Knowledge

Semmering Base Tunnel

Source đź“ť

33: 397:
to consist of 26 crossover passages between the two tunnels, along with an emergency station; a pair of 400 metre-deep ventilation shafts are also to be dug. By 7 June 2016, work on the third section of the SBT had commenced; this meant that full-rate construction activity upon the project, which was reportedly costed at €3.3 billion as of this point in time, was now underway.
409:
Additional major works will include the construction of entrances in Gloggnitz and MĂĽrzzuschlag, as well as ventilation shafts at Trattenbach and Sommerau. Substations located at Gloggnitz and Langenwang are intended to be used to supply electricity to the trains that will run through the SBT. Beyond
400:
To facilitate the construction work, three intermediate sites were established near to Göstritz, Fröschnitzgraben and Grautschenhof. At Göstritz, a 1,000 metre access gallery and multiple 250 metre-deep shafts were constructed to facilitate conventional tunnel excavation methods. At Fröschnitzgraben,
287:
at a significantly lower altitude. During 2006, a two-year route selection process was conducted; in April 2008, it was announced that the southernmost route had been determined to be the optimum of those studied. During the later half of 2009, the final route for the proposed SBT was selected; this
396:
During 2012, preparatory ground works for the SBT commenced. On 7 January 2014, construction began upon the tunnel's central section. Work on this section involved boring work along a length of 8.6 km, while a drill-and-blast method for the remaining 4.3 km section. The central section is
413:
Owing to encountering difficulties with the complex geology in the area, including the fault zone being traversed during construction and different rock types, an additional cost of €390 million was added taking the total cost to €3.9 billion, with measures to mitigate these risks in 2021 being
291:
Specifically, the tunnel comprises twin-parallel bores, each possessing a diameter of 10 meters and separated by up to 70 meters; for safety reasons, connecting pedestrian passages between the two bores are to occur at regular intervals of up to 500 meters. Being significantly faster than the
218:
Construction began on 25 April 2012 and the link is expected to enter operational service in 2030, delayed from the original estimate of 2026. The main benefit of the new tunnel will be increased ease of use for freight traffic. The gradients of the traditional routes requires the use of two
246:
will enable Graz-Klagenfurt journeys of approximately 45 minutes, as such it will bring Vienna-Klagenfurt journeys down to around 3 hours 25 minutes starting end of 2025. The SBT is projected to enable time savings of additional 45 minutes, which will enable journeys from Vienna to Graz and
528: 352:
for it to conduct tunnel excavation works, while Strabag was engaged to conduct drilling activities. During 2010, BGG Consult was awarded a contract to provide geotechnical and hydrogeological consulting services during both the tendering and construction phases of the programme.
339:
The primary contracts for the construction of the SBT is divided into three contract sections. During 2014, the contract for the construction of the 13 km-long central section of the tunnel, valued at approximately €623 million ($ 827 million), was awarded to a consortium of
215:. The existing route is 41 km long and the Semmering Base Tunnel will be 27.3 km long. The new route will offer time savings of up to 30 minutes, partly on account of the shorter route and partly on account of the higher speed limit (maximum 250 km/h). 303:
The SBT has a gradient of 0.85 per cent. This gradient was selected to enable it to be used by heavy freight trains with only a single locomotive. The plan involves several infrastructure changes, such as the integration of the railway stations at
276:. By the turn of the 21st century, a total of 70,000 goods and passenger trains were reportedly being run through the Semmering railway during each year, it is one of the busiest routes in 283:
In order to relieve pressure upon the original route, interest grew in the development of a more direct route over the Alps. These notions soon centered around the concept of boring a
