Knowledge

Point Aconi Generating Station

Source đź“ť

406:
Aconi Generating Station) was not required as the province's generating needs were met by current sources. Coincidentally, Nova Scotia Power had also promised to purchase electricity from small independent power producers in the province beginning in 1990, however this agreement was abolished after the Small Private Power Association of Nova Scotia intervened at the PUB hearings to block the proposed Point Aconi Generating Station. On April 27, 1989, Buchanan introduced a controversial amendment to the
896: 665: 29: 681:
understanding between Mitsui & Co. (Point Aconi) Ltd. and Jones Power Co. fixed compensation for Jones Power Corporation at $ 118 million. The companies agreed to complete the project on November 5, 1992 and leave the contractual dispute after the project's conclusion. Additional documents were discovered after the MOU had been signed but were deemed to be protected by solicitor-client privilege or litigation privilege as detailed in
910: 459:. The hearing received submissions from citizens and organizations that were strongly opposed to the Point Aconi Generating Station, pointing out the environmental impact, that its generating capacity wasn't required, and that it was a political mega-project that would add to the financial debt of the publicly owned Nova Scotia Power Corporation. 884:, and the coal destined for the Point Aconi Generating Station was trucked the final distance to the plant. DEVCO closed the Prince Colliery, its last operating coal mine, on November 23, 2001; ironically, the original reason for constructing the Point Aconi Generating Station had been to secure the long-term viability of the Prince Colliery. 608:
January 18, 1991 by stating that the Department of Fisheries and Oceans acted in accordance with the law in deciding not to order a full environmental assessment of the project. MacKay noted that the project has resulted in substantial testing of ground water around the plant. He also noted that because there are no standards for CO
800:
The in-plant ash-handling system conveys fly ash from hoppers under the baghouse, economizer, and air heater, as well as bottom ash from the combustor, to either of two silos located outside the powerhouse. Once in the silos, the ash is conditioned with water, loaded into trucks, and transported to a
672:
Construction of the Point Aconi Generating Station began in early 1990 after Mitsui & Co. (Point Aconi) Ltd. contracted with Jones Power Corporation to act as construction manager and carry out construction work for the Point Aconi Generating Station project. Jones Power Corporation's obligations
655:
Mitsui formed Mitsui & Co. (Point Aconi) Ltd. as an extraprovincial corporation in another province on December 1, 1989 as a result of its RFP submission. Mitsui & Co. (Point Aconi) Ltd. was registered in Nova Scotia on February 12, 1990 after the contract was signed with Nova Scotia Power in
595:
emissions. The DFO scientists noted widespread mistrust of the provincial government's decision and that the controversial one-day hearing in January left the impression "of a cooked-up deal between the province and federal government to slip this project by without a fair assessment of its potential
631:
near Point Aconi was a member of this committee at that time and had questions about how emissions from the plant or ground water withdrawn for it would affect his crops or how losses would be compensated, stating, "We see all these little mistakes happening and we know we're going to get dumped on.
804:
Point Aconi uses a once-through circulating seawater system. Seawater is drawn from 1,000 m (3,300 ft) offshore at a depth of 11 m (36 ft) through a velocity cap intake structure. A tunnel 40 m (130 ft) below the seabed connects the offshore velocity cap to the onshore
796:
Point Aconi’s coal-handling system comprises an active 27,500-ton storage pile; an inactive storage pile of identical size; receiving hoppers, conveyors, crushing equipment; and four in-plant storage bunkers. The conveying system can handle 440 tons of coal per hour or about 550,000 tons per year.
