the largest sewer construction project ever undertaken by the City of Portland. A contractor, Kiewit-Bilfinger Berger (KBB), used a
125:
The Portsmouth Forcemain, 3 miles (4.8 km) long and 66 inches (170 cm) in diameter, runs north from the pump station across Swan Island and under
64:. The combined projects were completed on time, and they reduced CSOs into the river by 94 percent and into the slough by more than 99 percent. 74: 129:
and North Willamette Boulevard. There it meets the pre-existing Portsmouth Tunnel, which conveys combined sewage by gravity to the treatment plant.
690: 700: 695: 150: 685: 17: 177: 118: 172: 111: 90: 167: 57: 40: 61: 545: 52: 624: 31:
Looking down the main construction shaft to the East Side Big Pipe during construction
669: 650: 584: 162: 651:"Combined Sewer Overflow CSO Abatement Program: Final Report, 1991–2011" 126: 44: 496: 482: 450: 436: 404: 390: 358: 344: 312: 298: 266: 252: 220: 206: 82: 114:. The pipe in the tunnel has an inside diameter of 22 feet (6.7 m). 546:"Sewer Repair Portland OR - Trenchless Sewer Line & Drain Cleaning" 101: 27: 48: 100: 26: 56:
nearly eliminate combined sewer overflows (CSO)s into the
653:. Portland Bureau of Environmental Services. January 2012 122:the Columbia Boulevard Wastewater Treatment Plant. 579: 577: 18:Columbia Boulevard Wastewater Treatment Plant 8: 681:Sewerage infrastructure in the United States 676:Buildings and structures in Portland, Oregon 587:. Portland Bureau of Environmental Services 187: 75:Oregon Department of Environmental Quality 567: 565: 528: 105:East Side Big Pipe under construction 7: 39:is a large sewer line and tunnel in 25: 77:to nearly eliminate these CSOs. 605:"Final Report", pp. 18–20 614:"Final Report, pp. 26–27 1: 691:2011 establishments in Oregon 535:"Final Report", pp. 4–5 585:"East Side Big Pipe Project" 178:GPX (secondary coordinates) 717: 701:Southeast Portland, Oregon 696:Northeast Portland, Oregon 173:GPX (primary coordinates) 148:Map all coordinates using 156:Download coordinates as: 625:"East Side CSO Shafts" 497:45.48651°N 122.64755°W 451:45.50271°N 122.66139°W 405:45.50619°N 122.66278°W 359:45.51773°N 122.66250°W 313:45.52936°N 122.66649°W 267:45.53670°N 122.67524°W 221:45.55302°N 122.69564°W 106: 32: 168:GPX (all coordinates) 119:tunnel boring machine 104: 30: 571:"Final Report", p. 6 502:45.48651; -122.64755 456:45.50271; -122.66139 410:45.50619; -122.66278 364:45.51773; -122.66250 318:45.52936; -122.66649 272:45.53670; -122.67524 226:45.55302; -122.69564 91:West Side CSO Tunnel 492: /  446: /  400: /  354: /  308: /  262: /  216: /  627:. City of Portland 324:Steel Bridge shaft 291:Steel Bridge shaft 278:River Street shaft 245:River Street shaft 107: 51:. It is part of a 37:East Side Big Pipe 33: 686:Tunnels in Oregon 550:NWHomeServicesLLC 520: 519: 232:Port Center shaft 199:Port Center shaft 97:Technical details 16:(Redirected from 708: 662: 660: 658: 637: 636: 634: 632: 621: 615: 612: 606: 603: 597: 596: 594: 592: 581: 572: 569: 560: 559: 557: 556: 542: 536: 533: 516: 515: 513: 512: 511: 509: 508:McLoughlin shaft 504: 503: 498: 493: 490: 489: 488: 485: 475:McLoughlin shaft 470: 469: 467: 466: 465: 463: 458: 457: 452: 447: 444: 443: 442: 439: 424: 423: 421: 420: 419: 417: 412: 411: 406: 401: 398: 397: 396: 393: 378: 377: 375: 374: 373: 371: 366: 365: 360: 355: 352: 351: 350: 347: 332: 331: 329: 328: 327: 325: 320: 319: 314: 309: 306: 305: 304: 301: 286: 285: 283: 282: 281: 279: 274: 273: 268: 263: 260: 259: 258: 255: 240: 239: 237: 236: 235: 233: 228: 227: 222: 217: 214: 213: 212: 209: 188: 58:Willamette River 21: 716: 715: 711: 710: 709: 707: 706: 705: 666: 665: 656: 654: 649: 646: 641: 640: 630: 628: 623: 622: 618: 613: 609: 604: 600: 590: 588: 583: 582: 575: 570: 563: 554: 552: 544: 543: 539: 534: 530: 525: 507: 505: 501: 499: 495: 494: 491: 486: 483: 481: 479: 478: 461: 459: 455: 453: 449: 448: 445: 440: 437: 435: 433: 432: 415: 413: 409: 407: 403: 402: 399: 394: 391: 389: 387: 386: 369: 367: 363: 361: 357: 356: 353: 348: 345: 343: 341: 340: 323: 321: 317: 315: 311: 310: 307: 302: 299: 297: 295: 294: 277: 275: 271: 269: 265: 264: 261: 256: 253: 251: 249: 248: 231: 229: 225: 223: 219: 218: 215: 210: 207: 205: 203: 202: 186: 185: 184: 183: 182: 139: 99: 70: 62:Columbia Slough 23: 22: 15: 12: 11: 5: 714: 712: 704: 703: 698: 693: 688: 683: 678: 668: 667: 664: 663: 645: 642: 639: 638: 616: 607: 598: 573: 561: 537: 527: 526: 524: 521: 518: 517: 476: 472: 471: 430: 426: 425: 384: 380: 379: 338: 334: 333: 292: 288: 287: 246: 242: 241: 200: 196: 195: 192: 181: 180: 175: 170: 165: 159: 153: 146: 145: 144: 138: 135: 98: 95: 69: 66: 53:combined sewer 24: 14: 13: 10: 9: 6: 4: 3: 2: 713: 702: 699: 697: 694: 692: 689: 687: 684: 682: 679: 677: 674: 673: 671: 652: 648: 647: 643: 626: 620: 617: 611: 608: 602: 599: 586: 580: 578: 574: 568: 566: 562: 551: 547: 541: 538: 532: 529: 522: 514: 477: 474: 473: 468: 462:Taggart shaft 431: 429:Taggart shaft 428: 427: 422: 385: 382: 381: 376: 339: 336: 335: 330: 293: 290: 289: 284: 247: 244: 243: 238: 201: 198: 197: 193: 191:Location name 190: 189: 179: 176: 174: 171: 169: 166: 164: 161: 160: 158: 157: 152: 151:OpenStreetMap 149: 143: 136: 134: 133:governments. 130: 128: 123: 120: 115: 113: 110:Boulevard to 103: 96: 94: 92: 86: 84: 78: 76: 67: 65: 63: 59: 54: 50: 46: 42: 38: 29: 19: 655:. Retrieved 629:. Retrieved 619: 610: 601: 589:. Retrieved 553:. Retrieved 549: 540: 531: 155: 154: 147: 140: 131: 124: 116: 108: 87: 79: 71: 36: 34: 644:Works cited 631:October 15, 500: / 487:122°38′51″W 454: / 441:122°39′41″W 416:Opera shaft 408: / 395:122°39′46″W 383:Opera shaft 370:Alder Shaft 362: / 349:122°39′45″W 337:Alder Shaft 316: / 303:122°39′59″W 270: / 257:122°40′31″W 224: / 211:122°41′44″W 194:Coordinate 112:Swan Island 670:Categories 657:August 28, 591:August 28, 555:2022-09-16 523:References 506: ( 484:45°29′11″N 460: ( 438:45°30′10″N 414: ( 392:45°30′22″N 368: ( 346:45°31′04″N 322: ( 300:45°31′46″N 276: ( 254:45°32′12″N 230: ( 208:45°33′11″N 127:Waud Bluff 85:) a year. 45:U.S. state 60:and the 41:Portland 68:History 43:in the 49:Oregon 137:Route 659:2013 633:2013 593:2013 35:The 163:KML 47:of 672:: 576:^ 564:^ 548:. 83:Gl 661:. 635:. 595:. 558:. 510:) 464:) 418:) 372:) 326:) 280:) 234:) 20:)

