Knowledge (XXG)

Tunnel boring machine

Source 📝

175: 543: 93: 417:. Its excavation diameter was 15.62 m (51.2 ft), total length 130 m (430 ft); excavation area of 192 m (2,070 sq ft), thrust value 39,485 t, total weight 4,500 tons, total installed capacity 18 MW. Its yearly energy consumption was about 62 GWh. It is owned and operated by the Italian construction company Toto S.p.A. Costruzioni Generali (Toto Group) for the Sparvo gallery of the Italian Motorway Pass A1 ("Variante di Valico A1"), near Florence. The same company built the 36: 459: 430: 565: 554: 349: 395: 167: 156: 254:, after inventor Charles Wilson. It drilled 3 meters (10 ft) into the rock before breaking down (the tunnel was eventually completed more than 20 years later, and as with the Fréjus Rail Tunnel, by using less ambitious methods). Wilson's machine anticipated modern TBMs in the sense that it employed cutting discs, like those of a 639:
Slurry separation plants use multi-stage filtration systems that separate spoil from slurry to allow reuse. The degree to which slurry can be 'cleaned' depends on the relative particle sizes of the muck. Slurry TBMs are not suitable for silts and clays as the particle sizes of the spoil are less than
290:
on the French side. However, despite this success, the cross-Channel tunnel project was abandoned in 1883 after the British military raised fears that the tunnel might be used as an invasion route. Nevertheless, in 1883, this TBM was used to bore a railway ventilation tunnel — 2 m (7 ft) in
261:
In 1853, the American Ebenezer Talbot also patented a TBM that employed Wilson's cutting discs, although they were mounted on rotating arms, which in turn were mounted on a rotating plate. In the 1870s, John D. Brunton of England built a machine employing cutting discs that were mounted eccentrically
145:
Tunneling speeds increase over time. The first TBM peaked at 4 meters per week. This increased to 16 meters per week four decades later. By the end of the 19th century, speeds had reached over 30 meters per week. 21st century rock TBMs can excavate over 700 meters per week, while
656:
Open face soft ground TBMs rely on the excavated ground to briefly stand without support. They are suitable for use in ground with a strength of up to about 10 MPa (1,500 psi) with low water inflows. They can bore tunnels with cross-section in excess of 10 m (30 ft). A backactor
701:
TBMs with positive face control, such as earth pressure balance (EPB) and slurry shield (SS), are used in such situations. Both types (EPB and SS) are capable of reducing the risk of surface subsidence and voids if ground conditions are well documented. When tunnelling in urban environments, other
324:
were proposed. Other TBMs consisted of a rotating drum with metal tines on its outer surface, or a rotating circular plate covered with teeth, or revolving belts covered with metal teeth. However, these TBMs proved expensive, cumbersome, and unable to excavate hard rock; interest in TBMs therefore
277:
supported a trial run using English's TBM. Its cutting head consisted of a conical drill bit behind which were a pair of opposing arms on which were mounted cutting discs. From June 1882 to March 1883, the machine tunneled, through chalk, a total of 1,840 m (6,036 ft). A French engineer,
1610:
In the U.S., the McKinlay Entry Driver, a track-mounted TBM or "continuous miner", was invented in 1918 for use in coal mines. Its boring head consisted of metal tines on two, side-by-side rotating arms. See: Thomas W. Garges (November 13, 2003) William N. Poundstone lecture: "Underground Mining
622:
tunnels completed in the last 20 years worldwide were excavated using this method. EPB has historically competed with the slurry shield method (see below), where the slurry is used to stabilize the tunnel face and transport spoil to the surface. EPB TBMs are mostly used in finer ground (such as
130:
TBMs limit the disturbance to the surrounding ground and produce a smooth tunnel wall. This reduces the cost of lining the tunnel, and is suitable for use in urban areas. TBMs are expensive to construct, and larger ones are challenging to transport. These fixed costs become less significant for
524:
Double Shield (or telescopic shield) TBMs have a leading shield that advances with the cutting head and a trailing shield that acts as a gripper. The two shields can move axially relative to each other (i.e., telescopically) over a limited distance. The gripper shield anchors the TBM so that
494:
following behind the cutter head to support the walls until permanent tunnel support is constructed further along the machine. The stability of the walls also influences the method by which the TBM anchors itself in place so that it can apply force to the cutting head. This in turn determines
515:
A single-shield TBM has a single cylindrical shield after the cutting head. A permanent concrete lining is constructed immediately after the shield, and the TBM pushes off the lining to apply force to the cutter head. Because this pushing cannot be done while a next ring of lining is being
506:
Machines such as a Wirth machine can be moved only while ungripped. Other machines can move continuously. At the end of a Wirth boring cycle, legs drop to the ground, the grippers are retracted, and the machine advances. The grippers then reengage and the rear legs lift for the next cycle.
