Mount Cass Wind Farm

Source 📝

278:. The court received submissions from 72 parties; supporters noted the importance of renewal energy to achieve government policy, while opponents were concerned with damage to the limestone ecosystems and habitats, and the noise and visual impact on locals. The court granted consent to a significantly modified design in December 2011. The judge noted that the area was not "an untouched, pristine natural environment - fire and farming have depleted and degraded the vegetation and habitat for fauna', and that the proposed land offset and conservation management measures would improve biodiversity in the area. The consent was originally due to lapse in February 2020, but was extended until 2025. 336: 322: 350: 304:. Marlborough Lines bought a 50% financial interest in the wind farm through its subsidiary Energy Marlborough, which it had created in 2021 to get into power generation. The two entities now jointly owned a company called GreenPower New Zealand which was now behind the project. MainPower said it expected construction to begin in 2024. 273:
By May 2009 the district council had declined the consents, on the basis that the site was an outstanding natural feature of national significance which the wind farm would degrade. Groups such as Forest and Bird and the Mt Cass Protection Society supported the decision to decline. MainPower appealed
269:
in June 2008, with public consultation on the consent starting in January 2009. MainPower's managing director said of the 6.5 km long wind farm that it had "the potential to provide enough electricity to supply all the homes in the Hurunui and Waimakariri districts. He acknowledged, though, that
260:
MainPower, a North Canterbury lines company, initially proposed the wind farm in 2006. It erected a 50 meter monitoring mast in April 2006, with plans to lodge resource consents in 2007. The original proposal was for a wind farm of between 15 and 25 MW, but subsequently increased to between 35 and
307:
In May 2024 Marlborough Lines refused further funding for the project. In July 2024 it ended its involvement in the project, though it still owns 50% of GreenPower New Zealand. Marlborough Lines would not say why it had left the project. MainPower has not commented on what its next steps will be.
223:
in 2009 but approved by the Environment Court in 2011. Preliminary work began in 2019 with the intent to be completed by late 2021, but was delayed by animal conservation concerns among other issues. As of July 2024 the project's status is unclear after a major investor pulled out.
297:, and was instead moving to a multi-contract model. In June 2023 MainPower stated that two permanent 76.5m meteorological masts had been installed to provide ongoing wind data, further geotechnical work had been undertaken, and contractors had been engaged for the main works. 281:
Preliminary work on construction began in December 2019, with the intent to complete construction by late 2021. Work was interrupted in December 2020 by the possible discovery of a colony of critically endangered
885: 429: 638: 880: 286:
on a nearby property. In April 2021 wildlife monitoring determined that there were no bats present. Construction was then scheduled to begin in late 2021.
730: 289:
In September 2021 MainPower announced that the project was "transitioning to an alternative delivery model". The company had intended to operate with a
53: 393: 370: 753: 783: 707: 583: 662: 645: 486: 455: 283: 240:
of 94.6 megawatts, enough to power 40,000 homes. As of 2019 the proposed wind farm would have been the largest in the
293:
contract with General Electric. MainPower said this model had become uneconomic particularly due to the effects of
365: 301: 100: 266: 220: 865: 610: 355: 206: 41: 835: 685: 400: 335: 270:
MainPower had heard concerns over the ecological impact during its own consultation of the public.
245: 327: 237: 175: 761: 791: 294: 275: 262: 216: 341: 233: 874: 241: 731:"Construction of South Island's largest wind farm to start soon in Nth Canterbury" 639:"Resource Consent Application - Report and Determination by Hearing Commissioners" 813: 615: 349: 249: 141:
Generates electricity up to 122 km/hr, and withstands gusts up to 350 km/hr
209:
region of New Zealand. The project dates back to 2006, and the current plan by
317: 68: 55: 430:"South Island's biggest wind farm to be constructed on Canterbury's Mt Cass" 210: 112: 96: 187: 290: 202: 860: 814:"Lines companies unite to deliver South Island's largest wind farm" 487:"Plans for massive wind farm on South Island ridgeline up in air" 236:
SWT-DD-120 wind turbines on Mount Cass, Waipara. It would have a
708:"New research confirms there are no long-tailed bats at Mt Cass" 213:
is to construct 22 wind turbines along a ridge of Mount Cass.
300:
In September 2023, MainPower announced a partnership with
399:(Press release). MainPower. 27 April 2009. Archived from 754:"Mt Cass Wind Farm transitions to new delivery model" 527:. 11 October 2006. p. A4 – via EBSCOHost. 174: 145: 137: 129: 121: 111: 106: 92: 84: 47: 37: 29: 20: 572:. 28 June 2008. p. A21 – via EBSCOHost. 557:. 3 August 2007. p. A4 – via EBSCOHost. 542:. 29 March 2007. p. A4 – via EBSCOHost. 512:. 10 March 2006. p. A6 – via EBSCOHost. 886:Buildings and structures in the Canterbury Region 686:"Threatened bats found near planned wind farm" 394:"MainPower appeals Mt Cass wind farm decision" 201:is a proposed wind farm to be located east of 8: 866:A Ridge Too Far - Mt Cass Protection Society 861:Mainpower - Mount Cass Wind Farm information 644:. Hurunui District Council. Archived from 17: 836:"Mt Cass Wind Farm exploring next steps" 456:"Farm's management to benefit ecosystem" 553:"Super-sized wind farm plan revealed". 382: 568:"Maelstrom swirls around wind farm". 508:"Wind-farm trials start in N Canty". 428:Emma Dangerfield (16 December 2019). 371:List of power stations in New Zealand 7: 480: 478: 476: 449: 447: 423: 421: 388: 386: 232:The current design would install 22 684:David Williams (22 December 2020). 881:Proposed wind farms in New Zealand 710:. Mt Cass Wind Farm. 13 April 2021 14: 454:Gorman, Paul (19 December 2011). 244:, though today the also-proposed 838:. Mt Cass Wind Farm. 21 May 2024 348: 334: 320: 729:Robyn Bristow (22 April 2021). 538:"Windfarm may launch in 2009". 523:"Consents lodged in new year". 1: 609:David Williams (7 May 2009). 219:was initially refused by the 784:"Project Update - June 2023" 637:Paul Rogers (2 April 2009). 284:New Zealand long-tailed bats 902: 665:. Hurunui District Council 485:Ian Allen (19 July 2024). 138:Rated wind speed 611:"Wind farm plan rejected" 366:Wind power in New Zealand 302:Marlborough Lines Limited 184: 162:Siemens Gamesa SWT-DD-120 154: 150: 25: 788:www.mtcasswindfarm.co.nz 758:www.mtcasswindfarm.co.nz 267:Hurunui District Council 221:Hurunui District Council 159:Make and model 356:Renewable energy portal 176:Nameplate capacity 69:43.07500°S 172.83750°E 584:"'Support' wind farm" 489:. Marlborough Express 261:63MW. It applied for 205:on Mount Cass in the 146:Power generation 752:Farm, Mt Cass Wind. 274:the decision to the 199:Mount Cass Wind Farm 74:-43.07500; 172.83750 21:Mount Cass Wind Farm 816:. 28 September 2023 733:. Otago Daily Times 663:"Mt Cass Wind Farm" 246:Southland Wind Farm 130:Rotor diameter 65: /  328:New Zealand portal 238:maximum generation 167:Units planned 651:on 15 April 2012. 590:. 31 January 2009 276:Environment Court 252:would be larger. 195: 194: 101:Marlborough Lines 893: 848: 847: 845: 843: 832: 826: 825: 823: 821: 810: 804: 803: 801: 799: 790:. Archived from 780: 774: 773: 771: 769: 760:. Archived from 749: 743: 742: 740: 738: 726: 720: 719: 717: 715: 704: 698: 697: 695: 693: 681: 675: 674: 672: 670: 659: 653: 652: 650: 643: 634: 628: 627: 625: 623: 606: 600: 599: 597: 595: 580: 574: 573: 565: 559: 558: 550: 544: 543: 535: 529: 528: 520: 514: 513: 505: 499: 498: 496: 494: 482: 471: 470: 468: 466: 451: 442: 441: 439: 437: 425: 416: 415: 413: 411: 405: 398: 390: 358: 353: 352: 344: 339: 338: 330: 325: 324: 323: 263:resource consent 217:Resource consent 188:edit on Wikidata 170:22 x 4.3 MW 80: 79: 77: 76: 75: 70: 66: 63: 62: 61: 58: 18: 901: 900: 896: 895: 894: 892: 891: 890: 871: 870: 857: 852: 851: 841: 839: 834: 833: 829: 819: 817: 