477: 420: 530: 31: 461: 514: 595: 610: 216:, which applied for resource consent for a 4.6 MW station in August 2008. The scheme was opposed by environmentalists and kayakers some of whom were angry that the 220:
were not notified nationwide. The proposal was approved and it included a concession granted by the Department of Conservation to build structures on public land.
454: 392: 507: 571: 615: 600: 590: 447: 66: 500: 245: 231:, and the scheme was finally commissioned in December 2020. Ownership was transferred to the Southern Generation partnership on completion. 227:
The development rights were purchased by Pioneer Energy in 2014. Construction began in 2018. Construction was delayed by a slip and by the
369: 240: 273: 170: 564: 605: 213: 343: 557: 476: 106: 294: 419: 152: 228: 541: 484: 431: 427: 217: 529: 537: 221: 30: 584: 202: 198: 206: 194: 393:"Moving slip near Murchison forces road closure, impedes work on power project" 224:
did not see that there would be any conservation gain in giving the approval.
140: 81: 68: 209:
and pipes it through a 2.4 km long buried pipeline to a power station.
317: 179: 205:
of New Zealand. The project takes water from a series of intake weirs at
545: 488: 435: 274:"Matiri hydro scheme officially opens near Murchison" 483:
This article about a New Zealand power station is a
370:"Two new hydro stations coming for the South Island" 166: 161: 151: 146: 136: 131: 123: 115: 105: 97: 60: 52: 44: 23: 565: 508: 455: 8: 295:"NZ Energy applies for Matiri Hydro consent" 596:Hydroelectric power stations in New Zealand 572: 558: 515: 501: 462: 448: 267: 265: 263: 261: 193:is a run-of-river hydroelectric scheme at 20: 611:New Zealand building and structure stubs 257: 212:The project was originally proposed by 171:Related media on Commons 246:List of power stations in New Zealand 7: 526: 524: 473: 471: 416: 414: 272:Cherie Sivignon (11 December 2020). 318:"Split over Lake Matiri hydro plan" 316:Kidson, Sally (25 September 2008). 544:. You can help Knowledge (XXG) by 487:. You can help Knowledge (XXG) by 434:. You can help Knowledge (XXG) by 391:Cherie Sivignon (22 August 2019). 14: 344:"DOC's hydro approval damns bats" 241:Electricity sector in New Zealand 528: 475: 418: 368:Ben Bootsma (6 September 2018). 132:Thermal power station 29: 616:Tasman District geography stubs 601:Hydroelectric power plant stubs 591:Hydroelectricity in New Zealand 297:. Whitewater NZ. 23 August 2008 119:Southern Generation Partnership 35:Intake weir of the hydro scheme 342:Murdock, Helen (26 May 2011). 56:Matiri Valley, Tasman District 1: 632: 523: 470: 413: 214:New Zealand Energy Limited 176: 40: 28: 540:geography article is a 153:Nameplate capacity 16:NZ hydroelectric scheme 82:41.66194°S 172.33444°E 426:This article about a 147:Power generation 107:Commission date 87:-41.66194; 172.33444 606:Power station stubs 162:External links 78: /  553: 552: 496: 495: 443: 442: 430:power plant is a 229:COVID-19 pandemic 218:resource consents 187: 186: 137:Primary fuel 623: 574: 567: 560: 532: 525: 517: 510: 503: 479: 472: 464: 457: 450: 422: 415: 405: 404: 402: 400: 388: 382: 381: 379: 377: 365: 359: 358: 356: 354: 339: 333: 332: 330: 328: 313: 307: 306: 304: 302: 291: 285: 284: 282: 280: 269: 180:edit on Wikidata 111:11 December 2020 93: 