Construction of the plant began in January 2016 under an Engineering, Procurement and Construction ("EPC") contract with a consortium comprising (a) Siemens AG of Germany (b) Siemens Nigeria Limited and (c) Julius Berger Nigeria Limited. Siemens also provided the turbines, generators, transformers
293:
The Azura-Edo IPP is an open-cycle gas fired power plant. The power station is often referred to as the "Azura-Edo Independent Power Plant" or "Azura-Edo IPP", because the finance required to build the plant was sourced from the private sector, rather than from the government. The private sector
624:
Nearly 5 million man-hours of labor were expended on the plant, without a single lost-time injury, and the names of all the developers and construction workers, numbering over 2,000 in total, are now inscribed on a brass plaque at the front of the plant's administration and control building.
321:
The minority equity investors in the plant are include: 1. Africa50, a pan-African infrastructure investment platform. 2. Anergi Group, an energy company active in Africa's emerging economies. 3. Amaya Capital, an investment firm with a focus on the infrastructure sector in Africa and 4. The
334:
The power station cost US$ 900 million to build. The financing was obtained from fifteen financial institutions, in nine countries. The table below, illustrates the debt investors in the project. In addition, the
799: 294:
owners of the plant took the construction risk. The post-construction risk and the operational risks are also borne by the plant's owners and their operations and maintenance contractors.
37: 336: 939: 934: 621:
and other electrical hardware. The plant was completed on 30 April 2018, six months ahead of schedule, a record achievement for a plant of this size.
344: 944: 455: 380: 83: 160: 257:. This is the first phase of a three-phase construction project of a combined cycle gas plant with planned capacity of 1,500 megawatts. 879: 306:, an investment holding company for independent power projects in Africa. The majority equity investor in the Azura Power Holdings is 664: 483: 315: 285:. The geographical coordinates of the power station are:06°24'32.0"N, 05°41'01.0"E (Latitude:6.408889; Longitude:5.683611). 425: 694: 310:, a private equity firm headquartered in London with US$ 7.8 billion under management. In 2004, it was spun-off from 277:, Nigeria's commercial capital. This location lies approximately 465 kilometres (289 mi), by road, southwest of 249:-powered open cycle electricity generation plant, with a current operational capacity of 461 megawatts, located in 572: 587: 527: 20: 499: 123: 856: 949: 827: 542: 190: 222: 352: 720: 695:"The pacemaker: Nigerian power plant sets new benchmarks for building in emerging markets" 139: 642: 532: 400: 348: 340: 928: 656: 557: 488: 385: 307: 562: 547: 282: 804: 777: 750: 460: 246: 178: 632: 266: 250: 98: 85: 831: 724: 650: 577: 517: 395: 323: 311: 270: 68: 231: 884: 410: 698: 607: 602: 592: 445: 430: 254: 144: 55: 504: 473: 415: 278: 274: 273:, approximately 316 kilometres (196 mi), by road, east of 746:"Road Distance Between Lagos, Nigeria And Benin City, Nigeria" 440: 919: 912: 209: 721:"Invest Edo State: Power Potentials: The Azura-Edo IPP" 326:, which holds a 2.5 percent equity stake in the plant. 880:"Azura Deal Only Power Agreement that Works, Says MD" 337:
International Bank for Reconstruction and Development
