917:, this determined how the examination would be carried out, including consideration of more detailed hearings on site-specific matters, as well as project-wide issues. While the inspectors gave a commitment to consider the alternatives to the tunnel, in the event they were not reviewed as part of the examination. Government legislation and the NPSWW required that all efforts be made to reduce carbon emissions in new projects, but the examiners did not manage to study this issue. Once the Inspectorate concluded its examination of the application, a recommendation on whether or not to issue a development consent order would be submitted to ministers to make the final decision.
369:
suburbs were equipped with separated foul water and rainwater drainage pipe work. Extending such separate systems would stop sewage flooding of homes and businesses, as well as into the rivers and the estuary, would reduce carbon emissions, and be cheaper in the long term, than the multitude of pumped water tanks otherwise needed to stop homes flooding plus the
Tideway tunnel. Pipes would be laid in a number of streets in each Borough each year over say twenty years, limiting traffic diversions. By 2011 overflows into the river took place more than once a week and as little as 2mm of rainfall can trigger a discharge. The mean total of this was 39,000,000 m (3.9
225:
1132:
and proper domain of its business which reduces tax; this is conventional practice. It explains that the money raised was used for essential maintenance and upgrade works. The earliest year in which customers' bills would be affected was 2014–15, with charges rising gradually after that. The project was estimated to add up to £70 to £80 (excluding inflation) to average annual wastewater bills from around 2019. However, these figures were subsequently revised downwards. In August 2015, the impact was expected to be around £20 to £25 per year by the mid-2020s.
691:
442:
outer London
Boroughs is that separated storm drainage can sustainably prevent all pollution. In a 2006 report commissioned for Ofwat, Jacobs Babtie strongly recommended using the computer model of the existing system to do detailed studies of the effects of laying separate storm water pipes, but their advice and that from Ofwat in 2007 concerning the poor value of the tunnel was not followed. A number of parties questioned the integrity of the TTSS study, in particular the dismissal of separation and future
623:
sites were sent letters explaining that these sites were being considered as alternative sites, and invited to attend drop-in sessions to pose questions and gain a better understanding of the project. In total ten two-day sessions and one community liaison meeting were held. These were attended by over 800 people. In all 168 comment cards and 147 pieces of site specific correspondence were received and considered.
1141:
minimise the impacts of the construction and ensure best practice standards and requirements across all sites and contracts. The Code also covered transport (both road and river), noise and vibration mitigation, air quality and water resources, land quality, waste management and resource use, ecology and conservation and historic environment. In the report that concluded its inspection of these documents, the
451:
making them eligible for discounted water treatment bills. This would reduce pressure on the foul system and take away the need for the tunnel. In
November 2010 the draft National Policy Statement for Waste Water (NPSWW) was issued, and eventually published largely unaltered, despite Parliamentary objections that it promoted the Tideway Tunnel as the only solution.
839:(TBMs) were needed to excavate the main tunnel plus two others for smaller connection tunnels. It also required two types of construction sites: main tunnel sites, where the TBM was either launched or received, and CSO sites, where interception tunnels and a connection culvert were built to connect the existing sewer to the new tunnel.
902:
Thames Water's consultation for the project had been adequate. All the application documents were made available in their own section of the
Planning Inspectorate's National Infrastructure website. Thames Water also made the documents available for scrutiny at six public places along the route, three either side of the river.
946:
Mills, plus some £1bn for the Lee Tunnel and upgrade of works at
Beckton. The total costs of all the Tideway schemes have therefore increased from £1.7bn six years ago to £4.6bn today (all costs at relevant year prices). There is no guarantee that the current estimate will not be subject to further escalation.
1106:
fully operational in 2025. In May 2024, a 1.5m thick reinforced concrete wall separating it from the Lee Tunnel 66m below ground was removed to allow commissioning and testing. This will enable flows captured by the Thames
Tideway Tunnel to be transported to Beckton sewage treatment works for treatment.
1131:
confirmed the extent of leveraging on the balance sheet, reducing tax due and allowing annual payouts of dividends – money which some feel should have cut the cost of the scheme. Thames Water maintains that it has done nothing unusual by making tax-deductible investments in the natural
945:
The estimated cost of the project has escalated, from £1.7bn in 2004 (including
Stratford to East Ham part and sewage treatment civil engineering construction movements (STW) costs) to £2.2bn in 2007 (also including Lee Tunnel and STW costs) to £3.6bn now for the shorter Thames Tunnel as far as Abbey
1226:
The number of CSO discharges is set to fall from an average of 60 a year to less than five. The
Environment Agency is satisfied that the Tideway water quality after such discharges will be acceptable. When both the tunnels are operational, overflows will occur only after sustained periods of intense
1178:
to promote the infiltration of rain-water, preventing it from reaching the combined sewer system, thus reducing peak flows and limiting the number of CSO overflows. Some of these advocates denounce Thames Water's 2011 five theoretical case studies of the solution (finding the threefold cost), citing
1145:
found that Thames Water had "underestimated of impacts on those that have been identified as having a significant effect and underestimated the number of receptors experiencing a significant effect" (12.97) and concluded "We do not consider that proposals meet the first aim of the NPS test to avoid
681:
Following this consultation, and taking into consideration all the feedback received, the proposed route was finalised as the Abbey Mills route and the preferred construction and drive sites were identified. Several sites were also identified as needing further, targeted consultation which resulted
604:
Abbey Mills Route – this route would connect the Thames Tunnel to the head of the
Stratford to East Ham part at Abbey Mills Pumping Station. This would follow the same route but deviate north-east to Abbey Mills. The main tunnel length would be about 9 km (5.6 mi) less than
1105:
Construction of the 25 km (16 mi) long tunnel was completed in March 2024 at a total cost of about £5bn. For test purposes, the first sewage was expected to flow into the tunnel during the summer of 2024 and, once testing was completed, it would be handed over to Thames Water, and become
850:
As the TBM moved forward, precast concrete segments were brought in and fixed together to create the tunnel wall. Excavated material would be transported out the tunnel via a conveyor belt and processed before being taken off-site. In order to minimise disruption, Thames Water committed to use the
626:
Based on this first round of consultation and interim engagement it was recommended that, for the project to be as cost-effective as possible and cause the least disruption, while still meeting the requirements of the UWWTD, the preferred scheme for the Thames
Tideway Tunnel would need to involve:
622:
In response to the comments received, changes and improvements to some of the sites, including the potential use of alternative sites and alternative technical solutions, were considered. Based on this a round of interim engagement took place from March to August 2011. Residents around 11 specific
450:
as a solution. Some groups that opposed the tunnel stated that it is an unsustainable 19th-century solution to a 21st-century problem. They argued that rainwater from roads should be sent directly to canals, rivers or the estuary, and that landowners could install soakaways for their roof run off,
360:
In 2001, London's population density was 18,457 people per square kilometre, compared to just 6,825 per square kilometre in Bazalgette's day. As the population has grown, so has development involving the building on and paving over large areas. This has altered the natural drainage of the sewerage
320:
The estimated capital cost – excluding financing, operations and maintenance – was £3.8bn with an additional £1.1bn for preparatory works. Due to the COVID-19 pandemic, additional costs of £233m were incurred. The 2021-22 annual report gave an updated cost of £4.3bn.
1140:
Some people who live alongside proposed sites were concerned about the noise, disruption and potential loss of public space resulting from construction. To address this Thames Water put together a Code of Construction Practice to outline site-specific and project-wide requirements and measures to
953:
Following detailed analysis it was decided that the best means to deliver the project would be through a regulated infrastructure provider (IP) as this would maximise value for money. The IP, originally to be formed through a competitive process starting in the spring of 2013, would hold its own
441:
After evaluation of alternatives it was decided that only one strategy, the screening, storage or treatment at the point of discharge, would meet the estuary objectives fully. The remainder were found to be either impractical or insufficient to provide a solution, although the evidence from the
368:
hosted just over 8.1 million residents and Thames Water in a leaflet of that year explained how its works and how sewers needed expansion. The older inner boroughs have combined sewerage systems which cannot cope with the extra hard standings. As London continued to grow the new developments and
901:
on 28 February 2013. It included a relatively recent quite inaccurate study of Separation. The Inspectorate then had 28 days to decide whether the application was valid and whether the consultation undertaken was adequate. On 27 March 2013, it was decided that the application was valid and that
614:
A long list of 373 potential sites was created using a desktop survey of the land on either side of the 34 most polluting CSOs (as identified in the Thames Tideway Strategic Report). These sites were then further evaluated against more detailed planning, engineering, environmental, property and
905:
On 3 June 2013, it was announced that the Secretary of State for Communities and Local Government had appointed inspectors Jan Bessell, Libby Gawith, Emrys Parry, Andrew Phillipson and David Prentis as the examining authority to consider any matters arising. As part of this process, interested
846:
At the main drive sites, four main activities took place: shaft construction (where a concrete cylinder 25–30 m (82–98 ft) in diameter and about 40–60 m (130–200 ft) deep was constructed), tunnelling preparations (preparing the site for arrival of the TBM), TBM assembly and
842:
Construction of the shafts at the CSO sites, to transfer flows from the existing sewer to the tunnel, would vary depending on the depth, the amount of flow they need to carry and the geology. The shaft would be a concrete cylinder with an internal diameter of 6–24 m (20–79 ft) and
1047:
In August 2015, the independent investors to finance and deliver the scheme were confirmed. Bazalgette Tunnel Limited, a new special-purpose company appointed to take the project forward, received its licence from Ofwat as a new regulated utilities business, separate from Thames Water. The
987:
However, procurement for main contractors (who would eventually be contracted to the IP) for up to three packages of work valued at around £500m each started in the summer of 2013. On 29 July, Thames Water announced that a contract notice for work on the tunnel had been published in the
982:
If Thames is unwilling to make a rights issue, the owners, Macquarie, should be expected to return funds to the utility. If they do not, Thames should go into special administration (allowing for continued service to customers) and another company or financier allowed to take over its
1179:
householders' assistance such as emptying water butts, gardening more, and not using land for parking, and say this could be the cheapest option. Green infrastructure would have further benefits for London in addition to addressing the rainwater overflow problem, such as:
582:
consulted with relevant authorities to get feedback from stakeholders who would potentially be affected by the construction of the Thames Tideway Tunnel. Thames Water sought feedback on the proposed tunnel routes and potential locations of construction sites.