792:
The drum-type reheat CFB boiler was designed to produce 547,550 kg/h (1,207,150 lb/h) of steam (maximum continuous rating) at 12,000 kPa (1,800 psi) and 538 Â°C (1,000 Â°F). Toshiba Corp. supplied the multicylinder, tandem-compound steam turbine-generator. The 3,600-rpm
405:
had authority to decide on all applications by Nova Scotia Power to construct new generating stations as well as associated rate increases. The PUB began to conduct hearings into the project in spring 1989 and stated that an economic analysis of Buchanan's election promise (the $ 500 million Point
844:
The Point Aconi Generating Station was originally designed to burn high sulphur coal mined in the Sydney Coal Field, which it sits atop. The primary source of coal was to be from the Prince Colliery, located 2 km (1.2 mi) east of the generating station property. The Prince Colliery was
607:
that Valcourt had made a legal error in rejecting a public environmental review panel and that federal Environmental Assessment Review Panel guidelines should be followed to institute a formal review of the $ 436 million project. Mr. Justice Andrew MacKay ruled against the application on Friday,
704:
Nova Scotia Power Corporation to remove public responsibility for the utility's $ 2.4 billion debt; Cameron stated that the debt had hurt the province's credit rating and that there had been allegations of political interference for setting electricity rates and decisions to build large power
680:
The Point Aconi Generating Station project ran into delays as a result of cost overruns, resulting in a series of prolonged contractual disputes that arose between 1991 and 1992. Jones Power Corporation claimed millions of dollars in additional compensation and a July 28, 1992 memorandum of
320:
which has four generating units, Point Aconi has only one. The Point Aconi unit, however, is the largest producing unit in Nova Scotia and is also the province’s newest. The facility is able to produce 165 MW and, unlike the vast majority of Canadian coal-fired power plants, uses
309:, located approximately 2 km (1.2 mi) west of the headland named Point Aconi and 2 km (1.2 mi) east of the headland named Table Head. Its civic address is 1800 Prince Mine Rd, Point Aconi, NS. The facility is located at the northern terminus of Prince Mine Rd – 797:
The limestone-handling system consists of receiving hoppers and conveyors common to the coal system, crushers, dryers, storage silos, and a pneumatic conveyor leading to two in-plant storage bunkers. Limestone also arrives by truck, at the rate of about 165,000 tons per year.
454:
Two weeks later, the provincial government announced that its Environmental Control Council would conduct a one-day hearing into the project on January 18, 1990 in place of the PUB hearings conducted the previous spring which were aborted as a result of the amendment to the
342:
Point Aconi was the world’s largest CFB plant—and the first to enter commercial service in North America—when it came on-line in 1993. Tokyo-based Mitsui & Co., Ltd. was the turnkey contractor for Point Aconi; Sargent & Lundy was the project’s architect/engineer.
712:
The Point Aconi Generating Station began operating in March 1994 and was officially opened in a ceremony on August 12, 1994 however construction was not completed until later in the fall of 1994 and the plant didn't begin commercial operation until January 1, 1995.
849:(DEVCO) which was beset with production problems at its three remaining collieries during the mid-late 1990s as a result of flooding, roof collapses and labour difficulties. The instability of locally mined coal forced Nova Scotia Power to import coal from the 542:
emissions as a result of the Point Aconi Generating Station (an estimated additional 1.5 million tonnes per year) went against a recent (1990) decision by federal and provincial energy ministers to reduce emissions of the gas by at least 20 per cent by 2005.
518:
emissions from its generating stations to 100,000 tonnes a year by 2010 from the 1990 level of 160,000 tonnes. Minister Leefe also noted that while the use of CFB technology would reduce acid rain, it would also result in a comparatively massive increase in
808:
The Point Aconi Generating Station consumes 189,000 tonnes of coal and 213,000 tonnes of petroleum coke per year and currently generates approximately 6.8% of the province's electricity and produces roughly 10.07% of the province's air pollution, including
780:
for particulate control. Point Aconi station is the only Nova Scotia Power Thermal plant without activated carbon injection system to control mercury emissions as it is an inherently lower emitter due to the injection of limestone into the process.
716:
Point Aconi was originally rated to produce 183 MW (gross) by burning 65 tons/hr of local coal and 15.5 tons/hr of limestone. The Ahlstrom Pyropower circulating fluidized-bed (CFB) combustion system was designed to achieve a 90% reduction in
462:
Other submissions from citizens and organizations were supportive of the project, which they claimed would create an estimated 500 construction and operating jobs, as well as theoretically guarantee work in Cape Breton's coal mines; the
1474: 478:
On Friday, March 9, 1990, the provincial government announced its approval of the estimated $ 436 million project, even though it had already signed a contract with Mitsui two months earlier. Nova Scotia's Environment Minister
740:
In the first years of operation the boiler was plagued by serious problems with fouling and corrosion. By 1999 the unit had an average capacity factor of 50% and a forced outage rate of 30%. A switch to a fuel blend including
582:
rejected a full environmental review of the project, arguing that any problems to the environment would be relatively minor. Valcourt justified this decision by referring to a scientific report on the project conducted by the
635:
In addition to the estimated $ 436 million cost for the generating station, the project also included construction of a $ 150 million transmission line running for 435 km (270 mi) from Point Aconi to
632:
But when we ask for a neutral party to look at this, Nova Scotia power brings in its big shooters and they knock us down like pegs. Now it's almost too late but people won't sit down and take this any more."
