Knowledge (XXG)

185th Tunnelling Company

Source 📝

434:: "shell farm") to the Germans and as "Glory Hole" to the British. In December 1914, French engineers had begun tunnelling beneath the ruins. With the war on the surface at stalemate, both sides continued to probe beneath the opponent's trenches and detonate ever-greater explosive charges. In August 1915, the French and Germans were working at a depth of 12 metres (39 ft); the size of their charges had reached 3,000 kilograms (6,600 lb). The British extended and deepened the system, first to 24 metres (79 ft) and ultimately 30 metres (98 ft). Above ground the infantry occupied trenches just 45 metres (148 ft) apart. Around La Boisselle, the Germans had dug defensive transversal tunnels at a depth of about 80 feet (24 metres), parallel to the front line. 344: 336: 517: 328: 49: 66: 592:. During summer and much of autumn 1916, the unit further developed and expanded its mining to create an effective underground defence at Roclincourt-Chantecler. In May 1916, a German infantry attack at Vimy, which forced the British back 640 metres (700 yd), was aimed at neutralising British mining activity by capturing the shaft entrances. From June 1916, however, the Germans withdrew many miners to work on the 237:
each commanded by a regular Royal Engineers officer. These companies each comprised 5 officers and 269 sappers; they were aided by additional infantrymen who were temporarily attached to the tunnellers as required, which almost doubled their numbers. The success of the first tunnelling companies formed under Norton-Griffiths' command led to mining being made a separate branch of the Engineer-in-Chief's office under
630:– where mines had so altered and damaged the landscape as to render occupation of the mine craters by the infantry all but impossible –, led to the decision to remove offensive mining from the central sector allocated to the Canadian Corps at Vimy Ridge. Further British mines in the area were vetoed following the blowing by the Germans on 23 March 1917 of nine craters along 26: 597:
this was subsequently postponed. After September 1916, when the Royal Engineers had completed their network of defensive galleries along most of the front line, offensive mining largely ceased although activities continued until 1917. The British gallery network beneath Vimy Ridge eventually grew to a length of 12 kilometres (7.5 mi).
642:
against the German strongpoint known as the Pimple, was not completed in time for the attack. The gallery had been pushed silently through the clay, avoiding the sandy and chalky layers of the Vimy Ridge, but by 9 April 1917 was still 21 metres (70 ft) short of its target. In the end, two mines
236:
was also restricted by the need to provide effective counter-measures to the German mining activities. To make the tunnels safer and quicker to deploy, the British Army enlisted experienced coal miners, many outside their nominal recruitment policy. The first nine companies, numbers 170 to 178, were
613:
charges were eventually laid. At the same time, 19 crater groups existed along this section of the Western Front, each with several large craters. In order to assess the consequences of infantry having to advance across cratered ground after a mining attack, officers from the Canadian Corps visited
580:
Tunnelling Companies. From spring 1916, the British had deployed five tunnelling companies along the Vimy Ridge, and during the first two months of their tenure in the area, 70 mines were fired, mostly by the Germans. Between October 1915 and April 1917 an estimated 150 French, British and German
596:
and also for work in coal mines in Germany. In the second half of 1916 the British constructed strong defensive underground positions, and from August 1916, the Royal Engineers developed a mining scheme to support a large-scale infantry attack on the Vimy Ridge proposed for autumn 1916, although
563:
The front sectors at Vimy and Arras, where extremely heavy fighting between the French and the Germans had taken place during 1915, had been taken over by the British in March 1916. Vimy, in particular, was an area of busy underground activity. British tunnellers progressively took over military
604:
was posted to the northern part of Vimy Ridge in October 1916 and preparations for an attack were revived in February 1917. 185th Tunnelling Company then dug subways near Neuville-Saint-Vaast in early 1917. Prior to the Battle of Vimy Ridge (9 – 12 April 1917), the British tunnelling companies
425:
Early attempts at mining by the British on the Western Front had commenced in late 1914 in the soft clay and sandy soils of Flanders. Mining at La Boisselle was in chalk, much harder and requiring different techniques. The German advance had been halted at La Boisselle by French troops on 28
405:
Tunnelling Companies there to relieve the French engineers, but the British did not have enough miners to take over the large number of French shafts and the French agreed to leave their engineers at work for several weeks. To provide the tunnellers needed, the British formed the
231:
which required the deployment of new drafts of tunnellers for several months after the formation of the first eight companies. The lack of suitably experienced men led to some tunnelling companies starting work later than others. The number of units available to the
1285: 501:
in March 1916, which finished and fired it. A month before the handover, eighteen men of the 185th Tunnelling Company (2 officers, 16 sappers) died to a German camouflet at La Boisselle on 4 February 1916.
