Knowledge

Single-minute exchange of die

Source 📝

241:) as a new model moved through the factory, dedicating tools to the die-change process so that all needed tools were nearby, and scheduling use of the overhead cranes so that the new die would be waiting as the old die was removed. Using these processes, Toyota engineers cut the change-over time to less than 10 minutes per die, and thereby reduced the economic lot size below one vehicle. 35: 539: 381:
Separate the internal and external activities. Internal activities are those that can only be performed when the process is stopped, while external activities can be done while the last batch is being produced, or once the next batch has started. For example, go and get the required tools for the job
233:
Toyota's first improvement was to place precision measurement devices on the transfer stamping machines, and record the necessary measurements for each model's die. Installing the die against these measurements, rather than by human eyesight, immediately cut the change-over to a mere hour and a half.
549:
By taking the 'actual' operations and making them into a network which contains the dependencies it is possible to optimize task attribution and further optimize setup time. Issues of effective communication between the operators must be managed to ensure safety is assured where potentially noisy or
225:
Toyota found that the most difficult tools to change were the dies on the large transfer-stamping machines that produce car vehicle body parts. The dies – which must be changed for each model – weigh many tons, and must be assembled in the stamping machines with tolerances of less than a millimeter,
358:
A) ensure that external setup actions are performed while the machine is still running, B) separate external and internal setup actions, ensure that the parts all function and implement efficient ways of transporting the die and other parts, C) convert internal setup actions to external, D) improve
229:
When Toyota engineers examined the change-over, they discovered that the established procedure was to stop the line, let down the dies by an overhead crane, position the dies in the machine by human eyesight, and then adjust their position with crowbars while making individual test stampings. The
208:
participated in one QDC workshop. After he started to publicize details of the Toyota Production System without permission, the business connection was terminated abruptly by Toyota. Shingo moved to the US and started to consult on lean manufacturing. Besides claiming to have invented this quick
106:
methods for reducing inefficiencies in a manufacturing process. It provides a rapid and efficient way of converting a manufacturing process from running the current product to running the next product. This is key to reducing production lot sizes, and reducing uneven flow
264:
Shigeo Shingo, who created the SMED approach, claims that in his data from between 1975 and 1985 that average setup times he has dealt with have reduced to 2.5% of the time originally required; a 40 times improvement.
170:, setup reduction approaches were clearly described. However, these approaches never became mainstream. For most parts during the 20th century, the economic order quantity was the gold standard for lot sizing. 181:
became manager of the machine shops at Toyota. On a trip to the US in 1955, Ohno observed Danly stamping presses with rapid die change capability. Subsequently, Toyota bought multiple Danly presses for the
388:
Streamline the remaining internal activities, by simplifying them. Focus on fixings – Shigeo Shingo observed that it's only the last turn of a bolt that tightens it—the rest is just movement.
511:
Lack of functional standardization, that is standardization of only the parts necessary for setup e.g. all bolts use same size spanner, die grip points are in the same place on all dies
311:
Ability to mix production gives flexibility and further inventory reductions as well as opening the door to revolutionized production methods (large orders ≠ large production lot sizes)
417:
Run N (not illustrated) would have changeovers that take 1.5 minutes (97% reduction) and whole shift time reduced from 420 minutes to 368 minutes a productivity improvement of 12%.
177:
