190:
25:
254:
Once the liquid was drained from Basin F, the drying of the soils, sediments, and liner began. This project caused an odor resulting in discomfort to members of the surrounding community. Because of the Army's concern for the comfort of the local community during the soil drying, air purifiers were
175:
The increased volume of liquid in Basin F caused by the heavy rainfall in May 1988 required additional storage capacity. Two double-lined holding ponds were constructed: a 5.5 million US gallons (21,000 m) pond (Pond B) and an 6.5 million US gallons (25,000 m) pond (Pond A). The
164:
The Basin F Interim
Response Action began in March 1988 and involved the transfer by tank truck of 4 million US gallons (15,000 m) of Basin F liquid to three 1.3 million US gallons (4,900 m) holding tanks and approximately 6.5 million US gallons (25,000 m) to a
147:
liner (approximately 3/8-inch (10 mm) thick) covered with a 12-inch (300 mm) protective soil blanket. Basin F had a maximum capacity of 243 million US gallons (920,000 m) and covered approximately 93 acres (380,000 m). Throughout the operation of Basin F, the
255:
distributed to affected homes in the community to help alleviate the odors. When the odor problem began, the Army asked several health agencies to study the problem to determine if there were any long-term or acute health effects. Toxicologists from
250:
The basin floor was capped with 12 inches (300 mm) of compact clay and 6 inches (150 mm) of topsoil and revegetated with native grass. This portion of the Basin F Interim
Response Action was completed in August 1989.
260:
379:
283:, the contractor for the project) identified the compounds and determined that there were no acute health effects. The odors ended with the completion of the excavation in December 1988.
369:
168:
In May 1988, near the start of the project, a heavy rainfall classified as a 25-year/24-hour event occurred which increased the volume of Basin F liquid. In June 1988, a
264:
140:, to provide for the disposal of contaminated liquid wastes from the chemical manufacturing operations of the Army and its lessee Shell Chemical Company.
176:
488,000 cubic yards (373,000 m) of basin overburden, liner, and subsoils were excavated and placed in a waste pile located within the basin area.
172:
touched down near the tanks and ponds. The need to inspect and repair structures and equipment affected by the twister caused a minor schedule delay.
237:
116:
152:
concentration increased as water evaporated. The liquid formerly stored in Basin F is very salty water that contains some metals,
286:
The total cost of the project was about $ 45 million. The decision on the final disposal of the liquid was reached in March 1990.
374:
364:
312:
307:
215:
50:
256:
97:
69:
144:
325:
211:
200:
76:
46:
35:
219:
204:
54:
39:
295:
137:
83:
268:
65:
272:
133:
316:
276:
358:
90:
189:
24:
340:
327:
153:
156:, wastewater, and toxic organics, which are about 1 percent of the liquid.
149:
169:
280:
183:
18:
261:
United States Agency for Toxic
Substance and Disease Registry
143:
As originally constructed, Basin F was equipped with a
380:Buildings and structures in Adams County, Colorado
16:Chemical waste disposal facility in Colorado, USA
265:United States Environmental Protection Agency
8:
218:. Unsourced material may be challenged and
53:. Unsourced material may be challenged and
370:Environmental issues in the United States
238:Learn how and when to remove this message
117:Learn how and when to remove this message
7:
216:adding citations to reliable sources
51:adding citations to reliable sources
14:
275:'s Surgeon General's Office, and
257:Colorado State Health Department
188:
23:
308:Basin F Interim Response Action
1:
319: (archived June 24, 2007)
165:double-lined holding pond.
145:catalytically-blown asphalt
396:
375:Environment of Colorado
365:Commerce City, Colorado
132:was constructed by the
296:Rocky Mountain Arsenal
180:Remediation of Basin F
138:Rocky Mountain Arsenal
267:, Shell Oil Company,
341:39.8458°N 104.8555°W
212:improve this section
47:improve this article
337: /
346:39.8458; -104.8555
313:Basin F Waste Pile
134:United States Army
269:Tri-County Health
248:
247:
240:
127:
126:
119:
101:
387:
352:
351:
349:
348:
347:
342:
338:
335:
334:
333:
330:
279:(or previously,
243:
236:
232:
229:
223:
192:
184:
160:Interim response
122:
115:
111:
108:
102:
100:
59:
27:
19:
395:
394:
390:
389:
388:
386:
385:
384:
355:
354:
345:
343:
339:
336:
331:
328:
326:
324:
323:
317:Wayback Machine
304:
292:
244:
233:
227:
224:
209:
193:
182:
162:
136:in 1956 at the
123:
112:
106:
103:
60:
58:
44:
28:
17:
12:
11:
5:
393:
391:
383:
382:
377:
372:
367:
357:
356:
321:
320:
310:
303:
302:External links
300:
299:
298:
291:
288:
277:Foster-Wheeler
246:
245:
196:
194:
187:
181:
178:
161:
158:
125:
124:
31:
29:
22:
15:
13:
10:
9:
6:
4:
3:
2:
392:
381:
378:
376:
373:
371:
368:
366:
363:
362:
360:
353:
350:
318:
314:
311:
309:
306:
305:
301:
297:
294:
293:
289:
287:
284:
282:
278:
274:
270:
266:
262:
258:
252:
242:
239:
231:
221:
217:
213:
207:
206:
202:
197:This section
195:
191:
186:
185:
179:
177:
173:
171:
166:
159:
157:
155:
151:
146:
141:
139:
135:
131:
121:
118:
110:
107:February 2011
99:
96:
92:
89:
85:
82:
78:
75:
71:
68: –
67:
63:
62:Find sources:
56:
52:
48:
42:
41:
37:
32:This article
30:
26:
21:
20:
322:
285:
253:
249:
234:
225:
210:Please help
198:
174:
167:
163:
142:
129:
128:
113:
104:
94:
87:
80:
73:
61:
45:Please help
33:
344: /
332:104°51′20″W
359:Categories
329:39°50′45″N
228:March 2018
77:newspapers
199:does not
154:hydrazine
66:"Basin F"
34:does not
290:See also
315:at the
220:removed
205:sources
170:tornado
130:Basin F
91:scholar
55:removed
40:sources
281:Ebasco
271:, the
150:saline
93:
86:
79:
72:
64:
98:JSTOR
84:books
273:Army
203:any
201:cite
70:news
38:any
36:cite
214:by
49:by
361::
263:,
259:,
241:)
235:(
230:)
226:(
222:.
208:.
120:)
114:(
109:)
105:(
95:·
88:·
81:·
74:·
57:.
43:.
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.