Knowledge (XXG)

Conesville Power Plant

Source 📝

31: 465: 451: 1240: 273:
Construction of Unit 1 began in 1955 and was commissioned by Columbus & Southern Ohio Electric (a forerunner of AEP). Unit 1 began commercial generation in 1957 while Unit 2 began operations two years later in 1959. Both units cost $ 36 million to construct and generated 125 MW each. Unit 3 began
395:
Units 1 and 2 were retired in 2005 after Unit 1's tubing to its boiler failed. Inspections on Unit 2 revealed severe corrosion in a pattern that was similar to Unit 1. The reported cost of $ 35 million to repair both units was not worth the benefit of returning to service. Unit 3 was retired in
1320: 1293: 970: 408:, and other toxic emissions. AEP announced in October 2018 they will shut down Conesville by May 2020. Units 5 and 6 retired on May 31, 2019, while Unit 4 remained in operation until April 2020. The decision to close the plant was due to operational costs, not clearing 330:'s (EPA) Clean Air Interstate Rule (CAIR) and Clean Air Mercury Rule (CAMR). The $ 450 million project for Unit 4, saw the construction of an 800 ft (240 m) smokestack for the FGD equipment. After it was installed, inspectors found corrosion. AEP settled with 349:) emissions, but it operated inefficiently. The scrubber was eventually upgraded in 2008. In the summer of 2001, Unit 6 was the test site for Thermal Energy International's THERMALONOx. The THERMALONOx was intended to show that 282:), Columbus & Southern Ohio Electric, and DP&L. Units 5 and 6 began operations in 1976 and 1978 respectively. Over the years, Units 5 and 6 have increased electrical generation from 375 MW to 405 MW. In 2014, 387:(EIA), the plant received 1,716,286 short tons of coal in 2017. All of the coal was shipped from mines within Ohio. Conesville used to employ 600 workers. In 2018, only 165 were employed at the plant. 274:
operations in 1962 with a generation capacity of 165 MW. Unit 4 began operations in 1973 with a generation capacity of 780 MW. At the time of its conception, the unit would be jointly owned by
1398: 1076: 1403: 1393: 1388: 1383: 1378: 1373: 1368: 397: 362:) emissions would be reduced by 70%. Unfortunately, the demonstration was halted in September 2001 after the "system did not appreciably reduce nitrogen oxide ( 327: 435:
In July 2004, a tank exploded burning two workers. They would later die from their injuries. AEP determined the cause was due to a sudden release of molten
1348: 660: 72: 56: 1413: 1124: 845: 1408: 767: 502: 816: 557: 384: 334:, the contractor who installed the FGD equipment, to address the corrosion. When Units 5 and 6 went into operation, $ 52 million in 1418: 219: 1204: 1051: 291: 478: 323: 275: 265:. All plant operations were handled by AEP. Conesville began operations in 1957 and ceased generation in April 2020. 303: 246: 1098: 379:
When the first unit went into operation, it was projected that Conesville would use between 300,000 and 400,000
664: 319: 310:
from going into the atmosphere. ESPs were later installed to Units 1–3 in the mid-1970s. Unit 4 also had
