Knowledge (XXG)

Avanti (project)

Source 📝

217:: Change the poor industry practice of producing information to individual standards and throwing it ‘over the wall’ to the next person in the supply chain who then reproduces their own information. Using an agreed standard for the project, spatially co-ordinated and high-quality 2D information will then be produced for the parties involved. 113:
Most construction projects are complex and involve co-ordination between many project participants both on- and off-site. As projects have increased in size and complexity, the number of participants involved in a single project has also increased. To improve collaboration between participants, the
117:
Its purpose was to support live construction project teams, as they collaborate to deliver projects, by helping them apply the appropriate technologies. It worked through a team of partners representing each stage of the project process, with the objective of improving project and business
162:
Avanti mobilised existing technologies to improve business performance by increasing the quality of information and predictability of outcomes and by reducing risk and waste. The core of the Avanti approach to a project's whole life cycle was based on team-working and access to a common
167:. All CAD information was generated with the same origin, orientation and scale, and organised in layers that could be shared. All layers and CAD model files were named consistently within a specific Avanti convention to allow others to find the relevant CAD data. 286:
Constructing Excellence is developing a self-sustaining business to support roll out of the Avanti methodology to the UK construction industry. It will also draw on the results of other DTI-supported collaborative research such as
159:, and on sharing of information, drawings and schedules, in an agreed and consistent manner. The Avanti approach was supported by handbooks, toolkits and on-site mentoring and was reliant on advice and materials provided by CPIC. 152:) that had previously gained too little market penetration to have significant impact on the sector. The objective was to deliver improved project and business performance by using ICT to support collaborative working. 77:
meeting of 1910 which stated "Architectural information is invariably inaccurate, ambiguous and incomplete". By the 1940s, the impact of this was valued at an additional 10% to the construction cost. By 1994 the
114:
industry needs tools that work well, appropriate processes to implement them, and the right approach from the people involved. Tackling these points was at the heart of the Avanti action research programme.
246:. Since the handover, Constructing Excellence endeavoured to promote the savings demonstrated on live projects. Further work was also carried out to make Avanti part of the update of 192:- comprising typical design management processes, information management processes, guidance on detailed task management and typical responsibilities of delivery team leaders. 97:) that recommended a common format and disciplined approach to reduce the problem. These suggestions were proven on DTI-funded projects and case studies at Endeavour House at 390: 525: 446: 47: 33: 175:
Learning from early projects, Avanti produced practical working documentation and tested the methods on live projects. This information supplemented the CPIC document
475: 480: 505: 515: 300: 176: 146: 119: 94: 398: 530: 535: 359: 343: 186:- advice on classification standards, spatial and technical co-ordination, example file and directory structures, and naming conventions. 105:, which showed that significant savings in project cost and drawing production could be made by addressing people and process issues. 19: 422:
British Standards, BS 1192:2007 Collaborative production of architectural, engineering and construction information. Code of practice
139: 410: 387: 520: 85:
suggested waste in the industry accounted for 25-30% of project costs. This figure is supported by earlier publications from the
443: 465: 86: 145:
To reduce the risks involved in adopting new working methods, Avanti brought together areas of current best practice (such as
206:
authoring information in a common data environment and controlling the sharing of information in a multi-author environment
230: 325: 223:: Implementation of those same principles to generate 3D project models to produce 2D drawings and material measurement. 510: 500: 61:
The Avanti programme aimed to help overcome problems caused by incomplete, inaccurate and ambiguous information.
485: 432: 421: 135: 243: 98: 55: 123: 50:
with the support of most of the largest UK firms in the construction industry. Avanti also involved the
155:
Avanti focused on early access to all project information by all partners, on early involvement of the
179:
and addressed problems of incomplete, inaccurate and ambiguous information. Avanti guidance included:
93:(BSRIA), which led to reports in 1987 from the Coordinating Committee for Project Information (now 70: 363: 340: 164: 247: 102: 43: 450: 394: 347: 329: 242:
In July 2006, the Avanti DTI Project documentation and brand ownership was transferred to
262:
Early commitment offering up to 80% saving on implementation cost on medium size project.
58:
and Co-Construct, a network of five construction research and information organizations.
494: 470: 79: 51: 156: 37: 18: 233:
systems. Each live project captures the lessons learned and the benefits gained.
149: 203:
guidance on ensuring the software chain supported the design and supply chains
322: 265:
50-85% saving on effort spent receiving information and formatting for reuse.