946: 685:
which is referenced as NSJ no. 258; 2000 NSCA 96; Mitsui & Co. (Point Aconi) Ltd. was removed from the Nova Scotia Registry of Joint Stock on June 23, 2003 after legal proceedings were completed.
793:
generator is totally enclosed and has a cylindrical rotor whose winding is directly cooled by hydrogen at 210 kPa (30 psi). The generator is rated at 217 MVA and has a power factor of 0.85.
410:, which would remove the requirement for Nova Scotia Power to submit proposals for new generating station to the PUB. Hearings into the Point Aconi project were cancelled after the amendment to the 693: 383: 587:
which stated that use of CFB technology could be mitigated. It noted, however, the widespread concern of local residents over the effect of the generating station's draw on
367:
region until its purchase by Nova Scotia Power in 1966 as part of DOSCO's ongoing asset liquidation. Nova Scotia Power opened the province's largest generating station, the
1479: 748:
The Point Aconi Generating Station has one 165 MW unit (name plate capacity 186 MW). Its boiler was supplied by Finland’s Ahlstrom Pyropower. The plant burns bituminous
434:
had won the Request for Proposals (RFP) that had been issued in fall 1988 and a contract was signed on behalf of the Government of Nova Scotia. The proposal detailed a
1245: 1351: 877: 640:. Several property owners along the proposed route rejected offers by Nova Scotia Power to purchase their land, citing the physiological effects of the 70: 394:. After Buchanan's government was returned to power, Nova Scotia Power issued a call for proposals in October 1988 to construct a 150 megawatt CFB ( 728:
After initial production issues at the Point Aconi facility were resolved, Nova Scotia Power Corporation closed and decommissioned the 65-year-old
745:
and design changes to the boiler solved these problems. By 2005 the capacity factor was increased to 92% and the outage rate reduced to under 2%.
252: 1022: 1311: 1381: 1217: 402: 382:
The idea of replacing the aging Seaboard Generating Station was discussed during the 1980s and was an important promise by the incumbent
846: 387: 376: 360: 1405: 439: 1130: 490:
Nova Scotia Power pointed out the environmental benefits of the Point Aconi project, stating that the use of CFB technology whereby
391: 291: 923: 619:
A citizens liaison committee was established by Nova Scotia Power to review the project. Current (2010) Member of Parliament for
546:
The debate over construction of the Point Aconi Generating Station took place in the shadow of a much larger global debate over
475:
asked at the one-day hearing, "Can you give us some evidence that this process is not an exercise in public relations, a sham?"
881: 464: 554:
which was signed by both countries on March 13, 1991 and stipulated that both countries would agree to reduce emissions of
531:; Leefe told reporters that Nova Scotia's coal-fired plants contributed 32 per cent of the 18 million tonnes per year of CO 1368: 761: 644:
from transmission lines. Additional controversy occurred when it was determined that the proposed route would disturb a
1348: 692:
in the wake of a corruption scandal relating to his tenure as premier. The selection of a new leader for the governing
584: 438:
project designed by Mitsui with the CFB steam boiler supplied by Pyro-Power through Kamtech Services (a subsidiary of
865: 700:, took place on February 26, 1991. Cameron made a surprise announcement on January 9, 1992 that his government would 1484: 688:
Construction of the plant was overshadowed by the resignation of Premier John Buchanan upon his appointment to the
550:
and its contributing factors, such as fossil fueled generating stations. The acid rain controversy resulted in the
873: 830: 729: 472: 395: 368: 352: 322: 317: 283: 54: 443: 706: 674: 604: 310: 1030: 697: 364: 356: 1285: 641: 637: 600: 118: 1189: 947:"Company/Facility information: Nova Scotia Power Incorporated/Point Aconi Generating Station (2017)" 664: 620: 401:
Significant controversy dogged Buchanan's election promise to build a new generating station as the
28: 1246:"Nova Scotia Power's Point Aconi plant overcomes CFB design problems to become rock of reliability" 1174: 1159: 1144: 1097: 1082: 1067: 1052: 1007: 988: 973: 836:
Nova Scotia Power anticipates that the Point Aconi generating station will be shut down by 2029.