961:
In January 2013, it was announced the IP was to be delayed because Thames Water as main funder sought state financial assurances. This was a polemic. Opponents argued the government should not bear any such risks; Thames Water have noted the government faced
618:
The three tunnel routes, as well as the shortlist of sites, were then put out for consultation between September 2010 and January 2011. In total 2,389 feedback forms (both online and hard copy), 480 pieces of correspondence and five petitions were received.
843:
20–60 m (66–197 ft) deep. Ventilation structures at CSO sites to allow air in and out of the shaft were also required. Construction at these sites was expected to take between 2½ and 3½ years and once complete each site would be landscaped.
361:
catchment so that now most rainfall and surface water run-off goes directly into London's sewers, rather than being naturally absorbed into permeable ground. An area twice the size of Hyde Park has been lost to hard surfacing every year up to 2001.
600:
Route – a similar alignment, but this would have cut additionally across the Rotherhithe Peninsula, reducing the length of the main tunnel by approximately 1.8 km (1.1 mi) but requiring longer connection tunnels from some
2734:
1102:, a project lockdown and revised working practices meant the project was delayed by nine months and had incurred additional costs of £233m (taking the estimated project cost to £4.133bn). Completion was targeted for the first half of 2025.
3438:
352:
was designed to capture both rainwater runoff and the sewage produced by four million people. As a failsafe, to prevent sewage backing up and flooding people's homes, Bazalgette's system had the ability to overflow into the Thames via 57
471:: a deep, broad storage and conveyance tunnel dug and lined from Jenkins Lane, Beckton to Abbey Mills, Stratford, sloping down the reverse way. This 6.9 km (4.3 mi) tunnel, running down to 75 m (246 ft) deep from
2822:"Thames Tideway Tunnel – Examining authority's Report of Findings and Conclusions and Recommendation to the Secretary of State for Communities and Local Government and the Secretary of State for Environment, Food and Rural Affairs"
4216:
305:
This tunnel will drain 34 of the most polluting combined sewer overflows (CSOs) and has been forecast to lead to the overflows operating for 3.7% of the time on a maximum of four days per year at the time of commissioning.
1162:, particularly uncovering streams and rivers in some places in inner London Boroughs where they were culverted in the past. Their most progressive arguments are for replacing paved, impermeable surfaces in London with
2895:
3080:
1114:
Since the initial proposal, questions focussed on the cost, the location of construction sites, duration, disruption, and whether a tunnel was the correct solution for London and for Thames Water customers.
3463:
2745:
2792:
565:
The final part is the Thames Tideway Tunnel. When built, it intercepts the outflows from London's most polluting CSOs, stores them and directs (conveys) them to sewage treatment works for processing.
3925:
3442:
1227:
rainfall and after the tunnels have captured the most damaging 'first flush' from the foul sewers. The remaining total overflow will average 2.6 million cubic metres per year, on 2011 estimates.
3003:
2685:
1504:
1391:
483:
10 L), or 16 million tonnes annually from the greatest-polluting CSO point in London. Thames Water awarded the £635 million construction contract to the MVB joint venture of
894:
In October 2012, the deadline of the tunnels' Section 48 consultation closed. This lasted 12 weeks and was the last opportunity for the public to have their say on the updated proposal.
854:
In 2017, the public voted on a short-list of 17 to name the six TBMs. They were named after female pioneers of their fields linked to where each began to dig. One began tunnelling from
2899:
925:
On 12 September 2014, the UK Government approved the plans, overriding some of the findings of the Planning Inspectorate. The decision gave rise to at least three Judicial Reviews.
3111:
3028:
658:
The second phase of consultation was carried out between November 2011 and February 2012 when local authorities, land owners, local businesses and communities were consulted on:
373:
10 L), that is 39 million tonnes, of storm sewage entering the river. These discharges, a mixture of raw sewage and rainwater, needed to be cut to comply with the EU's
3167:
2920:
397:, was intended to assess the impact of the CSO discharges into the Thames and to identify objectives and propose potential solutions, while keeping costs and benefits in mind.
1593:
3918:
390:
2452:
1685:
668:
Preferred sites and permanent works (taking into account the feedback received from the first phase of consultation such as the move from greenfield to brownfield sites)
268:. The tunnelling phase of the project was completed in April 2022; construction ended in March 2024 ahead of a testing and handover phase expected to conclude in 2025.
1365:
377:(UWWTD). If cut to such levels, it would thus restore the ecology of the river to that of 1865–70 or better, that is, before such unmitigated growth took place.
3084:
851:
river as much as possible to transport materials both in and out of the construction sites. At the main tunnelling sites, work was expected to occur 24 hours a day.
3413:
2270:
1438:
2296:
2166:
2504:
2114:
3911:
2426:
2218:
2036:
2010:
1158:
system (SUDS) under Central London streets and open spaces with small pumping stations in places of low gradient. They outline the added benefits of building
862:, after the engineer and advocate for women's employment rights, who set up the first women-only engineering company in Fulham. The others were cryobiologist
2796:
2400:
3055:
2952:
2322:
2244:
2140:
2659:
2478:
2735:"Application by Thames Water Utilities Limited for the Thames Tideway Tunnel Notice of preliminary meeting and availability of relevant representations"
2088:
1958:
933:
The budget for the scheme steadily increased since it was first estimated. For example, the budget in 2004 was estimated at £1.7bn, which included the
878:
who set up Bermondsey Medical Mission for Southwark's poor and disadvantaged residents. The machine for the Greenwich Connection Tunnel was named after
2192:
2348:
2062:
271:
Bazalgette Tunnel Limited (BTL) is the licensed infrastructure provider for its finance, building, maintenance and operation. It has as investors:
3362:
2689:
1477:
1395:
1099:
291:
2960:
897:
The Application for Development Consent – for the final, detailed plan for the construction – was delivered to the
1984:
992:(OJEU). Following prequalification questionnaires, Thames Water invited shortlisted contractors to tender between November 2013 and April 2014.
590:
River Thames Route – such an alignment, broadly, would follow the river from west London to Beckton STW and would cut across the
3543:
989:
2374:
3265:
374:
4186:
3670:
298:
in the west of London for over 25 km (16 mi) across the full width of Inner London finally reaching −70 m (−230 ft) at
2847:
2821:
294:
delayed this to early 2025. The main tunnel has an internal diameter of 7.2 m (24 ft) and runs from −30 m (−98 ft) at
1307:
4201:
3239:
3119:
3032:
4028:
3636:
3591:
2584:
1547:
4226:
4196:
3701:
1155:
443:
874:
for the Frogmore Connection Tunnel from Wandsworth to Fulham. The TBM for the east section from Bermondsey was named after doctor
3716:
3335:
525:
459:
The three-part solution to implement screening, storage and treatment was collectively known as the London Tideway Improvements.
3721:
2456:
1675:
3142:
4134:
3696:
1847:
1799:
1773:
1747:
1247:
531:
333:
314:
1369:
2712:"A Panel of 5 examining inspectors has been appointed to examine the application for the Thames Tideway Tunnel application"
3736:
3731:
1163:
519:
405:
After four years, the Thames Tideway Strategic Study report was published in 2005, and outlined the following objectives:
2711:
2274:
1434:
678:
A total of 1,374 feedback forms (online and hard copy), 4,636 pieces of correspondence and nine petitions were received.
4033:
3842:
3741:
2300:
2170:
883:
643:
selection of five out of 52 possible access shafts to be built including three to be combined with CSO interception; and
299:
178:
2508:
2326:
2248:
2118:
1280:
224:
4211:
3706:
3691:
3596:
3387:
2634:
2535:
1930:
1881:
1641:
1629:
823:
472:
2430:
2222:
1892:
1067:(RAB) model. If the cost overruns by more than 30%, the government would have to provide additional equity finance.
4221:
3822:
3536:
3290:
2040:
2014:
1154:
Some people prefer an option that Thames Water's studies show would be up to three times more expensive. This is a
938:
2404:
1707:
4048:
3887:
3726:
3711:
3631:
1460:
814:
3484:
2975:
2144:
1053:
4206:
3812:
3601:
690:
671:
Detailed proposals for the preferred sites (again taking into account feedback from the phase one consultation)
394:
329:
3471:
2848:"Planning Act 2008: Application for the proposed Thames Water Utilities Limited (Thames Tideway Tunnel) Order"
2663:
2482:
1127:
customers. This has angered customers who dispute an accounting practice confirmed by the industry regulator.
3903:
2092:
1962:
650:
The new preferred route and sites were then sent out for a second round of public consultation and feedback.
4013:
3958:
3953:
3807:
3802:
1680:
354:
260:
that currently overflows into the estuary. These events occur when rainfall volumes exceed the capacity of
2196:
3882:
3852:
3792:
3777:
3675:
3611:
2352:
1064:
748:
512:
385:
Instigated in 2001, the Thames Tideway Strategic Study, conducted by a group comprising Thames Water, the
349:
276:
265:
3317:
2635:"Notice publicising a proposed application for a development consent order for the Thames Tideway Tunnel"
2378:
2066:
1916:
1614:
4191:
4165:
3872:
3857:
3832:
3797:
3767:
3661:
3657:
3529:
1142:
914:
898:
836:
2932:
909:
A preliminary meeting, open to those who had registered an interest, began on 12 September 2013 at the
736:
721:
283:
and DIF. Since the licence award, it also trades as Tideway. On 3 November 2015, the award was made by
1041:
492:
4160:
4099:
4043:
4037:
3983:
3877:
3847:
3772:
1988:
1159:
1057:
760:
447:
280:
995:
The successful contractors for the three main tunnelling contracts were announced in February 2015:
674:
The effects the project would have (as outlined in the preliminary environmental information report)
4003:
3892:
3867:
3787:
3762:
3586:
879:
859:
778:
730:
591:
3194:
4124:
4058:
3862:
3837:
3827:
3652:
3621:
950:
Less than a year later, in November 2011, a further £500 million was added to the estimate.
