327:, which was the nation's most important rail corridor. Accordingly, the section between Vienna and St. Pölten saw the construction of two new tracks on an alignment free from challenging gradients and suitable for high speed operations, which deviated far to the North of the original line. It was along this new route that the Wienerwald Tunnel, which is the single biggest engineering structure, was constructed to convey the line across the Wienerwald mountain range. Its construction facilitate the movement of trains traversing the Westbahn to call at
138:
348:
316:
158:
36:
747:
804:
694:
857:
165:
375:
The excavation phase progressed steadily, reaching a peak rate of 254 meters in a single week. To minimise unfavourable movement associated with settlement, sidewall heading were driven at the start of the bi-tube section. The spoil generated by the excavation, estimated to be roughly 2 million m³ of
334:
In relation to the rest of the line, the
Wienerwald Tunnel formed only one element of a wider complex of tunnels. Towards the eastern end (nearest Vienna), it meets with an underground junction with another 2.2 km tunnel, carrying two extra tracks for the old Westbahn, which has been operational
380:
were also redeveloped or treated appropriately. For structural strength, the walls were lined with reinforced concrete segments, which are considered to be impermeable to water, throughout the tunnel's length. Secondary elements of the tunnel include 25 cross-passages, an emergency exit shaft, and a
359:
During autumn 2004, work commenced on the boring of the tunnel's single tube section. From its western portal, the first 11 km of the
Wienerwald Tunnel was constructed as a bi-tube tunnel (a tunnel consisting of two connected single-track tubes), which the remainder was constructed as a single
384:
On 16 August 2007, breakthrough in the tunnel was announced, a major milestone in the construction; use of the TBMs was discontinued in the same year as a result. During
February 2010, all structural work was declared to be complete, work progressed to the fitting out phase, during which elements
339:, a 12.3 km long twin-track single tube tunnel that was constructed in parallel with the Wienerwald Tunnel. When combined with the adjacent Lainzer Tunnel, the Wienerwald Tunnel results in trains covering an underground distance of 26 km, making it Austria's longest tunnel.
385:
such as the traditional slab-based track and various safety measures were installed, from the summer of 2010. On 9 December 2012, the tunnel and line were both inaugurated. The completed route has not only increased freight capacities but enabled a reduction in travel time.
297:
The
Wienerwald Tunnel was constructed as part of a major expansion of Austria's most important rail corridor, it was intentionally built as a measure to minimise gradients and facilitate high speed traffic, as well as for better accessibility to the newly constructed
302:
central station in Vienna. It is divided into two distinct sections, comprising a single bore accommodating a pair of tracks and two parallel bores each carrying a single track; it also meets up with several other neighbouring tunnels, including the
307:. Construction of the Wienerwald Tunnel commenced in autumn 2004, largely relying on conventional methods. Breakthrough was achieved in early 2010, after which fitting out commenced. The tunnel has been in operational use since 9 December 2012.
549:
76:, is a useful starting point for translations, but translators must revise errors as necessary and confirm that the translation is accurate, rather than simply copy-pasting machine-translated text into the English Knowledge.
360:
tube accommodating the two tracks. The early excavation work predominantly used conventional drilling and blasting techniques. Roughly one year later, the boring of the bi-tube section commenced using a pair of
468:
267:
928:
841:
943:
405:
731:
655:
894:
376:
material in all, was predominantly used as fill for an embankment running along a 10km section of the line. Residual waste, earthworks, roadworks, and
788:
79:
Do not translate text that appears unreliable or low-quality. If possible, verify the text with references provided in the foreign-language article.
647:
834:
157:
933:
87:
724:
368:. The route of the tunnel passed through layers of siltstone, mudstone, and sandstone, as well as more challenging geology such as
953:
948:
887:
918:
827:
958:
781:
938:
717:
880:
100:
Content in this edit is translated from the existing German
Knowledge article at ]; see its history for attribution.
455:"SAFETY DESIGN FOR THE WIENERWALD TUNNEL - FROM THE DECISION ON THE TUNNEL SYSTEM TO THE PERMIT APPLICATION DESIGN"
622:
553:
527:
472:
324:
291:
774:
95:
618:
431:
923:
581:
109:
913:
361:
352:
347:
315:
116:
372:; water ingress of up to 0.5 liters per second proved to be a particular challenge for the project.
323:
During the early twenty-first century, the
Austrian government authorised the four-tracking of the
143:
137:
328:
299:
91:
803:
271:
287:
48:
457:. PROCEEDINGS OF THE FOURTH INTERNATIONAL CONFERENCE ON SAFETY IN ROAD AND RAIL TUNNELS.