1077:"THERMALONOx demonstration project at AEP's Conesville Plant suggests need for additional laboratory research" 258: 149: 793: 254: 1226: 112: 585: 30: 412:'s capacity auction, and AEP unable to find a buyer. The facility was imploded on December 19, 2021. 409: 290:. Three years later in 2017, Dynegy sold its stake in Conesville in a swap with AEP for a stake of 198: 429: 401: 331: 294:. At the time of its closure in 2020, DP&L held a minority ownership of Unit 4 with AEP. 250: 60: 1352: 315: 262: 186: 153: 405: 350: 339: 638: 1362: 470: 311: 428:. The protestors spent three days on top of the smokestack. They were charged with 895:"AEP announces additional environmental investments at five plants in four states" 432:. The judge fined both protestors $ 250 and were sentenced to three days in jail. 920: 894: 456: 283: 279: 1267: 1177: 1150: 996: 943: 867: 741: 715: 611: 530: 446: 421: 1022: 686: 87: 74: 464: 425: 380: 424:
climbed up one of Conesville Power Plant's smokestacks to protest against
228: 335: 242: 204: 971:"Failing Pollution Scrubbers – 'Aggressive' decay eats at power plants" 307: 287: 436: 176: 846:"AEP plans to shut down Conesville coal plant in Ohio by 2020" 1205:"AEP to retire 750 MW of coal capacity at Conesville plant" 257:. Its units were co-owned at the time of its closing by 1247:. The Associated Press. February 11, 1982. p. 17-A 1294:"AEP Employee Dies 2 Weeks After Conesville Explosion" 314:
constructed which resulted in zero discharge into the
1241:"Smokestack sitters extend vigil without any regrets" 768:
Interconnection Service Agreement (PJM Queue #Y1-018)
716:"C&SOE Initiates Newest Electric Generating Unit" 1178:"Conesville plant labeled as a top-5 metal polluter" 318:. In 2009, Unit 4 would receive the installation of 1149:Dickerson, Kathie; Whiteman, Doug (June 10, 2011). 215: 210: 197: 192: 182: 172: 167: 159: 145: 131: 111: 103: 66: 52: 44: 23: 1399:Buildings and structures in Coshocton County, Ohio 868:"Conesville Unit 4 Contributing To CSOE Operation" 1321:"AEP officials determine cause of fatal accident" 742:"C&SOE's Leppla Met Challenge Of Past Winter" 586:"2 units at AEP Conesville plant to be shuttered" 710: 708: 612:"Conesville Power Plant Began Operating in 1958" 1052:"AEP to test nitrogen oxide control technology" 531:"Top Executives Tell of Conesville Power Plant" 496: 494: 773:(Report). PJM Interconnection. October 1, 2013 558:"AEP Conesville still fired up after 60 years" 525: 523: 1118: 1116: 1099:"Coal Data Browser – Shipments to Conesville" 817:"AEP, Dynegy swap Ohio power plant ownership" 326:(SCR) system to meet the requirements of the 8: 1029:. Associated Press. June 5, 1978. p. 11 839: 837: 1125:"AEP Conesville Plant to close by May 2020" 580: 578: 1071: 1069: 914: 912: 396:December 2012 in order to comply with the 20: 16:Coal power plant in Coshocton County, Ohio 1101:. Energy Information Administration (EIA) 1404:Former coal-fired power stations in Ohio 1349:DP&L Page for Conesville Power Plant 365: 356: 345: 1394:Energy infrastructure completed in 1978 1389:Energy infrastructure completed in 1976 1384:Energy infrastructure completed in 1973 1379:Energy infrastructure completed in 1962 1374:Energy infrastructure completed in 1959 1369:Energy infrastructure completed in 1957 1079:. Power Engineering. September 28, 2001 501:Hayhurst, Leonard L. (April 30, 2020). 