Knowledge (XXG)

Pajares Base Tunnel

Source 📝

181:
measures, such as polymeric paste injection and polymeric membranes, proved insufficient, while additional excavation was prohibitively expensive due to the walls being largely complete already. Instead, engineers turned to unorthodox means of channeling the water by installing a first-of-its-kind composite lining. After four years of work, the rate of water infiltration had been reduced by 40 percent. By 2014, the difficulties of constructing the Pajares Base Tunnel had become thoroughly apparent. Over the course of one decade, the initial plans of the tunnel were altered on 15 occasions. The costs of its construction has overrun substantially, rising to €3 billion against the originally budgeted price of €1.8 billion.
177:
sealing the tunnel against water infiltration. Furthermore, the geological conditions surrounding the tunnel featured multiple areas of high compressive tectonic stress regimes, such as thrust faults, which necessitated greater levels of support to be installed in the tunnel than had been originally anticipated. Despite this, the boring process was completed eight months ahead of schedule. On 11 July 2009, a ceremony was held to mark the completion of the tunnels.
20: 62:
deployment of unique engineering solutions, the infiltration issue has proved to be difficult to address, and questions have arisen as to if its electrification is even practical. As a result, the fitting-out of the tunnel has been delayed by several years. Early on, the through route was expected to be open in 2010. Finally, the tunnels were opened to passenger traffic the 30th November 2023.
106:. It was reportedly regarded as being one of the largest and most challenging civil engineering projects anywhere in Europe at that time. The tunnel would replace a relatively steep and winding conventional route through the mountains that had limited train speeds to a maximum speed of 70 kmph, while the new line was envisioned to facilitate speeds of up to 300 kmph. 61:
Work commenced on the Pajares Base Tunnel following its authorisation in 2003. During the construction process, multiple setbacks were incurred on the part of the geological conditions present, particularly the copious ingress of water into the tunnels. Despite multiple years of remedial work and the
176:
in the vicinity of the bores had been previously identified by surveys undertaken in the 1980s; accordingly, vast quantities of water continuously infiltrated into the bores. It has been alleged by construction workers that management had prioritised maintaining a high rate of progress over properly
180:
However, despite this milestone being attained, the fitting-out of the tunnel proceeded at a very slow rate due to the water infiltration issue; up to 2,200 liters of water was reportedly entering the tunnel every second, much of it via cracks in its concrete walls. Conventional waterproofing
168:) between July and September 2005 on the León slope and between April and July 2006 on the Asturian slope. The tunnel boring machines extracted 4.3 million m³ from the tunnels. The bulk of the excavation work for the Pajares Base Tunnel was performed by 98:, forming a part of the main line between Madrid - Oviedo main line. The most prominent civil engineering work of this line is the twin-bore Pajares Base Tunnel, which necessitated a length of 24,667 m (80,928 ft) to traverse the 109:
During 2003, the Public Works Ministry awarded a €1.8 billion contract for the Pajares Base Tunnel's construction to a consortium involving the majority of Spain’s major civil engineering firms, including
200:
to supply tunnel safety and security systems for the 12 tunnels of the Pajares New Line project, including the Pajares Base Tunnel. Despite plans for the tunnel to be electrified by
233: 346: 495: 442: 204:
throughout its 24,667 m (80,928 ft) length, questions have been raised if electrification is feasible due to the high level of water infiltration present.
259: 185: 79: 590: 546: 605: 456:
Pablo Valenzuela, María José Domínguez-Cuesta, Mónica Meléndez-Asensio, Montserrat Jiménez-Sánchez, José Antonio Sáenz de Santa Marí (2015).
510: 610: 332: 585: 535: 595: 153:
as well. It had been anticipated that the completed tunnel would facilitate a journey time of 2 hours and 12 minutes between
213: 172:(TBMs). The construction soon encountered substantial amounts of underground water, the presence of relatively porous 527: 398: 312: 197: 298: 234:"Asturias goes through the time tunnel: great chronicle of the historic day in which the Variant saw the light" 138: 131: 457: 150: 135: 600: 489: 436: 169: 417:"In-situ stress amplification due to geological factors in tunnels: The case of Pajares tunnels, Spain" 103: 43: 134:. As originally planned, both bores of the Pajares Base Tunnel would have been furnished only with 380: 458:"Active sinkholes: A geomorphological impact of the Pajares Tunnels (Cantabrian Range, NW Spain)" 164:
Its execution began with five TBMs (four for the large tubes and the fifth for the gallery from
87: 477: 99: 39: 469: 424: 83: 58:, and can be used by both high speed passenger trains as well as by slower freight trains. 51: 71: 579: 416: 146: 70:
During the early decades of the 21st century, Spain allocated a large proportion of
19: 95: 473: 428: 145:
arrangement would be installed instead, as it was thought that the presence of
260:"Spanish high-speed line under mountains opens after 20 years of construction" 142: 50:. The 24,667 m (80,928 ft) length tunnel forms a key portion of the 561: 548: 481: 123: 347:"Fomento prevé concluir las obras de la variante Pajares a finales de 2020" 201: 119: 91: 55: 115: 32: 189: 158: 154: 35: 193: 173: 165: 127: 47: 18: 511:"Adif awards €53m systems contract for Pajares New Line project" 78:
high speed rail network. On 1 March 2002, it was announced that
141:; however, mid-way through construction, it was decided that a 111: 75: 299:"€1.2 billion over budget and still no opening date in sight" 333:"Composites perform water rescue in high-speed rail tunnel" 74:-supplied infrastructure funding into the expansion of its 90:
for the design of a new 50 km high speed railway between
381:"Pajares: A Wet, Warm Tunnel, and other White Elephants" 188:(ADIF) had awarded a €53m contract to a consortium of 326: 324: 322: 374: 372: 370: 368: 186:Administrador de Infraestructuras Ferroviarias 292: 290: 288: 286: 284: 282: 280: 149:would make the tunnel particularly useful to 8: 494:: CS1 maint: multiple names: authors list ( 441:: CS1 maint: multiple names: authors list ( 399:"Trend Analysis of Long Tunnels Worldwide" 184:During June 2020, it was announced that 225: 82:(GIF) had awarded a €5·18m contract to 80:Gestor de Infraestructuras Ferroviarias 487: 434: 415:Hijazo, T. and Vallejo, L.I. (2012). 7: 591:Buildings and structures in Asturias 315:. railwaygazette.com. 1 March 2002. 404:. Mineta Transportation Institute. 14: 509:Cuenca, Oliver (20 July 2020). 331:Mason, Karen (7 January 2018). 313:"Pajares base tunnel contract" 1: 297:Mendez, Rafael (7 May 2014). 606:Railway lines opened in 2023 474:10.1016/j.enggeo.2015.07.007 429:10.1016/j.enggeo.2012.03.007 397:Pyeon, Jae-Ho (March 2016). 198:San José Construction Group 627: 379:Bent, Mike (Autumn 2014). 353:(in Spanish). 