Knowledge

SwePol

Source 📝

931: 650: 636: 622: 489:
SwePol lasted 6 days in September. Additionally, SwePol had 3 other planned maintenance outages and 1 other outage during 2020. SwePol had 3 minor disturbance outages and 1 more severe disturbance outage in 2020. The severe disturbance outage was caused by a fire in the AC filter on the Polish side in January, and it took 19 days to bring the HVDC link back online after it.
485:
which is slightly less than in 2018 but still higher than the average utilisation since 2012. The available capacity was lower than normally due to an unplanned maintenance outage and a disturbance outage. The unplanned maintenance outage was caused by an oil leakage and the disturbance outage was caused by a valve cooling system failure lasting 29 days.
488:
In 2020, SwePol had an available technical capacity of 87%. The technical capacity not used was 13%. Totally, 3.8 TWh (72% of the technical capacity) was transmitted south from Sweden to Poland and >0.1 TWh (0.2% of the technical capacity) was transmitted north to Sweden. The annual maintenance of
484:
In 2019, SwePol had an available technical capacity of 86%. The technical capacity not used was 24%. Totally, 3.1 TWh (59% of the technical capacity) was exported from Sweden to Poland and 0.2 TWh (4% of the technical capacity) was imported to Sweden. SwePol transmitted 62% of its technical capacity,
407:
of 225 mH and a weight of 27.5 tonnes (61,000 lb), with filters for the 11th, 13th, 24th, and 36th harmonics. Each filter consists of a coil and a capacitor switched in row. The filters for the 11th and 13th harmonics are adjustable. The filters deliver a reactive power of 95 Mvar.
351:
The cable has a cross section of 2,100 square millimetres (3.3 sq in). It runs for 2.22 kilometres (1.38 mi) as an underground cable from the Stärno HVDC Station to the shore of the Baltic Sea. The 239.28 kilometres (148.68 mi) long submarine cable comes ashore in Poland near
434:
Since coming online, 11 instances of cable damage have occurred: one on the high voltage line and 10 on the return cable. Causes have included ship anchors, fishing nets, fire, and grid power disturbances. On 14 February 2005, the smoothing reactor at the HVDC station at Bruskowo Wielkie was
492:
In 2021, SwePol had an available technical capacity of 91 %. The technical capacity not used was 22 %. Totally, 3.4 TWh (65 % of the technical capacity) was transmitted south (SE4→PL) and 0.2 TWh (4 % of the technical capacity) was transmitted north (PL→SE4). The annual
493:
maintenance of SwePol lasted 6 days in September. Additionally, SwePol had 10 other planned maintenance outages during 2021. There were 5 minor disturbance outages, of which one lasted more than 8 hours. SwePol was offline due to disturbance outages for 49 hours in total in 2021.
408:
Additional 95 Mvar reactive power is delivered by a capacitor bank. Each station's static inverter, which is switched as a 12-pulse thyristor bridge, consists of 792 thyristors arranged in three 16-metre (52 ft) high towers installed in a valve hall.
1076: 476:
In 2017, SwePol had an available technical capacity of 94.2%. The technical capacity not used was 31.9%. Totally, 3.1 TWh (59.4% of the technical capacity) was exported from Sweden to Poland and 0.2 TWh (2.9% of the technical capacity) was imported to Sweden.
472:
In 2016, SwePol had an available technical capacity of 87%. The technical capacity not used was 25%. Totally, 2.8 TWh (52.4% of the technical capacity) was exported from Sweden to Poland and 0.2 TWh (3.3% of the technical capacity) was imported to Sweden.
480:
In 2018, SwePol had an available technical capacity of 96%. The technical capacity not used was 30%. Totally, 3.1 TWh (59% of the technical capacity) was exported from Sweden to Poland and 0.4 TWh (7% of the technical capacity) was imported to Sweden.