490: 220:Related media on Commons 1227:"Towers at Former AEP Plant Come Down" 1176:Dickerson, Kathie (January 13, 2013). 1046: 1044: 420:In February 1982, two protestors from 1123:Hayhurst, Leonard (October 5, 2018). 919:McHenry, Melissa (January 17, 2008). 794:"Dynegy to buy 12,500 MW for $ 6.25B" 556:Hayhurst, Leonard (August 24, 2017). 7: 1266:Weidner, Nolan (February 12, 1982). 1207:. S&P Global Market Intelligence 848:. S&P Global Market Intelligence 792:Savenije, Davide (August 22, 2014). 687:"Conesville power plant constructed" 383:of coal each year. According to the 338:technology were installed to reduce 1319:Douglas, Kristy (August 12, 2004). 844:Sweeney, Darren (October 8, 2018). 503:"AEP Conesville reaches end of era" 57:Franklin Township, Coshocton County 1054:. Power Engineering. March 8, 2001 942:Dickerson, Kathie (May 14, 2009). 893:McHenry, Melissa (June 17, 2005). 14: 1355: (archived February 13, 2019) 637:Waitkus, Dave (January 7, 2013). 385:Energy Information Administration 306:(ESPs) were installed to prevent 302:With the installation of Unit 4, 1203:Sweeney, Darren (May 13, 2019). 1003:. October 15, 1975. p. 10-B 463: 449: 286:sold its stake in Conesville to 168:Thermal power station 29: 969:Hunt, Spencer (July 11, 2011). 815:Knox, Tom (February 24, 2017). 693:. January 27, 1971. p. D-3 641:. American Electric Power (AEP) 328:Environmental Protection Agency 292:William H. Zimmer Power Station 1414:2020 disestablishments in Ohio 1268:"Protestors Sentenced To Jail" 874:. April 28, 1974. p. 18-A 479:List of power stations in Ohio 35:Conesville Power Plant in 2020 1: 1023:"Governor Blasts Federal EPA" 944:"New unit ready to go online" 439:that overpressured the tank. 324:selective catalytic reduction 322:(FGD) equipment along with a 163:American Electric Power (AEP) 748:. April 30, 1978. p. 2B 722:. April 24, 1977. p. 8C 618:. August 20, 1961. p. 9 398:Environmental Protect Agency 278:(CG&E) (a forerunner of 1409:1957 establishments in Ohio 1300:. July 29, 2004. p. 8C 1282:– via Newspapers.com. 1192:– via Newspapers.com. 1165:– via Newspapers.com. 1037:– via Newspapers.com. 1011:– via Newspapers.com. 958:– via Newspapers.com. 882:– via Newspapers.com. 756:– via Newspapers.com. 730:– via Newspapers.com. 701:– via Newspapers.com. 626:– via Newspapers.com. 545:– via Newspapers.com. 304:electrostatic precipitators 276:Cincinnati Gas and Electric 1435: 1334:– via Newsbank.com. 1308:– via Newsbank.com. 1255:– via Newsbank.com. 1151:"AEP may close six sites" 985:– via Newsbank.com. 663:. DPL Inc. Archived from 537:. July 5, 1955. p. 6 225: 40: 28: 320:flue-gas desulfurization 