533:
In hard rock with minimal ground water, the area around the cutter head of a TBM can be unpressurized, as the exposed rock face can support itself. In weaker soil, or when there is significant ground water, pressure must be applied to the face of the tunnel to prevent collapse and/or the
440:
TBMs typically consist of a rotating cutting wheel in front, called a cutter head, followed by a main bearing, a thrust system, a system to remove excavated material (muck), and support mechanisms. Machines vary with site geology, amount of ground water present, and other factors.
489:
Depending on the stability of the local geology, the newly formed walls of the tunnel often need to be supported immediately after being dug to avoid collapse, before any permanent support or lining has been constructed. Many TBMs are equipped with one or more cylindrical
391:'s Rapid Transit with a boring diameter of 6.67 m (21.9 ft). The medium was water saturated sandy mudstone, schistose mudstone, highly weathered mudstone as well as alluvium. It achieved a maximum advance rate of more than 345 m (1,132 ft) per month. 596:, polymers and foam can be injected ahead of the face to stabilize the ground. Such additives can separately be injected in the cutter head and extraction screw to ensure that the muck is sufficiently cohesive to maintain pressure and restrict water flow. 319:
During the late 19th and early 20th century, inventors continued to design, build, and test TBMs for tunnels for railroads, subways, sewers, water supplies, etc. TBMs employing rotating arrays of drills or hammers were patented. TBMs that resembled giant
258:, which were attached to the rotating head of the machine. In contrast to traditional chiseling or drilling and blasting, this innovative method of removing rock relied on simple metal wheels to apply a transient high pressure that fractured the rock. 647:
system is sometimes placed at the cutting head to allow workers to operate the machine, although air pressure may reach elevated levels in the caisson, requiring workers to be medically cleared as "fit to dive" and able to operate pressure locks.
631:
Slurry shield machines can be used in soft ground with high water pressure or where granular ground conditions (sands and gravels) do not allow a plug to form in the screw. The cutter head is filled with pressurised slurry, typically made of
207:
in 1825. However, this was only the invention of the shield concept and did not involve the construction of a complete tunnel boring machine, the digging still having to be accomplished by the then standard excavation methods.
657:
arm or cutter head bore to within 150 mm (6 in) of the edge of the shield. After a boring cycle, the shield is jacked forward to begin a new cycle. Ground support is provided by precast concrete, or occasionally
681:
Behind all types of tunnel boring machines, in the finished part of the tunnel, are trailing support decks known as the backup system, whose mechanisms can include conveyors or other systems for muck removal; slurry
310:
was constructed from 1889 to 1904 using a Greathead shield TBM. The project used air compressed to 2.4 bar (35 psi) to reduce cave-ins. However, many workers died via cave-in or decompression sickness.
444:
Rock boring machines differ from earth boring machines in the way they cut the tunnel, the way they provide traction to support the boring activity, and in the way they support the newly formed tunnels walls.
269:(1833–1895); Beaumont's machine was further improved in 1880 by British Army officer Major Thomas English (1843–1935). In 1875, the French National Assembly approved the construction of a tunnel under the 764: 384:. The machine began operating in July 2013, but stalled in December 2013 and required substantial repairs that halted the machine until January 2016. Bertha completed boring the tunnel on April 4, 2017. 421:, excavation diameter of 17.6 meters (58 ft), owned and operated by the French construction company Dragages Hong Kong (Bouygues' subsidiary) for the Tuen Mun Chek Lap Kok link in Hong Kong. 661:(SGI) segments that are bolted or supported until a support ring has been added. The final segment, called the key, is wedge-shaped, and expands the ring until it is tight against the ground. 849: 1723: 1693: 262:
on rotating plates, which in turn were mounted eccentrically on a rotating plate, so that the cutting discs would travel over almost all of the rock face that was to be removed.
702:
tunnels, existing utility lines and deep foundations must be considered, and the project must accommodate measures to mitigate any detrimental effects to other infrastructure.