92: 90: 89: 88: 83: 79: 76: 75: 74: 71: 33: 21: 631: 630: 626: 625: 624: 622: 621: 620: 581: 580: 579: 578: 538:Tasman District 522: 521: 469: 468: 411: 409: 408: 398: 396: 390: 389: 385: 375: 373: 367: 366: 362: 352: 350: 341: 340: 336: 326: 324: 315: 314: 310: 300: 298: 293: 292: 288: 278: 276: 271: 270: 259: 254: 237: 222:Forest and Bird 183: 86: 84: 80: 77: 72: 69: 67: 65: 64: 36: 17: 12: 11: 5: 629: 627: 619: 618: 613: 608: 603: 598: 593: 583: 582: 577: 576: 569: 562: 554: 551: 550: 533: 520: 519: 512: 505: 497: 494: 493: 480: 467: 466: 459: 452: 444: 441: 440: 423: 407: 406: 383: 360: 334: 308: 286: 256: 255: 253: 250: 249: 248: 243: 236: 233: 191:Matiri Project 185: 184: 177: 174: 173: 168: 164: 163: 159: 158: 155: 149: 148: 144: 143: 138: 134: 133: 129: 128: 127:Pioneer Energy 125: 121: 120: 117: 113: 112: 109: 103: 102: 99: 95: 94: 62: 58: 57: 54: 50: 49: 46: 42: 41: 38: 37: 34: 26: 25: 24:Matiri Project 15: 13: 10: 9: 6: 4: 3: 2: 628: 617: 614: 612: 609: 607: 604: 602: 599: 597: 594: 592: 589: 588: 586: 575: 570: 568: 563: 561: 556: 555: 549: 547: 543: 539: 534: 531: 527: 518: 513: 511: 506: 504: 499: 498: 492: 490: 486: 481: 478: 474: 465: 460: 458: 453: 451: 446: 445: 439: 437: 433: 429: 428:hydroelectric 424: 421: 417: 412: 394: 387: 384: 371: 364: 361: 349: 345: 338: 335: 323: 319: 312: 309: 296: 290: 287: 275: 268: 266: 264: 262: 258: 251: 247: 244: 242: 239: 238: 234: 232: 230: 225: 223: 219: 215: 210: 208: 204: 200: 196: 192: 181: 175: 172: 169: 165: 160: 156: 154: 150: 145: 142: 139: 135: 130: 126: 122: 118: 114: 110: 108: 104: 100: 96: 91: 63: 59: 55: 51: 47: 43: 39: 32: 27: 22: 19: 546:expanding it 535: 489:expanding it 482: 436:expanding it 425: 410: 397:. Retrieved 386: 374:. Retrieved 363: 351:. Retrieved 347: 337: 325:. Retrieved 321: 311: 299:. Retrieved 289: 277:. Retrieved 226: 211: 203:South Island 199:Matiri River 190: 188: 18: 348:Nelson Mail 322:Nelson Mail 207:Lake Matiri 195:Lake Matiri 124:Operator(s) 101:Operational 85: / 61:Coordinates 48:New Zealand 585:Categories 327:30 October 252:References 141:Hydropower 73:172°20′4″E 70:41°39′43″S 235:See also 197:and the 116:Owner(s) 53:Location 395:. Stuff 372:. Stuff 201:in the 167:Commons 45:Country 399:1 July 376:1 July 353:26 May 301:1 July 279:1 July 157:4.6 MW 98:Status 536:This 178:[ 542:stub 485:stub 432:stub 401:2021 378:2021 355:2011 329:2008 303:2021 281:2021 189:The 587:: 346:. 320:. 260:^ 573:e 566:t 559:v 548:. 516:e 509:t 502:v 491:. 463:e 456:t 449:v 438:. 403:. 380:. 357:. 331:. 305:. 283:. 182:]

Index


41°39′43″S 172°20′4″E / 41.66194°S 172.33444°E / -41.66194; 172.33444
Commission date
Hydropower
Nameplate capacity
Related media on Commons
edit on Wikidata
Lake Matiri
Matiri River
South Island
Lake Matiri
New Zealand Energy Limited
resource consents
Forest and Bird
COVID-19 pandemic
Electricity sector in New Zealand
List of power stations in New Zealand




"Matiri hydro scheme officially opens near Murchison"
"NZ Energy applies for Matiri Hydro consent"
"Split over Lake Matiri hydro plan"
"DOC's hydro approval damns bats"
"Two new hydro stations coming for the South Island"
"Moving slip near Murchison forces road closure, impedes work on power project"
Stub icon
hydroelectric
stub

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.