15 June 2017 611:Tunnels completed in 2023 586:Railway tunnels in Spain 214:León-Gijón railway line 16:Railway tunnel in Spain 335:. compositesworld.com. 170:tunnel boring machines 132:Constructora Hispánica 54:line between León and 24: 596:Transport in Asturias 301:. english.elpais.com. 22: 562:43.01944°N 5.77528°W 423:. s 137–138: 13–20. 104:Cantabrian Mountains 44:Cantabrian Mountains 558: /  462:Engineering Geology 421:Engineering Geology 29:Pajares Base Tunnel 567:43.01944; -5.77528 513:. railjournal.com. 386:. eurorail.org.uk. 240:. 30 November 2023 31:is a twin pair of 25: 238:us.firenews.video 40:Puerto de Pajares 618: 573: 572: 570: 569: 568: 563: 559: 556: 555: 554: 551: 540: 532: 515: 514: 506: 500: 499: 493: 485: 453: 447: 446: 440: 432: 412: 406: 405: 403: 394: 388: 387: 385: 376: 363: 362: 360: 358: 343: 337: 336: 328: 317: 316: 309: 303: 302: 294: 275: 274: 272: 271: 256: 250: 249: 247: 245: 230: 626: 625: 621: 620: 619: 617: 616: 615: 576: 575: 566: 564: 560: 557: 552: 549: 547: 545: 544: 538: 530: 524: 519: 518: 508: 507: 503: 486: 455: 454: 450: 433: 414: 413: 409: 401: 396: 395: 391: 383: 378: 377: 366: 356: 354: 345: 344: 340: 330: 329: 320: 311: 310: 306: 296: 295: 278: 269: 267: 258: 257: 253: 243: 241: 232: 231: 227: 222: 210: 139:high-speed rail 68: 52:high-speed rail 23:Works on portal 17: 12: 11: 5: 624: 622: 614: 613: 608: 603: 598: 593: 588: 578: 577: 542: 541: 533: 523: 522:External links 520: 517: 516: 501: 448: 407: 389: 364: 338: 318: 304: 276: 251: 224: 223: 221: 218: 217: 216: 209: 206: 151:freight trains 136:standard gauge 72:European Union 67: 64: 15: 13: 10: 9: 6: 4: 3: 2: 623: 612: 609: 607: 604: 602: 599: 597: 594: 592: 589: 587: 584: 583: 581: 574: 571: 537: 534: 529: 526: 525: 521: 512: 505: 502: 497: 491: 483: 479: 475: 471: 467: 463: 459: 452: 449: 444: 438: 430: 426: 422: 418: 411: 408: 400: 393: 390: 382: 375: 373: 371: 369: 365: 352: 351:La Vanguardia 348: 342: 339: 334: 327: 325: 323: 319: 314: 308: 305: 300: 293: 291: 289: 287: 285: 283: 281: 277: 265: 261: 255: 252: 239: 235: 229: 226: 219: 215: 212: 211: 207: 205: 203: 199: 195: 191: 187: 182: 178: 175: 171: 167: 162: 160: 156: 152: 148: 147:Iberian gauge 144: 140: 137: 133: 129: 125: 121: 117: 113: 107: 105: 101: 97: 93: 89: 85: 81: 77: 73: 65: 63: 59: 57: 53: 49: 45: 41: 37: 34: 30: 21: 601:Base tunnels 543: 539:(in Spanish) 531:(in Spanish) 504: 490:cite journal 465: 461: 451: 437:cite journal 420: 410: 392: 355:. Retrieved 350: 341: 307: 268:. Retrieved 266:. 2023-12-01 263: 254: 242:. Retrieved 237: 228: 183: 179: 163: 108: 100:Pajares pass 96:Pola de Lena 69: 66:Construction 60: 42:pass in the 38:beneath the 28: 26: 565: / 536:Basic facts 528:Description 468:: 158–170. 244:30 November 580:Categories 550:43°01′10″N 270:2023-12-03 220:References 143:dual gauge 88:Geoconsult 553:5°46′31″W 482:0013-7952 161:by 2010. 124:Ferrovial 208:See also 202:25 kV AC 196:and the 120:Dragados 92:La Robla 357:5 March 116:Acciona 102:of the 36:tunnels 33:railway 480:  264:Trains 190:Alstom 159:Oviedo 155:Madrid 130:, and 402:(PDF) 384:(PDF) 194:Indra 174:karst 166:Buiza 128:Sacyr 84:Ineco 56:Gijón 48:Spain 496:link 478:ISSN 443:link 359:2020 246:2023 157:and 94:and 86:and 27:The 470:doi 466:196 425:doi 112:FCC 76:AVE 582:: 492:}} 488:{{ 476:. 464:. 460:. 439:}} 435:{{ 419:. 367:^ 349:. 321:^ 279:^ 262:. 236:. 192:, 126:, 122:, 118:, 114:, 46:, 498:) 484:. 472:: 445:) 431:. 427:: 361:. 273:. 248:.

Index


railway
tunnels
Puerto de Pajares
Cantabrian Mountains
Spain
high-speed rail
Gijón
European Union
AVE
Gestor de Infraestructuras Ferroviarias
Ineco
Geoconsult
La Robla
Pola de Lena
Pajares pass
Cantabrian Mountains
FCC
Acciona
Dragados
Ferrovial
Sacyr
Constructora Hispánica
standard gauge
high-speed rail
dual gauge
Iberian gauge
freight trains
Madrid
Oviedo

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.