1670: 1604:(iron miner) was developed in 1916 by Schmidt, Kranz & Co. for potash mines; its boring head consisted of a large rotating roller that was fitted with cutters See: 911: 785: 1329:(Abington, England: Routledge, 2006), Chapter 1, § 2: The commercial possibilities: Lord Richard Grosvenor, Sir Edward Watkin and the 'Manchester to Paris Railroad'. 477:
Main Beam machines do not install concrete segments behind the cutter head. Instead, the rock is held up using ground support methods such as ring beams, rock bolts,
235:. It consisted of more than 100 percussion drills mounted in the front of a locomotive-sized machine, mechanically power-driven from the entrance of the tunnel. The 1747: 669:
TBMs range diameter from 1 to 17 meters (3 to 56 ft). Micro tunnel shield TBMs are used to construct small tunnels, and is a smaller equivalent to a general
819: 756: 636:
clay that applies hydrostatic pressure to the face. The slurry mixes with the muck before it is pumped to a slurry separation plant, usually outside the tunnel.
1728: 1641: 1352: 1040: 174: 469:
The machine stabilizes itself in the tunnel with hydraulic cylinders that press against the shield, allowing the TBM to apply pressure at the tunnel face.
588:. By adjusting the rate of extraction of muck and the advance rate of the TBM, the pressure at the face of the TBM can be controlled without the use of 1854: 1497: 841: 569: 434: 1615: 381: 879: 503:
Gripper TBMs are used in rock tunnels. They forgo the use of a shield and instead push directly against the unreinforced sides of the tunnel.
1960: 1514: 1269: 1245: 599:
Like some other TBM types, EPB's use thrust cylinders to advance by pushing against concrete segments. The cutter head uses a combination of
1701: 1820: 1733: 57: 239:
affected the funding, and the tunnel was not completed until 10 years later, by using less innovative and less expensive methods such as
142:
rather than TBMs. TBM tunnels are typically circular in cross-section although they may be u-shaped, horseshoes, square or rectangular.
466:
Shielded TBMs are typically used to excavate tunnels in soil. They erect concrete segments behind the TBM to support the tunnel walls.
547: 134:
TBM-bored tunnel cross-sections range from 1 to 17.6 meters (3.3 to 57.7 ft) to date. Narrower tunnels are typically bored using
686:(if applicable); control rooms; electrical, dust-removal and ventilation systems; and mechanisms for transport of pre-cast segments. 1907: 1310: 872:"Shield Machines and Tunnel Boring Machines (TBMs) - Construction, Mining and Utility Equipment|Products & Services|Komatsu Ltd" 79: 1376: 2082: 179: 2072: 1285:
Thomas English, U.K. Patent no.s 4,347 (issued: October 25, 1880) and 5,317 (issued: December 5, 1881); "Tunneling-machine,"
542: 410: 900: 365: 576:
Earth pressure balance (EPB) machines are used in soft ground with less than 7 bar (100 psi) of pressure. It uses
1946:(Hoboken, New Jersey: John Wiley & Sons, 2013), Chapter 7: Tunnel-boring machines: History of tunnel-boring machine. 265:
The first TBM that tunneled a substantial distance was invented in 1863 and improved in 1875 by British Army officer Major
1880: 789: 717: 92: 1100: 1849: 1069: 698:
be avoided. The normal method of doing this in soft ground is to maintain soil pressures during and after construction.
1755: 2077: 811: 418: 328:
A TBM with a bore diameter of 14.4 m (47 ft 3 in) was manufactured by The Robbins Company for Canada's
50: 44: 1633: 220: 1263:
Patents for Inventions. Abridgments of Specifications. Class 85, Mining, Quarrying, Tunnelling, and Well-sinking
1239:
Patents for Inventions. Abridgments of Specifications relating to Mining, Quarrying, Tunnelling, and Well-sinking
640:
that of the bentonite. In this case, water is removed from the slurry leaving a clay cake, which may be polluted.
606:
EPB has allowed soft, wet, or unstable ground to be tunneled with a speed and safety not previously possible. The
246:
In the United States, the first boring machine to have been built was used in 1853 during the construction of the
1971: 1470:
Reginald Stanley, U.K. Patent no. 1,449 (issued: February 1, 1886); "Tunneling-machine" (issued: August 7, 1894).
1033: 369: 1508:
Patents for Inventions. bridgments of Specifications relating to Mining, Quarrying, Tunnelling, and Well-sinking
146:
soil tunneling machines can exceed 200 meters per week. Speed generally declines as tunnel size increases.