298:Environmental mitigation 150:AEP Generation Resources 1419:American Electric Power 821:Columbus Business First 590:Columbus Business First 259:American Electric Power 241:was a 2-gigwatt (2,005 199:Nameplate capacity 139:Units 5–6: May 31, 2019 1027:The Circleville Herald 997:"Firm Awards Contract" 400:(EPA) rules regarding 255:Coshocton County, Ohio 239:Conesville Power Plant 141:Unit 4: April 29, 2020 132:Decommission date 24:Conesville Power Plant 1298:The Columbus Dispatch 975:The Columbus Dispatch 193:Power generation 88:40.18611°N 81.87861°W 1229:. December 19, 2021. 371:) emission levels." 113:Commission date 661:"Conesville Unit 4" 410:PJM Interconnection 263:AES Ohio Generation 211:External links 183:Cooling source 154:AES Ohio Generation 93:40.18611; -81.87861 84: /  1325:The Times Reporter 1001:The Times Recorder 691:The Times Reporter 332:Black & Veatch 1272:Coshocton Tribune 1182:Coshocton Tribune 1155:Coshocton Tribune 1129:Coshocton Tribune 948:Coshocton Tribune 872:Coshocton Tribune 746:Coshocton Tribune 720:Coshocton Tribune 616:Coshocton Tribune 592:. October 3, 2005 562:Coshocton Tribune 535:Coshocton Tribune 507:Coshocton Tribune 430:criminal trespass 236: 235: 173:Primary fuel 1426: 1336: 1335: 1333: 1331: 1316: 1310: 1309: 1307: 1305: 1290: 1284: 1283: 1281: 1279: 1263: 1257: 1256: 1254: 1252: 1245:The Plain Dealer 1237: 1231: 1230: 1223: 1217: 1216: 1214: 1212: 1200: 1194: 1193: 1191: 1189: 1173: 1167: 1166: 1164: 1162: 1146: 1140: 1139: 1137: 1135: 1120: 1111: 1110: 1108: 1106: 1095: 1089: 1088: 1086: 1084: 1073: 1064: 1063: 1061: 1059: 1048: 1039: 1038: 1036: 1034: 1019: 1013: 1012: 1010: 1008: 993: 987: 986: 984: 982: 966: 960: 959: 957: 955: 939: 933: 932: 930: 928: 916: 907: 906: 904: 902: 890: 884: 883: 881: 879: 864: 858: 857: 855: 853: 841: 832: 831: 829: 827: 812: 806: 805: 803: 801: 789: 783: 782: 780: 778: 772: 764: 758: 757: 755: 753: 738: 732: 731: 729: 727: 712: 703: 702: 700: 698: 683: 677: 676: 674: 672: 667:on June 26, 2018 657: 651: 650: 648: 646: 634: 628: 627: 625: 623: 608: 602: 601: 599: 597: 582: 573: 572: 570: 568: 553: 547: 546: 544: 542: 527: 518: 517: 515: 513: 498: 473: 468: 467: 459: 454: 453: 452: 370: 361: 348: 251:Conesville, Ohio 249:located east of 247:coal power plant 229:edit on Wikidata 99: 98: 96: 95: 94: 89: 85: 82: 81: 80: 77: 61:Conesville, Ohio 33: 21: 1434: 1433: 1429: 1428: 1427: 1425: 1424: 1423: 1359: 1358: 1353:Wayback Machine 1345: 1340: 1339: 1329: 1327: 1318: 1317: 1313: 1303: 1301: 1292: 1291: 1287: 1277: 1275: 1265: 1264: 1260: 1250: 1248: 1239: 1238: 1234: 1225: 1224: 1220: 1210: 1208: 1202: 1201: 1197: 1187: 1185: 1175: 1174: 1170: 1160: 1158: 1148: 1147: 1143: 1133: 1131: 1122: 1121: 1114: 1104: 1102: 1097: 1096: 1092: 1082: 1080: 1075: 1074: 1067: 1057: 1055: 1050: 1049: 1042: 1032: 1030: 1021: 1020: 1016: 1006: 1004: 995: 994: 990: 980: 978: 968: 967: 963: 953: 951: 941: 940: 936: 926: 924: 921:"News Releases" 918: 917: 910: 900: 898: 892: 891: 887: 877: 875: 866: 865: 861: 851: 849: 843: 842: 835: 825: 823: 