757: 628: 372: 306: 221: 1337: 789:
is handled dry and land-filled. The unit has one chimney 100 m (330 ft) above ground.
487:
emissions, stating " absolutely inconsequential in terms of global carbon dioxide production."
1377: 1213: 1126: 822: 818: 810: 649: 612:, it was impossible to say that the plant would create a pollution problem with its massive CO 295: 131: 1204: 596:
dangers. In fact, problems are relatively minor... Point Aconi is in some respects a model."
294:. A thermal generating station, the Point Aconi Generating Station is owned and operated by 1187:"Aconi generates more jobs, less flak: Power plant officially opened, but still not ready." 826: 689: 645: 579: 869: 861: 555: 495: 1455:
History of Nova Scotia with special attention given to Communications and Transportation
1436:
History of Nova Scotia with special attention given to Communications and Transportation
1448: 1429: 814: 753: 742: 563: 528: 520: 503: 484: 333: 164: 1468: 1355: 1319:. Triton Environmental Consultants Ltd. for Environment Canada. June 2010. p. 17 915: 901: 854: 850: 174: 1065:
Special to the Globe and Mail "Lawyer contends minister erred in coal plant ruling"
805:
pump house. The two-pass, surface-type deaerating condenser operates at 1 inch HgA.
591:
supplies (CFB requires large amounts of fresh water) as well as ash discharge and CO
860:
From 1998 to 2000, Nova Scotia Power brought imported coal into Nova Scotia at the
765: 588: 415: 302: 193: 1338:"Dirty Air from Power Plants Fuels Health Problems in Nova Scotia" Pollution Watch 1005:
Kevin Cox (March 10, 1990). "Nova Scotia to construct a coal-fired power plant".
624: 468: 287: 58: 1270: 1142:
Kevin Cox "N.S. to sell off electrical utility: Premier sets June stock sale."
891: 786: 480: 375:
to take advantage of relatively cheap Cape Breton coal being produced by the
85: 72: 909: 725:
emissions—very respectable numbers in 1994, when the plant began operation.
701: 547: 511: 491: 1430:"NSP to Import More U.S. Coal: Coal Shortage Shuts Down Generating Plant" 1406:"Nova Scotia Power plans to burn heavy fuel oil at phased-out coal plants" 986:
Kevin Cox "Panel asked to show evidence power plant hearing not 'sham'."
777: 276: 227: 872:. That required coal ordered for the Point Aconi Generating Station and 442:
of Abilene, Texas), project management and engineering by Chicago-based
261: 782: 668:
Point Aconi Generating Station seen from the waters of the Cabot Strait
435: 971:"Buchanan short-circuits N.S. utilities board with power plant bill." 298:. It opened on August 13, 1994 following four years of construction. 1206:
North America natural gas market dynamics : global LNG, a review
431: 279: 709:
for 85 million shares of the utility took place on August 12, 1992.
514:. Minister Leefe stated that Nova Scotia Power intended to reduce SO 301:
The Point Aconi Generating Station is situated on the shores of the
1050:
Kevin Cox "Ottawa rejects full review of power station's effects."
756:
in a variety of blends, which is transported to the facility using
446:, and construction of the plant itself by Jones Power Corporation. 663: 427: 1475:
Buildings and structures in the Cape Breton Regional Municipality
1123:
The Civil Litigation Process: Cases and Materials, Sixth Edition.
749: 603:
and six property owners who live near Point Aconi argued in the
578:
On September 20, 1990, federal Minister of Fisheries and Oceans
154: 1212:. Calgary AL: Canadian Energy Research Institute. p. 28. 326: 426:
In early January 1990, Nova Scotia Power announced that the
398:) coal-fired electrical generating station in Point Aconi. 953:. Environment and Climate Change Canada. 13 September 2018 648:
colony, which brought angry responses from members of the
282:
electrical generating station located in the community of
1349:
Facility and Greenhouse Gas Emissions, Environment Canada
1110: 242: 16:
Thermal Generating System in eastern Nova Scotia, Canada
857:
beginning in 1998 to supplement the supply from DEVCO.