784:
754:
540:– an £85 million upgrade to improve water quality and produce renewable energy on site
386:
1048:
special-purpose company is backed by pension funds and other long-term investors represented by
875:
634:
a main tunnel 23 km (14 mi) long with an internal diameter of 7.2 m (24 ft);
2851:
2825:
4119:
3948:
3782:
3757:
3616:
3571:
1205:
1024:
871:
867:
772:
727:
Carnwath Road riverside – main tunnel drive and reception and connection tunnel reception site
511:
The second part was the £675 million project to modernise and extend London's five major
364:
In the 2011 census returns (that is, omitting residents who did not disclose their residence)
345:
261:
4114:
4078:
4063:
4023:
3968:
3817:
3576:
1196:
1171:
543:
2793:"More on the Government's summary dismissal of the Planning Inspectorate's recommendations"
2609:
228:
Proposed route. Black arrows show direction of boring machine movement, not flow of sewage
4104:
4073:
1579:
1554:
1339:
910:
766:
537:
496:
3978:
2873:
2770:
553:
These intend to improve the standard to which the sewage is treated, thus improving the
515:
to treat more sewage, thus greatly reducing the need for storm discharges to the river:
4129:
3993:
3987:
3606:
3566:
1192:
1011:
1007:
963:
484:
365:
237:
211:
197:
135:
4180:
4053:
3973:
1187:
1033:
703:
646:
selection of seventeen out of 71 CSO alternate positionings from the final shortlist.
500:
295:
167:
4155:
4139:
4068:
3552:
1217:
Earlier avoidance of EU fines for not meeting water standards than under the scheme
1212:
1124:
975:
863:
579:
249:
245:
3464:"The role of the civil engineer in society: engineering ethics and major projects"
3220:
1851:
1825:
1803:
1777:
1751:
1725:
1652:
1409:
1251:
640:
indirect interception of a further 12, and a local solution for the remaining CSO;
3081:"Thousands of jobs to be created as contractors named for London's 'super sewer'"
4109:
3581:
1146:
significant adverse impacts on health and quality of life from noise" (12.357).
1003:
790:
742:
709:
597:
847:
lowering into the shaft, and then driving the TBM to excavate the main tunnel.
662:
The need for the project and whether a tunnel was the most appropriate solution
317:. Following treatment the water will then be released into the Thames Estuary.
4083:
3963:
3665:
1175:
1167:
934:
594:, reducing the length of the tunnel where there are no CSOs to be intercepted.
468:
325:
310:
70:
17:
4008:
3998:
3626:
3291:"BBC – Democracy Live – Peers calls on Thames Water not to pay shareholders"
1020:
971:
808:
715:
665:
The preferred tunnel route (including the detailed alignment of the tunnel)
4018:
2375:"Earl Pumping Station – phase one site information paper – Thames Tunnel"
1208:
effects with an associated reduction in cooling load and carbon emissions
1037:
802:
547:
495:, in January 2010. Construction began in 2010 and on 28 January 2016 the
488:
1123:
The £4.3bn cost of the Thames Tideway Tunnel project is to be funded by
1082:
2016: Primary work completed; Main works preliminary construction begins
321:
The final cost was £5bn. It is set to become fully operational in 2025.
1049:
554:
534:– a £190 million upgrade to extend treatment capacity by 60%
528:– a £220 million upgrade to extend treatment capacity by 44%
522:– a £140 million upgrade to extend treatment capacity by 50%
476:
272:
241:
3173:. Department for Business, Energy & Industrial Strategy. July 2019
855:
695:
253:
1201:
Enjoyment, aesthetics and health benefits of green spaces and nature
434:
Screening, storage or treatment at the discharge point to river; and
3318:"Water companies pay billions to shareholders but little tax. Why?"
1594:"Census gives insights into characteristics of London's population"
811:
pumping station – CSO interception and connection tunnel drive site
769:
pumping station – CSO interception and connection tunnel drive site
712:
pumping station – CSO interception and connection tunnel drive site
3485:"Roger S. Ulrich, Ph.D., EDAC | The Center for Health Design"
2896:"Walney wind farm gets consent as A160 beats records – Other News"
2325:. Thamestunnelconsultation.co.uk. 21 November 2011. Archived from
2221:. Thamestunnelconsultation.co.uk. 21 November 2011. Archived from
2195:. Thamestunnelconsultation.co.uk. 21 November 2011. Archived from
2143:. Thamestunnelconsultation.co.uk. 21 November 2011. Archived from
2013:. Thamestunnelconsultation.co.uk. 11 November 2011. Archived from
1987:. Thamestunnelconsultation.co.uk. 21 November 2011. Archived from
1128:
955:
689:
290:
Started in 2016, the project was due to be completed by 2024. The
284:
223:
2273:. Thamestunnelconsultation.co.uk. 7 December 2011. Archived from
1953:
1951:
682:
in further refinement and improvement of designs at those sites.
2686:"Green light for examination of Thames Tideway Tunnel proposals"
257:
4217:
Nationally Significant Infrastructure Projects (United Kingdom)
3907:
3525:
3521:
3472:
Proceedings of the ICE – Civil Engineering, Volume 165, Issue 3
3195:"London super sewer causes stink over opaque funding structure"
1392:"Green Light for examination of Thames Tideway Tunnel Proposal"
412:
To reduce aesthetic pollution due to sewage-derived litter; and
937:
and sewage treatment works upgrade costs. In the words of the
3363:"Supersewer tunneling set to force hundreds from their homes"
2561:
781:
foreshore – CSO interception and connection tunnel drive site
775:
foreshore – CSO interception and connection tunnel drive site
757:
foreshore – CSO interception and connection tunnel drive site
724:
foreshore – CSO interception and connection tunnel drive site
3514:
615:
community considerations resulting in a shortlist of sites.
3266:"Final work starts to connect super sewer to London system"
1848:"Long Reach Sewage Treatment Works – Sewage Works Upgrades"
1478:"In London, the Long Wait for a Super Sewer Is Almost Over"
3934:
Approved and current major construction projects in London
3414:"Axe supersewer and adopt my greener plan, says US expert"
2874:"Southwark Council launches 'super sewer' legal challenge"
1826:"Riverside Sewage Treatment Works – Sewage Works Upgrades"
1774:"Crossness Sewage Treatment Works – Sewage Works Upgrades"
431:
Separation of foul and surface drainage and local storage;
428:
Adoption of source control and sustainable urban drainage;
309:
The tunnel will transfer the combined sewers water to the
3439:"Tideway Tunnel chief responds to 'supersewer' criticism"
1308:"Tideway | Tunnelling complete on London's 'super sewer'"
252:
intended to capture, store and convey almost all the raw
1800:"Beckton Sewage Treatment Works – Sewage Works Upgrades"
1505:""Sweet Thames, run softly": Constructing a Clean River"
706:
Storm Tanks – main tunnel reception and CSO interception
1877:
1875:
1873:
1871:
1869:
1748:"Mogden Sewage Treatment Works – Sewage Works Upgrades"
1368:. Thames Tideway Forum. 3 November 2015. Archived from
3412:
Lindsay Watling and Matthew Beard (17 December 2012).
2662:. Infrastructure.planningportal.gov.uk. Archived from
745:
pumping station – CSO and connection tunnel drive site
3441:. Waterbriefing.org. 17 December 2012. Archived from
3361:
Matthew Beard and Lindsay Watling (16 October 2012).
3240:"London 25km Super Sewer hooked up for commissioning"
3029:"Contract Notice published for Thames Tideway Tunnel"
2585:"Video | First of six TBMs delivered to Tideway site"
2453:"King Edward Memorial Park Foreshore – Thames Tunnel"
1931:"Thames Tunnel – main report on Phase 2 consultation"
1726:"Sewage Works Upgrades – London Tideway Improvements"
796:
Chambers Wharf – main tunnel drive and reception site
2816:
2814:
1195:
mitigation – contrasted to the tunnel's significant
73:, Abbey Mills, between Hackney and Stratford, London
4148:
4092:
3939:
3750:
3684:
3645:
3559:
1094:
2024: All works completed (now scheduled for 2025).
966:fines if the work was not done. In a letter to the
958:, and would build, manage and maintain the tunnel.
751:– CSO interception and connection tunnel drive site
733:
CSO – interception and connection tunnel drive site
718:– CSO interception and connection tunnel drive site
605:
the River Thames Route and save about £900 million.