814: 813: 809: 799: 797: 796:. Utility Drive 791: 790: 786: 776: 774: 770: 766: 765: 761: 751: 749: 740: 739: 735: 725: 723: 714: 713: 706: 696: 694: 685: 684: 680: 670: 668: 659: 658: 654: 644: 642: 639:"End of an era" 636: 635: 631: 621: 619: 610: 609: 605: 595: 593: 584: 583: 576: 566: 564: 555: 554: 550: 540: 538: 529: 528: 521: 511: 509: 500: 499: 492: 487: 469: 462: 455: 450: 448: 445: 418: 393: 377: 369: 363: 360: 354: 347: 343: 316:Muskingum River 300: 271: 232: 187:Muskingum River 152: 140: 138: 136: 126: 124: 122: 120: 118: 92: 90: 86: 83: 78: 75: 73: 71: 70: 36: 17: 12: 11: 5: 1432: 1430: 1422: 1421: 1416: 1411: 1406: 1401: 1396: 1391: 1386: 1381: 1376: 1371: 1361: 1360: 1357: 1356: 1344: 1343:External links 1341: 1338: 1337: 1311: 1285: 1258: 1232: 1218: 1195: 1168: 1141: 1112: 1090: 1065: 1040: 1014: 988: 961: 934: 908: 885: 859: 833: 807: 784: 759: 733: 704: 678: 652: 629: 603: 574: 548: 519: 489: 488: 486: 483: 482: 481: 475: 474: 460: 444: 441: 417: 414: 392: 389: 376: 373: 351:nitrogen oxide 340:sulfur dioxide 312:cooling towers 299: 296: 270: 267: 234: 233: 226: 223: 222: 217: 213: 212: 208: 207: 201: 195: 194: 190: 189: 184: 180: 179: 174: 170: 169: 165: 164: 161: 157: 156: 147: 143: 142: 135:Unit 1–2: 2005 133: 129: 128: 115: 109: 108: 107:Decommissioned 105: 101: 100: 68: 64: 63: 54: 50: 49: 46: 42: 41: 38: 37: 34: 26: 25: 15: 13: 10: 9: 6: 4: 3: 2: 1431: 1420: 1417: 1415: 1412: 1410: 1407: 1405: 1402: 1400: 1397: 1395: 1392: 1390: 1387: 1385: 1382: 1380: 1377: 1375: 1372: 1370: 1367: 1366: 1364: 1354: 1350: 1347: 1346: 1342: 1326: 1322: 1315: 1312: 1299: 1295: 1289: 1286: 1273: 1269: 1262: 1259: 1246: 1242: 1236: 1233: 1228: 1222: 1219: 1206: 1199: 1196: 1183: 1179: 1172: 1169: 1156: 1152: 1145: 1142: 1130: 1126: 1119: 1117: 1113: 1100: 1094: 1091: 1078: 1072: 1070: 1066: 1053: 1047: 1045: 1041: 1028: 1024: 1018: 1015: 1002: 998: 992: 989: 976: 972: 965: 962: 950:. p. 1-A 949: 945: 938: 935: 922: 915: 913: 909: 896: 889: 886: 873: 869: 863: 860: 847: 840: 838: 834: 822: 818: 811: 808: 795: 788: 785: 769: 763: 760: 747: 743: 737: 734: 721: 717: 711: 709: 705: 692: 688: 682: 679: 666: 662: 656: 653: 640: 633: 630: 617: 613: 607: 604: 591: 587: 581: 579: 575: 563: 559: 552: 549: 536: 532: 526: 524: 520: 508: 504: 497: 495: 491: 484: 480: 477: 476: 472: 471:Energy portal 466: 461: 458: 447: 442: 440: 438: 433: 431: 427: 423: 415: 413: 411: 407: 403: 399: 390: 388: 386: 382: 374: 372: 368: 359: 352: 341: 337: 333: 329: 325: 321: 317: 313: 309: 305: 297: 295: 293: 289: 285: 281: 277: 268: 266: 264: 260: 256: 252: 248: 244: 240: 230: 224: 221: 218: 214: 209: 206: 202: 200: 196: 191: 188: 185: 181: 178: 175: 171: 166: 162: 158: 155: 151: 148: 144: 134: 130: 116: 114: 110: 106: 102: 97: 69: 65: 62: 58: 55: 51: 48:United States 47: 43: 39: 32: 27: 22: 19: 1328:. Retrieved 1324: 1314: 1302:. Retrieved 1297: 1288: 1276:. Retrieved 1271: 1261: 1249:. Retrieved 1244: 1235: 1221: 1209:. Retrieved 1198: 1186:. Retrieved 1184:. p. 3A 1181: 1171: 1159:. Retrieved 1157:. p. 1A 