138:
systems could revolutionise projects, provided they were used for more than
122:(ICT) to support collaborative working. It set out to show the advantages of 36:
in 2002 to formulate an approach to collaborative working in order to enable
131: 127: 40: 274:
50% saving on time spent to assess tenders and award sub-contracts.
200:
a business case on the commercial imperatives for collaborative ICT
210:
For most projects, using this guidance consisted of three phases:
90: 17: 268:
60-80% saving on effort spent finding information and documents.
74: 46:
to work together effectively. The project was promoted by the
134:
rather than a drawing cabinet, and aimed to demonstrate that
30: 258:
Evaluation of the impacts of the Avanti project showed:
271:
75–80% saving in effort to achieve design co-ordination.
277:
50% saving on effort in sub-contractor design approval.
323:
DTI The Construction Research Programme, February 2007
91:
Building Services Research and Information Association
229:: Full implementation of 3D object-oriented and 177:Code of Procedure for the Construction Industry 318: 316: 8: 250:. The BS 5555 committee coded the methods. 52:International Alliance for Interoperability 120:information and communication technologies 526:2002 establishments in the United Kingdom 73:report (1965) printed an extract from an 399:Royal Institution of Chartered Surveyors 312: 411:Modern Building Services (MBS) Journal 383: 381: 360:"Full list of collaborative companies" 196:The advice also covers areas such as: 7: 506:Construction in the United Kingdom 14: 516:Organizations established in 2002 130:, with information managed as a 48:Department of Trade and Industry 34:Department of Trade and Industry 118:performance through the use of 87:Building Research Establishment 471:Constructing Excellence Avanti 231:Building information modelling 1: 531:Research in the United States 184:Standard Method and Procedure 536:Projects established in 2002 190:Design Management Principles 341:Design Productivity Journal 552: 393:February 27, 2008, at the 346:November 27, 2006, at the 328:February 27, 2008, at the 126:systems over conventional 481:People + Process + Tools 397:, Construction Journal, 136:3D Computer Aided Design 109:The problem and approach 521:Loughborough University 449:March 12, 2008, at the 388:"An historical problem" 244:Constructing Excellence 99:London Stansted Airport 56:Loughborough University 29:was established by the 444:Building Down Barriers 289:Building Down Barriers 23: 83:Constructing the Team 21: 366:on 19 November 2008 238:Further development 171:Guidance and Phases 71:Tavistock Institute 24: 511:Research projects 501:Civil engineering 165:information model 543: 453: 441: 435: 430: 424: 419: 413: 408: 402: 385: 376: 375: 373: 371: 362:. Archived from 356: 350: 338: 332: 320: 103:Heathrow Express 551: 550: 546: 545: 544: 542: 541: 540: 491: 490: 476:What is Avanti? 462: 457: 456: 451:Wayback Machine 442: 438: 431: 427: 420: 416: 409: 405: 395:Wayback Machine 386: 379: 369: 367: 358: 357: 353: 348:Wayback Machine 339: 335: 330:Wayback Machine 321: 314: 309: 297: 284: 256: 240: 173: 111: 67: 12: 11: 5: 549: 547: 539: 538: 533: 528: 523: 518: 513: 508: 503: 493: 492: 489: 488: 483: 478: 473: 468: 466:Avanti website 461: 460:External links 458: 455: 454: 436: 425: 414: 403: 377: 351: 333: 311: 310: 308: 305: 304: 303: 296: 293: 283: 280: 279: 278: 275: 272: 269: 266: 263: 255: 252: 239: 236: 235: 234: 224: 218: 208: 207: 204: 201: 194: 193: 187: 172: 169: 110: 107: 89:(BRE) and the 66: 63: 13: 10: 9: 6: 4: 3: 2: 548: 537: 534: 532: 529: 527: 524: 522: 519: 517: 514: 512: 509: 507: 504: 502: 499: 498: 496: 487: 486:IAI home page 484: 482: 479: 477: 474: 472: 469: 467: 464: 463: 459: 452: 448: 445: 440: 437: 434: 429: 426: 423: 418: 415: 412: 407: 404: 400: 396: 392: 389: 384: 382: 378: 365: 361: 355: 352: 349: 345: 342: 337: 334: 331: 327: 324: 319: 317: 313: 306: 302: 299: 298: 294: 292: 290: 281: 276: 273: 270: 267: 264: 261: 260: 259: 253: 251: 249: 245: 237: 232: 228: 225: 222: 219: 216: 213: 212: 211: 205: 202: 199: 198: 197: 191: 188: 185: 182: 181: 180: 178: 170: 168: 166: 160: 158: 153: 151: 148: 143: 141: 140:visualisation 137: 133: 129: 125: 121: 115: 108: 106: 104: 100: 96: 92: 88: 84: 81: 80:Latham Report 76: 72: 64: 62: 59: 57: 53: 49: 45: 42: 39: 35: 32: 28: 20: 16: 439: 428: 417: 406: 401:, April 2006 368:. Retrieved 364:the original 354: 336: 288: 285: 257: 241: 226: 220: 214: 209: 195: 189: 183: 174: 161: 157:supply chain 154: 144: 116: 112: 101:and the BAA 82: 68: 60: 38:construction 26: 25: 15: 370:29 February 22:Avanti logo 495:Categories 307:References 282:The future 65:Background 150:protocols 447:Archived 391:Archived 344:Archived 326:Archived 295:See also 132:database 128:drawings 44:partners 433:BS 5555 254:Results 248:BS 1192 227:Phase 3 221:Phase 2 215:Phase 1 54:(IAI), 41:project 27:Avanti 372:2008 301:CPIC 147:CPIC 95:CPIC 75:RICS 69:The 124:CAD 497:: 380:^ 315:^ 291:. 142:. 31:UK 374:.

Index


UK
Department of Trade and Industry
construction
project
partners
Department of Trade and Industry
International Alliance for Interoperability
Loughborough University
Tavistock Institute
RICS
Latham Report
Building Research Establishment
Building Services Research and Information Association
CPIC
London Stansted Airport
Heathrow Express
information and communication technologies
CAD
drawings
database
3D Computer Aided Design
visualisation
CPIC
protocols
supply chain
information model
Code of Procedure for the Construction Industry
Building information modelling
Constructing Excellence

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.