1240: 1238: 1236: 683:
Mitsui & Co. (Point Aconi) Ltd. v. Jones Power Co.
483:
defended the projected 1.5 million tonnes per year of
1157:
Dennis Slocum "N.S. Power share offering a sellout."
471:, the environment critic for the official opposition 768:. The unit is a fluidized bed combustor built for NO 1095:Kevin Cox "Power plant ruffles more than feathers" 248: 238: 233: 220: 199: 188: 180: 170: 160: 150: 145: 137: 127: 117: 109: 101: 64: 50: 42: 21: 1273:History of Electric Power Companies in Nova Scotia 599:On December 13, 1990, lawyers for Greenpeace, the 363:and was the sole supplier of electricity for the 1125:Toronto: Emond Montgomery Publications Limited 951:NPRI Data Search - Detailed Facility Information 833:under Nova Scotia's Cap-and Trade regulations. 467:Local 26 had lobbied hard for the power plant. 1080:Kevin Cox "Power but no glory in Point Aconi" 825:. In 2007, it created 1.465 million tonnes of 1370:2019 Summary of 2017 Greenhouse Gas Emissions 1252:. Access Intelligence, LLC. 14 September 2006 941: 939: 8: 1367:Department of Environment (February 2019). 878:Cape Breton and Central Nova Scotia Railway 776:, control. The station has a fabric filter 1023:"Canada-United States Clean Air Agreement" 721:emissions and a 65% to 75% reduction in NO 574:Full federal environmental review rejected 552:Canada-United States Air Quality Agreement 538:The projected increase in Nova Scotia's CO 18: 801:disposal site located next to the plant. 1480:Coal-fired power stations in Nova Scotia 1449:"Pennsylvania Coal Unloaded at Sydney," 1271:"Seaboard Power Corporation" taken from 1000: 998: 935: 845:owned by the federal Crown corporation 829:. In 2017 it reported 1,188,377 tonnes 627:whose family operated several farms on 253:Related media on Commons 535:emitted by the province (as of 1990). 7: 1457:, Chapter 40, September-October 1998 1438:, Chapter 40, September-October 1998 1111:Nova Scotia Registry of Joint Stock 880:to the DEVCO coal washing plant at 847:Cape Breton Development Corporation 760:from a bulk ship unloading pier in 510:) which were major contributors to 440:Lauren Engineers & Constructors 377:Cape Breton Development Corporation 361:Dominion Steel and Coal Corporation 1313:Control of Mercury Emission-to-Air 673:were guaranteed by its subsidiary 585:Department of Fisheries and Oceans 14: 292:Cape Breton Regional Municipality 1290:2016 Emera Sustainability Report 924:List of power stations in Canada 908: 894: 146:Thermal power station 27: 864:aggregate loading facility in 694:Progressive Conservative Party 465:United Mine Workers of America 384:Progressive Conservative Party 273:Point Aconi Generating Station 33:Point Aconi Generating Station 22:Point Aconi Generating Station 1: 1453:October 23, 1998, taken from 1434:October 23, 1998, taken from 1203:Kralovic, Paul (March 2011). 325:(CFB) to reduce emissions of 296:Nova Scotia Power Corporation 1404:Withers, Paul (4 Jul 2023). 705:projects. The $ 850 million 494:would be used to filter out 1376:. Province of Nova Scotia. 