1154: 1144: 1132:. Retrieved 1128: 1103:. Retrieved 1093: 1081:. Retrieved 1056:. Retrieved 1031:. Retrieved 1026: 1017: 1005:. Retrieved 1000: 991: 979:. Retrieved 977:. p. 1A 974: 964: 952:. Retrieved 947: 937: 925:. Retrieved 899:. Retrieved 888: 876:. Retrieved 871: 862: 850:. Retrieved 824:. Retrieved 820: 810: 798:. Retrieved 787: 775:. Retrieved 762: 750:. Retrieved 745: 736: 724:. Retrieved 719: 695:. Retrieved 690: 681: 669:. Retrieved 665:the original 655: 643:. Retrieved 632: 620:. Retrieved 615: 606: 594:. Retrieved 589: 565:. Retrieved 561: 551: 539:. Retrieved 534: 510:. Retrieved 506: 434: 419: 394: 378: 366: 357: 301: 272: 238: 237: 137:Unit 3: 2012 127:Unit 6: 1978 125:Unit 5: 1976 123:Unit 4: 1973 121:Unit 3: 1962 119:Unit 2: 1959 117:Unit 1: 1957 18: 1274:. p. 1 457:Ohio portal 284:Duke Energy 280:Duke Energy 160:Operator(s) 91: / 67:Coordinates 1363:Categories 1134:October 5, 852:October 8, 485:References 422:Greenpeace 391:Retirement 381:short tons 375:Operations 261:(AEP) and 79:81°52′43″W 76:40°11′10″N 512:April 30, 426:acid rain 416:Incidents 1330:June 26, 1304:June 26, 1278:June 26, 1251:June 26, 1188:June 20, 1161:June 20, 1105:June 18, 1083:June 25, 1058:June 25, 1033:June 24, 1007:June 24, 981:June 26, 954:June 25, 927:June 24, 901:June 24, 878:June 24, 826:June 21, 800:June 21, 777:June 26, 752:June 26, 726:June 26, 697:June 24, 671:June 21, 645:June 26, 622:June 26, 596:June 20, 567:June 18, 541:June 24, 443:See also 336:scrubber 146:Owner(s) 53:Location 1351:at the 1211:May 31, 402:mercury 308:fly ash 269:History 216:Commons 59:, near 45:Country 288:Dynegy 203:2,005 104:Status 923:. AEP 897:. AEP 771:(PDF) 227:[ 1332:2018 1306:2018 1280:2018 1253:2018 1213:2019 1190:2018 1163:2018 1136:2018 1107:2018 1085:2018 1060:2018 1035:2018 1009:2018 983:2018 956:2018 929:2018 903:2018 880:2018 854:2018 828:2018 802:2018 779:2018 754:2018 728:2018 699:2018 673:2018 647:2018 624:2018 598:2018 569:2018 543:2018 514:2020 437:slag 406:lead 177:Coal 253:in 245:), 1365:: 1323:. 1296:. 1270:. 1243:. 1180:. 1153:. 1127:. 1115:^ 1068:^ 1043:^ 1025:. 999:. 973:. 946:. 911:^ 870:. 836:^ 819:. 744:. 718:. 707:^ 689:. 614:. 588:. 577:^ 560:. 533:. 522:^ 505:. 493:^ 404:, 364:NO 355:NO 344:SO 243:MW 205:MW 1215:. 1138:. 1109:. 1087:. 1062:. 931:. 905:. 856:. 830:. 804:. 781:. 675:. 649:. 600:. 571:. 516:. 367:x 358:x 353:( 346:2 342:( 231:]

Index


Franklin Township, Coshocton County
Conesville, Ohio
40°11′10″N 81°52′43″W / 40.18611°N 81.87861°W / 40.18611; -81.87861
Commission date
AEP Generation Resources
AES Ohio Generation
Coal
Muskingum River
Nameplate capacity
MW
Related media on Commons
edit on Wikidata
MW
coal power plant
Conesville, Ohio
Coshocton County, Ohio
American Electric Power
AES Ohio Generation
Cincinnati Gas and Electric
Duke Energy
Duke Energy
Dynegy
William H. Zimmer Power Station
electrostatic precipitators
fly ash
cooling towers
Muskingum River
flue-gas desulfurization
selective catalytic reduction

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.