218: 204: 199: 189: 184: 174: 169: 153: 132: 122: 114: 77: 61: 51: 30: 351:insurance. Both IBRD and MIGA are members of the 265:The power station is located to the northeast of 878:Emmanuel Addeh and Mary Nnah (4 August 2020). 8: 360:Fund Sources for Azura Thermal Power Station 940:Natural gas-fired power stations in Nigeria 357: 27: 345:Multilateral Investment Guarantee Agency 676: 456:Netherlands Development Finance Company 381:Overseas Private Investment Corporation 223:Related media on Commons 46:Location of the Azura Edo Power Station 800:"Location of Azura-Edo Power Station" 7: 850: 848: 688: 686: 684: 682: 680: 514:Emerging African Infrastructure Fund 161:Seplat Petroleum Development Company 773:"Distance From Abuja To Benin City" 14: 855:Jon Whiteaker (13 January 2016). 665:List of power stations in Nigeria 484:International Finance Corporation 935:Energy infrastructure in Nigeria 649: 635: 316:Government of the United Kingdom 170:Thermal power station 36: 693:Janine Stephen (28 June 2018). 945:2018 establishments in Nigeria 857:"Azura-Edo gas-fired, Nigeria" 302:The power station is owned by 1: 558:Standard Bank of South Africa 426:German Investment Corporation 826:CDC Group (5 August 2020). 719:Edo State (5 August 2020). 966: 18: 573:Mauritius Commercial Bank 228: 44: 35: 588:First City Monument Bank 339:(IBRD) provided partial 723:. Benin City, Nigeria: 528:Standard Chartered Bank 243:Azura-Edo Power Station 191:Nameplate capacity 31:Azura Edo Power Station 920:Official Azura-Edo App 828:"Azura Power Holdings" 470:Swedfund International 16:Nigerian power station 185:Power generation 324:Edo State Government 304:Azura Power Holdings 124:Commission date 19:For other uses, see 697:. Munich, Germany: 362: 200:External links 99:6.40889°N 5.68361°E 95: /  859:. London: IJGlobal 725:Edo State, Nigeria 543:Rand Merchant Bank 358: 128:Phase 1 - May 2018 613: 612: 239: 238: 175:Primary fuel 957: 916: 915: 913:Official website 898: 897: 895: 893: 875: 869: 868: 866: 864: 852: 843: 842: 840: 838: 823: 817: 816: 814: 812: 796: 790: 789: 787: 785: 769: 763: 762: 760: 758: 742: 736: 735: 733: 731: 716: 710: 709: 707: 705: 690: 659: 654: 653: 645: 640: 639: 638: 363: 353:World Bank Group 347:(MIGA) provided 281:, the country's 232:edit on Wikidata 214: 211: 110: 109: 107: 106: 105: 104:6.40889; 5.68361 100: 96: 93: 92: 91: 88: 40: 28: 965: 964: 960: 959: 958: 956: 955: 954: 925: 924: 911: 910: 907: 902: 901: 891: 889: 877: 876: 872: 862: 860: 854: 853: 846: 836: 834: 825: 824: 820: 810: 808: 798: 797: 793: 783: 781: 771: 770: 766: 756: 754: 744: 743: 739: 729: 727: 718: 717: 713: 703: 701: 692: 691: 678: 673: 655: 648: 641: 636: 634: 631: 618: 341:risk guarantees 332: 314:, owned by the 300: 291: 263: 235: 208: 165: 149: 103: 101: 97: 94: 89: 86: 84: 82: 81: 73: 47: 24: 17: 12: 11: 5: 963: 961: 953: 952: 947: 942: 937: 927: 926: 923: 922: 917: 906: 905:External links 903: 900: 899: 870: 844: 818: 791: 764: 737: 711: 699:Siemens Global 675: 674: 672: 669: 668: 667: 661: 660: 646: 643:Nigeria portal 630: 627: 617: 614: 611: 610: 605: 600: 596: 595: 590: 585: 581: 580: 575: 570: 566: 565: 560: 555: 551: 550: 545: 540: 536: 535: 533:United Kingdom 530: 525: 521: 520: 515: 512: 508: 507: 502: 497: 493: 492: 486: 481: 477: 476: 471: 468: 464: 463: 458: 453: 449: 448: 443: 438: 434: 433: 428: 423: 419: 418: 413: 408: 404: 403: 401:United Kingdom 398: 393: 389: 388: 383: 378: 374: 373: 370: 369:Name of Lender 367: 349:political risk 331: 328: 299: 296: 290: 287: 262: 259: 237: 236: 229: 226: 225: 220: 216: 215: 206: 202: 201: 197: 196: 193: 187: 186: 182: 181: 176: 172: 171: 167: 166: 164: 163: 157: 155: 151: 150: 148: 147: 142: 136: 134: 130: 129: 126: 120: 