workflow of Toyota had a problem of tool changeover taking between two and eight hours. Setup time and lot reduction had been ongoing in Toyota's production system since 1945 when
397:
Do it all again: For each iteration of the above process, a 45% improvement in set-up times should be expected, so it may take several iterations to cross the ten-minute line.
756: 490:
Shortages, mistakes, inadequate verification of equipment causing delays and can be avoided by check tables, especially visual ones, and setup on an intermediary jig
201:
Over time, Toyota decreased changeover times from hours to fifteen minutes by the 1960s, three minutes by the 1970s, and ultimately just 180 seconds by the 1990s.
155:
studied and improved working processes in many different industries, from bricklaying to surgery. As part of his work, he also looked into changeovers. His book
749: 428:
The SMED concept is credited to Shigeo Shingo, one of the main contributors to the consolidation of the Toyota Production System, along with
411:
Run 3 shows the impact of the improvements in changeover times that come from doing more of them and building learning into their execution.
560: 555: 268:
However, the power of SMED is that it has a lot of other effects which come from systematically looking at operations; these include:
414:
Run 4 shows how these improvements can get you back to the same production time but now with more flexibility in production capacity.
868: 742: 82: 363: 422: 118:
minute, rather, it should take less than 10 minutes ("single-digit minute"). A closely associated yet more difficult concept is
64: 45: 712: 802: 832: 352:
NB External setup can be done without the line being stopped whereas internal setup requires that the line be stopped.
863: 661: 302:
Lower skill requirements since changes are now designed into the process rather than a matter of skilled judgement
385:
Convert (where possible) internal activities into external ones (pre-heating of tools is a good example of this).
237:
Further observations led to further improvements – scheduling the die changes in a standard sequence (as part of
249: 238: 142: 60: 401:
This diagram shows four successive runs with learning from each run and improvements applied before the next.
508:
Forcing a changeover between different raw materials when a continuous feed, or near equivalent, is possible
245: 777: 152: 451:
Preparation, after-process adjustment, and checking of raw materials, blades, dies, jigs, gauges, etc.
323:
Shigeo Shingo recognizes eight fundamental techniques that should be considered in implementing SMED.
797: 792: 787: 576: 253: 131: 108: 827: 127: 499:
Unheated molds which require several wasted 'tests' before they will be at the temperature to work
765: 391:
Streamline the external activities, so that they are of a similar scale to the internal ones (D).
174: 217:
stands for a single digit minute (i.e., less than ten minutes). He promoted TPS and SMED in US.
684:
A revolution in manufacturing: The SMED system, Shigeo Shingo, Productivity Press, 1985, p 113
194:
for short. They developed a structured approach based on a framework from the US World War II
130:
is a tool used in manufacturing. However, SMED's utility is not limited to manufacturing (see
702:
A revolution in manufacturing: The SMED system, Shigeo Shingo, Productivity Press, 1985, p 27
281:
Increased machine work rates from reduced setup times even if number of changeovers increases
17: 837: 226:
otherwise the stamped metal will wrinkle, if not melt, under the intense heat and pressure.
114:
The phrase "single minute" does not mean that all changeovers and startups should only take
183: 103: 631: 56: 693:
A study of the Toyota Production System, Shigeo Shingo, Productivity Press, 1989, p 47
857: 205: 186:
plant and started improving the changeover time of their presses. This was known as
149:(page 171). However, he did not create any method or structured approach around it. 716: 429: 178: 166:'s factories were using some setup reduction techniques. In the 1915 publication 502:
Using slow precise adjustment equipment for the large coarse part of adjustment
305:
Elimination of unusable stock from model changeovers and demand estimate errors
571: 559: 517:
More attachment points than actually required for the forces to be constrained
355:
He suggests that SMED improvement should pass through four conceptual stages:
284:
Elimination of setup errors and elimination of trial runs reduces defect rates
275:
Reduction in footprint of processes with reduced inventory freeing floor space
163: 647: 822: 812: 782: 554: 734: 374:
There are seven basic steps to reducing changeover using the SMED system:
538: 256:
much more achievable by reducing economic lot size and thus stock levels.
230:
existing process took from twelve hours to almost three days to complete.
198:(TWI) program, called ECRS – Eliminate, Combine, Rearrange, and Simplify. 493:
Inadequate or incomplete repairs to equipment causing rework and delays
126:), which says changeovers can and should take less than 100 seconds. A 505:
Lack of visual lines or benchmarks for part placement on the equipment
362: 204:
During the late 1970s, when Toyota's method was already well refined,
807: 605: 394:
Document the new procedure, and actions that are yet to be completed.
287:
Improved quality from fully regulated operating conditions in advance
421: 537: 648:"The History of Quick Change Over (SMED) | AllAboutLean.com" 842: 408:
Run 2 shows what would happen if more changeovers were included.
293:
Simplified housekeeping from fewer tools and better organization
738: 314:
New attitudes on controllability of work process amongst staff
28: 529:
Any adjustments of assisting tools such as guides or switches
595:
Study of Toyota Production System, Shigeo Shingo, 1981, p 70
420: 361: 159:(also from 1911) described approaches to reduce setup time. 145:
analyzed non-value-adding parts of setups in his 1911 book,
272:
Stockless production which drives inventory turnover rates,
209:
changeover method (among many other things), he renamed it
662:"Microsoft PowerPoint - Origins and Facts Regarding TPS" 520:
Attachment points that take more than one turn to fasten
514:
Much operator movement around the equipment during setup
336:
Use functional clamps or eliminate fasteners altogether
52: 496:
Optimization for least work as opposed to least delay
636:. unknown library. The Engineering magazine company. 244:
The success of this program contributed directly to
63:, and by adding encyclopedic content written from a 467:Centering, dimensioning and setting of conditions 278:Productivity increases or reduced production time 630:Horace Lucien Arnold, Fay Leone Faurote (1915). 327:Separate internal from external setup operations 610:Library of Congress, Washington, D.C. 20540 USA 750: 8: 547:Parallel operations using multiple operators 111:), production loss, and output variability. 342:Adopt parallel operations (see image below) 757: 743: 735: 299:Operator preferred since easier to achieve 405:Run 1 illustrates the original situation. 83:Learn how and when to remove this message 439: 308:Goods are not lost through deterioration 588: 550:visually obstructive conditions occur. 44:contains content that is written like 7: 290:Increased safety from simpler setups 523:Any adjustments after initial setup 459:Mounting and removing blades, etc. 96:Single-minute digit exchange of die 330:Convert internal to external setup 25: 558: 553: 33: 633:Ford Methods and the Ford Shops 526:Any use of experts during setup 378:OBSERVE the current methodology 333:Standardize function, not shape 1: 833:Total productive maintenance 818:Single-minute exchange of die 803:Continuous-flow manufacturing 211:Single Minute Exchange of Die 18:Single-Minute Exchange of Die 475:Trial runs and adjustments 168:Ford Methods and Ford Shops 885: 382:before the machine stops. 246:just-in-time manufacturing 773: 534:Record all necessary data 319:Implementation techniques 260:Effects of implementation 120:one-touch exchange of die 869:Toyota Production System 798:Muri - Standardized work 250:Toyota Production System 213:or, in short, SMED. The 196:Training within Industry 143:Frederick Winslow Taylor 436:Key elements to observe 296:Lower expense of setups 778:Cellular manufacturing 543: 425: 366: 542:Data capture template 541: 424: 365: 345:Eliminate adjustments 339:Use intermediate jigs 248:which is part of the 153:Frank Bunker Gilbreth 102:) is one of the many 65:neutral point of view 577:Value stream mapping 132:value stream mapping 828:Production leveling 446:Proportion of time 359:all setup actions. 