864:
811:
758:
746:
701:
336:
304:
252:
907:
604:
493:
286:. It is part of a 250-kilometre-per-hour (160 mph) section between Vienna and
283:
17:
365:
224:
693:
670:
657:
369:
335:
since
December 2008, and direct tracks across the junction continue in the
377:
98:
to the source of your translation. A model attribution edit summary is
754:
409:
279:
454:
364:(TBMs); this was the first tunnel in Austria to use TBMs outside
73:
29:
278:) is a 13.35 km (8.30 mi) long railway tunnel near
319:
View from just inside the tunnel, facing towards
Tullnerfeld
700:
This article about an
Austrian building or structure is a
331:, the recently completed central station serving Vienna.
868:
815:
762:
705:
355:(TBM) outside the under-construction Wienerwald Tunnel
619:"Neubaustrecke Wien-St. Pölten/Abschnitt Wienerwald"
69:
223:
215:
210:
195:
190:
182:
177:
499:(in German). Fritsch, Chiari & Partner ZT GmbH
605:"The Wienerwald tunnel - A tunnelling challenge"
400:
398:
648:Safety Management for Austrian Railway Tunnels
94:accompanying your translation by providing an
60:Click for important translation instructions.
47:expand this article with text translated from
888:
835:
810:This article about transport in Austria is a
782:
725:
8:
929:Buildings and structures in Penzing (Vienna)
576:
574:
572:
570:
522:
520:
518:
516:
514:
130:
434:(in German). Eisenbahn-Tunnel in Österreich
142:Entrance to the Wienerwald Tunnel from the
895:
881:
863:This European tunnel-related article is a
842:
828:
789:
775:
732:
718:
282:, passing underneath the northern part of
136:
129:
453:Bauer, F.; Kohl, B.; Neumann, C. (2001).
164:
346:
314:
432:"Weichenhalle Purkersdorf: 2.200 Meter"
394:
944:Austrian building and structure stubs
7:
853:
851:
800:
798:
743:
741:
690:
688:
603:C. Stahn; K. Grimm (January 2006).
494:"Lainzer Tunnel / Wienerwaldtunnel"
106:{{Translated|de|Wienerwaldtunnel}}
25:
406:"Längster Bahntunnel Österreichs"
855:
802:
745:
692:
163:
156:
34:
104:You may also add the template
1:
219:13,356 m (8.299 mi)
867:. You can help Knowledge by
814:. You can help Knowledge by
761:. You can help Knowledge by
704:. You can help Knowledge by
311:Background and configuration
290:which is part of Austria's
975:
934:Railway tunnels in Austria
850:
797:
740:
687:
68:Machine translation, like
381:490 m long muck heading.
199:9 December 2012
151:
135:
49:the corresponding article
408:(in German). Webpage of
954:Austria transport stubs
949:Austria geography stubs
115:For more guidance, see
27:Austrian railway tunnel
919:Wien-Umgebung District
757:location article is a
550:"Abschnitt Wienerwald"
362:tunnel boring machines
356:
320:
275:
959:European tunnel stubs
353:tunnel boring machine
350:
318:
117:Knowledge:Translation
88:copyright attribution
939:Tunnels in the Alps
671:48.1792°N 16.2072°E
667: /
607:. pp. 167–172.
582:"Wienerwald Tunnel"
528:"Wienerwald Tunnel"
132:
18:Vienna Woods Tunnel
530:. herrenknecht.com
357:
321:
96:interlanguage link
876:
875:
823:
822:
770:
769:
713:
712:
623:ÖBB Infrastruktur
554:ÖBB Infrastruktur
473:ÖBB Infrastruktur
329:Wien Hauptbahnhof
300:Wien Hauptbahnhof
263:Wienerwald Tunnel
259:
258:
131:Wienerwald Tunnel
128:
127:
61:
57:
16:(Redirected from
966:
897:
890:
883:
859:
858:
852:
844:
837:
830:
806:
799:
791:
784:
777:
749:
742:
734:
727:
720:
696:
689:
682:
681:
679:
678:
677:
676:48.1792; 16.2072
672:
668:
665:
664:
663:
660:
635:
634:
632:
630:
615:
609:
608:
600:
594:
593:
591:
589:
578:
565:
564:
562:
560:
546:
540:
539:
537:
535:
524:
509:
508:
506:
504:
498:
490:
484:
483:
481:
479:
469:"Lainzer Tunnel"
465:
459:
458:
450:
444:
443:
441:
439:
428:
422:
421:
419:
417:
402:
276:Wienerwaldtunnel
270:
255:
249:
247:
246:
242:
239:
231:
206:
204:
167:
166:
160:
140:
133:
107:
101:
74:Google Translate
59:
55:
38:
37:
30:
21:
974:
973:
969:
968:
967:
965:
964:
963:
904:
903:
902:
901:
856:
849:
848:
796:
795:
739:
738:
685:
675:
673:
669:
666:
661:
658:
656:
654:
653:
644:
639:
638:
628:
626:
617:
616:
612:
602:
601:
597:
587:
585:
580:
579:
568:
558:
556:
548:
547:
543:
533:
531:
526:
525:
512:
502:
500:
496:
492:
491:
487:
477:
475:
467:
466:
462:
452:
451:
447:
437:
435:
430:
429:
425:
415:
413:
404:
403:
396:
391:
345:
313:
292:Western Railway
266:
251:
244:
240:
237:
235:
234:4 ft
233:
229:
202:
200:
173:
172:
171:
170:
169:
168:
147:
124:
123:
122:
105:
99:
62:
39:
35:
28:
23:
22:
15:
12:
11:
5:
972:
970:
962:
961:
956:
951:
946:
941:
936:
931:
926:
924:Tulln District
921:
916:
906:
905:
900:
899:
892:
885:
877:
874:
873:
860:
847:
846:
839:
832:
824:
821:
820:
807:
794:
793:
786:
779:
771:
768:
767:
750:
737:
736:
729:
722:
714:
711:
710:
697:
651:
650:
643:
642:External links
640:
637:
636:
610:
595:
566:
541:
510:
485:
460:
445:
423:
393:
392:
390:
387:
344:
341:
337:Lainzer Tunnel
312:
309:
305:Lainzer Tunnel
257:
256:
253:standard gauge
227:
221:
220:
217:
213:
212:
208:
207:
197:
193:
192:
188:
187:
184:
180:
179:
175:
174:
162:
161:
155:
154:
153:
152:
149:
148:
141:
126:
125:
121:
120:
113:
102:
80:
77:
66:
63:
44:
43:
42:
40:
33:
26:
24:
14:
13:
10:
9:
6:
4:
3:
2:
971:
960:
957:
955:
952:
950:
947:
945:
942:
940:
937:
935:
932:
930:
927:
925:
922:
920:
917:
915:
912:
911:
909:
898:
893:
891:
886:
884:
879:
878:
872:
870:
866:
861:
854:
845:
840:
838:
833:
831:
826:
825:
819:
817:
813:
808:
805:
801:
792:
787:
785:
780:
778:
773:
772:
766:
764:
760:
756:
751:
748:
744:
735:
730:
728:
723:
721:
716:
715:
709:
707:
703:
698:
695:
691:
686:
683:
680:
649:
646:
645:
641:
624:
621:(in German).
620:
614:
611:
606:
599:
596:
584:. daub-ita.de
583:
577:
575:
573:
571:
567:
555:
552:(in German).
551:
545:
542:
529:
523:
521:
519:
517:
515:
511:
495:
489:
486:
474:
471:(in German).
470:
464:
461:
456:
449:
446:
433:
427:
424:
411:
407:
401:
399:
395:
388:
386:
382:
379:
373:
371:
367:
363:
354:
349:
342:
340:
338:
332:
330:
326:
317:
310:
308:
306:
301:
295:
293:
289:
285:
281:
277:
273:
269:
264:
254:
230:1,435 mm
228:
226:
222:
218:
214:
209:
198:
194:
189:
185:
181:
176:
159:
150:
145:
139:
134:
118:
114:
111:
103:
97:
93:
89:
85:
81:
78:
75:
71:
67:
65:
64:
58:
56:(August 2013)
52:
50:
45:You can help
41:
32:
31:
19:
914:Vienna Woods
869:expanding it
862:
816:expanding it
809:
763:expanding it
752:
706:expanding it
699:
684:
652:
627:. Retrieved
613:
598:
586:. Retrieved
557:. Retrieved
544:
532:. Retrieved
501:. Retrieved
488:
476:. Retrieved
463:
448:
436:. Retrieved
426:
414:. Retrieved
412:. 1 May 2007
383:
374:
366:conurbations
358:
343:Construction
333:
322:
296:
262:
260:
92:edit summary
83:
54:
46:
674: /
503:2 September
438:2 September
416:2 September
225:Track gauge
216:Line length
144:Tullnerfeld
908:Categories
662:16°12′26″E
659:48°10′45″N
629:5 November
625:. May 2010
559:5 November
478:5 November
389:References
288:St. Pölten
284:Wienerwald
203:2012-12-09
370:marlstone
268:‹See Tfd›
211:Technical
191:Operation
110:talk page
51:in German
325:Westbahn
248: in
178:Overview
86:provide
588:14 July
534:14 July
243:⁄
201: (
108:to the
90:in the
53:.
755:Vienna
410:Vienna
378:sewers
280:Vienna
272:German
196:Opened
186:Active
183:Status
753:This
497:(PDF)
70:DeepL
865:stub
812:stub
759:stub
702:stub
631:2010
590:2020
561:2010
536:2020
505:2010
480:2010
440:2010
418:2010
261:The
146:side
84:must
82:You
72:or
910::
569:^
513:^
397:^
351:A
294:.
274::
250:)
896:e
889:t
882:v
871:.
843:e
836:t
829:v
818:.
790:e
783:t
776:v
765:.
733:e
726:t
719:v
708:.
633:.
592:.
563:.
538:.
507:.
482:.
442:.
420:.
265:(
245:2
241:1
238:+
236:8
232:(
205:)
119:.
112:.
20:)
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.