203:
Norton-Griffiths ensured that tunnelling companies numbers 170 to 177 were ready for deployment in mid-February 1915. In the spring of that year, there was constant underground fighting in the
457:
and allow the infantry to attack the German positions from a comparatively short distance. Four mines were planned at La Boisselle: Two 3,600-kilogram (8,000 lb) charges (known as
258: 605:
secretly laid a series of explosive charges under German positions in an effort to destroy surface fortifications before the assault. The original plan had called for 17 mines and 9
268:
Most tunnelling companies were formed under Norton-Griffiths' leadership during 1915, and one more was added in 1916. On 10 September 1915, the British government sent an appeal to
150:
for troop accommodation, the digging of subways, saps (a narrow trench dug to approach enemy trenches), cable trenches and underground chambers for signals and medical services.
1290: 250: 265:
unit. The formation of twelve new tunnelling companies, between July and October 1915, helped to bring more men into action in other parts of the Western Front.
360: 426:
September 1914. There was bitter fighting for possession of the village cemetery, and for farm buildings on the south-western edge of the village, known as "
159: 127: 79: 771: 233: 185: 165: 758:
Peter Barton/Peter Doyle/Johan Vandewalle, Beneath Flanders Fields - The Tunnellers' War 1914-1918, Staplehurst (Spellmount) (978-1862272378) p. 165.
176:
to a planned system. As the British had failed to develop suitable counter-tactics or underground listening devices before the war, field marshals
489:
after the trenches from which they were dug, were laid to the north-east and the south-east of La Boisselle on either side of the German salient –
308:
tunnelling companies were formed by March 1916, resulting in 30 tunnelling companies of the Royal Engineers being available by the summer of 1916.
638:
were also dropped from the British plans. They were left in place after the assault and were only removed in the 1990s. Another mine, prepared by
377:
In the Somme sector of the Western Front, local but very fierce underground fighting had taken place in the winter of 1914 and spring of 1915 at
1295: 731: 193: 1225: 1137: 181: 1244: 623: 442: 322: 184:
agreed to investigate the suitability of forming British mining units. Following consultations between the Engineer-in-Chief of the
1199: 1158: 634:
as it was probable that the Germans were aiming to restrict an Allied attack to predictable points. The three mines already laid by
557: 262: 25: 343: 816: 949: 867: 490: 627: 589: 293: 177: 1229: 304:
unit was formed from men on the battlefield, plus two other companies trained in Canada and then shipped to France. Three
1104: 468: 427: 1257: 707: 371: 169: 441:(1 July – 18 November 1916) were begun, the tunnelling companies were to make two major contributions by placing 142:. The tunnelling units were occupied in offensive and defensive mining involving the placing and maintaining of 639: 635: 577: 573: 569: 565: 553: 549: 498: 419: 415: 411: 407: 402: 398: 366:
185th Tunnelling Company was formed in Rouen in October 1915, moved immediately to the Somme area, for work at
1262: 775: 552:, which had moved to Neuville-Saint-Vaast in April 1916 and remained there for a considerable time, and the 220: 292:. On 17 September, New Zealand became the first Dominion to agree the formation of a tunnelling unit. The 254: 216: 545: 474: 367: 348: 335: 1148: 564:
mining in the area from the French between February and May 1916. Other units active around Vimy were
533: 511: 208: 89: 735: 516: 438: 1267: 394: 189: 327: 1240: 1221: 1195: 1164: 1154: 1133: 668: 228: 173: 143: 1006: 631: 450: 224: 147: 477:
fire along no man's land. To assist the attack on the village, two further mines, known as
871: 820: 711: 593: 431: 305: 212: 131: 65: 245:
office of the Engineer-in-Chief. A second group of tunnelling companies were formed from
601: 494: 485: 445:
beneath the German positions along the front line and by preparing a series of shallow
356: 289: 238: 93: 54: 1150:
The Thirty-Fourth Division, 1915–1919: The Story of its Career from Ripon to the Rhine
813: 1279: 953: 864: 386: 301: 204: 647:
charges were fired to support the attack, including those forming a northern flank.