207:
196:
184:
173:
162:
154:
146:
141:
131:
123:
106:
98:
90:
82:
77:
66:
58:
50:
42:
37:
3193:
2974:
2953:"Invalid UDL link. - TED Tenders Electronic Daily"
1676:"Boris Johnson opens new 'super sewer' Lee Tunnel"
1630:Thames Tideway Strategic Study – Executive Summary
974:(former Director General of Ofwat) and politician
3336:"Londoners to pay £25 a year for Thames clean-up"
3004:"Thames Water delays £4.1bn 'super sewer' tender"
1925:
1923:
2660:"The process – National Infrastructure Planning"
2507:. Thamestunnelconsultation.co.uk. Archived from
2481:. Thamestunnelconsultation.co.uk. Archived from
2455:. Thamestunnelconsultation.co.uk. Archived from
2429:. Thamestunnelconsultation.co.uk. Archived from
2403:. Thamestunnelconsultation.co.uk. Archived from
2377:. Thamestunnelconsultation.co.uk. Archived from
2351:. Thamestunnelconsultation.co.uk. Archived from
2299:. Thamestunnelconsultation.co.uk. Archived from
2247:. Thamestunnelconsultation.co.uk. Archived from
2169:. Thamestunnelconsultation.co.uk. Archived from
2117:. Thamestunnelconsultation.co.uk. Archived from
2091:. Thamestunnelconsultation.co.uk. Archived from
2065:. Thamestunnelconsultation.co.uk. Archived from
2039:. Thamestunnelconsultation.co.uk. Archived from
1961:. Thamestunnelconsultation.co.uk. Archived from
1079:2015: Main works and financing contracts awarded
3466:. Prof Richard Ashley. 1 August 2012. section "
2562:"Thames Tunnel Construction Animation on Vimeo"
2530:
2528:
2526:
2271:"Victoria Embankment Foreshore – Thames Tunnel"
1802:. Thames Water. 22 January 2013. Archived from
1708:"Boris Flushed With Pride At New 'Super Sewer'"
1334:
1332:
1330:
1328:
1275:
1273:
1271:
1269:
569:Thames Tideway Tunnel planning and consultation
27:Sewage system being created for London, England
3143:"All systems go for £4.2bn London super sewer"
2976:"Thames Water is obliged to fund big projects"
2297:"Blackfriars Bridge Foreshore – Thames Tunnel"
2167:"Chelsea Embankment Foreshore – Thames Tunnel"
1850:. Thames Water. 27 August 2012. Archived from
1776:. Thames Water. 27 August 2012. Archived from
1674:Amy Ashenden; Luke Garrett (28 January 2016).
578:Following the Thames Tideway Strategic Study,
415:Protect the health of recreational water users
3919:
3537:
3112:"Green light for £4.2bn London 'super sewer'"
2795:. Clean Thames Now and Always. Archived from
2505:"Abbey Mills Pumping Station – Thames Tunnel"
2323:"Shad Thames Pumping Station – Thames Tunnel"
2245:"Albert Embankment Foreshore – Thames Tunnel"
2115:"Falconbrook Pumping Station – Thames Tunnel"
1435:"Who will pay for the Thames Tideway Tunnel?"
1394:. Thames Water. 27 March 2013. Archived from
1366:"Green light for £4.2bn London 'super sewer'"
1340:"Thames Tideway Tunnel super sewer completed"
820:Bekesbourne Street – system modification site
479:is forecast to capture 16,000,000 m (1.6
8:
3388:"Section 48 – code of construction practice"
1750:. Thames Water. 5 March 2013. Archived from
1063:The funding scheme used was later named the
882:, the first female scientist to work at the
799:Earl pumping station – CSO interception site
32:
2923:. Consumer Council for Water. January 2011.
2921:"Thames Water's Thames Tunnel Consultation"
2824:. The Planning Inspectorate. Archived from
2427:"Greenwich Pumping Station – Thames Tunnel"
2219:"Heathwall Pumping Station – Thames Tunnel"
906:parties were able to make representations.
3926:
3912:
3904:
3544:
3530:
3522:
2939:. 3 November 2011. Retrieved 30 July 2013
2771:"London's 'super sewer' gets the go ahead"
1653:"Lee Tunnel – London Tideway Improvements"
1242:
1240:
1183:Increased resilience to drought and floods
793:pumping station – system modification site
739:– CSO and connection tunnel reception site
424:Four potential strategies were discussed:
31:
2037:"Carnwath Road Riverside – Thames Tunnel"
2011:"Putney Bridge Foreshore – Thames Tunnel"
1553:. Thames Water. July 2011. Archived from
1548:"Why does London need the Thames Tunnel?"
835:To build the Thames Tideway Tunnel, four
3056:"Thames Tideway names preferred bidders"
2401:"Deptford Church Street – Thames Tunnel"
3118:. Thames Tideway Tunnel. Archived from
3106:
3104:
3102:
3083:. Thames Tideway Tunnel. Archived from
2744:. Planning Inspectorate. Archived from
1620:(Summer 2010) accessed: 16 January 2014
1542:
1236:
574:Initial design and phase 1 consultation
2560:Thames Tunnel Plus (4 November 2011).
2141:"Cremorne Wharf Depot – Thames Tunnel"
1540:
1538:
1536:
1534:
1532:
1530:
1528:
1526:
1524:
1522:
1119:Cost and reward to the business owners
990:Official Journal of the European Union
586:Three tunnel routes were considered:
546:– a £40 million upgrade in
409:To protect the ecology of the Tideway;
3054:Wynne, Alexandra (27 February 2015).
1281:"Tideway sewer hits nine-month delay"
1076:2014: Planning decisions and approval
954:license from the industry regulator,
805:Church Street – CSO interception site
287:, ensuring the start of the project.
7:
3671:Thames Gateway Water Treatment Works
2898:. Bircham Dyson Bell. Archived from
2479:"Bekesbourne Street – Thames Tunnel"
2089:"King George's Park – Thames Tunnel"
1688:from the original on 28 January 2016
870:for the Central area and suffragist
507:Sewage treatment works modernisation
357:(CSO) along the banks of the river.
3316:Boffey, Daniel (10 November 2012).
2536:"Project Information Paper – Build"
1959:"Acton Storm Tanks – Thames Tunnel"
1509:The London Literary Society Journal
1466:. Bazalgette Tunnel Ltd. p. 6.
4029:Northumberland Development Project
3637:1854 Broad Street cholera outbreak
2850:. Defra & DGLG. Archived from
1893:"Site Selection Methodology paper"
694:Thames Tideway construction site,
25:
3702:Coppermills Water Treatment Works
2933:"Super-sewer's price rises £500m"
2193:"Kirtling Street – Thames Tunnel"
1441:from the original on 1 April 2019
1038:Vinci Construction Grands Projets
787:foreshore – CSO interception site
654:Phase 2 and targeted consultation
544:Long Reach Sewage Treatment Works
489:VINCI Construction Grands Projets
3717:Crossness Sewage Treatment Works
2349:"Chambers Wharf – Thames Tunnel"
1632:(2005). Accessed 17 January 2014
1250:. Tideway London. Archived from
831:Proposed design and construction
538:Riverside Sewage Treatment Works
526:Crossness Sewage Treatment Works
463:Stratford to Beckton: Lee Tunnel
455:Screening, storage and treatment
311:Stratford to East Ham Lee Tunnel
3722:Deephams Sewage Treatment Works
3192:Plimmer, Gill (8 August 2017).
3141:Morby, Aaron (24 August 2015).
2063:"Dormay Street – Thames Tunnel"
1655:. Thames Water. 17 January 2013
1461:"Tideway Annual Report 2021-22"
763:– main tunnel double drive site
637:direct interception of 21 CSOs;
375:Waste Water Treatment Directive
3697:Beckton Sewage Treatment Works
3031:. Thames Water. Archived from
3002:Pitt, Vern (31 January 2013).
2688:. Thames Water. Archived from
1828:. Thames Water. 27 August 2012
1596:. Ons.gov.uk. 11 December 2012
532:Beckton Sewage Treatment Works
334:Beckton Sewage Treatment Works
315:Beckton Sewage Treatment Works
214:5 billion (2024 estimate)
1:
3737:Mogden Sewage Treatment Works
3732:Hampton Water Treatment Works
2773:. BBC News. 12 September 2014
2610:"Nine Elms on the South Bank"
2541:. Thames Water. November 2011
1728:. Thames Water. 23 March 2011
1503:Skilton, David (March 2007).
1306:Horgan, Rob (29 April 2022).
1088:2019: Secondary lining begins
520:Mogden Sewage Treatment Works
503:, confirmed the tunnel open.
344:Built between 1859 and 1875,
236:is a 25 km (16 mi)
177:−70 m (−230 ft) at
3843:Queen Elizabeth II Reservoir
3742:Walton water treatment works
3468:Examples of ethical dilemmas
3238:Morby, Aaron (14 May 2024).
1222:Continued overflows forecast
826:– main tunnel reception site
467:This earliest phase was the
166:−30 m (−98 ft) at
4187:London water infrastructure
3964:Canary Wharf's New District
3707:Cricklewood Pumping Station
3692:Abbey Mills Pumping Station
3597:Metropolitan Board of Works
3393:. Thames Water. Summer 2012
3264:Morby, Aaron (3 May 2024).
2614:Nine Elms on the South Bank
1985:"Barn Elms – Thames Tunnel"
1898:. Thames Water. Summer 2011
1098:In August 2020, during the
1025:Laing O'Rourke Construction
824:Abbey Mills pumping station
242:the tidal section (estuary)
4243:
4202:2024 in the United Kingdom
3823:Lee Valley Reservoir Chain
1156:sustainable urban drainage
1054:Amber Infrastructure Group
939:Consumer Council for Water
935:East Ham to Stratford part
3888:William Girling Reservoir
3727:Greenwich pumping station
3712:Crossness Pumping Station
3474:. Retrieved 30 July 2013.
