Maredelanto Compania Naviera SA v Bergbau-Handel GmbH

Source 📝

31: 172:
rights which he has lost were capable by the terms of the contract of being rendered either less valuable or valueless in certain events, and if it can be shown that those events were, at the date of acceptance of the repudiation, predestined to happen, then in my view the damages which he can recover are not more than the true value, if any, of the rights which he has lost, having regard to those predestined events.
128:, still discharging cargo from her previous voyage. It was physically impossible for her to finish discharging and reach Haiphong by 20 July. The charterers gave notice cancelling the charter. The owners treated this as a repudiation and claimed damages, which were the subject of arbitration and of an appeal to Mocatta J. On further appeal, there were three issues: 171:
In my view, where there is an anticipatory breach of contract, the breach is the repudiation once it has been accepted, and the other party is entitled to recover by way of damages the true value of the contractual rights which he has thereby lost; subject to his duty to mitigate. If the contractual
147:
On the first issue, all three members of the court decided in favour of the charterers, Bergbau, and against the owners, Maredelanto, that 'expected ready' was a condition of the contract. On the second issue, Lord Denning held that the charterers had not repudiated the contract by cancelling on 17
200:
case, from the viewpoint of the shipping trade, was the "wait and see" principle. That is, one had to "wait and see" whether the breach had indeed "denied the plaintiff of the main benefit". Given the huge daily cost of hiring and running a ship, parties could not afford to wait. The shipping
176:
All members of the court were viewing the case as from the date of acceptance of the repudiation (although only Megaw LJ said so in terms). They were not taking account of later events. They were recognising, as was obvious on the facts as found, that the value of the contractual right which the
160:, in agreement with the arbitrators, who were themselves agreed, held that they had suffered no damage (p 197): "Seeing that the charterers would, beyond doubt, have cancelled, I am clearly of opinion that the shipowners suffered no loss: and would be entitled at most to nominal damages." 191:
had helped to clarify the distinction between breach of "condition" (where both damages and repudiation lie) and breach of "warranty" (whose sole remedy is damages). The court declared that the victim of a breach of contract could lawfully repudiate only if the "breach had denied the
120:"Should the vessel not be ready to load (whether in berth or not) on or before July 20, 1965, charterers have the option of cancelling this contract, such option to be declared, if demanded, at least 48 hours before vessel's expected arrival at port of loading". 163:
Edmund Davies LJ agreed (p 202): "One must look at the contract as a whole, and if it is clear that the innocent party has lost nothing, he should recover no more than nominal damages for the loss of his right to have the whole contract completed."
115:
dated 25 May 1965 the shipowners ("the owners") stated that the ship was "expected ready to load under this charter about July 1, 1965". The charterparty also provided, in the first sentence of the cancelling clause,
196:
of the main benefit of the contract". Here, even though the vessel's unseaworthiness (through insufficient and incompetent crew) might seem important, its effect was only minor. The problem with the
30: 239: 187: 288: 231: 293: 177:
owners had lost, as of the date of acceptance of the repudiation, was nil because the charter was bound to be lawfully cancelled three days later.
132:
Was the "expected readiness" clause was a condition of which the owners were in breach, entitling the charterers to terminate the charter contract?
138:
Was the damage suffered by the owners (on the assumption that the charterers' premature cancellation had been a repudiation) to be considered?
283: 259:
The concepts of "conditions" and "warranties" were derived from the law of sale of goods, and later adopted by the general law of contract.
149: 135:
If so, had the charterers properly repudiated the contract by cancelling on 17 July, three days before the specified 20 July deadline?
66: 223: 62: 93: 209:
that certain breaches such as breach of an "Expected Readiness to Load" clause (a type of
206: 89: 49: 277: 157: 112: 153: 70: 193: 125: 108: 210: 213:) were inherently repudiatory, with no need to "wait and see". 205:
decision, as it effectively established a new commercial
240:
Golden Strait Corporation v Nippon Yusen Kubishka Kaisha
268:
Cost may amount to tens of thousands of dollars per day
111:
and there load a cargo for delivery in Europe. In the
188:
Hong Kong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha
80:
Maredelanto Compania Naviera SA v Bergbau-Handel GmbH
56: 45: 37: 23: 169: 232:L Schuler AG v Wickman Machine Tool Sales Ltd 8: 29: 20: 289:Court of Appeal (England and Wales) cases 156:held that they had. On the third issue, 252: 96:case, concerning breach of contract. 7: 14: 167:Megaw LJ (at pp 209–210) stated: 124:On 17 July 1965 the ship was at 294:1970 in United Kingdom case law 1: 224:Bunge Corporation v Tradax SA 284:English termination case law 310: 61: 28: 174: 122: 118: 107:was fixed to sail to 94:English contract law 201:trade welcomed the 105:The Mihalis Angelos 86:The Mihalis Angelos 24:The Mihalis Angelos 16:English legal case 185:The 1962 case of 76: 75: 301: 269: 266: 260: 257: 150:Edmund Davies LJ 67:Edmund Davies LJ 33: 21: 309: 308: 304: 303: 302: 300: 299: 298: 274: 273: 272: 267: 263: 258: 254: 250: 219: 203:Mihalis Angelos 183: 145: 102: 63:Lord Denning MR 41:Court of Appeal 17: 12: 11: 5: 307: 305: 297: 296: 291: 286: 276: 275: 271: 270: 261: 251: 249: 246: 245: 244: 236: 228: 218: 215: 182: 179: 144: 141: 140: 139: 136: 133: 101: 98: 74: 73: 59: 58: 54: 53: 47: 43: 42: 39: 35: 34: 26: 25: 15: 13: 10: 9: 6: 4: 3: 2: 306: 295: 292: 290: 287: 285: 282: 281: 279: 265: 262: 256: 253: 247: 242: 241: 237: 234: 233: 229: 226: 225: 221: 220: 216: 214: 212: 208: 204: 199: 198:Hong Kong Fir 195: 190: 189: 180: 178: 173: 168: 165: 161: 159: 155: 151: 142: 137: 134: 131: 130: 129: 127: 121: 117: 114: 110: 106: 99: 97: 95: 91: 88: 87: 82: 81: 72: 68: 64: 60: 57:Case opinions 55: 51: 48: 44: 40: 36: 32: 27: 22: 19: 264: 255: 238: 230: 227:2 All ER 513 222: 202: 197: 186: 184: 181:Significance 175: 170: 166: 162: 158:Lord Denning 146: 123: 119: 113:charterparty 104: 103: 85: 84: 79: 78: 77: 18: 52:, 1 QB 164 278:Categories 248:References 207:convention 148:July, but 90:EWCA Civ 4 50:EWCA Civ 4 194:plaintiff 126:Hong Kong 46:Citations 217:See also 154:Megaw LJ 143:Judgment 109:Haiphong 71:Megaw LJ 243:UKHL 12 235:AC 235 92:is an 100:Facts 38:Court 152:and 69:and 211:NOR 83:or 280:: 65:,

Index


EWCA Civ 4
Lord Denning MR
Edmund Davies LJ
Megaw LJ
EWCA Civ 4
English contract law
Haiphong
charterparty
Hong Kong
Edmund Davies LJ
Megaw LJ
Lord Denning
Hong Kong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha
plaintiff
convention
NOR
Bunge Corporation v Tradax SA
L Schuler AG v Wickman Machine Tool Sales Ltd
Golden Strait Corporation v Nippon Yusen Kubishka Kaisha
Categories
English termination case law
Court of Appeal (England and Wales) cases
1970 in United Kingdom case law