454: 615: 581:
charges were fired in this 7 kilometres (4.3 mi) sector of the Western Front.
378: 273: 135: 69: 1210:
The Work of the Royal Engineers in the European War 1914 -1919, – MILITARY MINING
146:
under enemy lines, as well as other underground work such as the construction of
585: 446: 281: 139: 111: 36: 300:
on 3 February 1916 and was deployed to the Western Front in northern France. A
1258:
List of tunnelling companies of the Royal Engineers, with short unit histories
1218:
Thirty-odd Feet Below Belgium: An Affair of Letters in the Great War 1915-1916
609:
charges to support the infantry attack, of which 13 (possibly 14) mines and 8
529: 479: 242: 197: 888: 1112: 277: 1168: 704: 655:
Units of 185th Tunnelling Company were the first British troops to enter
619: 382: 297: 285: 1153:(Naval & Military Press ed.). London: H. F. & G. Witherby. 370:. From its formation until the end of the war the company served under 772:"Corps History – Part 14: The Corps and the First World War (1914–18)" 548:. 185th Tunnelling Company seems to have shared this sector with the 1084: 626:
had been blown. Their reports and the experience of the Canadians at
390: 269: 200:
formally approved the tunnelling company scheme on 19 February 1915.
1263:'Men of 179th and 185th Tunnelling Companies' Paper by Simon Jones. 524:
185th Tunnelling Company next moved to the "Labyrinth" sector near
473:, intended to wreck German tunnels and create crater lips to block 656: 537: 515: 342: 334: 326: 246: 856: 1286:
Military units and formations of the British Army in World War I
812:
Anthony Byledbal, "New Zealand Tunnelling Company: Chronology" (
541: 525: 584:
On 29 March 1916, the 185th Tunnelling Company was relieved at
497:
on 11 November 1915, and eventually handed the tunnels over to
414:
Tunnelling Companies in August 1915, followed by the 185th and
1237:
The Corps of Royal Engineers: Organization and Units 1889–2018
359:; for an aerial view of the site with marked front lines, see 241:, and the appointment of an 'Inspector of Mines' at the GHQ 659:, on 17 October 1918, during the great advance to victory. 732:"Lieutenant Colonel Sir John Norton-Griffiths (1871–1930)" 808: 806: 804: 643:
were blown before the attack, while three mines and two
976: 974: 972: 970: 107: 99: 85: 75: 60: 42: 32: 18: 1192:War Underground – The Tunnellers of the Great War 852: 850: 339:Geological cross-section of the Somme battlefield 493:. 185th Tunnelling Company started work on the 924: 1001: 999: 997: 995: 993: 991: 989: 700: 698: 696: 694: 692: 690: 688: 686: 684: 164:By January 1915 it had become evident to the 8: 754: 752: 466: 1291:Tunnelling companies of the Royal Engineers 1235:Graham E. Watson & Richard A. Rinaldi, 160:Tunnelling companies of the Royal Engineers 912: 520:British-dug fighting tunnel in Vimy sector 24: 794: 792: 766: 764: 556:, which was relieved in this area by the 774:. Royal Engineers Museum. Archived from 734:. Royal Engineers Museum. Archived from 726: 724: 722: 720: 936: 680: 528:in March 1916. The German "Labyrinth" 15: 1066: 1054: 1042: 980: 900: 841: 418:Tunnelling Companies in October. The 331:Map of chalk areas in northern France 284:to raise tunnelling companies in the 7: 261:of the Royal Engineers, which was a 624:mines on the first day of the Somme 323:Mines on the first day of the Somme 14: 1083:Banning, J.; et al. (2011). 