119: 116: 112: 111: 79: 75: 74: 72: 71: 65: 63: 59: 58: 53: 49: 48: 45: 42: 41: 33: 32: 15: 13: 10: 9: 6: 4: 3: 2: 962: 951: 948: 946: 943: 941: 938: 936: 933: 932: 930: 921: 918: 914: 909: 908: 904: 887: 886: 881: 874: 871: 858: 851: 849: 845: 833: 829: 822: 819: 807: 806: 801: 795: 792: 780: 779: 774: 768: 765: 753: 752: 747: 741: 738: 726: 722: 715: 712: 700: 696: 689: 687: 685: 683: 681: 677: 670: 666: 663: 662: 658: 657:Energy portal 652: 647: 644: 633: 628: 626: 622: 615: 609: 606: 604: 601: 598: 597: 594: 591: 589: 586: 583: 582: 579: 576: 574: 571: 568: 567: 564: 561: 559: 556: 553: 552: 549: 546: 544: 541: 538: 537: 534: 531: 529: 526: 523: 522: 519: 516: 513: 510: 509: 506: 503: 501: 500:ICF Debt Pool 498: 495: 494: 490: 489:United States 487: 485: 482: 479: 478: 475: 472: 469: 466: 465: 462: 459: 457: 454: 451: 450: 447: 444: 442: 439: 436: 435: 432: 429: 427: 424: 421: 420: 417: 414: 412: 409: 406: 405: 402: 399: 397: 394: 391: 390: 387: 386:United States 384: 382: 379: 376: 375: 371: 368: 365: 364: 361: 356: 354: 350: 346: 342: 338: 329: 327: 325: 319: 317: 313: 309: 308:Actis Capital 305: 297: 295: 288: 286: 284: 280: 276: 272: 268: 260: 258: 256: 252: 248: 244: 233: 227: 224: 221: 217: 213: 207: 203: 198: 194: 192: 188: 183: 180: 177: 173: 168: 162: 159: 158: 156: 152: 146: 143: 141: 138: 137: 135: 131: 127: 125: 121: 117: 113: 108: 80: 76: 70: 67: 66: 64: 60: 57: 54: 50: 43: 39: 34: 29: 26: 22: 890:. Retrieved 883: 873: 861:. Retrieved 835:. Retrieved 821: 809:. Retrieved 803: 794: 782:. Retrieved 776: 767: 755:. Retrieved 749: 740: 728:. Retrieved 714: 702:. Retrieved 623: 619: 616:Construction 603:Siemens Bank 563:South Africa 548:South Africa 359: 343:; while the 333: 320: 303: 301: 292: 283:capital city 264: 242: 240: 25: 805:Google Maps 778:Google Maps 751:Google Maps 461:Netherlands 247:natural gas 179:Natural gas 154:Operator(s) 118:Operational 102: / 78:Coordinates 929:Categories 830:. London: 671:References 267:Benin City 251:Benin City 90:05°41′01″E 87:06°24′32″N 950:Edo State 832:CDC Group 578:Mauritius 518:Mauritius 396:CDC Group 372:Domicile 330:Financing 312:CDC Group 298:Ownership 271:Edo State 69:Edo State 892:5 August 885:This Day 863:5 August 837:5 August 811:5 August 784:5 August 757:5 August 730:5 August 704:5 August 629:See also 411:Proparco 289:Overview 261:Location 210:azuraedo 133:Owner(s) 62:Location 888:. Lagos 802:(Map). 775:(Map). 748:(Map). 608:Germany 593:Nigeria 491:  446:Germany 431:Germany 255:Nigeria 219:Commons 205:Website 145:Nigeria 56:Nigeria 52:Country 505:Canada 474:Sweden 416:France 195:461 MW 115:Status 279:Abuja 275:Lagos 245:is a 230:[ 140:Amaya 21:Azura 894:2020 865:2020 839:2020 813:2020 786:2020 759:2020 732:2020 706:2020 241:The 212:.com 441:KfW 366:No. 269:in 253:in 931:: 882:. 847:^ 679:^ 599:16 584:15 569:14 554:13 539:12 524:11 511:10 355:. 318:. 896:. 867:. 841:. 815:. 788:. 761:. 734:. 708:. 496:9 480:8 467:7 452:6 437:5 422:4 407:3 392:2 377:1 234:] 23:.

Index

Azura

Nigeria
Edo State
06°24′32″N 05°41′01″E / 6.40889°N 5.68361°E / 6.40889; 5.68361
Commission date
Amaya
Nigeria
Seplat Petroleum Development Company
Natural gas
Nameplate capacity
azuraedo.com
Related media on Commons
edit on Wikidata
natural gas
Benin City
Nigeria
Benin City
Edo State
Lagos
Abuja
capital city
Actis Capital
CDC Group
Government of the United Kingdom
Edo State Government
International Bank for Reconstruction and Development
risk guarantees
Multilateral Investment Guarantee Agency
political risk

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.