1172:"N.S. Power earnings off." 1163:, Thursday, August 13, 1992 730:Seaboard Generating Station 353:Seaboard Generating Station 305:at the northeastern tip of 290:, a rural community in the 1501: 1148:, Friday, January 10, 1992 1056:Friday, September 21, 1990 992:, Friday, January 19, 1990 977:, Thursday, April 27, 1989 1193:Saturday, August 13, 1994 1178:Saturday, August 13, 1994 1071:Friday, December 13, 1990 876:to be transported by the 874:Lingan Generating Station 862:Martin Marietta Materials 831:carbon dioxide equivalent 396:Circulating Fluidized Bed 369:Lingan Generating Station 323:Circulating Fluidized Bed 318:Lingan Generating Station 258: 208: 204: 38: 26: 1086:Saturday, March 16, 1991 527:) emissions which was a 430:industrial conglomerate 392:1988 provincial election 1286:"Improving Air Quality" 707:initial public offering 675:J.A. Jones Construction 605:Federal Court of Canada 444:Sargent & Lundy LLC 371:, at the height of the 222:Nameplate capacity 171:Turbine technology 110:Construction began 86:46.321633°N 60.329987°W 1121:Walker, Janet (2005). 1101:Saturday, July 6, 1991 764:near the community of 669: 365:Industrial Cape Breton 243:https://www.nspower.ca 213:Units operational 667: 642:electromagnetic field 601:Ecology Action Centre 422:Request for proposals 200:Power generation 91:46.321633; -60.329987 1190:The Chronicle Herald 457:Public Utilities Act 418:in early June 1989. 412:Public Utilities Act 408:Public Utilities Act 403:Public Utility Board 119:Commission date 758:semi-trailer trucks 234:External links 189:Cooling source 161:Secondary fuel 82: /  1175:The Globe and Mail 1160:The Globe and Mail 1145:The Globe and Mail 1098:The Globe and Mail 1083:The Globe and Mail 1068:The Globe and Mail 1053:The Globe and Mail 1027:Environment Canada 1008:The Globe and Mail 989:The Globe and Mail 974:The Globe and Mail 670: 629:Boularderie Island 373:1979 energy crisis 316:Unlike the nearby 307:Boularderie Island 1485:Nova Scotia Power 1383:978-1-55457-930-3 1219:978-1-896091-97-6 882:Victoria Junction 819:hexachlorobenzene 811:hydrochloric acid 269: 268: 151:Primary fuel 132:Nova Scotia Power 1492: 1459: 1451:Cape Breton Post 1446: 1440: 1432:Cape Breton Post 1427: 1421: 1420: 1418: 1416: 1401: 1395: 1394: 1392: 1390: 1375: 1364: 1358: 1346: 1340: 1335: 1329: 1328: 1326: 1324: 1318: 1308: 1302: 1301: 1299: 1297: 1282: 1276: 1268: 1262: 1261: 1259: 1257: 1242: 1231: 1230: 1228: 1226: 1211: 1200: 1194: 1185: 1179: 1170: 1164: 1155: 1149: 1140: 1134: 1119: 1113: 1108: 1102: 1093: 1087: 1078: 1072: 1063: 1057: 1048: 1042: 1041: 1039: 1038: 1029:. Archived from 1019: 1013: 1012: 1002: 993: 984: 978: 969: 963: 962: 960: 958: 943: 918: 913: 912: 904: 899: 898: 897: 827:greenhouse gases 690:Senate of Canada 646:great blue heron 580:Bernard Valcourt 262:edit on Wikidata 97: 96: 94: 93: 92: 87: 83: 80: 79: 78: 75: 31: 19: 1500: 1499: 1495: 1494: 1493: 1491: 1490: 1489: 1465: 1464: 1463: 1462: 1447: 1443: 1428: 1424: 1414: 1412: 1403: 1402: 1398: 1388: 1386: 1384: 1373: 1366: 1365: 1361: 1347: 1343: 1336: 1332: 1322: 1320: 1316: 1310: 1309: 1305: 1295: 1293: 1284: 1283: 1279: 1269: 1265: 1255: 1253: 1244: 1243: 1234: 1224: 1222: 1220: 1209: 1202: 1201: 1197: 1186: 1182: 1171: 1167: 1156: 1152: 1141: 1137: 1120: 1116: 1109: 1105: 1094: 1090: 1079: 1075: 1064: 1060: 1049: 1045: 1036: 1034: 1021: 1020: 1016: 1004: 1003: 996: 985: 981: 970: 966: 956: 954: 945: 944: 937: 932: 914: 907: 900: 895: 893: 890: 870:Strait of Canso 842: 775: 771: 738: 724: 720: 662: 656:early January. 