558:2nd Australian Tunnelling Company 449:from the British front line into 430:" to the French, as "Granathof" ( 80:Royal Engineer tunnelling company 259:1st Northumberland Field Company 64: 47: 437:As Allied preparations for the 422:was also present on the Somme. 857:http://www.lochnagarcrater.org 590:New Zealand Tunnelling Company 294:New Zealand Tunnelling Company 1: 1296:Tunnel warfare in World War I 1130:Underground Warfare 1914–1918 1005:The Durand Group: Vimy Ridge 1132:. Pen & Sword Military. 832:Watson & Rinaldi, p. 19. 798:Watson & Rinaldi, p. 49. 192:, and the mining specialist 714:, access date 25 April 2015 705:The Tunnelling Companies RE 453:, which would be opened at 257:, who were attached to the 1312: 1239:, Tiger Lily Books, 2018, 1030: 1018: 883:La Boisselle Study Group, 823:), access date 5 July 2015 509: 347:Plan of the area south of 320: 157: 1190:Alexander Barrie (1988). 23: 1147:Shakespear, J. (2001) . 1089:La Boisselle Study Group 1009:, access date 2016-08-03 891:), accessed 25 June 2015 874:), accessed 25 June 2015 640:176th Tunnelling Company 636:172nd Tunnelling Company 554:172nd Tunnelling Company 550:176th Tunnelling Company 499:179th Tunnelling Company 443:19 large and small mines 420:181st Tunnelling Company 124:185th Tunnelling Company 19:185th Tunnelling Company 1216:Arthur Stockwin (ed.), 239:Major-General S.R. Rice 521: 467: 428:L'îlot de La Boisselle 363: 351:with locations of the 340: 332: 255:Monmouthshire Regiment 251:1st and 3rd Battalions 172:that the Germans were 1128:Jones, Simon (2010). 738:on September 19, 2006 628:St Eloi in April 1916 546:Notre Dame de Lorette 519: 346: 338: 330: 194:John Norton-Griffiths 1220:, Parapress (2005), 1103:Dunning, R. (2015). 534:Neuville-Saint-Vaast 512:Battle of Vimy Ridge 128:tunnelling companies 90:military engineering 1045:, pp. 134–135. 925:Banning et al. 2011 778:on January 18, 2007 588:-Chantecler by the 439:Battle of the Somme 355:(top left) and the 1270:The Lochnagar Mine 870:2015-06-29 at the 819:2015-07-06 at the 710:2015-05-10 at the 522: 465:) were planted at 364: 341: 333: 1226:978-1-89859-480-2 1139:978-1-84415-962-8 1105:"Military Mining" 544:and not far from 532:was located near 117: 116: 1303: 1213: 1205: 1179: 1177: 1175: 1143: 1124: 1122: 1120: 1111:. Archived from 1109:Lochnagar Crater 1099: 1097: 1095: 1070: 1064: 1058: 1052: 1046: 1040: 1034: 1028: 1022: 1016: 1010: 1003: 984: 978: 965: 964: 962: 961: 952:. Archived from 946: 940: 934: 928: 922: 916: 910: 904: 898: 892: 881: 875: 854: 845: 839: 833: 830: 824: 810: 799: 796: 787: 786: 784: 783: 768: 759: 756: 747: 746: 744: 743: 728: 715: 702: 472: 249:miners from the 68: 53: 51: 50: 28: 16: 1311: 1310: 1306: 1305: 1304: 1302: 1301: 1300: 1276: 1275: 1254: 1245:978-171790180-4 1208: 1202: 1189: 1186: 1184:Further reading 1173: 1171: 1161: 1146: 1140: 1127: 1118: 1116: 1115:on 27 June 2015 1102: 1093: 1091: 1082: 1079: 