29:
673:
As part of their application to purchase the facility, MG&E and WPS conducted an economic feasibility analysis. The analysis indicated it would cost between $ 90 million to $ 180 million (2018 dollars) to repower the facility, that is to replace the existing solar panels with new solar panels.
279:
in southwestern
Wisconsin, would save $ 100 million over its lifetime. Construction formally started later in 2019 and by July 2020 half of the panels had been installed. An estimated 300 people were required to construct the facility, mostly in the form of installing support posts and racking the
937:
296:
In 2023 Two Creeks generated 193 GWh, approximately 0.3% of the total electric power generated in
Wisconsin (63,216 GWh) for that year. The facility had an approximate annual capacity factor of 14.6% in 2023. A capacity factor of 24% was used during the economic analysis during the transfer of
247:
Construction for the plant was completed in
November 2020 at a cost of $ 195 million. As part of project application materials, the facility was expected to require three full-time staff once constructed. The facility is eligible for the Federal Solar Investment Tax Credit (ITC). The ITC is
287:
Energy
Resources, LCC) for approximately $ 1,299 per kW for a total project cost of $ 195 million. The PSC denied MGE and WPS's request for authorization to acquire Two Creeks at a cost of up to 110 percent of the $ 195 million cost, which would have covered allowance for funds used during
268:(CPCN) on May 31, 2018. On May 31, 2019, the CPCN application to construct the facility was approved by the PSC. In its approval ruling, the PSC found that the project satisfied the requirements of Wisconsin Statute § 1.12 and 196.025(1), known as the Energy Priorities Law.
678:
over time due to ultraviolet light and weather, reducing the efficiency and electrical output of the panel. Repowering aims to increase the output efficiency of a solar facility by replacing some or all of the photovoltaic panels.
768:
865:
889:
823:"Re: Docket 5-BS-228: Joint Application of Wisconsin Public Service Corporation and Madison Gas and Electric Company for Approval to Acquire Ownership of Solar Generating Facilities"
996:
275:
and senior executives from MG&E, WPS, WEC, and Next Era Energy
Resources LCC. At the time, a spokesperson for WPS stated that the Two Creeks plant, along with the
265:
240:
output rating of the facility is 213 MW. The facility covers approximately 800 acres within the towns of Two Creeks and Two Rivers, southwest of the nearby
61:
236:. PV panels are Jinko Eagle HC mono-crystalline measuring approximately 2 meters by 1 meter and rated at 400 watts (i.e. maximum output). The total
261:
222:
991:
229:, at 100 MW and 50MW, respectively. It was the first utility-scale solar plant approved and constructed in Wisconsin.
796:"Two Creeks Solar, LLC Solar CPCN Application Manitowoc and Kewaunee Counties, Wisconsin PSC Docket No. 9696-CE-100"
283:
The PSC approved MG&E and WPS's purchase and acquisition of the solar park from Two Creeks Solar (an entity of
218:
241:
276:
249:
226:
961:
913:
109:
769:"Wisconsin's first large-scale solar plant enters service; Two Creeks plant to power 33,000 homes"
697:
171:
822:
795:
746:
715:
840:
727:
181:
284:
237:
191:
28:
985:
304:
233:
151:
675:
272:
76:
63:
203:
890:"Construction at halfway mark for Wisconsin's first large-scale solar farm"
866:"Wisconsin's first large-scale solar project breaks ground in Two Rivers"
232:
The facility consists of approximately 533,000 PV panels on single-axis
280:
panels. The facility started generating electricity in
November 2020.
248:
normalized over the 30 year life of the project as required by the
271:
A groundbreaking ceremony was held in late August 2019 featuring
221:
in
Manitowoc County, Wisconsin. Ownership is shared between
260:
Two Creeks Solar, LLC submitted an engineering plan to the
190:
180:
170:
165:
157:
147:
142:
134:
126:
118:
108:
100:
92:
55:
47:
39:
21:
264:(PSC) on March 20, 2018, and an application for a
266:Certificate of Public Convenience and Necessity
8:
997:Solar energy companies of the United States
51:Town of Two Creeks & Town of Two Rivers
767:Journal, Chris Hubbuch | Wisconsin State.
