Knowledge

Rambler Channel Bridge (railway bridge)

Source 📝

33: 335:
Dragages et Travaux Publics was found solely responsible for the collapse. The company was fined HK$ 105,000 on 8 August 1997 after admitting to three charges of failing to ensure safety and failing to maintain properly built scaffolding. In October 1997 Takamura Limited (also known as Pacific Island
331:
On 4 December 1996, the Labour Department issued summonses to Dragages et Travaux Publics; its manager, Didier Noel; and subcontractor Takamura Limited (which built the platform), under charges of breaching general duties provisions under the Factory and Industrial Undertakings Ordinance. Dragages
327:
The tragedy was blamed on the wrong type of bolt being used to affix the work platform to a concrete pillar. A Coroner's Court inquest before coroner David Thomas heard that the anchor bolts were only half the length required, were designed to hold electric cables, and were screwed into plastic
332:
was accused of not providing sufficient training to workers, and failing to ensure the safety of the platform. A representative for Takamura argued against prosecuting the company as it was only responsible for installing the platform.
306:
Six construction workers were killed when a metal work platform collapsed on 6 June 1996. The platform, which held four men, plunged 20 metres and crushed two workers below. The men were rushed to
298:. Construction began in October 1995. It was structurally completed in February 1997. The bridge began carrying revenue passengers with the opening of the Tung Chung line on 21 June 1998. 328:
sockets. The platform collapsed after two of the bolts detached. The weight on the platform exceeded four tonnes, or three times more than the bolts could support.
674: 355:. The bilevel main deck segments are eight metres high and weigh 120 tonnes each. The segments are held together with epoxy glue and high-strength steel tendons. 793: 317: 313:
Those killed were engineer Tam Wai-shing, 40; Yeung Sung-po, 50; Shek Shing, 58; Wong Kam-wo, 30; and brothers-in-law Law Tai-yau, 36, and Cheng Chi-ming, 33.
683: 709: 633: 714: 50: 837: 324:. Construction of the bridge was temporarily halted and the Labour Department inspected all similar work platforms across the territory. 852: 847: 667: 779: 434: 316:
The Labour Department launched an investigation to determine the cause of the accident. It was aided by specialists from the
660: 43: 295: 719: 290:
awarded the contract to design and construct the bridge to Dragages et Travaux Publics, in partnership with
340: 774: 769: 259: 89: 637: 704: 321: 351:
The bridge is 1,100 metres long. It is made up of precast concrete segments lowered into place by a
749: 724: 699: 455: 734: 694: 32: 832: 307: 729: 534:
Lee, Naomi; Wong, Billy Wai-yuk (10 June 1996). "Tragedy may delay airport bridge project".
352: 275: 271: 764: 754: 287: 267: 263: 99: 85: 615:
Gren, Manuel (3 August 1998). "Campaign on airport project deaths allowed at terminal".
759: 826: 739: 842: 567:
Delfino, Brendan; Szeto, Wanda (5 December 1996). "Viaduct deaths firm charged".
291: 162: 504:
Chin, Michelle (16 January 1998). "`Wrong bolts used' in collapsed platform".
389: 374:
Wallis, Keith (29 November 1994). "MTRC awards $ 1.4b in new airport orders".
109: 808: 795: 65: 52: 251: 113: 549:
Chin, Michelle (17 January 1998). "Warning on fatal misuse of materials".
310:
in nearby Tsuen Wan and declared dead shortly after arrival at 6:00 pm.
149: 652: 600:
Poole, Oliver (10 October 1997). "Firm cleared over platform deaths".
519:
Chin, Michelle (7 June 1996). "Sisters mourn men in bridge tragedy".
247: 294:. The contract was worth $ 490 million. The bridge was designed by 582:
Chin, Michelle (16 January 1997). "Companies accused on safety".
656: 255: 414:
Wallis, Keith (7 June 1996). "Pieces held in place by glue".
336:
Consultants) was cleared of responsibility for the accident.
339:
The tragedy was the single greatest loss of life during the
231: 213: 205: 187: 169: 155: 145: 140: 132: 124: 119: 105: 95: 81: 42: 23: 668: 480:"Platform tests ordered after death plunge". 318:Electrical and Mechanical Services Department 8: 675: 661: 653: 595: 593: 562: 560: 450: 448: 446: 444: 20: 369: 367: 499: 497: 495: 493: 491: 475: 473: 363: 636:. Film Services Office. Archived from 409: 407: 37:Tsing Lai Bridge viewed from Tsing Yi 7: 16:Bridge in New Territories, Hong Kong 710:Hong Kong–Shenzhen Western Corridor 14: 288:Mass Transit Railway Corporation 31: 780:Duplicate Tsing Yi South Bridge 435:Information Services Department 760:Tseung Kwan O Cross Bay Bridge 1: 715:Hong Kong–Zhuhai–Macau Bridge 456:"Rambler Channel Rail Bridge" 390:"Rambler Channel Rail Bridge" 246:is a quadruple-track railway 838:Railway bridges in Hong Kong 193:; 27 years ago 175:; 28 years ago 869: 429:Howlett, Bob, ed. (1997). 302:1996 construction accident 853:Bridges completed in 1998 848:1996 industrial disasters 690: 484:. 9 June 1996. p. 4. 236: 30: 809:22.356917°N 114.112361°E 705:New Clear Water Bay Road 617:South China Morning Post 602:South China Morning Post 584:South China Morning Post 569:South China Morning Post 551:South China Morning Post 536:South China Morning Post 521:South China Morning Post 506:South China Morning Post 482:South China Morning Post 416:South China Morning Post 376:South China Morning Post 296:Bouygues Travaux Publics 292:Penta-Ocean Construction 163:Penta-Ocean Construction 150:Bouygues Travaux Publics 720:Island Eastern Corridor 431:Hong Kong Yearbook 1997 745:Rambler Channel Bridge 341:Airport Core Programme 244:Rambler Channel Bridge 219:; 26 years ago 25:Rambler Channel Bridge 814:22.356917; 114.112361 775:Tsing Yi South Bridge 770:Tsing Yi North Bridge 684:Bridges in Hong Kong 640:on 27 September 2007 458:. Dragages Hong Kong 322:Buildings Department 66:22.3569°N 114.1124°E 805: /  750:Stonecutters Bridge 725:Kap Shui Mun Bridge 700:Cheung Tsing Bridge 161:Dragages Hong Kong- 62: /  735:Lai Chi Kok Bridge 695:Ap Lei Chau Bridge 191:February 1997 170:Construction start 788: 787: 634:"Rambler Channel" 308:Yan Chai Hospital 254:. It carries the 240: 239: 217:21 June 1998 206:Construction cost 173:October 1995 71:22.3569; 114.1124 860: 820: 819: 817: 816: 815: 810: 806: 803: 802: 801: 798: 730:Kwun Tong Bypass 677: 670: 663: 654: 649: 647: 645: 621: 620: 612: 606: 605: 597: 588: 587: 579: 573: 572: 564: 555: 554: 546: 540: 539: 531: 525: 524: 516: 510: 509: 501: 486: 485: 477: 468: 467: 465: 463: 452: 439: 438: 426: 420: 419: 411: 402: 401: 399: 397: 386: 380: 379: 371: 353:launching gantry 276:Lai King station 272:Tsing Yi station 227: 225: 220: 201: 199: 194: 188:Construction end 183: 181: 176: 158: 77: 76: 74: 73: 72: 67: 63: 60: 59: 58: 55: 35: 21: 868: 867: 863: 862: 861: 859: 858: 857: 823: 822: 813: 811: 807: 804: 799: 796: 794: 792: 791: 789: 784: 765:Tsing Ma Bridge 755:Ting Kau Bridge 686: 681: 643: 641: 632: 629: 624: 614: 613: 609: 599: 598: 591: 581: 580: 576: 566: 565: 558: 548: 547: 543: 533: 532: 528: 518: 517: 513: 503: 502: 489: 479: 478: 471: 461: 459: 454: 453: 442: 428: 427: 423: 413: 412: 405: 395: 393: 392:. Bouygues Asia 388: 387: 383: 373: 372: 