1074: 1073: 1065: 1061: 1053: 1049: 1041: 1037: 1029: 1025: 1017: 1013: 1004: 987: 979: 968: 959: 957: 950:"List of names" 948: 947: 943: 935: 931: 923: 919: 913:Shakespear 1921 911: 907: 899: 895: 882: 878: 872:Wayback Machine 861:Military Mining 855: 848: 840: 836: 831: 827: 821:Wayback Machine 811: 802: 797: 790: 781: 779: 770: 769: 762: 757: 750: 741: 739: 730: 729: 718: 712:Wayback Machine 703: 682: 677: 665: 653: 594:Hindenburg Line 514: 508: 325: 319: 314: 162: 156: 134:created by the 132:Royal Engineers 126:was one of the 120: 48: 46: 12: 11: 5: 1309: 1307: 1299: 1298: 1293: 1288: 1278: 1277: 1274: 1273: 1265: 1260: 1253: 1252:External links 1250: 1249: 1248: 1233: 1214: 1206: 1200: 1185: 1182: 1181: 1180: 1159: 1144: 1138: 1125: 1100: 1078: 1075: 1072: 1071: 1069:, p. 135. 1059: 1057:, p. 136. 1047: 1035: 1023: 1011: 985: 983:, p. 133. 966: 941: 929: 917: 905: 903:, p. 115. 893: 876: 846: 844:, p. 114. 834: 825: 800: 788: 760: 748: 716: 679: 678: 676: 673: 672: 671: 664: 661: 652: 649: 602:Canadian Corps 510:Main article: 507: 504: 495:Lochnagar mine 357:Lochnagar mine 321:Main article: 318: 315: 313: 310: 290:British Empire 221:Sanctuary Wood 158:Main article: 155: 152: 118: 115: 114: 109: 105: 104: 101: 97: 96: 94:tunnel warfare 87: 83: 82: 77: 73: 72: 62: 58: 57: 55:United Kingdom 44: 40: 39: 34: 30: 29: 21: 20: 13: 10: 9: 6: 4: 3: 2: 1308: 1297: 1294: 1292: 1289: 1287: 1284: 1283: 1281: 1272: 1271: 1268:Simon Jones, 1266: 1264: 1261: 1259: 1256: 1255: 1251: 1246: 1242: 1238: 1234: 1231: 1227: 1223: 1219: 1215: 1211: 1207: 1203: 1201:1-871085-00-4 1197: 1193: 1188: 1187: 1183: 1170: 1166: 1162: 1160:1-84342-050-3 1156: 1152: 1151: 1145: 1141: 1135: 1131: 1126: 1114: 1110: 1106: 1101: 1090: 1086: 1081: 1080: 1076: 1068: 1063: 1060: 1056: 1051: 1048: 1044: 1039: 1036: 1032: 1027: 1024: 1020: 1015: 1012: 1008: 1002: 1000: 998: 996: 994: 992: 990: 986: 982: 977: 975: 973: 971: 967: 956:on 2015-06-29 955: 951: 945: 942: 938: 933: 930: 926: 921: 918: 915:, p. 37. 914: 909: 906: 902: 897: 894: 890: 886: 880: 877: 873: 869: 866: 862: 858: 853: 851: 847: 843: 838: 835: 829: 826: 822: 818: 815: 809: 807: 805: 801: 795: 793: 789: 777: 773: 767: 765: 761: 755: 753: 749: 737: 733: 727: 725: 723: 721: 717: 713: 709: 706: 701: 699: 697: 695: 693: 691: 689: 687: 685: 681: 674: 670: 667: 666: 662: 660: 658: 650: 648: 646: 641: 637: 633: 632:no man's land 629: 625: 621: 617: 612: 608: 603: 598: 595: 591: 587: 582: 579: 575: 571: 567: 561: 560:in May 1916. 559: 555: 551: 547: 543: 539: 535: 531: 527: 518: 513: 505: 503: 500: 496: 492: 488: 487: 482: 481: 476: 471: 470: 464: 460: 459:No 2 straight 456: 452: 451:no man's land 448: 444: 440: 435: 433: 429: 423: 421: 417: 413: 409: 404: 400: 396: 392: 388: 387:Bois Français 384: 380: 375: 373: 369: 362: 358: 354: 350: 345: 337: 329: 324: 317:Somme 1915/16 316: 311: 309: 307: 303: 299: 295: 291: 287: 283: 279: 275: 271: 266: 264: 260: 256: 252: 248: 244: 240: 235: 230: 226: 222: 218: 214: 210: 206: 205:Ypres Salient 201: 199: 195: 191: 187: 183: 179: 175: 171: 170:Western Front 167: 161: 153: 151: 149: 145: 141: 137: 133: 129: 125: 119:Military unit 113: 