223:Wisconsin Public Service Corporation (WPS)
18:
299:
688:
262:Public Services Commission of Wisconsin
723:
713:
7:
817:
815:
813:
790:
788:
741:
739:
737:
227:Madison Gas and Electric (MG&E)
14:
219:solar photovoltaic energy station
27:
1:
841:"Wisconsin Legislature: 1.12"
192:Annual net output
1013:
962:"Electricity Data Browser"
938:"Electricity Data Browser"
914:"Electricity Data Browser"
242:Point Beach Nuclear Plant
200:
35:
26:
845:docs.legis.wisconsin.gov
674:Solar panels experience
277:Badger Hollow Solar Farm
16:Solar plant in Wisconsin
870:Green Bay Press-Gazette
773:Wisconsin State Journal
308:) Two Creeks Solar Park
172:Nameplate capacity
101:Construction began
292:Electricity Production
288:construction (AFUDC).
119:Construction cost
669:Repower Cost Analysis
215:Two Creeks Solar Park
166:Power generation
77:44.24778°N 87.54333°W
22:Two Creeks Solar Park
182:Capacity factor
110:Commission date
992:Energy in Wisconsin
696:Group, WEC Energy.
310:
273:Governor Tony Evers
82:44.24778; -87.54333
73: /
864:Edquist, Kaitlin.
726:has generic name (
698:"WEC Clean Energy"
300:
297:ownership stage.
158:Solar tracker
130:WPS & MG&E
666:
665:
640:
635:
622:
617:
612:
607:
602:
597:
592:
587:
582:
577:
572:
567:
554:
549:
544:
539:
534:
529:
524:
519:
514:
509:
504:
499:
486:
481:
476:
471:
466:
461:
456:
451:
446:
441:
436:
431:
418:
413:
408:
403:
398:
393:
388:
383:
378:
373:
368:
363:
211:
210:
1004:
976:
975:
973:
972:
958:
952:
951:
949:
948:
934:
928:
927:
925:
924:
910:
904:
903:
901:
900:
886:
880:
879:
877:
876:
861:
855:
854:
852:
851:
837:
831:
830:
819:
808:
807:
805:
803:
792:
783:
782:
780:
779:
764:
758:
757:
755:
754:
749:. April 18, 2019
747:"FINAL DECISION"
743:
732:
731:
725:
721:
719:
711:
709:
708:
702:WEC Energy Group
693:
638:
633:
620:
615:
610:
605:
600:
595:
590:
585:
580:
575:
570:
565:
552:
547:
542:
537:
532:
527:
522:
517:
512:
507:
502:
497:
484:
479:
474:
469:
464:
459:
454:
449:
444:
439:
434:
429:
416:
411:
406:
401:
396:
391:
386:
381:
376:
371:
366:
361:
311:
234:tracking systems
204:edit on Wikidata
143:Solar farm
88:
87:
85:
84:
83:
78:
74:
71:
70:
69:
66:
31:
19:
1012:
1011:
1007:
1006:
1005:
1003:
1002:
1001:
982:
981:
980:
979:
970:
968:
960:
959:
955:
946:
944:
936:
935:
931:
922:
920:
912:
911:
907:
898:
896:
888:
887:
883:
874:
872:
863:
862:
858:
849:
847:
839:
838:
834:
829:. May 31, 2018.
827:January 8, 2023
821:
820:
811:
801:
799:
794:
793:
786:
777:
775:
766:
765:
761:
752:
750:
745:
744:
735:
722:
712:
706:
704:
695:
694:
690:
685:
671:
353:Annual (Total)
294:
258:
207:
81:
79:
75:
72:
67:
64:
62:
60:
59:
17:
12:
11:
5:
1010:
1008:
1000:
999:
994:
984:
983:
978:
977:
953:
929:
905:
881:
856:
832:
809:
798:. May 31, 2018
784:
759:
733:
687:
686:
684:
681:
670:
667:
664:
663:
661:
659:
657:
655:
653:
651:
649:
647:
645:
643:
641:
636:
631:
627:
626:
623:
618:
613:
608:
603:
598:
593:
588:
583:
578:
573:
568:
563:
559:
558:
555:
550:
545:
540:
535:
530:
525:
520:
515:
510:
505:
500:
495:
491:
490:
487:
482:
477:
472:
467:
462:
457:
452:
447:
442:
437:
432:
427:
423:
422:
419:
414:
409:
404:
399:
394:
389:
384:
379:
374:
369:
364:
359:
355:
354:
351:
348:
345:
342:
339:
336:
333:
330:
327:
324:
321:
318:
315:
293:
290:
257:
254:
209:
208:
201:
198:
197:
196:192 GWh (2023)
194:
188:
187:
184:
178:
177:
174:
168:
167:
163:
162:
159:
155:
154:
149:
145:
144:
140:
139:
136:
132:
131:
128:
124:
123:
120:
116:
115:
112:
106:
105:
102:
98:
97:
94:
90:
89:
57:
53:
52:
49:
45:
44:
41:
37:
36:
33:
32:
24:
23:
15:
13:
10:
9:
6:
4:
3:
2:
1009:
998:
995:
993:
990:
989:
987:
967:
963:
957:
954:
943:
939:
933:
930:
919:
915:
909:
906:
895:
891:
885:
882:
871:
867:
860:
857:
846:
842:
836:
833:
828:
824:
818:
816:
814:
810:
797:
791:
789:
785:
774:
770:
763:
760:
748:
742:
740:
738:
734:
729:
717:
703:
699:
692:
689:
682:
680:
677:
668:
662:
660:
658:
656:
654:
652:
650:
648:
646:
644:
642:
637:
632:
629:
628:
624:
619:
614:
609:
604:
599:
594:
589:
584:
579:
574:
569:
564:
561:
560:
556:
551:
546:
541:
536:
531:
526:
521:
516:
511:
506:
501:
496:
493:
492:
488:
483:
478:
473:
468:
463:
458:
453:
448:
443:
438:
433:
428:
425:
424:
420:
415:
410:
405:
400:
395:
390:
385:
380:
375:
370:
365:
360:
357:
356:
352:
349:
346:
343:
340:
337:
334:
331:
328:
325:
322:
319:
316:
313:
312:
309:
306:
303:
298:
291:
289:
286:
281:
278:
274:
269:
267:
263:
255:
253:
251:
245:
243:
239:
235:
230:
228:
224:
220:
216:
205:
199:
195:
193:
189:
185:
183:
179:
175:
173:
169:
164:
160:
156:
153:
152:Flat-panel PV
150:
146:
141:
137:
133:
129:
125:
122:$ 195 Million
121:
117:
113:
111:
107:
103:
99:
95:
91:
86:
58:
54:
50:
46:
43:United States
42:
38:
34:
30:
25:
20:
969:. Retrieved
965:
956:
945:. Retrieved
941:
932:
921:. Retrieved
917:
908:
897:. Retrieved
893:
884:
873:. Retrieved
869:
859:
848:. Retrieved
844:
835:
826:
800:. Retrieved
776:. Retrieved
772:
762:
751:. Retrieved
705:. Retrieved
701:
691:
672:
307:
302:Generation (
301:
295:
282:
270:
259:
246:
231:
217:is a 150 MW
214:
212:
186:14.6% (2023)
96:Commissioned
966:www.eia.gov
942:www.eia.gov
918:www.eia.gov
894:madison.com
724:|last=
676:degradation
161:Single-Axis
80: /
56:Coordinates
986:Categories
971:2024-05-14
947:2024-05-14
923:2023-01-08
899:2023-01-08
875:2023-01-08
850:2023-01-09
802:January 8,
778:2023-01-08
753:2023-01-08
707:2023-01-08
683:References
68:87°32′36″W
65:44°14′52″N
135:Employees
716:cite web
625:192,900
557:186,381
489:196,818
127:Owner(s)
114:Nov 2020
48:Location
421:13,405
285:NextEra
256:History
104:Q4 2019
40:Country
639:11,800
611:10,699
606:16,241
601:24,137
596:27,610
591:25,744
586:24,606
581:17,220
576:16,707
571:11,565
543:14,015
538:17,862
533:23,210
528:26,583
523:25,563
518:23,380
513:15,312
508:15,136
470:19,253
465:23,884
460:27,087
455:25,736
450:22,339
445:19,017
440:17,514
435:15,428
176:150 MW
93:Status
634:4,846
630:2024
621:4,467
616:9,454
566:4,450
562:2023
553:3,423
548:7,876
503:9,861
498:7,583
494:2022
485:3,120
480:8,067
475:9,865
430:5,508
426:2021
417:4,568
412:8,837
358:2020
314:Year
202:[
804:2021
728:help
350:Dec
347:Nov
344:Oct
341:Sep
338:Aug
335:Jul
332:Jun
329:May
326:Apr
323:Mar
320:Feb
317:Jan
225:and
213:The
148:Type
305:MWh
250:IRS
988::
964:.
940:.
916:.
892:.
868:.
843:.
825:.
812:^
787:^
771:.
736:^
720::
718:}}
714:{{
700:.
407:--
402:--
397:--
392:--
387:--
382:--
377:--
372:--
367:--
362:--
252:.
244:.
238:DC
974:.
950:.
926:.
902:.
878:.
853:.
806:.
781:.
756:.
730:)
710:.
206:]
138:3
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.