772: 268:, and has been commonly referred to as the world's first true mountain railway. The historic significance of this traditional route is such that it has been declared a 109: 105: 665: 410:
the tunnel itself, ancillary work involves the construction of two new railway bridges, as well as a new road bridge and an underpass for the B27.
618: 512: 723: 767: 582: 219:
locomotives; the reduced gradient of the new link will enable the transit of freight traffic using just one locomotive. The SBT and the
405:. Once assembled, these will be used to create the bore towards Gloggnitz. Breakthrough of this section occurred on 10 June 2022. 603: 777: 648: 32: 436: 693: 633: 529:"New Semmering Base Tunnel – the current state of tunnel design taking the newest investigation results into account." 456: 377: 357: 678: 264:, which was constructed between 1848 and 1854, holds the distinction of being the first railway to traverse the 496: 401:
a pair of 400 metre-deep shafts, possessing a diameter of 22 metres, were dug ahead of the deployment of
762: 402: 373: 349: 481: 381: 321: 564: 364:
of Werner Consult and Witrisal consortium to conduct the route planning for the tunnel. Separately,
223:
in combination will enable freight transit across the whole southern line with just one locomotive.
385: 345: 326: 269: 527:
Daller Dipl.-Ing, Josef & Vigl Dipl.-Ing. Dr.techn, Alois & K. Wagner Dipl.-Ing, Oliver.
317: 261: 313: 380:
systems. Soil mechanical and geotechnical consulting services at the intermediate sites at
124: 309: 204: 92: 220: 212: 368:
was also involved in the design for the new twin-tube tunnels; this work included its
756: 292:
Semmering line, it would enable a reduction in the travel time between the cities of
128: 69: 132: 369: 284: 152: 361: 243: 235: 738: 725: 365: 305: 200: 87: 38: 242:
services are 2 hours 35 minutes and 3 hours 55 minutes, respectively. The
341: 277: 239: 208: 65: 708: 247:
Klagenfurt of 1 hour 50 minutes and 2 hours 40 minutes, respectively.
293: 273: 227: 73: 316:
scheme is required to mitigate against the risk posed by the nearby
482:
Semmering-Basistunnel in der Steiermark fertig gegraben (in German)
297: 265: 231: 679:"Semmering base tunnel – major contract for the Marti groupe." 312:
with the proposed route. Outside of railway infrastructure, a
288:
ran between Gloggnitz and the MĂĽrzzuschlag-Langenwang area.
513:"The Semmering Base Tunnel: powerful and future-oriented." 360:
contracted the planning of the proposed SBT's route to a
694:"Milestone for the Semmering base tunnel (SBT) lot 2.1." 709:"Durchschlag beim Semmering-Basistunnel" (in German) 185: 151: 143: 138: 120: 115: 101: 80: 61: 51: 46: 21: 604:"Construction starts on Semmering Base Tunnel." 199:is a railway tunnel under construction between 583:"Ground preparation at Semmering Base Tunnel." 484:8 September 2023, Retrieved 12 September 2023. 619:"Semmering base tunnel (lots 1.1. and 2.1.)." 8: 578: 576: 560: 497:"Semmering railway tunnel gets green light." 773:Transport infrastructure under construction 558: 556: 554: 552: 550: 548: 546: 544: 542: 540: 598: 596: 594: 492: 490: 442:. Austrian Federal Railways. August 2008. 431: 429: 427: 457:"Further delay to Semmering Base Tunnel" 649:"Work starts on Semmering base tunnel." 423: 376:, including operational and emergency 18: 348:. A separate contract was awarded to 7: 451: 449: 16:Railway tunnel in southern Austria 14: 664:Briginshaw, David (7 June 2016). 437:"Semmering Base Tunnel Factsheet" 31: 666:"Semmering Base Tunnel update" 331:road would also be necessary. 1: 461:International Railway Journal 320:while the relocation of the 189:230 km/h (145 mph) 147:27.3 km (17.0 mi) 794: 768:Railway tunnels in Austria 37:Northern tunnel portal at 654:, Retrieved: 29 May 2018. 624:, Retrieved: 29 May 2018. 570:, Retrieved: 28 May 2018. 358:Austrian Federal Railways 30: 639:, Retrieved 29 May 2018. 634:"Semmering Base Tunnel." 565:"Semmering Base Tunnel." 388:by INSITU Geotechnics. 226:Currently, the fastest 778:2027 in rail transport 568:railway-technology.com 403:tunnel boring machines 22:Semmering Base Tunnel 516:Global Railway Review 374:environmental control 197:Semmering Base Tunnel 25:Semmering-Basistunnel 739:47.6758°N 15.9224°E 735: /  270:World Heritage Site 652:Allan J Hargreaves 609:, 14 January 2016. 