2640:. Thames Water. July 2012
1166:options and implementing
815:King Edward Memorial Park
610:Route and sites selection
448:blue-green infrastructure
264:'s and other engineers'
218:
192:
4227:Infrastructure in London
4197:Tunnelling organizations
4079:Westfield London Phase 2
3813:King George VI Reservoir
3602:Metropolitan Water Board
1936:. Thames Water. May 2012
880:Annie Scott Dill Russell
395:Greater London Authority
355:combined sewer overflows
330:London Borough of Newham
3959:Brent Cross Cricklewood
3954:Battersea Power Station
3808:King George V Reservoir
3803:Kempton Park Reservoirs
3418:London Evening Standard
3367:London Evening Standard
3168:"RAB Model for Nuclear"
2941:(subscription required)
2714:. Planning Inspectorate
1681:London Evening Standard
1085:2018: Tunnelling begins
817:– CSO interception site
313:for onward delivery to
188:7.2 m (24 ft)
158:25 km (16 mi)
3883:West Warwick Reservoir
3878:Walthamstow Reservoirs
3853:Queen Mother Reservoir
3793:High Maynard Reservoir
3778:East Warwick Reservoir
3676:Thames Water Ring Main
3612:William Chadwell Mylne
3340:The Construction Index
1285:The Construction Index
985:
970:in November 2012, Sir
948:
837:tunnel boring machines
699:
513:sewage treatment works
350:London sewerage system
328:, runs deep under the
266:London sewerage system
229:
4166:Thames Tideway Tunnel
3984:Elephant & Castle
3873:Tilehurst Water Tower
3858:Stain Hill Reservoirs
3833:Low Maynard Reservoir
3798:Island Barn Reservoir
3768:Bessborough Reservoir
3662:Thames Tideway Tunnel
3658:Thames Tideway Scheme
3270:Construction Enquirer
3244:Construction Enquirer
3147:Construction Enquirer
3116:Thames Tideway Tunnel
1150:The need for a tunnel
1143:Planning Inspectorate
1091:2022: Tunnelling ends
980:
943:
915:Planning Inspectorate
899:Planning Inspectorate
884:Greenwich Observatory
864:Audrey 'Ursula' Smith
693:
631:the Abbey Mills route
346:Sir Joseph Bazalgette
240:running mostly under
234:Thames Tideway Tunnel
227:
150:Various (see article)
127:Bazalgette Tunnel Ltd
113:Bazalgette Tunnel Ltd
94:Various (see article)
33:Thames Tideway Tunnel
4161:London Power Tunnels
4100:40 Leadenhall Street
4044:Paddington Waterside
4014:King's Cross Central
3848:Queen Mary Reservoir
3773:Chingford Reservoirs
2963:on 17 February 2013.
2742:Letter dated 25 July
2121:on 22 September 2012
1854:on 18 September 2012
1806:on 18 September 2012
1780:on 18 September 2012
1160:green infrastructure
1065:Regulated Asset Base
1021:Ferrovial Agroman UK
1012:Balfour Beatty Group
929:Funding and delivery
890:Planning application
749:Cremorne Wharf Depot
420:Potential strategies
277:Amber Infrastructure
116:(trading as Tideway)
4004:Greenwich Peninsula
3893:Wraysbury Reservoir
3868:Sunnyside Reservoir
3788:Grimsbury Reservoir
3763:Bath Road Reservoir
3592:London water supply
3587:London sewer system
3445:on 18 February 2016
3181:– via gov.uk.
2751:on 18 February 2016
2303:on 13 December 2012
2147:on 10 February 2012
2043:on 3 September 2012
1991:on 13 December 2012
1754:on 10 February 2013
1484:. 24 September 2023
1372:on 17 November 2015
1254:on 12 February 2019
1186:Reduction in urban
1032:: Joint venture of
1019:: Joint venture of
1002:: Joint venture of
921:Planning acceptance
779:Victoria Embankment
592:Greenwich Peninsula
34:
4212:2020s architecture
4059:Southall Gas Works
3863:Staines Reservoirs
3838:Molesey Reservoirs
3828:Lockwood Reservoir
3653:Abingdon Reservoir
3221:"Tideway timeline"
3060:New Civil Engineer
2983:. 11 November 2012
2902:on 4 December 2014
2589:New Civil Engineer
2583:Smale, Katherine.
2511:on 2 February 2012
2485:on 2 February 2012
2459:on 2 February 2012
2355:on 2 February 2012
2277:on 2 February 2012
2199:on 2 February 2012
2173:on 6 December 2011
2095:on 2 February 2012
2017:on 5 February 2012
1965:on 5 February 2012
1560:on 16 January 2014
1312:New Civil Engineer
785:Blackfriars Bridge
755:Chelsea Embankment
737:King George's Park
700:
686:Site list and type
561:Acton to Stratford
557:'s water quality.
437:In-river treatment
387:Environment Agency
381:Options assessment
230:
4222:Tunnels in London
4174:
4173:
4120:Landmark Pinnacle
4074:Westfield Croydon
4049:Royal Albert Dock
4009:Kidbrooke Village
3949:Barking Riverside
3901:
3900:
3783:Farmoor Reservoir
3758:Banbury Reservoir
3617:New River Company
3572:Joseph Bazalgette
3297:. 15 January 2013
3122:on 26 August 2015
3087:on 27 August 2015
3035:on 21 August 2013
2854:on 8 October 2014
2828:on 8 October 2014
2799:on 9 October 2014
2407:on 24 August 2013
1206:urban heat island
1100:COVID-19 pandemic
913:. Chaired by the
872:Charlotte Despard
868:Millicent Fawcett
773:Albert Embankment
722:Putney Embankment
324:Its outfall, the
292:COVID-19 pandemic
222:
221:
163:Highest elevation
16:(Redirected from
4234:
4115:Heron Quays West
4064:South Quay Plaza
4024:London Riverside
4019:Lewisham Gateway
3969:Chelsea Barracks
3928:
3921:
3914:
3905:
3818:Knight Reservoir
3577:Edmund Colthurst
3546:
3539:
3532:
3523:
3518:
3517:
3515:Official website
3500:
3499:
3497:
3495:
3489:Healthdesign.org
3481:
3475:
3461:
3455:
3454:
3452:
3450:
3435:
3429:
3428:
3426:
3424:
3409:
3403:
3402:
3400:
3398:
3392:
3384:
3378:
3377:
3375:
3373:
3358:
3352:
3351:
3349:
3347:
3342:. 24 August 2015
3332:
3326:
3325:
3313:
3307:
3306:
3304:
3302:
3287:
3281:
3280:
3278:
3276:
3261:
3255:
3254:
3252:
3250:
3235:
3229:
3228:
3217:
3211:
3210:
3208:
3206:
3197:
3189:
3183:
3182:
3180:
3178:
3172:
3164:
3158:
3157:
3155:
3153:
3138:
3132:
3131:
3129:
3127:
3108:
3097:
3096:
3094:
3092:
3077:
3071:
3070:
3068:
3066:
3051:
3045:
3044:
3042:
3040:
3025:
3019:
3018:
3016:
3014:
2999:
2993:
2992:
2990:
2988:
2978:
2971:
2965:
2964:
2959:. Archived from
2949:
2943:
2942:
2930:
2924:
2918:
2912:
2911:
2909:
2907:
2892:
2886:
2885:
2883:
2881:
2870:
2864:
2863:
2861:
2859:
2844:
2838:
2837:
2835:
2833:
2818:
2809:
2808:
2806:
2804:
2789:
2783:
2782:
2780:
2778:
2767:
2761:
2760:
2758:
2756:
2750:
2739:
2730:
2724:
2723:
2721:
2719:
2708:
2702:
2701:
2699:
2697:
2682:
2676:
2675:
2673:
2671:
2666:on 22 March 2013
2656:
2650:
2649:
2647:
2645:
2639:
2631:
2625:
2624:
2622:
2620:
2606:
2600:
2599:
2597:
2595:
2580:
2574:
2573:
2571:
2569:
2557:
2551:
2550:
2548:
2546:
2540:
2532:
2521:
2520:
2518:
2516:
2501:
2495:
2494:
2492:
2490:
2475:
2469:
2468:
2466:
2464:
2449:
2443:
2442:
2440:
2438:
2423:
2417:
2416:
2414:
2412:
2397:
2391:
2390:
2388:
2386:
2371:
2365:
2364:
2362:
2360:
2345:
2339:
2338:
2336:
2334:
2329:on 21 April 2013
2319:
2313:
2312:
2310:
2308:
2293:
2287:
2286:
2284:
2282:
2267:
2261:
2260:
2258:
2256:
2251:on 21 April 2013
2241:
2235:
2234:
2232:
2230:
2225:on 29 March 2012
2215:
2209:
2208:
2206:
2204:
2189:
2183:
2182:
2180:
2178:
2163:
2157:
2156:
2154:
2152:
2137:
2131:
2130:
2128:
2126:
2111:
2105:
2104:
2102:
2100:
2085:
2079:
2078:
2076:
2074:
2059:
2053:
2052:
2050:
2048:
2033:
2027:
2026:
2024:
2022:
2007:
2001:
2000:
1998:
1996:
1981:
1975:
1974:
1972:
1970:
1955:
1946:
1945:
1943:
1941:
1935:
1927:
1918:
1914:
1908:
1907:
1905:
1903:
1897:
1889:
1883:
1879:
1864:
1863:
1861:
1859:
1844:
1838:
1837:
1835:
1833:
1822:
1816:
1815:
1813:
1811:
1796:
1790:
1789:
1787:
1785:
1770:
1764:
1763:
1761:
1759:
1744:
1738:
1737:
1735:
1733:
1722:
1716:
1715:
1704:
1698:
1697:
1695:
1693:
1671:
1665:
1664:
1662:
1660:
1649:
1643:
1639:
1633:
1627:
1621:
1612:
1606:
1605:
1603:
1601:
1590:
1584:
1576:
1570:
1569:
1567:
1565:
1559:
1552:
1544:
1517:
1516:
1500:
1494:
1493:
1491:
1489:
1474:
1468:
1467:
1465:
1457:
1451:
1450:
1448:
1446:
1437:. Thames Water.
