217:: Change the poor industry practice of producing information to individual standards and throwing it ‘over the wall’ to the next person in the supply chain who then reproduces their own information. Using an agreed standard for the project, spatially co-ordinated and high-quality 2D information will then be produced for the parties involved.
113:
Most construction projects are complex and involve co-ordination between many project participants both on- and off-site. As projects have increased in size and complexity, the number of participants involved in a single project has also increased. To improve collaboration between participants, the
117:
Its purpose was to support live construction project teams, as they collaborate to deliver projects, by helping them apply the appropriate technologies. It worked through a team of partners representing each stage of the project process, with the objective of improving project and business
162:
Avanti mobilised existing technologies to improve business performance by increasing the quality of information and predictability of outcomes and by reducing risk and waste. The core of the Avanti approach to a project's whole life cycle was based on team-working and access to a common
167:. All CAD information was generated with the same origin, orientation and scale, and organised in layers that could be shared. All layers and CAD model files were named consistently within a specific Avanti convention to allow others to find the relevant CAD data.
286:
Constructing
Excellence is developing a self-sustaining business to support roll out of the Avanti methodology to the UK construction industry. It will also draw on the results of other DTI-supported collaborative research such as
159:, and on sharing of information, drawings and schedules, in an agreed and consistent manner. The Avanti approach was supported by handbooks, toolkits and on-site mentoring and was reliant on advice and materials provided by CPIC.
152:) that had previously gained too little market penetration to have significant impact on the sector. The objective was to deliver improved project and business performance by using ICT to support collaborative working.
77:
meeting of 1910 which stated "Architectural information is invariably inaccurate, ambiguous and incomplete". By the 1940s, the impact of this was valued at an additional 10% to the construction cost. By 1994 the
114:
industry needs tools that work well, appropriate processes to implement them, and the right approach from the people involved. Tackling these points was at the heart of the Avanti action research programme.
246:. Since the handover, Constructing Excellence endeavoured to promote the savings demonstrated on live projects. Further work was also carried out to make Avanti part of the update of
192:- comprising typical design management processes, information management processes, guidance on detailed task management and typical responsibilities of delivery team leaders.
97:) that recommended a common format and disciplined approach to reduce the problem. These suggestions were proven on DTI-funded projects and case studies at Endeavour House at
390:
525:
446:
47:
33:
175:
Learning from early projects, Avanti produced practical working documentation and tested the methods on live projects. This information supplemented the CPIC document
475:
480:
505:
515:
300:
176:
146:
119:
94:
398:
530:
535:
359:
343:
186:- advice on classification standards, spatial and technical co-ordination, example file and directory structures, and naming conventions.
105:, which showed that significant savings in project cost and drawing production could be made by addressing people and process issues.
19:
422:
British
Standards, BS 1192:2007 Collaborative production of architectural, engineering and construction information. Code of practice
139:
410:
387:
520:
85:
suggested waste in the industry accounted for 25-30% of project costs. This figure is supported by earlier publications from the
443:
465:
86:
145:
To reduce the risks involved in adopting new working methods, Avanti brought together areas of current best practice (such as
206:
authoring information in a common data environment and controlling the sharing of information in a multi-author environment
230:
325:
223:: Implementation of those same principles to generate 3D project models to produce 2D drawings and material measurement.
510:
500:
61:
The Avanti programme aimed to help overcome problems caused by incomplete, inaccurate and ambiguous information.
485:
432:
421:
135:
243:
98:
55:
123:
50:
with the support of most of the largest UK firms in the construction industry. Avanti also involved the
155:
Avanti focused on early access to all project information by all partners, on early involvement of the
179:
and addressed problems of incomplete, inaccurate and ambiguous information. Avanti guidance included:
93:(BSRIA), which led to reports in 1987 from the Coordinating Committee for Project Information (now
70:
363:
340:
164:
247:
102:
43:
450:
394:
347:
329:
242:
In July 2006, the Avanti DTI Project documentation and brand ownership was transferred to
262:
Early commitment offering up to 80% saving on implementation cost on medium size project.
58:
and Co-Construct, a network of five construction research and information organizations.
494:
470:
79:
51:
156:
37:
18:
233:
systems. Each live project captures the lessons learned and the benefits gained.
149:
203:
guidance on ensuring the software chain supported the design and supply chains
322:
265:
50-85% saving on effort spent receiving information and formatting for reuse.
138:
systems could revolutionise projects, provided they were used for more than
122:(ICT) to support collaborative working. It set out to show the advantages of
36:
in 2002 to formulate an approach to collaborative working in order to enable
131:
127:
40:
274:
50% saving on time spent to assess tenders and award sub-contracts.
200:
a business case on the commercial imperatives for collaborative ICT
210:
For most projects, using this guidance consisted of three phases:
90:
17:
268:
60-80% saving on effort spent finding information and documents.
74:
46:
to work together effectively. The project was promoted by the
134:
rather than a drawing cabinet, and aimed to demonstrate that
30:
258:
Evaluation of the impacts of the Avanti project showed:
271:
75–80% saving in effort to achieve design co-ordination.