399:
consisting of 2 cables with 630 square millimetres (0.98 sq in) sections for the submarine portion of the line, and a single cable with 1,100 square millimetres (1.7 sq in) sections for the land portions.
1071: 517: 62: 880: 441:
From January to October 2020 Poland exported 1,225.9 GWh of electricity and imported 12,573.1 GWh compared to 872.8 GWh and 9,326.7 GWh in the same period 2019. The largest import was from
563: 102: 863: 829: 1051: 673: 1096: 1091: 1081: 795: 1046: 355: 1101: 812: 1121: 1116: 1111: 728: 457: 974: 952: 1106: 750: 1086: 55: 897: 846: 411:
It was initially owned and maintained by SwePol Link AB, a company jointly owned by the state-owned Swedish power company
1041: 668: 392:
and runs underground for the remaining 12.55 kilometres (7.80 mi) to Bruskowo Wielkie HVDC Static Inverter Plant.
1036: 460:
in September 2022 and sabotage was suspected, many people feared that the SwePol link had also been damaged. Tests by
396: 310: 307: 449:
2,561.5 GW. Poland's power market will face a supply squeeze from 2025, when a tightening of EU rules on plants’ CO
317: 773: 945: 939: 711: 956: 992: 313: 453:
emissions will force nearly 5 GW of thermal capacity out of the system, the nation's TSO has warned.
461: 424: 412: 194: 1031: 1019: 663: 329: 175: 1014: 1056: 1009: 446: 1065: 655: 641: 627: 610:
Swepol Link is also the name of a local soccer team in the town of Bruskowo Wielkie.
690: 428: 420: 198: 1077:
Electrical interconnectors to and from the Synchronous Grid of Continental Europe
901: 684: 617: 416: 165: 579: 565: 533: 519: 371: 357: 118: 104: 78: 64: 649: 404: 321: 223: 213: 333: 464:, published on 4 October the same year, indicated that was not the case. 341: 881:"Nordic and Baltic HVDC utilisation and unavailability statistics 2021" 864:"Nordic and Baltic HVDC utilisation and unavailability statistics 2020" 847:"Nordic and Baltic HVDC utilisation and unavailability statistics 2019" 830:"Nordic and Baltic HVDC utilisation and unavailability statistics 2018" 813:"Nordic and Baltic HVDC utilisation and unavailability statistics 2017" 796:"Nordic and Baltic HVDC utilisation and unavailability statistics 2016" 678: 442: 345: 1004: 337: 325: 179: 155: 48: 44: 423:(33%), but the company was liquidated and the cable was acquired by 712:"SwePol Link sets new environmental standard for HVDC transmission" 340:. The link was inaugurated in 2000 and can transmit up to 600  729:"Import prądu do Polski przekroczył już wartość za cały 2019 rok" 438:
Initially SwePol was used to export electricity to Poland only.
924: 456:
When the Nord Stream gas pipeline, also in the Baltic Sea,
772:
Johan Zachrisson Winberg, Johan Wikén (4 October 2022).
