Knowledge (XXG)

Kilsby Tunnel

Source 📝

286: 333: 341: 29: 377:, Network Rail took the rare opportunity to close the tunnel for two weeks in May 2020 in order to carry out major works, including replacing much of the tunnel's drainage system, which had become clogged by heavily limed water seeping through, causing flooding problems, and also replacing much of the track and ballast. This was the longest total closure of the tunnel since it was opened, with all trains diverted temporarily via 363:; furthermore, the two largest ventilation shafts were also listed, the north shaft being Grade II* listed while the south shaft was Grade II listed. During the tunnel's service life, there have been no major problems or difficulties with the structure. During a survey conducted during the 2010s, it was found to be in a largely good condition. 197:(L&BR). It was constructed by contractors Joseph Nowell & Sons and later by the L&BR. It took much longer to construct and exceeded its estimated cost, attributed to a roof collapse and consequential flooding. At the time of its opening in 1838, it was the longest railway tunnel ever constructed. 320:
On 21 June 1838, resident engineer Charles Lean laid the final brick of the tunnel, marking its completion. It took three years, and cost £320,000 to build, (equivalent to £36,390,000 in 2023) three times the original estimate. The high accident rate in the course of its construction included the
293:
An unusual feature of the tunnel is the size of its ventilation shafts, which were adapted from ten of the working shafts used during its construction. In May 1836, work started on the first of two shafts, which were 132 feet deep and 20 yards in diameter. The shafts were sunk using sequentially dug
249:
to authorise construction of the line. Stephenson surveyed an alternative route to the west of the town that included Kilsby Tunnel. The 2,423 yard tunnel would be the world's longest railway tunnel. In May 1835, Joseph Nowell & Sons was awarded the tunnel contract, which was valued at £98,988
306:
Author Graeme Bickerdike has speculated that, while their size is excessive in regards to providing airflow, considerable importance was placed on overcoming public perceptions and worries over personal health due to insufficient ventilation, especially in regards to the use of steam locomotives
277:
were installed to extract water from the quicksand inside the tunnel. The pumps removed up to 2,000 gallons of water from a depth of 120 feet every minute of operation and took up to eight months. Seven more shafts were sunk to install timber cylinders to hold back the sand. During this time,
370:. Maintenance focused on inspecting the ventilation shafts and repairs to the brickwork of one shaft was carried out, sections of the tunnel's lining were replaced. While unusual means of access were used because of the listed status of the shafts, the repairs were described as routine. 381:. In normal times the work would have required many short blockades, and taken months to complete. It allowed a temporary speed restriction through the tunnel of 70 mph to be lifted, enabling trains to operate at the normal line speed of 110 mph. 265:
a few decades earlier. Problems posed by the quicksand at tunnel level were so severe that abandoning the shaft and restarting work elsewhere was considered. Stress from the project was said to have caused Joseph Nowell's ill-health and death.
278:
multiple attempts were made to construct the tunnel's brick lining using a raft to float men and materials into position. As a protective measure, the lining's thickness was increased from 18 inches to in excess of two feet and
298:
around the circumference and took over a year to reach the bottom of each shaft. Its three-foot-thick walls required over one million bricks and weighed an estimated 4,034 tonnes. For aesthetic reasons both shafts are
311:
had negatively commented on the issues, and it is likely that Stephenson would have wanted to silence critics and assuage these sentiments by visibly demonstrating how much ventilation was being provided.
321:
deaths of 26 of the 1,250 workers. The length of time it took to build delayed the opening of the L&BR. On 20 August 1838, the directors of the L&BR conducted the first ever rail journey between