110: 106: 102: 98: 95: 91: 88: 84: 81: 78: 74: 71: 67: 63: 59: 56: 45: 41: 38: 35: 31: 27: 22: 17: 1269: 1236: 1217: 1209: 1191: 1172:. Retrieved 1149: 1129: 1117:. Retrieved 1113:the original 1108: 1092:. Retrieved 1088: 1085:"Tunnellers" 1077:Bibliography 1062: 1050: 1038: 1031:Boire (1992) 1026: 1019:Boire (1992) 1014: 958:. Retrieved 954:the original 944: 937:Dunning 2015 932: 920: 908: 896: 884: 879: 860: 837: 828: 780:. Retrieved 776:the original 740:. Retrieved 736:the original 669:Mine warfare 654: 644: 616:La Boisselle 610: 606: 599: 583: 562: 523: 506:Vimy 1916/17 484: 478: 462: 458: 447:Russian saps 436: 424: 379:La Boisselle 376: 368:La Boisselle 365: 352: 349:La Boisselle 312:Unit history 274:South Africa 267: 217:Railway Wood 202: 190:George Fowke 188:, Brigadier 163: 148:deep dugouts 136:British Army 123: 121: 70:British Army 586:Roclincourt 296:arrived at 282:New Zealand 263:Territorial 140:World War I 112:World War I 108:Engagements 103:"The Moles" 100:Nickname(s) 37:World War I 1280:Categories 1174:19 October 1067:Jones 2010 1055:Jones 2010 1043:Jones 2010 981:Jones 2010 960:2015-06-26 901:Jones 2010 842:Jones 2010 782:2015-12-02 742:2015-12-02 675:References 651:Douai 1918 622:where the 536:, between 530:stronghold 463:No 5 right 397:moved the 372:First Army 353:Glory Hole 306:Australian 243:Saint-Omer 198:War Office 154:Background 1021:pp. 22–23 486:Lochnagar 455:zero hour 286:Dominions 278:Australia 229:The Bluff 182:Kitchener 868:Archived 817:Archived 708:Archived 663:See also 620:Fricourt 475:enfilade 383:Fricourt 302:Canadian 298:Plymouth 1169:6148340 1119:26 June 1094:26 June 885:History 491:see map 288:of the 253:of the 225:St Eloi 213:Hill 60 168:at the 138:during 130:of the 43:Country 1243:  1230:online 1224:  1198:  1167:  1157:  1136:  1007:online 889:online 865:online 814:online 645:Wombat 611:Wombat 607:Wombat 469:L'îlot 432:German 391:Carnoy 270:Canada 196:, the 178:French 174:mining 61:Branch 52:  33:Active 1033:p. 20 657:Douai 578:255th 574:184th 570:182nd 566:175th 538:Arras 480:Y Sap 416:252nd 412:179th 408:178th 403:183rd 399:174th 395:Fowke 247:Welsh 209:Hooge 144:mines 1241:ISBN 1222:ISBN 1196:ISBN 1176:2014 1165:OCLC 1155:ISBN 1134:ISBN 1121:2015 1096:2015 618:and 600:The 576:and 542:Vimy 540:and 526:Vimy 483:and 461:and 410:and 401:and 389:and 361:here 280:and 227:and 180:and 122:The 86:Role 76:Type 234:BEF 207:at 186:BEF 166:BEF 1282:: 1232:). 1194:. 1163:. 1107:. 1087:. 988:^ 969:^ 859:, 849:^ 803:^ 791:^ 763:^ 751:^ 719:^ 683:^ 572:, 568:, 393:. 385:, 381:, 374:. 276:, 272:, 223:, 219:, 215:, 211:, 92:, 1247:. 1228:( 1212:. 1204:. 1178:. 1142:. 1123:. 1098:. 963:. 939:. 927:. 887:( 863:( 785:. 745:.

Index


World War I
United Kingdom

British Army
Royal Engineer tunnelling company
military engineering
tunnel warfare
World War I
tunnelling companies
Royal Engineers
British Army
World War I
mines
deep dugouts
Tunnelling companies of the Royal Engineers
BEF
Western Front
mining
French
Kitchener
BEF
George Fowke
John Norton-Griffiths
War Office
Ypres Salient
Hooge
Hill 60
Railway Wood
Sanctuary Wood

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.