545:
SwePol - Bruskowo Wielkie (Slupsk) Static Inverter Plant
90:
SwePol - Bruskowo Wielkie (Slupsk) Static Inverter Plant
1072:
Electrical interconnectors to and from the Nordic grid
16:
High-voltage submarine cable between Sweden and Poland
751:"Poland faces power supply squeeze after 2025 – TSO" 395:Unlike other monopolar HVDC schemes, Swepol uses a 290: 282: 274: 266: 258: 250: 242: 237: 229: 219: 209: 204: 190: 185: 171: 161: 150: 142: 54: 40: 35: 23: 674:List of high-voltage transmission links in Sweden 774:"Polenkabeln oskadd efter Nord Stream-läckorna" 419:(16%), and Polish transmission system operator 8: 306:is a 254.05-kilometre (157.86 mi)-long 693:, subsea cable between Lithuania and Poland 500: 435:destroyed by fire. Repairs took 20 hours. 975:Learn how and when to remove this message 938:This article includes a list of general 900:(in Polish). 13 May 2011. Archived from 445:3,222.2 GWh, Sweden 3,195.9 GWh and the 1097:Electric power infrastructure in Sweden 1092:Electric power infrastructure in Poland 1082:Energy infrastructure completed in 2000 703: 512:Bruskowo Wielkie Static Inverter Plant 403:Both stations use air-core inductance 20: 591:SwePol - Stärnö Static Inverter Plant 130:SwePol - Stärnö Static Inverter Plant 7: 1052:A cable marker on Google Street View 687:, cable between Lithuania and Poland 681:, cable between Estonia and Finland 944:it lacks sufficient corresponding 431:for the Polish part of the cable. 311:high-voltage direct current (HVDC) 14: 1102:Connections across the Baltic Sea 929: 648: 634: 620: 210:Manufacturer of conductor/cable 291: 154:Stärnö Static Inverter Plant, 1: 1122:2000 establishments in Sweden 1117:2000 establishments in Poland 731:(in Polish). 18 October 2014 669:Electricity sector in Sweden 558:Stärnö Static Inverter Plant 1020:GPX (secondary coordinates) 220:Manufacturer of substations 1138: 1015:GPX (primary coordinates) 990:Map all coordinates using 776:(in Swedish). SVT Nyheter 262:254 km (158 mi) 28: 998:Download coordinates as: 205:Construction information 1112:Poland–Sweden relations 1107:HVDC transmission lines 959:more precise citations. 580:56.152972°N 14.841500°E 534:54.502111°N 16.891222°E 278:400 kV (both ends) 178:Static Inverter Plant, 119:56.152972°N 14.841500°E 79:54.502111°N 16.891222°E 1087:Submarine power cables 1042:The ABB Group: SwePol 1010:GPX (all coordinates) 372:54.57361°N 16.78250°E 238:Technical information 186:Ownership information 585:56.152972; 14.841500 539:54.502111; 16.891222 427:for the Swedish and 405:smoothing rectifiers 383:SwePol enters Poland 124:56.152972; 14.841500 84:54.502111; 16.891222 575: /  529: /  367: /  114: /  74: /  1057:Skyscraperpage.com 753:. 