621:Sydney—Victoria 615: 611: 594: 576: 569: 561: 556:sulphur dioxide 541: 534: 526: 517: 509: 501: 496:sulphur dioxide 452: 450:Public hearings 424: 386:led by Premier 349: 337: 330: 265: 192:Water from the 90: 88: 84: 81: 76: 73: 71: 69: 68: 34: 17: 12: 11: 5: 1498: 1496: 1488: 1487: 1482: 1477: 1467: 1466: 1461: 1460: 1441: 1422: 1396: 1382: 1359: 1354:2013-06-27 at 1341: 1330: 1303: 1277: 1263: 1250:POWER magazine 1232: 1218: 1195: 1180: 1165: 1150: 1135: 1114: 1103: 1088: 1073: 1058: 1043: 1014: 994: 979: 964: 934: 933: 931: 928: 927: 926: 920: 919: 905: 889: 886: 841: 838: 815:sulphuric acid 773: 769: 762:Sydney Harbour 754:petroleum coke 743:petroleum coke 737: 734: 722: 718: 698:Donald Cameron 661: 658: 650:Mi'kmaq Nation 613: 609: 592: 575: 572: 567: 564:nitrogen oxide 559: 539: 532: 529:greenhouse gas 524: 521:carbon dioxide 515: 507: 504:nitrogen oxide 499: 485:carbon dioxide 451: 448: 423: 420: 348: 345: 335: 328: 267: 266: 259: 256: 255: 250: 246: 245: 240: 236: 235: 231: 230: 224: 218: 217: 214: 210: 209: 206: 205: 202: 201: 197: 196: 190: 186: 185: 182: 178: 177: 172: 168: 167: 165:Petroleum coke 162: 158: 157: 152: 148: 147: 143: 142: 139: 135: 134: 129: 125: 124: 123:13 August 1994 121: 115: 114: 111: 107: 106: 103: 99: 98: 66: 62: 61: 52: 48: 47: 44: 40: 39: 36: 35: 32: 24: 23: 15: 13: 10: 9: 6: 4: 3: 2: 1497: 1486: 1483: 1481: 1478: 1476: 1473: 1472: 1470: 1458: 1456: 1452: 1445: 1442: 1439: 1437: 1433: 1426: 1423: 1411: 1407: 1400: 1397: 1385: 1379: 1372: 1371: 1363: 1360: 1357: 1356:archive.today 1353: 1350: 1345: 1342: 1339: 1334: 1331: 1315: 1314: 1307: 1304: 1291: 1287: 1281: 1278: 1275: 1274: 1267: 1264: 1251: 1247: 1241: 1239: 1237: 1233: 1221: 1215: 1208: 1207: 1199: 1196: 1192: 1191: 1184: 1181: 1177: 1176: 1169: 1166: 1162: 1161: 1154: 1151: 1147: 1146: 1139: 1136: 1132: 1131:1-55239-146-9 1128: 1124: 1118: 1115: 1112: 1107: 1104: 1100: 1099: 1092: 1089: 1085: 1084: 1077: 1074: 1070: 1069: 1062: 1059: 1055: 1054: 1047: 1044: 1033:on 2007-08-04 1032: 1028: 1024: 1018: 1015: 1010: 1009: 1001: 999: 995: 991: 990: 983: 980: 976: 975: 968: 965: 952: 948: 942: 940: 936: 929: 925: 922: 921: 917: 916:Energy portal 911: 906: 903: 902:Canada portal 892: 887: 885: 883: 879: 875: 871: 867: 863: 858: 856: 855:South America 852: 851:United States 848: 839: 837: 834: 832: 828: 824: 820: 816: 812: 806: 802: 798: 794: 790: 788: 784: 779: 767: 763: 759: 755: 751: 746: 744: 735: 733: 731: 726: 714: 710: 708: 703: 699: 695: 691: 686: 684: 678: 676: 666: 659: 657: 653: 651: 647: 643: 639: 633: 630: 626: 622: 617: 606: 602: 597: 590: 586: 581: 573: 571: 565: 557: 553: 549: 544: 536: 530: 522: 513: 505: 497: 493: 488: 486: 482: 476: 474: 473:Liberal Party 470: 466: 460: 458: 449: 447: 445: 441: 437: 433: 429: 421: 419: 417: 413: 409: 404: 399: 397: 393: 389: 388:John Buchanan 385: 380: 378: 374: 370: 366: 362: 358: 354: 346: 344: 340: 338: 331: 324: 319: 314: 312: 308: 304: 299: 297: 293: 289: 285: 281: 278: 