57:promotional content 864:Lean manufacturing 788:Muda - Over burden 766:Lean manufacturing 544: 426: 367: 59:and inappropriate 851: 850: 843:Plan–do–check–act 793:Mura - Unevenness 606:"Shop management" 482: 481: 93: 92: 85: 16:(Redirected from 876: 838:5S (methodology) 759: 752: 745: 736: 729: 728: 726: 724: 719:on 23 March 2006 715:. Archived from 713:"How to do SMED" 709: 703: 700: 694: 691: 685: 682: 676: 675: 673: 671: 666: 658: 652: 651: 644: 638: 637: 627: 621: 620: 618: 616: 602: 596: 593: 562: 557: 440: 188:Quick Die Change 88: 81: 77: 74: 68: 46:an advertisement 37: 36: 29: 21: 884: 883: 879: 878: 877: 875: 874: 873: 854: 853: 852: 847: 769: 763: 733: 732: 722: 720: 711: 710: 706: 701: 697: 692: 688: 683: 679: 669: 667: 664: 660: 659: 655: 650:. 2 March 2014. 646: 645: 641: 629: 628: 624: 614: 612: 604: 603: 599: 594: 590: 585: 568: 438: 372: 321: 262: 223: 147:Shop Management 140: 104:lean production 89: 78: 72: 69: 50: 38: 34: 23: 22: 15: 12: 11: 5: 882: 880: 872: 871: 866: 856: 855: 849: 848: 846: 845: 840: 835: 830: 825: 820: 815: 810: 805: 800: 795: 790: 785: 780: 774: 771: 770: 764: 762: 761: 754: 747: 739: 731: 730: 704: 695: 686: 677: 653: 639: 622: 597: 587: 586: 584: 581: 580: 579: 574: 567: 564: 531: 530: 527: 524: 521: 518: 515: 512: 509: 506: 503: 500: 497: 494: 491: 480: 479: 476: 472: 471: 468: 464: 463: 460: 456: 455: 452: 448: 447: 444: 437: 434: 419: 418: 415: 412: 409: 406: 399: 398: 395: 392: 389: 386: 383: 379: 371: 368: 350: 349: 346: 343: 340: 337: 334: 331: 328: 320: 317: 316: 315: 312: 309: 306: 303: 300: 297: 294: 291: 288: 285: 282: 279: 276: 273: 261: 258: 254:load balancing 222: 219: 139: 136: 91: 90: 61:external links 41: 39: 32: 24: 14: 13: 10: 9: 6: 4: 3: 2: 881: 870: 867: 865: 862: 861: 859: 844: 841: 839: 836: 834: 831: 829: 826: 824: 821: 819: 816: 814: 811: 809: 806: 804: 801: 799: 796: 794: 791: 789: 786: 784: 781: 779: 776: 775: 772: 767: 760: 755: 753: 748: 746: 741: 740: 737: 718: 714: 708: 705: 699: 696: 690: 687: 681: 678: 663: 657: 654: 649: 643: 640: 635: 634: 626: 623: 611: 607: 601: 598: 592: 589: 582: 578: 575: 573: 570: 569: 565: 563: 561: 556: 551: 548: 540: 536: 535: 528: 525: 522: 519: 516: 513: 510: 507: 504: 501: 498: 495: 492: 489: 488: 487: 486: 477: 474: 473: 469: 466: 465: 461: 458: 457: 453: 450: 449: 445: 442: 441: 435: 433: 431: 423: 416: 413: 410: 407: 404: 403: 402: 396: 393: 390: 387: 384: 380: 377: 376: 375: 370:Formal method 369: 364: 360: 356: 353: 348:Mechanization 347: 344: 341: 338: 335: 332: 329: 326: 325: 324: 318: 313: 310: 307: 304: 301: 298: 295: 292: 289: 286: 283: 280: 277: 274: 271: 270: 269: 266: 259: 257: 255: 252:. SMED makes 251: 247: 242: 240: 235: 231: 227: 220: 218: 216: 215:Single Minute 212: 207: 206:Shigeo Shingo 202: 199: 197: 193: 189: 185: 180: 176: 171: 169: 165: 160: 158: 154: 150: 148: 144: 137: 135: 133: 129: 125: 121: 117: 112: 110: 105: 101: 97: 87: 84: 76: 66: 62: 58: 54: 48: 47: 42:This article 40: 31: 30: 27: 19: 817: 721:. Retrieved 717:the original 707: 698: 689: 680: 668:. Retrieved 656: 642: 632: 625: 613:. Retrieved 609: 600: 591: 552: 546: 545: 533: 532: 484: 483: 430:Taiichi Ohno 427: 400: 373: 357: 354: 351: 322: 267: 263: 243: 236: 232: 228: 224: 214: 210: 203: 200: 195: 191: 187: 179:Taiichi Ohno 172: 167: 161: 157:Motion Study 156: 151: 146: 141: 123: 119: 115: 113: 99: 95: 94: 79: 70: 55:by removing 51:Please help 43: 26: 723:29 November 670:29 November 858:Categories 583:References 572:Changeover 443:Operation 164:Henry Ford 53:improve it 823:Poka-yoke 813:Five whys 783:Takt time 485:Look for: 184:Motomachi 73:July 2016 615:1 August 566:See also 221:Example 138:History 808:Kanban 768:tools 665:(PDF) 190:, or 162:Even 725:2019 672:2019 617:2023 478:50% 470:15% 454:30% 173:The 124:OTED 109:Mura 100:SMED 462:5% 239:FRS 192:QDC 175:JIT 134:). 128:die 116:one 860:: 608:. 432:. 758:e 751:t 744:v 727:. 674:. 619:. 122:( 107:( 98:( 86:) 80:( 75:) 71:( 67:. 49:. 20:)

Index

Single-Minute Exchange of Die
an advertisement
improve it
promotional content
external links
neutral point of view
Learn how and when to remove this message
lean production
Mura
die
value stream mapping
Frederick Winslow Taylor
Frank Bunker Gilbreth
Henry Ford
JIT
Taiichi Ohno
Motomachi
Shigeo Shingo
FRS
just-in-time manufacturing
Toyota Production System
load balancing


Taiichi Ohno



Changeover
Value stream mapping

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.