Index

Columbia Boulevard Wastewater Treatment Plant

Portland
U.S. state
Oregon
combined sewer
Willamette River
Columbia Slough
Oregon Department of Environmental Quality
Gl
West Side CSO Tunnel

Swan Island
tunnel boring machine
Waud Bluff
OpenStreetMap
KML
GPX (all coordinates)
GPX (primary coordinates)
GPX (secondary coordinates)
45°33′11″N 122°41′44″W / 45.55302°N 122.69564°W / 45.55302; -122.69564 (Port Center shaft)
45°32′12″N 122°40′31″W / 45.53670°N 122.67524°W / 45.53670; -122.67524 (River Street shaft)
45°31′46″N 122°39′59″W / 45.52936°N 122.66649°W / 45.52936; -122.66649 (Steel Bridge shaft)
45°31′04″N 122°39′45″W / 45.51773°N 122.66250°W / 45.51773; -122.66250 (Alder Shaft)
45°30′22″N 122°39′46″W / 45.50619°N 122.66278°W / 45.50619; -122.66278 (Opera shaft)
45°30′10″N 122°39′41″W / 45.50271°N 122.66139°W / 45.50271; -122.66139 (Taggart shaft)
45°29′11″N 122°38′51″W / 45.48651°N 122.64755°W / 45.48651; -122.64755 (McLoughlin shaft)
"Sewer Repair Portland OR - Trenchless Sewer Line & Drain Cleaning"

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.