61: 458: 1494: 611: 525:
pressure can be applied to the cutter head while simultaneously the concrete lining is being constructed.
361: 329: 495:
whether the machine can bore and advance simultaneously, or whether these are done in alternating modes.
1874: 1493:
William F. Cooke and George Hunter, U.K. patent no. 433 (issued: August 10, 1866). Available online at:
735: 673:
and generally bore tunnels of 1 to 1.5 meters (3.3 to 4.9 ft), too small for operators to walk in.
644: 135: 124: 564: 325:
declined. Nevertheless, TBM development continued in potash and coal mines, where the rock was softer.
224: 1612: 568:
The support structures at the rear of a TBM. This machine was used to excavate the main tunnel of the
399: 353: 200: 2019:
Bilger, Burkhard (September 15, 2008). "The Long Dig: Getting through the Swiss Alps the hard way".
1998:(Cambridge, England: Cambridge University Press, 1988), Chapter 11: Hard rock tunnelling machines. 553: 429: 581: 348: 307: 236: 1935: 1511: 1266: 1242: 968: 871: 694:
Urban tunnelling has the special requirement that the surface remain undisturbed, and that ground
1034:
Hapgood, Fred, "The Underground Cutting Edge: The innovators who made digging tunnels high-tech",
683: 615: 377: 283: 279: 274: 266: 139: 1824: 1956: 1903: 1306: 1226: 670: 196: 1922: 1237:
Frederick Edward Blackett Beaumont, U.K. Patent no. 1,904 (issued: July 30, 1864). (See:
600: 2045: 1619: 1613:
Benjamin M. Statler College of Engineering and Mineral Resources, West Virginia University
1518: 1501: 1273: 1249: 1044: 270: 178:
A tunnel boring machine cutter head being lowered underground for the construction of the
160: 340:
hydroelectric dams to which it tunnelled to provide an additional hydroelectric tunnel.
711: 607: 585: 97: 546:
Tunnel boring machine at the site of Weinberg tunnell Altstetten-Zürich-Oerlikon near
2066: 619: 577: 516:
constructed, the single-shield TBM operates in alternating cutting and lining modes.
333: 247: 204: 1989:
Stack, Barbara, "Encyclopaedia of Tunnelling, Mining, and Drilling Equipment", 1995.
658: 414: 388: 300: 183: 1821:"Sydney Airport Link Rail Tunnel Project, Des Walters: Under Pressure Underground" 1104: 394: 166: 1241:(London, England: Office of the Commissioners of Patents for Inventions, 1874), 1077: 1510:(London, England: Office of the Commissioners of Patents for Inventions, 1874), 1070:"FINDING AID FOR THE HOOSAC TUNNEL COLLECTION at the NORTH ADAMS PUBLIC LIBRARY" 255: 155: 757:""U-shape": First Shield Machine for horseshoe-shaped Cross Sections - tunnel" 729: 723: 695: 603:
cutting bits, carbide disc cutters, drag picks and/or hard rock disc cutters.
292: 240: 212: 1951:
Maidl, Bernhard; Schmid, Leonhard; Ritz, Willy; Herrenknecht, Martin (2008).
1582: 1556: 1547: 1475: 1437: 1428: 1419: 1287: 623:
clay) while slurry TBMs are mostly used for coarser ground (such as gravel).
1792: 1662: 1463: 1410: 1196: 1154: 633: 593: 478: 337: 296: 17: 1169: 1139: 1223:
Modern Tunneling: With Special Reference to Mine and Water-supply Tunnels
321: 287: 1261:
F.E.B. Beaumont, U.K. Patent no. 4,166 (issued: Dec. 2, 1875). (See:
558: 373: 1917:
Bancroft, George J. (1908) "A history of the tunnel boring machine,"
589: 113: 112:), also known as a "mole" or a "worm", is a machine used to excavate 2028:
Foley, Amanda (May 2009). "Life on the Cutting Edge: Dick Robbins".