10 December 2014 377:54.57361; 16.78250 30:Location of SwePol 1047:Site on GeoPortal 985: 984: 977: 603: 602: 301: 300: 143:General direction 1129: 980: 973: 969: 966: 960: 955:this article by 946:inline citations 933: 932: 925: 914: 913: 911: 909: 894: 888: 887: 885: 877: 871: 870: 868: 860: 854: 853: 851: 843: 837: 836: 834: 826: 820: 819: 817: 809: 803: 802: 800: 792: 786: 785: 783: 781: 769: 763: 762: 760: 758: 747: 741: 740: 738: 736: 725: 719: 718: 716: 708: 664:Energy in Poland 658: 653: 652: 644: 639: 638: 637: 630: 625: 624: 623: 606:Cultural meaning 599: 598: 596: 595: 594: 592: 587: 586: 581: 576: 573: 572: 571: 568: 553: 552: 550: 549: 548: 546: 541: 540: 535: 530: 527: 526: 525: 522: 501: 462:Svenska Kraftnät 425:Svenska Kraftnät 413:Svenska Kraftnät 391: 390: 388: 387: 386: 384: 379: 378: 373: 368: 365: 364: 363: 360: 348:of 450 kV. 330:Bruskowo Wielkie 293: 195:Svenska Kraftnät 176:Bruskowo Wielkie 138: 137: 135: 134: 133: 131: 126: 125: 120: 115: 112: 111: 110: 107: 98: 97: 95: 94: 93: 91: 86: 85: 80: 75: 72: 71: 70: 67: 21: 1137: 1136: 1132: 1131: 1130: 1128: 1127: 1126: 1062: 1061: 1037:PSE-SwePol Link 1028: 1027: 1026: 1025: 1024: 981: 970: 964: 961: 951:Please help to 950: 934: 930: 923: 918: 917: 907: 905: 896: 895: 891: 883: 879: 878: 874: 866: 862: 861: 857: 849: 845: 844: 840: 832: 828: 827: 823: 815: 811: 810: 806: 798: 794: 793: 789: 779: 777: 771: 770: 766: 756: 754: 749: 748: 744: 734: 732: 727: 726: 722: 714: 710: 709: 705: 700: 654: 647: 640: 635: 633: 626: 621: 619: 616: 608: 590: 588: 584: 582: 578: 577: 574: 569: 566: 564: 562: 561: 544: 542: 538: 536: 532: 531: 528: 523: 520: 518: 516: 515: 499: 470: 452: 397:metallic return 382: 380: 376: 374: 370: 369: 366: 361: 358: 356: 354: 353: 320:peninsula near 314:submarine cable 251:Type of current 129: 127: 123: 121: 117: 116: 113: 108: 105: 103: 101: 100: 99: 89: 87: 83: 81: 77: 76: 73: 68: 65: 63: 61: 60: 31: 17: 12: 11: 5: 1135: 1133: 1125: 1124: 1119: 1114: 1109: 1104: 1099: 1094: 1089: 1084: 1079: 1074: 1064: 1063: 1060: 1059: 1054: 1049: 1044: 1039: 1034: 1032:SwePol Link AB 1023: 1022: 1017: 1012: 1007: 1001: 995: 988: 987: 986: 983: 982: 937: 935: 928: 922: 921:External links 919: 916: 915: 904:on 5 June 2011 889: 872: 855: 838: 821: 804: 787: 764: 742: 720: 702: 701: 699: 696: 695: 694: 688: 682: 676: 671: 666: 660: 659: 645: 631: 615: 612: 607: 604: 601: 600: 559: 555: 554: 513: 509: 508: 505: 498: 495: 469: 468:Annual reports 466: 450: 447:Czech Republic 299: 298: 295: 288: 287: 284: 280: 279: 276: 272: 271: 268: 264: 263: 260: 256: 255: 252: 248: 247: 244: 240: 239: 235: 234: 231: 227: 226: 221: 217: 216: 211: 207: 206: 202: 201: 192: 188: 187: 183: 182: 173: 169: 168: 163: 162:Passes through 159: 158: 152: 148: 147: 144: 140: 139: 58: 52: 51: 42: 38: 37: 33: 32: 29: 26: 25: 15: 13: 10: 9: 6: 4: 3: 2: 1134: 1123: 1120: 1118: 1115: 1113: 1110: 1108: 1105: 1103: 1100: 1098: 1095: 1093: 1090: 1088: 1085: 1083: 1080: 1078: 1075: 1073: 1070: 1069: 1067: 1058: 1055: 1053: 1050: 1048: 1045: 1043: 1040: 1038: 1035: 1033: 1030: 1029: 1021: 1018: 1016: 1013: 1011: 1008: 1006: 1003: 1002: 1000: 999: 994: 993:OpenStreetMap 991: 979: 976: 968: 958: 954: 948: 947: 941: 936: 927: 926: 920: 903: 899: 898:"Aktualności" 893: 890: 882: 876: 873: 865: 859: 856: 848: 842: 839: 831: 825: 822: 814: 808: 805: 797: 791: 788: 775: 768: 765: 752: 746: 743: 730: 724: 721: 