812: 811: 807: 797: 795: 794:on 20 July 2023 782: 781: 777: 767: 765: 764:on 20 July 2023 751: 750: 746: 736: 734: 728: 727: 723: 713: 711: 706: 705: 701: 691: 689: 683: 682: 678: 668: 666: 661: 660: 656: 648: 641: 636: 635: 631: 621: 619: 608: 607: 603: 593: 591: 582: 581: 577: 567: 566: 562: 552: 551: 547: 537: 536: 532: 522: 521: 517: 507: 506: 502: 492: 490: 484: 483: 474: 464: 462: 453: 452: 445: 435: 433: 427: 426: 419: 409: 407: 403: 396: 392: 391: 384: 379: 362: 361: 354: 347: 340: 333: 326: 321: 319: 314: 258: 230: 191: 122:Hub height 107:Wind farm 73: 71: 67: 64: 59: 56: 54: 52: 51: 12: 11: 5: 899: 897: 889: 888: 883: 873: 872: 869: 868: 863: 856: 855:External links 853: 850: 849: 827: 805: 775: 744: 721: 699: 676: 654: 629: 601: 575: 560: 545: 530: 515: 500: 472: 443: 417: 406:on 14 May 2010 381: 380: 378: 375: 374: 373: 368: 360: 359: 345: 342:Weather portal 331: 316: 315: 313: 310: 257: 254: 234:Siemens Gamesa 229: 226: 193: 192: 185: 182: 181: 178: 172: 171: 168: 164: 163: 160: 156: 155: 152: 151: 148: 147: 143: 142: 139: 135: 134: 131: 127: 126: 123: 119: 118: 115: 109: 108: 104: 103: 94: 90: 89: 86: 82: 81: 49: 45: 44: 39: 35: 34: 31: 27: 26: 23: 22: 13: 10: 9: 6: 4: 3: 2: 898: 887: 884: 882: 879: 878: 876: 867: 864: 862: 859: 858: 854: 837: 831: 828: 815: 809: 806: 793: 789: 785: 779: 776: 763: 759: 755: 748: 745: 732: 725: 722: 709: 703: 700: 687: 680: 677: 664: 658: 655: 647: 640: 633: 630: 618: 617: 612: 605: 602: 589: 585: 579: 576: 571: 564: 561: 556: 549: 546: 541: 534: 531: 526: 519: 516: 511: 504: 501: 488: 481: 479: 477: 473: 461: 457: 450: 448: 444: 431: 424: 422: 418: 402: 395: 389: 387: 383: 376: 372: 369: 367: 364: 363: 357: 351: 346: 343: 337: 332: 329: 318: 311: 309: 305: 303: 298: 296: 292: 287: 285: 279: 277: 271: 268: 264: 255: 253: 251: 247: 243: 239: 235: 227: 225: 222: 218: 214: 212: 208: 204: 200: 189: 183: 179: 177: 173: 169: 166: 165: 161: 158: 157: 153: 149: 144: 140: 136: 132: 128: 124: 120: 116: 114: 110: 105: 102: 98: 95: 91: 87: 83: 78: 50: 46: 43: 40: 36: 32: 28: 24: 19: 16: 840:. Retrieved 830: 818:. Retrieved 808: 796:. Retrieved 792:the original 787: 778: 766:. Retrieved 762:the original 757: 747: 735:. Retrieved 724: 712:. Retrieved 702: 690:. Retrieved 679: 667:. Retrieved 657: 646:the original 632: 620:. Retrieved 614: 604: 592:. Retrieved 587: 578: 569: 563: 554: 548: 539: 533: 524: 518: 509: 503: 491:. Retrieved 463:. Retrieved 459: 434:. Retrieved 408:. Retrieved 401:the original 306: 299: 288: 280: 272: 259: 242:South Island 231: 215: 198: 196: 180:94.6 MW 15: 820:29 December 616:Stuff.co.nz 250:The Catlins 125:76.5 m 72: / 60:172°50′15″E 48:Coordinates 33:New Zealand 875:Categories 688:. Newsroom 669:1 December 410:6 November 377:References 207:Canterbury 133:120 m 42:Canterbury 570:The Press 555:The Press 540:The Press 525:The Press 510:The Press 265:from the 211:MainPower 97:MainPower 57:43°4′30″S 312:See also 295:COVID-19 228:Proposal 93:Owner(s) 38:Location 842:12 July 798:20 July 768:20 July 737:27 June 714:27 June 692:27 June 622:27 June 594:30 July 493:19 July 465:31 July 436:27 June 432:. Stuff 291:turnkey 256:History 203:Waipara 117:Onshore 88:Planned 30:Country 85:Status 649:(PDF) 642:(PDF) 588:Stuff 460:Stuff 404:(PDF) 397:(PDF) 186:[ 844:2024 822:2023 800:2023 770:2023 739:2021 716:2021 694:2021 671:2021 624:2021 596:2024 495:2024 467:2024 438:2021 412:2009 197:The 113:Type 248:in 99:, 877:: 786:. 756:. 613:. 586:. 475:^ 458:. 446:^ 420:^ 385:^ 846:. 824:. 802:. 772:. 741:. 718:. 696:. 673:. 626:. 598:. 497:. 469:. 440:. 414:. 190:]

Index

Canterbury
43°4′30″S 172°50′15″E / 43.07500°S 172.83750°E / -43.07500; 172.83750
MainPower
Marlborough Lines
Type
Nameplate capacity
edit on Wikidata
Waipara
Canterbury
MainPower
Resource consent
Hurunui District Council
Siemens Gamesa
maximum generation
South Island
Southland Wind Farm
The Catlins
resource consent
Hurunui District Council
Environment Court
New Zealand long-tailed bats
turnkey
COVID-19
Marlborough Lines Limited
New Zealand portal
icon
Weather portal
icon
Renewable energy portal
Wind power in New Zealand

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.