602:Reidinger, Erwin. 588:, 7 February 2013. 350:Amberg Engineering 56:under construction 697:tunnelbuilder.com 511:Gobiet, Gerhard. 262:Semmering railway 193: 192: 785: 750: 749: 747: 746: 745: 744:47.6758; 15.9224 740: 736: 733: 732: 731: 728: 715: 706: 700: 699:, 21 March 2018. 691: 685: 676: 670: 669: 661: 655: 646: 640: 631: 625: 616: 610: 600: 589: 580: 571: 562: 535: 532:researchgate.net 525: 519: 518:, 6 August 2015. 509: 503: 494: 485: 478: 472: 471: 469: 468: 453: 444: 443: 441: 433: 382:Fröschnitzgraben 330: 314:flood protection 238:journeys on the 181: 177: 175: 174: 170: 167: 159: 35: 19: 793: 792: 788: 787: 786: 784: 783: 782: 753: 752: 743: 741: 737: 734: 729: 726: 724: 722: 721: 719: 718: 714:, 10 June 2022. 707: 703: 692: 688: 684:, 21 July 2016. 677: 673: 668:. Rail Journal. 663: 662: 658: 647: 643: 632: 628: 617: 613: 601: 592: 581: 574: 563: 538: 526: 522: 510: 506: 495: 488: 479: 475: 466: 464: 455: 454: 447: 439: 435: 434: 425: 420: 408: 394: 337: 324: 258: 253: 211:underneath the 186:Operating speed 179: 172: 168: 165: 163: 162:4 ft  161: 157: 131: 127: 125:High-speed rail 97: 42: 23: 17: 12: 11: 5: 791: 789: 781: 780: 775: 770: 765: 755: 754: 717: 716: 701: 686: 671: 656: 641: 626: 611: 590: 586:tunneltalk.com 572: 536: 520: 504: 502:, 27 May 2015. 486: 473: 445: 422: 421: 419: 416: 414:unsuccessful. 393: 390: 336: 333: 318:River Schwarza 257: 254: 252: 249: 221:Koralm Railway 213:Semmering Pass 191: 190: 187: 183: 182: 180:standard gauge 155: 149: 148: 145: 141: 140: 136: 135: 122: 118: 117: 113: 112: 103: 99: 98: 96: 95: 90: 84: 82: 78: 77: 63: 59: 58: 53: 49: 48: 44: 43: 36: 28: 27: 15: 13: 10: 9: 6: 4: 3: 2: 790: 779: 776: 774: 771: 769: 766: 764: 761: 760: 758: 751: 748: 713: 710: 705: 702: 698: 695: 690: 687: 683: 680: 675: 672: 667: 660: 657: 653: 650: 645: 642: 638: 635: 630: 627: 623: 620: 615: 612: 608: 605: 599: 597: 595: 591: 587: 584: 579: 577: 573: 569: 566: 561: 559: 557: 555: 553: 551: 549: 547: 545: 543: 541: 537: 533: 530: 524: 521: 517: 514: 508: 505: 501: 498: 493: 491: 487: 483: 477: 474: 462: 458: 452: 450: 446: 438: 432: 430: 428: 424: 417: 415: 411: 406: 404: 398: 391: 389: 387: 386:Grautschenhof 383: 379: 375: 371: 367: 363: 359: 354: 351: 347: 343: 334: 332: 328: 323: 319: 315: 311: 307: 301: 299: 295: 289: 286: 281: 279: 275: 271: 267: 263: 255: 250: 248: 245: 241: 237: 233: 229: 224: 222: 216: 214: 210: 206: 202: 198: 188: 184: 158:1,435 mm 156: 154: 150: 146: 142: 137: 134: 130: 129:Commuter rail 126: 123: 119: 114: 111: 107: 104: 100: 94: 91: 89: 86: 85: 83: 79: 75: 71: 70:Lower Austria 67: 64: 60: 57: 54: 50: 45: 40: 34: 29: 26: 20: 763:Base tunnels 720: 711: 704: 696: 689: 681: 674: 659: 651: 644: 637:ic-group.org 636: 629: 621: 614: 607:Rail Journal 606: 585: 567: 531: 523: 515: 507: 499: 480:OEBB Press: 476: 465:. Retrieved 463:. 2022-04-26 460: 412: 407: 399: 395: 392:Construction 370:aerodynamics 355: 338: 310:MĂĽrzzuschlag 302: 290: 282: 259: 225: 217: 205:MĂĽrzzuschlag 196: 194: 133:Freight rail 93:MĂĽrzzuschlag 55: 24: 742: / 682:Marti Group 378:ventilation 335:Contractors 325: [ 285:base tunnel 234:and Vienna- 153:Track gauge 144:Line length 757:Categories 730:15°55′21″E 727:47°40′33″N 467:2022-04-27 418:References 362:consortium 346:Swietelsky 256:Background 244:Koralmbahn 236:Klagenfurt 500:The Local 366:Gruner AG 306:Gloggnitz 201:Gloggnitz 139:Technical 88:Gloggnitz 39:Gloggnitz 622:Implenia 342:Implenia 176: in 47:Overview 534:, 2010. 278:Austria 251:History 240:Railjet 209:Austria 171:⁄ 116:Service 110:English 102:Website 81:Termini 66:Austria 294:Vienna 274:UNESCO 228:Vienna 106:German 74:Styria 62:Locale 52:Status 41:(2019) 440:(PDF) 329:] 384:and 372:and 356:The 344:and 308:and 298:Graz 296:and 266:Alps 260:The 232:Graz 203:and 195:The 121:Type 712:ORF 322:B27 272:by 207:in 759:: 593:^ 575:^ 539:^ 489:^ 459:. 448:^ 426:^ 327:de 300:. 280:. 178:) 108:/ 72:, 470:. 230:- 173:2 169:1 166:+ 164:8 160:( 76:) 68:(

Index


Gloggnitz
Austria
Lower Austria
Styria
Gloggnitz
MĂĽrzzuschlag
German
English
High-speed rail
Commuter rail
Freight rail
Track gauge
Gloggnitz
MĂĽrzzuschlag
Austria
Semmering Pass
Koralm Railway
Vienna
Graz
Klagenfurt
Railjet
Koralmbahn
Semmering railway
Alps
World Heritage Site
UNESCO
Austria
base tunnel
Vienna

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.

↑