1431:
1425:
1424:
1422:
1420:
1406:
1400:
1399:
1388:
1382:
1381:
1379:
1377:
1362:
1356:
1355:
1353:
1351:
1336:
1323:
1322:
1320:
1318:
1303:
1297:
1296:
1294:
1292:
1287:. 25 August 2020
1277:
1264:
1263:
1261:
1259:
1244:
1197:carbon footprint
1071:Planned timeline
1042:Bachy Soletanche
493:Bachy Soletanche
482:
372:
174:Lowest elevation
35:
21:
4242:
4241:
4237:
4236:
4235:
4233:
4232:
4231:
4207:2020s in London
4177:
4176:
4175:
4170:
4144:
4135:Riverside South
4105:100 Bishopsgate
4088:
3999:Embassy Gardens
3941:
3935:
3932:
3902:
3897:
3746:
3680:
3641:
3632:William Webster
3555:
3550:
3513:
3512:
3509:
3504:
3503:
3493:
3491:
3483:
3482:
3478:
3462:
3458:
3448:
3446:
3437:
3436:
3432:
3422:
3420:
3411:
3410:
3406:
3396:
3394:
3390:
3386:
3385:
3381:
3371:
3369:
3360:
3359:
3355:
3345:
3343:
3334:
3333:
3329:
3315:
3314:
3310:
3300:
3298:
3289:
3288:
3284:
3274:
3272:
3263:
3262:
3258:
3248:
3246:
3237:
3236:
3232:
3219:
3218:
3214:
3204:
3202:
3200:Financial Times
3191:
3190:
3186:
3176:
3174:
3170:
3166:
3165:
3161:
3151:
3149:
3140:
3139:
3135:
3125:
3123:
3110:
3109:
3100:
3090:
3088:
3079:
3078:
3074:
3064:
3062:
3053:
3052:
3048:
3038:
3036:
3027:
3026:
3022:
3012:
3010:
3001:
3000:
2996:
2986:
2984:
2981:Financial Times
2973:
2972:
2968:
2951:
2950:
2946:
2940:
2937:Financial Times
2931:
2927:
2919:
2915:
2905:
2903:
2894:
2893:
2889:
2879:
2877:
2872:
2871:
2867:
2857:
2855:
2846:
2845:
2841:
2831:
2829:
2820:
2819:
2812:
2802:
2800:
2791:
2790:
2786:
2776:
2774:
2769:
2768:
2764:
2754:
2752:
2748:
2737:
2732:
2731:
2727:
2717:
2715:
2710:
2709:
2705:
2695:
2693:
2684:
2683:
2679:
2669:
2667:
2658:
2657:
2653:
2643:
2641:
2637:
2633:
2632:
2628:
2618:
2616:
2608:
2607:
2603:
2593:
2591:
2582:
2581:
2577:
2567:
2565:
2559:
2558:
2554:
2544:
2542:
2538:
2534:
2533:
2524:
2514:
2512:
2503:
2502:
2498:
2488:
2486:
2477:
2476:
2472:
2462:
2460:
2451:
2450:
2446:
2436:
2434:
2433:on 23 June 2012
2425:
2424:
2420:
2410:
2408:
2399:
2398:
2394:
2384:
2382:
2373:
2372:
2368:
2358:
2356:
2347:
2346:
2342:
2332:
2330:
2321:
2320:
2316:
2306:
2304:
2295:
2294:
2290:
2280:
2278:
2269:
2268:
2264:
2254:
2252:
2243:
2242:
2238:
2228:
2226:
2217:
2216:
2212:
2202:
2200:
2191:
2190:
2186:
2176:
2174:
2165:
2164:
2160:
2150:
2148:
2139:
2138:
2134:
2124:
2122:
2113:
2112:
2108:
2098:
2096:
2087:
2086:
2082:
2072:
2070:
2069:on 27 July 2012
2061:
2060:
2056:
2046:
2044:
2035:
2034:
2030:
2020:
2018:
2009:
2008:
2004:
1994:
1992:
1983:
1982:
1978:
1968:
1966:
1957:
1956:
1949:
1939:
1937:
1933:
1929:
1928:
1921:
1915:
1911:
1901:
1899:
1895:
1891:
1890:
1886:
1880:
1867:
1857:
1855:
1846:
1845:
1841:
1831:
1829:
1824:
1823:
1819:
1809:
1807:
1798:
1797:
1793:
1783:
1781:
1772:
1771:
1767:
1757:
1755:
1746:
1745:
1741:
1731:
1729:
1724:
1723:
1719:
1706:
1705:
1701:
1691:
1689:
1673:
1672:
1668:
1658:
1656:
1651:
1650:
1646:
1640:
1636:
1628:
1624:
1613:
1609:
1599:
1597:
1592:
1591:
1587:
1580:Daily Telegraph
1577:
1573:
1563:
1561:
1557:
1550:
1546:
1545:
1520:
1502:
1501:
1497:
1487:
1485:
1476:
1475:
1471:
1463:
1459:
1458:
1454:
1444:
1442:
1433:
1432:
1428:
1418:
1416:
1408:
1407:
1403:
1398:on 7 June 2013.
1390:
1389:
1385:
1375:
1373:
1364:
1363:
1359:
1349:
1347:
1346:. 27 March 2024
1338:
1337:
1326:
1316:
1314:
1305:
1304:
1300:
1290:
1288:
1279:
1278:
1267:
1257:
1255:
1246:
1245:
1238:
1233:
1224:
1211:Improved urban
1152:
1138:
1121:
1112:
1073:
1058:Dalmore Capital
968:Financial Times
931:
923:
911:Barbican Centre
892:
866:and suffragist
833:
761:Kirtling Street
688:
656:
612:
576:
571:
563:
509:
497:Mayor of London
480:
465:
457:
422:
403:
383:
370:
342:
281:Dalmore Capital
147:Design engineer
119:
28:
23:
22:
15:
12:
11:
5:
4240:
4238:
4230:
4229:
4224:
4219:
4214:
4209:
4204:
4199:
4194:
4189:
4179:
4178:
4172:
4171:
4169:
4168:
4163:
4158:
4152:
4150:
4149:Infrastructure
4146:
4145:
4143:
4142:
4137:
4132:
4130:One Park Drive
4127:
4122:
4117:
4112:
4107:
4102:
4096:
4094:
4090:
4089:
4087:
4086:
4081:
4076:
4071:
4066:
4061:
4056:
4051:
4046:
4041:
4031:
4026:
4021:
4016:
4011:
4006:
4001:
3996:
3994:Meridian Water
3991:
3988:Heygate Estate
3981:
3976:
3971:
3966:
3961:
3956:
3951:
3945:
3943:
3937:
3936:
3933:
3931:
3930:
3923:
3916:
3908:
3899:
3898:
3896:
3895:
3890:
3885:
3880:
3875:
3870:
3865:
3860:
3855:
3850:
3845:
3840:
3835:
3830:
3825:
3820:
3815:
3810:
3805:
3800:
3795:
3790:
3785:
3780:
3775:
3770:
3765:
3760:
3754:
3752:
3748:
3747:
3745:
3744:
3739:
3734:
3729:
3724:
3719:
3714:
3709:
3704:
3699:
3694:
3688:
3686:
3685:Infrastructure
3682:
3681:
3679:
3678:
3673:
3668:
3655:
3649:
3647:
3646:Major projects
3643:
3642:
3640:
3639:
3634:
3629:
3624:
3619:
3614:
3609:
3607:Hugh Myddelton
3604:
3599:
3594:
3589:
3584:
3579:
3574:
3569:
3567:John Backhouse
3563:
3561:
3557:
3556:
3551:
3549:
3548:
3541:
3534:
3526:
3520:
3519:
3508:
3507:External links
3505:
3502:
3501:
3476:
3456:
3430:
3404:
3379:
3353:
3327:
3308:
3282:
3256:
3230:
3225:Tideway.london
3212:
3184:
3159:
3133:
3098:
3072:
3046:
3020:
2994:
2966:
2944:
2925:
2913:
2887:
2865:
2839:
2810:
2784:
2762:
2733:Bessell, Jan.