368:
with a bore diameter of 17.45 meters (57.3 ft) was produced by
286:, used a similar machine to drill 1,669 m (5,476 ft) from 738: – Underground construction that minimizes surface disruption 563: 552: 541: 457: 428: 393: 347: 232: 173: 165: 154: 91: 1932:
Treatise on Explosive Compounds, Machine Rock Drills and Blasting
842:"New tunnel-boring machine makes cutting corners perfectly sound" 228: 117: 250:
in northwest Massachusetts. Made of cast iron, it was known as
116:. Tunnels are excavated through hard rock, wet or dry soil, or 1754:. Metro Kuala Lumpur, Malaysia > Tech Specs. Archived from 332:. The machine was used to bore a hydroelectric tunnel beneath 29: 1850:"Medical support for the Sydney Airport Link Tunnel project" 336:. The machine was named "Big Becky" in reference to the Sir 1377:"ASCE Metropolitan Section - Hudson & Manhattan Tunnel" 1167:
Ebenezer Talbot, "Machine for tunnelling or boring rock,"
557:
Urban installation for an 2.1-meter (84 in) sewer in
812:"Special Shield Machine | Kawasaki Heavy Industries" 291:
diameter and 2.06 km (6,750 ft) long — between
211:
The first boring machine reported to have been built was
170:
Looking towards the cutting shield at the hydraulic jacks
1900:
The greater genius?: a biography of Marc Isambard Brunel
1194:
John D. Brunton, "Improved machine for sinking shafts,"
1724:"Alaskan Way Viaduct - Recapping Bertha's breakthrough" 1408:
Thales Lindsey, "Improved machine for tunneling rock,"
1017: 1015: 1013: 720: – Method of modern tunnel design and construction 1694:"Bertha the giant drill is ready to rumble in Seattle" 1327:
The Official History of Britain and the Channel Tunnel
1291:(filed: June 4, 1884 ; issued: October 28, 1884). 580:
to maintain pressure at the tunnel face. The muck (or
1560:(filed: February 17, 1908; issued: October 13, 1908). 1479:(filed: April 3, 1893 ; issued: April 23, 1895). 1305:. New York, NY, USA: Harper Collins. pp. 14–21. 1152:
Charles Wilson, "Machine for tunneling rocks, etc.,"
732: – Vehicle that moves through solid rock or soil 1862:(2). Archived from the original on December 11, 2008 1823:. Descend Underwater Training Centre. Archived from 1774: 1772: 1580:
William A. Lathrop, "Machine for cutting headings,"
1441:(filed: July 30, 1907 ; issued: June 23, 1908). 1225:(New York, New York: John Wiley & Sons, 1914), 936: 934: 932: 387:
Two TBMs supplied by CREG excavated two tunnels for
231:, Maus had it built in 1846 in an arms factory near 1611:Technology Evolution", p. 8. Available online at: 1551:(filed: November 29, 1905; issued: March 26, 1907). 1996:Innovation and the Rise of the Tunnelling Industry 1934:(New York, New York: J. Wiley & Sons, 1883), 1423:(filed: December 23, 1901; issued: June 30, 1903). 1461:Charles Wilson, Machine for excavating tunnels," 1426:Russell B. Sigafoos, "Rotary tunneling machine," 714: – Undersea rail tunnel linking France to UK 120:, each of which requires specialized technology. 1586:(filed: August 31, 1903; issued: April 3, 1906). 1432:(filed: May 18, 1907; issued: October 20, 1908). 534:infiltration of ground water into the machine. 