713: 707: 704: 697: 692: 689: 686: 683: 680: 677: 675: 672: 670: 667: 665: 662: 661: 657: 656:Energy portal 651: 646: 643: 642:Poland portal 632: 629: 628:Sweden portal 618: 613: 611: 605: 597: 560: 557: 556: 551: 514: 511: 510: 506: 503: 502: 496: 494: 490: 486: 482: 478: 474: 467: 465: 463: 459: 458:began to leak 454: 448: 444: 439: 436: 432: 430: 426: 422: 418: 414: 409: 406: 401: 398: 393: 389: 349: 347: 343: 339: 335: 331: 327: 323: 319: 315: 312: 309: 305: 296: 289: 285: 281: 277: 273: 269: 265: 261: 257: 253: 249: 245: 241: 236: 232: 228: 225: 222: 218: 215: 212: 208: 203: 200: 196: 193: 189: 184: 181: 177: 174: 170: 167: 164: 160: 157: 153: 149: 145: 141: 136: 96: 59: 57: 53: 50: 46: 43: 39: 34: 27: 22: 19: 997: 996: 989: 971: 965:January 2010 962: 943: 906:. Retrieved 902:the original 892: 875: 858: 841: 824: 807: 790: 778:. Retrieved 767: 755:. Retrieved 745: 733:. Retrieved 723: 706: 691:Harmony Link 609: 570:14°50′29.4″E 567:56°09′10.7″N 524:16°53′28.4″E 507:Coordinates 491: 487: 483: 479: 475: 471: 455: 440: 437: 433: 429:PSE-Operator 421:PSE-Operator 410: 402: 394: 350: 316:between the 303: 302: 267:Power rating 259:Total length 246:subsea cable 230:Commissioned 199:PSE-Operator 109:14°50′29.4″E 106:56°09′10.7″N 69:16°53′28.4″E 18: 957:introducing 757:24 November 735:24 November 685:LitPol Link 583: / 537: / 521:54°30′7.6″N 375: / 344:power at a 286:450 kV 270:600 MW 146:north–south 122: / 82: / 66:54°30′7.6″N 56:Coordinates 1066:Categories 940:references 698:References 589: ( 543: ( 417:Vattenfall 381: ( 362:16°46′57″E 359:54°34′25″N 283:DC voltage 275:AC voltage 166:Baltic Sea 128: ( 88: ( 908:1 October 780:4 October 352:Ustka at 322:Karlshamn 308:monopolar 614:See also 294:of poles 36:Location 953:improve 679:Estlink 443:Germany 415:(51%), 346:voltage 332:, near 41:Country 942:, but 338:Poland 334:Słupsk 328:, and 326:Sweden 318:Stärnö 304:SwePol 180:Poland 156:Sweden 49:Poland 45:Sweden 24:SwePol 884:(PDF) 867:(PDF) 850:(PDF) 833:(PDF) 816:(PDF) 799:(PDF) 715:(PDF) 497:Sites 191:Owner 910:2022 782:2022 759:2020 737:2020 504:Site 254:HVDC 243:Type 233:2000 151:From 1005:KML 292:No. 224:ABB 214:ABB 1068:: 342:MW 336:, 324:, 197:, 172:To 47:, 978:) 972:( 967:) 963:( 949:. 912:. 886:. 869:. 852:. 835:. 818:. 801:. 784:. 761:. 739:. 717:. 593:) 547:) 451:2 385:) 297:1 132:) 92:)

Index

Sweden
Poland
Coordinates
54°30′7.6″N 16°53′28.4″E / 54.502111°N 16.891222°E / 54.502111; 16.891222 (SwePol - Bruskowo Wielkie (Slupsk) Static Inverter Plant)
56°09′10.7″N 14°50′29.4″E / 56.152972°N 14.841500°E / 56.152972; 14.841500 (SwePol - Stärnö Static Inverter Plant)
Sweden
Baltic Sea
Bruskowo Wielkie
Poland
Svenska Kraftnät
PSE-Operator
ABB
ABB
monopolar
high-voltage direct current (HVDC)
submarine cable
Stärnö
Karlshamn
Sweden
Bruskowo Wielkie
Słupsk
Poland
MW
voltage
54°34′25″N 16°46′57″E / 54.57361°N 16.78250°E / 54.57361; 16.78250 (SwePol enters Poland)
metallic return
smoothing rectifiers
Svenska Kraftnät
Vattenfall
PSE-Operator

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.