2725:
2703:
2692:on 7 June 2013
2677:
2651:
2626:
2601:
2575:
2552:
2522:
2496:
2470:
2444:
2418:
2392:
2366:
2340:
2314:
2288:
2262:
2236:
2210:
2184:
2158:
2132:
2106:
2080:
2054:
2028:
2002:
1976:
1947:
1919:
1909:
1884:
1865:
1839:
1817:
1791:
1765:
1739:
1717:
1699:
1666:
1644:
1634:
1622:
1607:
1585:
1571:
1518:
1495:
1469:
1452:
1426:
1401:
1383:
1357:
1324:
1298:
1265:
1235:
1234:
1232:
1229:
1223:
1220:
1219:
1218:
1215:
1209:
1202:
1199:
1193:Climate change
1190:
1184:
1151:
1148:
1137:
1134:
1120:
1117:
1111:
1108:
1096:
1095:
1092:
1089:
1086:
1083:
1080:
1077:
1072:
1069:
1045:
1044:
1027:
1014:
1008:Morgan Sindall
930:
927:
922:
919:
891:
888:
860:Rachel Parsons
832:
829:
828:
827:
821:
818:
812:
806:
800:
797:
794:
788:
782:
776:
770:
764:
758:
752:
746:
740:
734:
728:
725:
719:
713:
707:
687:
684:
676:
675:
672:
669:
666:
663:
655:
652:
648:
647:
644:
641:
638:
635:
632:
611:
608:
607:
606:
602:
595:
575:
572:
570:
567:
562:
559:
551:
550:
541:
535:
529:
523:
508:
505:
485:Morgan Sindall
464:
461:
456:
453:
439:
438:
435:
432:
429:
421:
418:
417:
416:
413:
410:
402:
399:
382:
379:
366:Greater London
341:
338:
238:combined sewer
220:
219:
216:
215:
209:
205:
204:
201:
194:
193:
190:
189:
186:
182:
181:
175:
171:
170:
164:
160:
159:
156:
152:
151:
148:
144:
143:
139:
138:
136:Combined sewer
133:
129:
128:
125:
121:
120:
118:
117:
114:
110:
108:
104:
103:
100:
96:
95:
92:
88:
87:
84:
80:
79:
75:
74:
68:
64:
63:
60:
56:
55:
52:
48:
47:
46:Greater London
44:
40:
39:
26:
24:
18:Tideway tunnel
14:
13:
10:
9:
6:
4:
3:
2:
4239:
4228:
4225:
4223:
4220:
4218:
4215:
4213:
4210:
4208:
4205:
4203:
4200:
4198:
4195:
4193:
4190:
4188:
4185:
4184:
4182:
4167:
4164:
4162:
4159:
4157:
4154:
4153:
4151:
4147:
4141:
4138:
4136:
4133:
4131:
4128:
4126:
4123:
4121:
4118:
4116:
4113:
4111:
4108:
4106:
4103:
4101:
4098:
4097:
4095:
4091:
4085:
4082:
4080:
4077:
4075:
4072:
4070:
4067:
4065:
4062:
4060:
4057:
4055:
4054:Ruskin Square
4052:
4050:
4047:
4045:
4042:
4039:
4035:
4032:
4030:
4027:
4025:
4022:
4020:
4017:
4015:
4012:
4010:
4007:
4005:
4002:
4000:
3997:
3995:
3992:
3989:
3985:
3982:
3980:
3977:
3975:
3974:Convoys Wharf
3972:
3970:
3967:
3965:
3962:
3960:
3957:
3955:
3952:
3950:
3947:
3946:
3944:
3938:
3929:
3924:
3922:
3917:
3915:
3910:
3909:
3906:
3894:
3891:
3889:
3886:
3884:
3881:
3879:
3876:
3874:
3871:
3869:
3866:
3864:
3861:
3859:
3856:
3854:
3851:
3849:
3846:
3844:
3841:
3839:
3836:
3834:
3831:
3829:
3826:
3824:
3821:
3819:
3816:
3814:
3811:
3809:
3806:
3804:
3801:
3799:
3796:
3794:
3791:
3789:
3786:
3784:
3781:
3779:
3776:
3774:
3771:
3769:
3766:
3764:
3761:
3759:
3756:
3755:
3753:
3749:
3743:
3740:
3738:
3735:
3733:
3730:
3728:
3725:
3723:
3720:
3718:
3715:
3713:
3710:
3708:
3705:
3703:
3700:
3698:
3695:
3693:
3690:
3689:
3687:
3683:
3677:
3674:
3672:
3669:
3667:
3663:
3659:
3656:
3654:
3651:
3650:
3648:
3644:
3638:
3635:
3633:
3630:
3628:
3625:
3623:
3620:
3618:
3615:
3613:
3610:
3608:
3605:
3603:
3600:
3598:
3595:
3593:
3590:
3588:
3585:
3583:
3580:
3578:
3575:
3573:
3570:
3568:
3565:
3564:
3562:
3558:
3554:
3547:
3542:
3540:
3535:
3533:
3528:
3527:
3524:
3516:
3511:
3510:
3506:
3490:
3486:
3480:
3477:
3473:
3469:
3465:
3460:
3457:
3444:
3440:
3434:
3431:
3419:
3415:
3408:
3405:
3389:
3383:
3380:
3368:
3364:
3357:
3354:
3341:
3337:
3331:
3328:
3323:
3319:
3312:
3309:
3296:
3292:
3286:
3283:
3271:
3267:
3260:
3257:
3245:
3241:
3234:
3231:
3226:
3222:
3216:
3213:
3201:
3196:
3188:
3185:
3169:
3163:
3160:
3148:
3144:
3137:
3134:
3121:
3117:
3113:
3107:
3105:
3103:
3099:
3086:
3082:
3076:
3073:
3061:
3057:
3050:
3047:
3034:
3030:
3024:
3021:
3009:
3005:
2998:
2995:
2982:
2977:
2970:
2967:
2962:
2958:
2957:ted.europa.eu
2954:
2948:
2945:
2938:
2934:
2929:
2926:
2922:
2917:
2914:
2901:
2897:
2891:
2888:
2875:
2869:
2866:
2853:
2849:
2843:
2840:
2827:
2823:
2817:
2815:
2811:
2798:
2794:
2788:
2785:
2772:
2766:
2763:
2747:
2743:
2736:
2729:
2726:
2713:
2707:
2704:
2691:
2687:
2681:
2678:
2665:
2661:
2655:
2652:
2636:
2630:
2627:
2615:
2611:
2605:
2602:
2590:
2586:
2579:
2576:
2563:
2556:
2553:
2537:
2531:
2529:
2527:
2523:
2510:
2506:
2500:
2497:
2484:
2480:
2474:
2471:
2458:
2454:
2448:
2445:
2432:
2428:
2422:
2419:
2406:
2402:
2396:
2393:
2381:on 5 May 2013
2380:
2376:
2370:
2367:
2354:
2350:
2344:
2341:
2328:
2324:
2318:
2315:
2302:
2298:
2292:
2289:
2276:
2272:
2266:
2263:
2250:
2246:
2240:
2237:
2224:
2220:
2214:
2211:
2198:
2194:
2188:
2185:
2172:
2168:
2162:
2159:
2146:
2142:
2136:
2133:
2120:
2116:
2110:
2107:
2094:
2090:
2084:
2081:
2068:
2064:
2058:
2055:
2042:
2038:
2032:
2029:
2016:
2012:
2006:
2003:
1990:
1986:
1980:
1977:
1964:
1960:
1954:
1952:
1948:
1932:
1926:
1924:
1920:
1917:
1913:
1910:
1894:
1888:
1885:
1882:
1878:
1876:
1874:
1872:
1870:
1866:
1853:
1849:
1843:
1840:
1827:
1821:
1818:
1805:
1801:
1795:
1792:
1779:
1775:
1769:
1766:
1753:
1749:
1743:
1740:
1727:
1721:
1718:
1713:
1709:
1703:
1700:
1687:
1683:
1682:
1677:
1670:
1667:
1654:
1648:
1645:
1642:
1638:
1635:
1631:
1626:
1623:
1619:
1618:
1615:Thames Water
1611:
1608:
1595:
1589:
1586:
1582:
1581:
1575:
1572:
1556:
1549:
1543:
1541:
1539:
1537:
1535:
1533:
1531:
1529:
1527:
1525:
1523:
1519:
1514:
1510:
1506:
1499:
1496:
1483:
1482:Bloomberg.com
1479:
1473:
1470:
1462:
1456:
1453:
1440:
1436:
1430:
1427:
1415:
1411:
1405:
1402:
1397:
1393:
1387:
1384:
1371:
1367:
1361:
1358:
1345:
1341:
1335:
1333:
1331:
1329:
1325:
1313:
1309:
1302:
1299:
1286:
1282:
1276:
1274:
1272:
1270:
1266:
1253:
1249:
1243:
1241:
1237:
1230:
1228:
1221:
1216:
1214:
1210:
1207:
1203:
1200:
1198:
1194:
1191:
1189:
1188:air pollution
1185:
1182:
1181:
1180:
1177:
1173:
1169:
1165:
1161:
1157:
1149:
1147:
1144:
1135:
1133:
1130:
1126:
1118:
1116:
1109:
1107:
1103:
1101:
1093:
1090:
1087:
1084:
1081:
1078:
1075:
1074:
1070:
1068:
1066:
1061:
1059:
1055:
1051:
1043:
1039:
1035:
1031:
1028:
1026:
1022:
1018:
1015:
1013:
1009:
1005:
1001:
998:
997:
996:
993:
991:
984:
979:
977:
973:
969:
965:
959:
957:
951:
947:
942:
940:
936:
928:
926:
920:
918:
916:
912:
907:
903:
900:
895:
889:
887:
885:
881:
877:
873:
869:
865:
861:
858:in 2018, the
857:
852:
848:
844:
840:
838:
830:
825:
822:
819:
816:
813:
810:
807:
804:
801:
798:
795:
792:
789:
786:
783:
780:
777:
774:
771:
768:
765:
762:
759:
756:
753:
750:
747:
744:
741:
738:
735:
732:
731:Dormay Street
729:
726:
723:
720:
717:
714:
711:
708:
705:
702:
701:
697:
692:
685:
683:
679:
673:
670:
667:
664:
661:
660:
659:
653:
651:
645:
642:
639:
636:
633:
630:
629:
628:
624:
620:
616:
609:
603:
599:
596:
593:
589:
588:
587:
584:
581:
573:
568:
566:
560:
558:
556:
549:
545:
542:
539:
536:
533:
530:
527:
524:
521:
518:
517:
516:
514:
506:
504:
502:
501:Boris Johnson
498:
494:
490:
486:
478:
474:
470:
462:
460:
454:
452:
449:
445:
436:
433:
430:
427:
426:
425:
419:
414:
411:
408:
407:
406:
400:
398:
396:
392:
388:
380:
378:
376:
367:
362:
358:
356:
351:
347:
339:
337:
335:
331:
327:
322:
318:
316:
312:
307:
303:
302:in the east.