356:, Switzerland, the world's longest rail tunnel 1729:Washington State Department of Transportation 352:A tunnel boring machine used to excavate the 123:Tunnel boring machines are an alternative to 8: 1605: 1523: 1435:George A. Fowler, "Tunnel driving machine," 1221:David William Brunton and John Allen Davis, 1076:. North Adams Public Library. Archived from 1055: 1004: 788:. CREG Underground Solutions. Archived from 690:Urban tunnelling and near-surface tunnelling 1925:, 85–88, 106–108, 125–127, 145–146, 165-167 1101:"Hoosac Tunnel History - Abridged Timeline" 398:Top view of a model of the TBM used on the 2012:TBM tunnelling in jointed and faulted rock 1814: 1812: 481:, steel straps, ring steel and wire mesh. 1972:"The Evolution of Tunnel Boring Machines" 1855:South Pacific Underwater Medicine Society 1265:(London, England: Patent Office, 1904), 901:"Tunnel Boring Machines (Shield and TBM)" 433:A tunnel boring machine that was used at 80:Learn how and when to remove this message 1843: 1841: 1574: 1539: 1473:Jonas L. Mitchell, "Tunneling-machine," 1455: 1402: 1125: 1021: 980: 96:One of the boring machines used for the 43:This article includes a list of general 1793:"TBM selection - EPB and SlurrySi Shen" 964: 748: 570:Yucca Mountain nuclear waste repository 435:Yucca Mountain nuclear waste repository 299:, England, through sandstone under the 252:Wilson's Patented Stone-Cutting Machine 2030:Tunnels & Tunnelling International 1872: 1554:Olin S. Proctor, "Tunneling-machine," 1353:"Hudson and Manhattan Railroad Tunnel" 1301:Wilson, Jeremy; Spick, Jérôme (1994). 952: 940: 852:from the original on February 27, 2020 462:Hydraulic jacks holding a TBM in place 1778: 1351:American Society of Civil Engineers. 786:"Special Application TBM U-Shape TBM" 227:between France and Italy through the 127:(D&B) methods and "hand mining". 100:between France and the United Kingdom 7: 1545:John P. Karns, "Tunneling-machine," 1338: 1209: 1182: 992: 1417:Pedro Unanue, "Tunneling machine," 1303:Eurotunnel: The Illustrated Journey 917:from the original on 1 October 2021 419:world's largest-diameter slurry TBM 1137:Charles Wilson, "Dressing stone," 840:Tan, Christopher (June 14, 2016). 267:Frederick Edward Blackett Beaumont 197:first successful tunnelling shield 49:it lacks sufficient corresponding 25: 1673:from the original on 28 July 2023 584:) is admitted into the TBM via a 1970:Potter, Brian (6 October 2023). 34: 1953:Hardrock Tunnel Boring Machines 1848:Bennett, MH; Lehm, J; Barr, P. 1644:from the original on 2023-01-23 882:from the original on 2023-07-28 822:from the original on 2021-09-26 767:from the original on 2020-02-27 548:Zürich Oerlikon railway station 140:horizontal directional drilling 27:Device used to excavate tunnels 1712:– via www.bloomberg.com. 1: 1944:Practical Tunnel Construction 1074:Hooac Tunnel Historical Notes 718:New Austrian tunneling method 372:in 2013. It was delivered to 1976:www.construction-physics.com 1791:Shen, Si (25 October 2021). 1732:. 2017-04-06. Archived from 1663:"Alaskan Way Viaduct - Home" 1405:, pp. 66, 125, 127, 146 726: – Excavation equipment 159:Cutting shield used for the 1634:"Shield Tunneling Machines" 529:Tunnel-face support methods 2099: 1036:Invention & Technology 2046:"Tunneling World Records" 1879:: CS1 maint: unfit URL ( 1638:Hitachi Zosen Corporation 1200:(issued: July 21, 1868). 1158:(issued: March 18, 1856). 1143:(issued: March 13, 1847). 382:Highway 99 tunnel project 370:Hitachi Zosen Corporation 1930:Drinker, Henry Sturgis. 1902:. Ian Allan Publishing. 1467:(issued: June 23, 1857). 1414:(issued: June 12, 1866). 1173:(issued: June 7, 1853). 659:spheroidal graphite iron 2083:19th-century inventions 1898:Bagust, Harold (2006). 136:trenchless construction 64:more precise citations. 2073:Tunnel boring machines 1698:Bloomberg Businessweek 1458:, pp. 66, 85, 106 1381:www.ascemetsection.org 761:www.tunnel-online.info 612:Thames Water Ring Main 573: 561: 550: 538:Earth Pressure Balance 463: 437: 402: 362:earth pressure balance 357: 330:Niagara Tunnel Project 219:. Commissioned by the 186: 171: 163: 101: 2014:. Rotterdam: Balkema. 