277:
50% saving on effort in sub-contractor design approval.
323:
91:
Building
Services Research and Information Association
229:: Full implementation of 3D object-oriented and
177:Code of Procedure for the Construction Industry
318:
316:
8:
250:. The BS 5555 committee coded the methods.
52:International Alliance for Interoperability
120:information and communication technologies
526:2002 establishments in the United Kingdom
73:report (1965) printed an extract from an
399:Royal Institution of Chartered Surveyors
312:
411:Modern Building Services (MBS) Journal
383:
381:
360:"Full list of collaborative companies"
196:The advice also covers areas such as:
7:
506:Construction in the United Kingdom
14:
516:Organizations established in 2002
130:, with information managed as a
48:Department of Trade and Industry
34:Department of Trade and Industry
118:performance through the use of
87:Building Research Establishment
471:Constructing Excellence Avanti
231:Building information modelling
1:
531:Research in the United States
184:Standard Method and Procedure
536:Projects established in 2002
190:Design Management Principles
341:Design Productivity Journal
552:
393:February 27, 2008, at the
346:November 27, 2006, at the
328:February 27, 2008, at the
126:systems over conventional
481:People + Process + Tools
397:, Construction Journal,
136:3D Computer Aided Design
109:The problem and approach
521:Loughborough University
449:March 12, 2008, at the
388:"An historical problem"
244:Constructing Excellence
99:London Stansted Airport
56:Loughborough University
29:was established by the
444:Building Down Barriers
289:Building Down Barriers
23:
83:Constructing the Team
21:
366:on 19 November 2008
238:Further development
171:Guidance and Phases
71:Tavistock Institute
24:
511:Research projects
501:Civil engineering
165:information model
543:
453:
441:
435:
430:
424:
419:
413:
408:
402:
385:
376:
375:
373:
371:
362:. Archived from
356:
350:
338:
332:
320:
103:Heathrow Express
551:
550:
546:
545:
544:
542:
541:
540:
491:
490:
476:What is Avanti?
462:
457:
456:
451:Wayback Machine
442:
438:
431:
427:
420:
416:
409:
405:
395:Wayback Machine
386:
379:
369:
367:
358:
357:
353:
348:Wayback Machine
339:
335:
330:Wayback Machine
321:
314:
309:
297:
284:
256:
240:
173:
111:
67:
12:
11:
5:
549:
547:
539:
538:
533:
528:
523:
518:
513:
508:
503:
493:
492:
489:
488:
483:
478:
473:
468:
466:Avanti website
461:
460:External links
458:
455:
454:
436:
425:
414:
403:
377:
351:
333:
311:
310:
308:
305:
304:
303:
296:
293:
283:
280:
279:
278:
275:
272:
269:
266:
263:
255:
252:
239:
236:
235:
234:
224:
218:
208:
207:
204:
201:
194:
193:
187:
172:
169:
110:
107:
89:(BRE) and the
66:
63:
13:
10:
9:
6:
4:
3:
2:
548:
537:
534:
532:
529:
527:
524:
522:
519:
517:
514:
512:
509:
507:
504:
502:
499:
498:
496:
487:
486:IAI home page
484:
482:
479:
477:
474:
472:
469:
467:
464:
463:
459:
452:
448:
445:
440:
437:
434:
429:
426:
423:
418:
415:
412:
407:
404:
400:
396:
392:
389:
384:
382:
378:
365:
361:
355:
352:
349:
345:
342:
337:
334:
331:
327:
324:
319:
317:
313:
306:
302:
299:
298:
294:
292:
290:
281:
276:
273:
270:
267:
264:
261:
260:
259:
253:
251:
249:
245:
237:
232:
228:
225:
222:
219:
216:
213:
212:
211:
205:
202:
199:
198:
197:
191:
188:
185:
182:
181:
180:
178:
170:
168:
166:
160:
158:
153:
151:
148:
143:
141:
140:visualisation
137:
133:
129:
125:
121:
115:
108:
106:
104:
100:
96:
92:
88:
84:
81:
80:Latham Report
76:
72:
64:
62:
59:
57:
53:
49:
45:
42:
39:
35:
32:
28:
20:
16:
439:
428:
417:
406:
401:, April 2006
368:. Retrieved
364:the original
354:
336:
288:
285:
257:
241:
226:
220:
214:
209:
195:
189:
183:
174:
161:
157:supply chain
154:
144:
116:
112:
101:and the BAA
82:
68:
60:
38:construction
26:
25:
15:
370:29 February
22:Avanti logo
495:Categories
307:References
282:The future
65:Background
150:protocols
447:Archived
391:Archived
344:Archived
326:Archived
295:See also
132:database
128:drawings
44:partners
433:BS 5555
254:Results
248:BS 1192
227:Phase 3
221:Phase 2
215:Phase 1
54:(IAI),
41:project
27:Avanti
372:2008
301:CPIC
147:CPIC
95:CPIC
75:RICS
69:The
124:CAD
497::
380:^
315:^
291:.
142:.
31:UK
374:.
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.