352:, one at either end of the tunnel, who signalled the presence of a train to each other, and only one train was allowed to enter the tunnel at a time. In June 1852, a fatal collision occurred between a 329:, London. On the way, the train briefly stopped at the tunnel so that they could marvel at the structure and meet some of the workmen. Regular services using the tunnel commenced soon after. 208:
to pass through. On opening in 1838, the tunnel was single track and in 1879, double-track was laid. In March 1987, Kilsby Tunnel portals and its two ventilation shafts were given
682: 322: 253:
Construction proved to be less than straightforward. Within months of work commencing, the second of the working shafts was flooded because of large amounts of
574: 677: 348:
Kilsby Tunnel had been designed for double tracks, but opened with a single track. During early operations, train movements were controlled by two
702: 692: 373:
At the beginning of 2020, an estimated 400 trains were using the tunnel daily. Due to the drastic reduction in rail traffic caused by the
687: 61: 356:
train and a coal train as a result of signals that were either not issued or were not received. In 1879, the single track was doubled.
697: 634: 609: 629: 604: 285: 282:
was used to deflect and control the ingress of water to prevent wet concrete from being washed away from newly laid bricks.
230: 194: 54: 378: 460: 552: 660:
of an air shaft by Si Horton using data collected by Colin Humphreys using a Faro Focus X330 laser scanner (on
332: 340: 257:
not revealed by trial borings into the hill. Similar problems had been encountered during the construction of
106: 28: 326: 155: 536: 393: 234: 171: 131: 183: 485: 374: 270: 262: 226: 201: 190: 625: 600: 258: 205: 179: 47: 399: 360: 209: 575:"Longest tunnel closure since Victorian-era improves West Coast main line journey times" 496: 242: 671: 353: 518: 367: 300: 274: 121: 651: 491: 204:, because of a lack of experience as to how much ventilation would be needed for 238: 492:"The Annual RPI and Average Earnings for Britain, 1209 to Present (New Series)" 657: 246: 76: 63: 308: 254: 33:
Air shaft in the Kilsby Tunnel, illustrated in an 1852 railway publication
661: 359:
In March 1987, both the north and south portals of Kilsby Tunnel were
349: 336:
Drawing from 1839 of one of the tunnel portals shortly after opening.
295: 175: 96: 339: 331: 284: 279: 237:). After opposition from several landowners and proprietors in 654:
includes the classic image of the tunnel under construction.
461:"Stairway to heaven: shaft repairs at Kilsby tunnel" 150: 142: 137: 127: 117: 112: 102: 92: 53: 43: 38: 630:"South Ventilation Shaft, Kilsby Tunnel (1343043)" 605:"North Ventilation Shaft, Kilsby Tunnel (1076406)" 189:The Kilsby Tunnel was designed and engineered by 366:During the 2010s, Kilsby Tunnel was restored by 454: 452: 450: 448: 446: 444: 442: 440: 438: 436: 532: 530: 528: 480: 478: 434: 432: 430: 428: 426: 424: 422: 420: 418: 416: 289:One of the ventilation towers above the tunnel 8: 683:Buildings and structures in Northamptonshire 21: 182:, roughly 5 miles (8 km) southeast of 16:Railway tunnel in Northamptonshire, England 186:. It is 2,423 yards (2,216 m) long. 27: 20: 488:inflation figures are based on data from 553:"Kilsby tunnel work planned in 10 days!" 323:Birmingham Curzon Street railway station 250:(equivalent to £12,310,000 in 2023) 412: 7: 459:Bickerdike, Graeme (27 April 2018). 316:Completion and subsequent activities 344:South portal of the tunnel in 2005. 678:Rail transport in Northamptonshire 635:National Heritage List for England 610:National Heritage List for England 14: 307:inside lengthy tunnels. Several 200:The tunnel had atypically large 174:in England, near the village of 233:(L&BR) (later known as the 231:London & Birmingham Railway 195:London & Birmingham Railway 151: 1: 703:London and Birmingham Railway 555:. Rail Insider. 15 June 2020 693:Tunnels in Northamptonshire 577:. Network Rail. 18 May 2020 170:is a railway tunnel on the 719: 688:Railway tunnels in England 698:Tunnels completed in 1838 540:engineering-timelines.com 269:At the recommendation of 26: 542:, Retrieved: 6 May 2018. 