274: 263: 257: 254: 251: 247: 244: 241: 237: 232: 229: 225: 223: 219: 215: 212: 211: 207: 203: 198: 195: 191: 187: 183: 179: 176: 175:Steam turbine 173: 169: 166: 163: 159: 156: 153: 149: 144: 140: 136: 133: 130: 126: 122: 120: 116: 112: 108: 104: 100: 95: 67: 63: 60: 56: 53: 49: 45: 41: 37: 30: 25: 20: 1454: 1450: 1444: 1435: 1431: 1425: 1413:. Retrieved 1409: 1399: 1387:. Retrieved 1369: 1362: 1344: 1333: 1321:. Retrieved 1312: 1306: 1294:. Retrieved 1289: 1280: 1272: 1266: 1254:. Retrieved 1249: 1223:. Retrieved 1205: 1198: 1188: 1183: 1173: 1168: 1158: 1153: 1143: 1138: 1122: 1117: 1106: 1096: 1091: 1081: 1076: 1066: 1061: 1051: 1046: 1035:. Retrieved 1031:the original 1026: 1017: 1006: 987: 982: 972: 967: 955:. Retrieved 950: 859: 843: 835: 807: 803: 799: 795: 791: 766:Whitney Pier 747: 739: 727: 715: 711: 687: 682: 679: 671: 660:Construction 654: 634: 618: 598: 589:ground water 577: 551: 545: 537: 489: 477: 461: 456: 453: 425: 416:royal assent 411: 407: 400: 381: 350: 341: 315: 303:Cabot Strait 300: 272: 270: 194:Cabot Strait 113:January 1990 1292:. Emera Inc 866:Auld's Cove 840:Coal supply 625:Mark Eyking 616:emissions. 469:Richie Mann 390:during the 359:in 1931 by 347:Development 311:Highway 162 288:Nova Scotia 284:Point Aconi 105:Operational 89: / 65:Coordinates 59:Nova Scotia 55:Point Aconi 1469:Categories 1389:16 October 1037:2010-04-26 930:References 787:bottom ash 481:John Leefe 414:receiving 355:opened in 77:60°19′48″W 74:46°19′18″N 1133:, pg. 826 736:Operation 732:in 1997. 702:privatize 548:acid rain 512:acid rain 492:limestone 379:(DEVCO). 357:Glace Bay 275:is a 165 226:185  138:Employees 1415:3 August 1410:CBC News 1352:Archived 1256:10 April 957:10 April 888:See also 778:baghouse 428:Japanese 280:Canadian 181:Chimneys 128:Owner(s) 51:Location 1323:9 April 1296:9 April 1225:9 April 868:on the 823:mercury 783:Fly ash 638:Halifax 436:turnkey 249:Commons 239:Website 43:Country 1380:  1216:  1129:  772:and SO 562:) and 502:) and 432:Mitsui 102:Status 46:Canada 1374:(PDF) 1317:(PDF) 1210:(PDF) 260:[ 1417:2024 1391:2019 1378:ISBN 1325:2020 1298:2020 1258:2020 1227:2020 1214:ISBN 1127:ISBN 959:2020 853:and 821:and 785:and 752:and 750:coal 351:The 332:and 271:The 155:Coal 570:). 566:(NO 558:(SO 523:(CO 506:(NO 498:(SO 1471:: 1408:. 1288:. 1248:. 1235:^ 1025:. 997:^ 949:. 938:^ 817:, 813:, 717:SO 696:, 677:. 652:. 623:, 339:. 334:SO 327:NO 313:. 286:, 277:MW 228:MW 141:65 57:, 1419:. 1393:. 1327:. 1300:. 1260:. 1229:. 1040:. 1011:. 961:. 774:2 770:x 723:x 719:2 614:2 610:2 593:2 568:x 560:2 540:2 533:2 525:2 516:2 508:x 500:2 336:2 329:x 264:] 216:1 184:1

Index


Point Aconi
Nova Scotia
46°19′18″N 60°19′48″W / 46.321633°N 60.329987°W / 46.321633; -60.329987
Commission date
Nova Scotia Power
Coal
Petroleum coke
Steam turbine
Cabot Strait
Nameplate capacity
MW
https://www.nspower.ca
Related media on Commons
edit on Wikidata
MW
Canadian
Point Aconi
Nova Scotia
Cape Breton Regional Municipality
Nova Scotia Power Corporation
Cabot Strait
Boularderie Island
Highway 162
Lingan Generating Station
Circulating Fluidized Bed
NOx
SO2
Seaboard Generating Station
Glace Bay

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.

↑