365: 361: 349: 304: 284: 268:Rambler Channel 264:Tung Chung line 260:Airport Express 223: 221: 218: 197: 195: 192: 179: 177: 174: 156: 120:Characteristics 100:Rambler Channel 90:Airport Express 88: 86:Tung Chung line 70: 68: 64: 61: 56: 53: 51: 49: 48: 38: 26: 17: 12: 11: 5: 866: 864: 856: 855: 850: 845: 840: 835: 825: 824: 786: 785: 783: 782: 777: 772: 767: 762: 757: 752: 747: 742: 737: 732: 727: 722: 717: 712: 707: 702: 697: 691: 688: 687: 682: 680: 679: 672: 665: 657: 651: 650: 628: 627:External links 625: 623: 622: 607: 589: 574: 556: 541: 526: 511: 487: 469: 440: 421: 403: 381: 362: 360: 357: 348: 345: 303: 300: 283: 280: 238: 237: 234: 233: 229: 228: 215: 211: 210: 207: 203: 202: 189: 185: 184: 171: 167: 166: 159: 157:Constructed by 153: 152: 147: 143: 142: 138: 137: 134: 130: 129: 126: 122: 121: 117: 116: 107: 103: 102: 97: 93: 92: 83: 79: 78: 46: 40: 39: 36: 28: 27: 24: 15: 13: 10: 9: 6: 4: 3: 2: 865: 854: 851: 849: 846: 844: 841: 839: 836: 834: 831: 830: 828: 821: 818: 781: 778: 776: 773: 771: 768: 766: 763: 761: 758: 756: 753: 751: 748: 746: 743: 741: 740:Liu To Bridge 738: 736: 733: 731: 728: 726: 723: 721: 718: 716: 713: 711: 708: 706: 703: 701: 698: 696: 693: 692: 689: 685: 678: 673: 671: 666: 664: 659: 658: 655: 639: 635: 631: 630: 626: 618: 611: 608: 603: 596: 594: 590: 585: 578: 575: 570: 563: 561: 557: 552: 545: 542: 537: 530: 527: 522: 515: 512: 507: 500: 498: 496: 494: 492: 488: 483: 476: 474: 470: 457: 451: 449: 447: 445: 441: 436: 433:. Hong Kong: 432: 425: 422: 417: 410: 408: 404: 391: 385: 382: 377: 370: 368: 364: 358: 356: 354: 346: 344: 342: 337: 333: 329: 325: 323: 319: 314: 311: 309: 301: 299: 297: 293: 289: 286:In 1994, the 281: 279: 277: 273: 269: 265: 261: 257: 253: 249: 245: 235: 230: 216: 212: 209:$ 490 million 208: 204: 190: 186: 172: 168: 164: 160: 154: 151: 148: 144: 139: 135: 131: 127: 123: 118: 115: 111: 108: 104: 101: 98: 94: 91: 87: 84: 80: 75: 47: 45: 41: 34: 29: 22: 19: 800:114°6′44.5″E 797:22°21′24.9″N 790: 744: 642:. Retrieved 638:the original 619:. p. 3. 616: 610: 604:. p. 6. 601: 586:. p. 7. 583: 577: 571:. p. 3. 568: 553:. p. 5. 550: 544: 538:. p. 3. 535: 529: 523:. p. 3. 520: 514: 508:. p. 3. 505: 481: 460:. Retrieved 430: 424: 418:. p. 3. 415: 394:. Retrieved 384: 378:. p. 3. 375: 350: 338: 334: 330: 326: 315: 312: 305: 285: 243: 241: 133:Total length 18: 812: / 347:Description 69: / 57:114°06′45″E 44:Coordinates 827:Categories 359:References 270:, linking 224:1998-06-21 110:Kwai Chung 54:22°21′25″N 266:over the 252:Hong Kong 114:Hong Kong 833:Tsing Yi 644:29 March 320:and the 232:Location 146:Designer 128:Concrete 125:Material 282:History 222: ( 198:1997-02 196: ( 180:1995-10 178: ( 141:History 136:1,100 m 96:Crosses 82:Carries 462:7 June 396:7 June 248:bridge 214:Opened 106:Locale 646:2007 464:2016 398:2016 274:and 262:and 242:The 843:MTR 258:'s 256:MTR 250:in 829:: 592:^ 559:^ 490:^ 472:^ 443:^ 406:^ 366:^ 343:. 278:. 165:JV 112:, 676:e 669:t 662:v 648:. 466:. 437:. 400:. 226:) 200:) 182:)

Index


Coordinates
22°21′25″N 114°06′45″E / 22.3569°N 114.1124°E / 22.3569; 114.1124
Tung Chung line
Airport Express
Rambler Channel
Kwai Chung
Hong Kong
Bouygues Travaux Publics
Penta-Ocean Construction
bridge
Hong Kong
MTR
Airport Express
Tung Chung line
Rambler Channel
Tsing Yi station
Lai King station
Mass Transit Railway Corporation
Penta-Ocean Construction
Bouygues Travaux Publics
Yan Chai Hospital
Electrical and Mechanical Services Department
Buildings Department
Airport Core Programme
launching gantry


"Rambler Channel Rail Bridge"

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.