301:
297:
293:
288:
286:
282:
278:
274:
269:
267:
263:
259:
255:
251:
247:
243:
239:
235:
226:
217:
213:
210:
206:
202:
199:
195:
191:
187:
183:
180:
176:
172:
169:
165:
161:
157:
153:
149:
145:
140:
137:
134:
130:
126:
122:
115:
112:
111:
109:
105:
101:
97:
93:
89:
85:
81:
76:
72:
69:
65:
62:Acton, London
61:
57:
53:
49:
45:
41:
36:
30:
19:
4192:Thames Water
4156:High Speed 2
4140:Spire London
4069:Wembley City
4038:East Village
4034:Olympic Park
3979:Earl's Court
3660:, including
3553:Thames Water
3492:. Retrieved
3488:
3479:
3467:
3459:
3447:. Retrieved
3443:the original
3433:
3421:. Retrieved
3417:
3407:
3395:. Retrieved
3382:
3370:. Retrieved
3366:
3356:
3344:. Retrieved
3339:
3330:
3322:The Guardian
3321:
3311:
3299:. Retrieved
3294:
3285:
3273:. Retrieved
3269:
3259:
3247:. Retrieved
3243:
3233:
3224:
3215:
3203:. Retrieved
3199:
3187:
3175:. Retrieved
3162:
3150:. Retrieved
3146:
3136:
3124:. Retrieved
3120:the original
3115:
3089:. Retrieved
3085:the original
3075:
3063:. Retrieved
3059:
3049:
3037:. Retrieved
3033:the original
3023:
3011:. Retrieved
3007:
2997:
2985:. Retrieved
2980:
2969:
2961:the original
2956:
2947:
2936:
2928:
2916:
2904:. Retrieved
2900:the original
2890:
2878:. Retrieved
2868:
2856:. Retrieved
2852:the original
2842:
2830:. Retrieved
2826:the original
2801:. Retrieved
2797:the original
2787:
2777:21 September
2775:. Retrieved
2765:
2753:. Retrieved
2746:the original
2741:
2728:
2716:. Retrieved
2706:
2694:. Retrieved
2690:the original
2680:
2668:. Retrieved
2664:the original
2654:
2642:. Retrieved
2629:
2617:. Retrieved
2613:
2604:
2592:. Retrieved
2588:
2578:
2566:. Retrieved
2555:
2543:. Retrieved
2513:. Retrieved
2509:the original
2499:
2487:. Retrieved
2483:the original
2473:
2461:. Retrieved
2457:the original
2447:
2435:. Retrieved
2431:the original
2421:
2409:. Retrieved
2405:the original
2395:
2383:. Retrieved
2379:the original
2369:
2357:. Retrieved
2353:the original
2343:
2331:. Retrieved
2327:the original
2317:
2305:. Retrieved
2301:the original
2291:
2279:. Retrieved
2275:the original
2265:
2253:. Retrieved
2249:the original
2239:
2227:. Retrieved
2223:the original
2213:
2201:. Retrieved
2197:the original
2187:
2175:. Retrieved
2171:the original
2161:
2149:. Retrieved
2145:the original
2135:
2123:. Retrieved
2119:the original
2109:
2097:. Retrieved
2093:the original
2083:
2071:. Retrieved
2067:the original
2057:
2045:. Retrieved
2041:the original
2031:
2019:. Retrieved
2015:the original
2005:
1993:. Retrieved
1989:the original
1979:
1967:. Retrieved
1963:the original
1938:. Retrieved
1912:
1900:. Retrieved
1887:
1856:. Retrieved
1852:the original
1842:
1830:. Retrieved
1820:
1808:. Retrieved
1804:the original
1794:
1782:. Retrieved
1778:the original
1768:
1756:. Retrieved
1752:the original
1742:
1730:. Retrieved
1720:
1711:
1702:
1690:. Retrieved
1679:
1669:
1657:. Retrieved
1647:
1637:
1625:
1617:Needs report
1616:
1610:
1598:. Retrieved
1588:
1578:
1574:
1562:. Retrieved
1555:the original
1512:
1508:
1498:
1486:. Retrieved
1481:
1472:
1455:
1443:. Retrieved
1429:
1419:16 September
1417:. Retrieved
1413:
1404:
1396:the original
1386:
1374:. Retrieved
1370:the original
1360:
1348:. Retrieved
1343:
1315:. Retrieved
1311:
1301:
1289:. Retrieved
1284:
1256:. Retrieved
1252:the original
1225:
1213:biodiversity
1153:
1139:
1125:Thames Water
1122:
1113:
1104:
1097:
1062:
1046:
1029:
1016:
999:
994:
986:
981:
976:Simon Hughes
967:
960:
952:
949:
944:
932:
924:
908:
904:
896:
893:
853:
849:
845:
841:
834:
680:
677:
657:
649:
625:
621:
617:
613:
585:
580:Thames Water
577:
564:
552:
510:
466:
458:
440:
423:
404:
384:
363:
359:
348:'s original
343:
323:
319:
308:
304:
289:
270:
250:Inner London
246:River Thames
233:
231:
29:
4110:Arena Tower
3940:Development
3582:Great Stink
3470:". Also in
3397:13 February
2906:21 November
2880:21 November
2644:13 February
2564:. Vimeo.com
2545:13 February
1940:13 February
1902:13 February
1583:8 June 2011
1445:10 November
1376:15 November
1317:6 September
1258:10 November
1176:water butts
1168:green roofs
1110:Controversy
1004:BAM Nuttall
983:activities.
978:MP stated:
791:Shad Thames
743:Falconbrook
710:Hammersmith
598:Rotherhithe
473:Abbey Mills
300:Abbey Mills
200:intercepted
179:Abbey Mills
91:Constructed
4181:Categories
4125:North Quay
4084:Wood Wharf
3751:Reservoirs
3666:Lee Tunnel
3013:31 January
1410:"Timeline"
1248:"Timeline"
1231:References
1136:Disruption
876:Selina Fox
469:Lee Tunnel
340:Background
326:Lee Tunnel
262:Bazalgette
83:Work begun
71:Lee Tunnel
4093:Buildings
3627:John Snow
3622:New River
3346:24 August
3324:. London.
3152:24 August
3126:24 August
3091:24 August
3065:24 August
2858:6 October
2832:6 October
2803:6 October
1291:26 August
1164:permeable
1060:and DIF.
972:Ian Byatt
941:in 2011:
809:Greenwich
767:Heathwall
716:Barn Elms
258:rainwater
142:Technical
132:Character
78:Operation
54:Completed
3449:23 March
3423:23 March
3372:23 March
3301:23 March
3295:BBC News
3008:Building
2670:23 March
2568:23 March
2515:23 March
2489:23 March
2463:23 March
2437:23 March
2411:23 March
2385:23 March
2359:23 March
2333:23 March
2307:23 March
2281:23 March
2255:23 March
2229:23 March
2203:23 March
2177:23 March
2151:23 March
2125:23 March
2099:23 March
2073:23 March
2047:23 March
2021:23 March
1995:23 March
1969:23 March
1858:23 March
1832:23 March
1810:23 March
1784:23 March
1758:23 March
1732:23 March
1712:Sky News
1692:27 March
1686:Archived
1659:23 March
1600:23 March
1564:23 March
1488:31 March
1439:Archived
1344:BBC News
1204:Reduced
803:Deptford
548:Dartford
401:Outcomes
393:and the
124:Operator
43:Location
38:Overview
3560:History
3494:28 July
3205:23 July
3177:23 July
3039:31 July
2987:28 July
2755:31 July
2718:31 July
2696:31 July
2619:17 June
2594:17 June
1414:Tideway
1350:2 April
1050:Allianz
1034:Costain
1017:Central
555:Tideway
477:Beckton
273:Allianz
248:across
244:of the
3249:14 May
1172:swales
856:Fulham
698:, 2021
696:Putney
254:sewage
155:Length
51:Status
3942:sites
3391:(PDF)
3275:3 May
3171:(PDF)
2876:. BBC
2749:(PDF)
2738:(PDF)
2638:(PDF)
2539:(PDF)
1934:(PDF)
1896:(PDF)
1558:(PDF)
1551:(PDF)
1464:(PDF)
1129:Ofwat
956:Ofwat
704:Acton
601:CSOs.
391:DEFRA
296:Acton
285:Ofwat
185:Width
168:Acton
107:Owner
99:Opens
59:Start
3664:and
3496:2016
3451:2013
3425:2013
3399:2016
3374:2013
3348:2015
3303:2013
3277:2024
3251:2024
3207:2022
3179:2022
3154:2015
3128:2015
3093:2015
3067:2015
3041:2013
3015:2013
2989:2016
2908:2014
2882:2014
2860:2014
2834:2014
2805:2014
2779:2014
2757:2013
2720:2013
2698:2013
2672:2013
2646:2016
2621:2019
2596:2019
2570:2013
2547:2016
2517:2013
2491:2013
2465:2013
2439:2013
2413:2013
2387:2013
2361:2013
2335:2013
2309:2013
2283:2013
2257:2013
2231:2013
2205:2013
2179:2013
2153:2013
2127:2013
2101:2013
2075:2013
2049:2013
2023:2013
1997:2013
1971:2013
1942:2016
1904:2016
1860:2013
1834:2013
1812:2013
1786:2013
1760:2013
1734:2013
1694:2016
1661:2013
1602:2013
1566:2013
1515:(1).
1490:2024
1447:2019
1421:2019
1378:2015
1352:2024
1319:2022
1293:2020
1260:2019
1174:and
1040:and
1030:East
1023:and
1010:and
1000:West
491:and
444:SUDs
256:and
232:The
208:Cost
198:CSOs
102:2025
86:2016
475:to
332:to
67:End
4183::
3487:.
3416:.
3365:.
3338:.
3320:.
3293:.
3268:.
3242:.
3223:.
3198:.
3145:.
3114:.
3101:^
3058:.
3006:.
2979:.
2955:.
2935:.
2813:^
2740:.
2612:.
2587:.
2525:^
1950:^
1922:^
1868:^
1710:.
1684:.
1678:.
1521:^
1511:.
1507:.
1480:.
1412:.
1342:.
1327:^
1310:.
1283:.
1268:^
1239:^
1170:,
1056:,
1052:,
1036:,
1006:,
964:EU
886:.
499:,
487:,
389:,
336:.
279:,
275:,
203:34
4040:)
4036:(
3990:)
3986:(
3927:e
3920:t
3913:v
3545:e
3538:t
3531:v
3498:.
3453:.
3427:.
3401:.
3376:.
3350:.
3305:.
3279:.
3253:.
3227:.
3209:.
3156:.
3130:.
3095:.
3069:.
3043:.
3017:.
2991:.
2910:.
2884:.
2862:.
2836:.
2807:.
2781:.
2759:.
2722:.
2700:.
2674:.
2648:.
2623:.
2598:.
2572:.
2549:.
2519:.
2493:.
2467:.
2441:.
2415:.
2389:.
2363:.
2337:.
2311:.
2285:.
2259:.
2233:.
2207:.
2181:.
2155:.
2129:.
2103:.
2077:.
2051:.
2025:.
1999:.
1973:.
1944:.
1906:.
1862:.
1836:.
1814:.
1788:.
1762:.
1736:.
1714:.
1696:.
1663:.
1604:.
1568:.
1513:5
1492:.
1449:.
1423:.
1380:.
1354:.
1321:.
1295:.
1262:.
481:×
446:/
371:×
212:£
20:)
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.