521:. Spartacus Educational. 389:Other L&BR tunnels: 490:Clark, Gregory (2017). 345: 337: 327:Euston railway station 290: 245:rejected the original 343: 335: 288: 394:Primrose Hill Tunnel 235:West Coast Main Line 172:West Coast Main Line 132:West Coast Main Line 275:steam-powered pumps 73: /  23: 486:Retail Price Index 346: 338: 291: 241:in July 1832, the 202:ventilation shafts 375:COVID-19 pandemic 271:George Stephenson 263:Grand Union Canal 227:Robert Stephenson 206:steam locomotives 191:Robert Stephenson 164: 163: 710: 646: 644: 642: 626:Historic England 621: 619: 617: 601:Historic England 587: 586: 584: 582: 571: 565: 564: 562: 560: 549: 543: 537:"Kilsby Tunnel." 534: 523: 522: 515: 509: 508: 506: 504: 482: 473: 472: 470: 468: 456: 361:Grade II* listed 259:Blisworth Tunnel 180:Northamptonshire 153: 88: 87: 85: 84: 83: 78: 77:52.331°N 1.164°W 74: 71: 70: 69: 66: 48:Northamptonshire 31: 24: 718: 717: 713: 712: 711: 709: 708: 707: 668: 667: 640: 638: 624: 615: 613: 599: 596: 591: 590: 580: 578: 573: 572: 568: 558: 556: 551: 550: 546: 535: 526: 519:"Kilsby Tunnel" 517: 516: 512: 502: 500: 489: 483: 476: 466: 464: 463:. Rail Engineer 458: 457: 414: 409: 402:, Hertfordshire 400:Watford Tunnels 387: 318: 223: 218: 81: 79: 75: 72: 67: 64: 62: 60: 59: 34: 17: 12: 11: 5: 716: 714: 706: 705: 700: 695: 690: 685: 680: 670: 669: 666: 665: 655: 648: 647: 622: 595: 594:External links 592: 589: 588: 566: 544: 524: 510: 497:MeasuringWorth 474: 411: 410: 408: 405: 404: 403: 397: 386: 383: 317: 314: 243:House of Lords 229:developed the 225:In the 1830s, 222: 219: 217: 214: 162: 161: 158: 148: 147: 144: 140: 139: 135: 134: 129: 125: 124: 119: 115: 114: 110: 109: 104: 100: 99: 94: 90: 89: 82:52.331; -1.164 57: 51: 50: 45: 41: 40: 36: 35: 32: 15: 13: 10: 9: 6: 4: 3: 2: 715: 704: 701: 699: 696: 694: 691: 689: 686: 684: 681: 679: 676: 675: 673: 663: 659: 658:A short video 656: 653: 652:Kilsby Tunnel 650: 649: 637: 636: 631: 627: 623: 612: 611: 606: 602: 598: 597: 593: 576: 570: 567: 554: 548: 545: 541: 538: 533: 531: 529: 525: 520: 514: 511: 499: 498: 493: 487: 481: 479: 475: 462: 455: 453: 451: 449: 447: 445: 443: 441: 439: 437: 435: 433: 431: 429: 427: 425: 423: 421: 419: 417: 413: 406: 401: 398: 395: 392: 391: 390: 384: 382: 380: 376: 371: 369: 364: 362: 357: 355: 351: 342: 334: 330: 328: 324: 315: 313: 310: 304: 302: 297: 287: 283: 281: 276: 272: 267: 264: 260: 256: 251: 248: 244: 240: 236: 232: 228: 220: 215: 213: 211: 210:listed status 207: 203: 198: 196: 192: 187: 185: 181: 177: 173: 169: 168:Kilsby Tunnel 159: 157: 149: 145: 141: 136: 133: 130: 126: 123: 120: 116: 111: 108: 105: 101: 98: 95: 91: 86: 58: 56: 52: 49: 46: 42: 37: 30: 25: 22:Kilsby Tunnel 19: 639:. Retrieved 633: 614:. Retrieved 608: 579:. Retrieved 569: 557:. Retrieved 547: 539: 513: 501:. Retrieved 495: 465:. Retrieved 388: 372: 368:Network Rail 365: 358: 347: 319: 305: 292: 268: 252: 224: 221:Construction 199: 188: 167: 165: 143:Track length 122:Network Rail 18: 379:Northampton 301:castellated 239:Northampton 80: / 55:Coordinates 672:Categories 407:References 309:newspapers 273:, several 65:52°19′52″N 350:policeman 255:quicksand 138:Technical 113:Operation 68:1°09′50″W 396:, London 385:See also 296:trenches 193:for the 128:Operator 44:Location 39:Overview 662:YouTube 641:1 March 616:1 March 354:ballast 261:on the 216:History 146:2,216 m 581:5 July 559:5 July 467:5 July 176:Kilsby 156:tracks 97:Kilsby 503:7 May 280:straw 184:Rugby 118:Owner 107:Crick 93:Start 643:2023 618:2023 583:2020 561:2020 505:2024 469:2020 325:and 247:bill 166:The 484:UK 303:. 178:in 160:Two 154:of 152:No. 103:End 674:: 632:. 628:. 607:. 603:. 527:^ 494:. 477:^ 415:^ 212:. 664:) 645:. 620:. 585:. 563:. 507:. 471:.

Index


Northamptonshire
Coordinates
52°19′52″N 1°09′50″W / 52.331°N 1.164°W / 52.331; -1.164
Kilsby
Crick
Network Rail
West Coast Main Line
tracks
West Coast Main Line
Kilsby
Northamptonshire
Rugby
Robert Stephenson
London & Birmingham Railway
ventilation shafts
steam locomotives
listed status
Robert Stephenson
London & Birmingham Railway
West Coast Main Line
Northampton
House of Lords
bill
quicksand
Blisworth Tunnel
Grand Union Canal
George Stephenson
steam-powered pumps
straw

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.