2010:Barton, Nick (2000). 1038:Vol.20, #2, Fall 2004 736:Trenchless technology 652:Open face soft ground 567: 556: 545: 461: 432: 397: 351: 284:Suez Canal contractor 199:was developed by Sir 177: 169: 158: 125:drilling and blasting 106:tunnel boring machine 95: 1955:. Ernst & Sohn. 1752:www.creg-germany.com 592:. Additives such as 405:The world's largest 400:Gotthard Base Tunnel 354:Gotthard Base Tunnel 201:Marc Isambard Brunel 180:City & Southwest 1583:U.S. patent 816,923 1557:U.S. patent 900,951 1548:U.S. patent 848,107 1542:, pp. 146, 165 1476:U.S. patent 537,899 1438:U.S. patent 891,473 1429:U.S. patent 901,392 1420:U.S. patent 732,326 1288:U.S. patent 307,278 1212:, pp. 243–247. 1185:, pp. 239–242. 908:global.kawasaki.com 816:global.kawasaki.com 792:on 9 September 2017 308:Hudson River Tunnel 237:Revolutions of 1848 223:in 1845 to dig the 2078:British inventions 1942:Hemphill, Gary B. 1618:2016-10-20 at the 1517:2023-07-28 at the 1500:2016-03-04 at the 1464:U.S. patent 17,650 1411:U.S. patent 55,514 1272:2023-07-28 at the 1248:2023-07-28 at the 1197:U.S. patent 80,056 1155:U.S. patent 14,483 1080:on 15 January 2004 1043:2005-03-15 at the 616:London Underground 614:, sections of the 574: 562: 551: 464: 438: 403: 358: 280:Alexandre Lavalley 275:British Parliament 225:Fréjus Rail Tunnel 187: 172: 164: 102: 1962:978-3-433-01676-3 1606:Maidl et al. 2008 1524:Maidl et al. 2008 1170:U.S. patent 9,774 1140:U.S. patent 5,012 1056:Maidl et al. 2008 1005:Maidl et al. 2008 846:The Straits Times 671:tunnelling shield 449:Tunnel wall types 282:, who was also a 90: 89: 82: 16:(Redirected from 2090: 2059: 2057: 2056: 2033: 2024: 2015: 1999: 1990: 1985: 1983: 1982: 1966: 1947: 1938: 1926: 1913: 1885: 1884: 1878: 1870: 1868: 1867: 1845: 1836: 1835: 1833: 1832: 1816: 1807: 1806: 1804: 1803: 1788: 1782: 1776: 1767: 1766: 1764: 1763: 1744: 1738: 1737: 1720: 1714: 1713: 1711: 1709: 1700:. Archived from 1689: 1683: 1682: 1680: 1678: 1667:www.wsdot.wa.gov 1659: 1653: 1652: 1650: 1649: 1630: 1624: 1602:Eisener Bergmann 1600:In Germany, the 1595: 1589: 1585: 1569: 1563: 1559: 1550: 1534: 1528: 1488: 1482: 1478: 1466: 1450: 1444: 1440: 1431: 1422: 1413: 1397: 1391: 1390: 1388: 1387: 1373: 1367: 1366: 1364: 1363: 1348: 1342: 1336: 1330: 1325:Terry Gourvish, 1323: 1317: 1316: 1298: 1292: 1290: 1283: 1277: 1259: 1253: 1235: 1229: 1219: 1213: 1207: 1201: 1199: 1192: 1186: 1180: 1174: 1172: 1165: 1159: 1157: 1150: 1144: 1142: 1135: 1129: 1123: 1117: 1116: 1114: 1112: 1103:. Archived from 1096: 1090: 1089: 1087: 1085: 1065: 1059: 1053: 1047: 1031: 1025: 1019: 1008: 1002: 996: 990: 984: 978: 972: 962: 956: 950: 944: 938: 927: 926: 924: 922: 916: 905: 897: 891: 890: 888: 887: 868: 862: 861: 859: 857: 837: 831: 830: 828: 827: 808: 802: 801: 799: 797: 782: 776: 775: 773: 772: 753: 601:tungsten carbide 559:Chicago, IL, USA 241:pneumatic drills 221:King of Sardinia 203:to excavate the 131:longer tunnels. 85: 78: 74: 71: 65: 60:this article by 51:inline citations 38: 37: 30: 21: 2098: 2097: 2093: 2092: 2091: 2089: 2088: 2087: 2063: 2062: 2054: 2052: 2043: 2040: 2027: 2018: 2009: 2006: 2004:Further reading 1993: 1988: 1980: 1978: 1969: 1963: 1950: 1941: 1929: 1916: 1910: 1897: 1894: 1889: 1888: 1871: 1865: 1863: 1847: 1846: 1839: 1830: 1828: 1818: 1817: 1810: 1801: 1799: 1790: 1789: 1785: 1777: 1770: 1761: 1759: 1746: 1745: 1741: 1722: 1721: 1717: 1707: 1705: 1691: 1690: 1686: 1676: 1674: 1661: 1660: 1656: 1647: 1645: 1632: 1631: 1627: 1620:Wayback Machine 1596: 1592: 1581: 1570: 1566: 1555: 1546: 1535: 1531: 1519:Wayback Machine 1502:Wayback Machine 1489: 1485: 1474: 1462: 1451: 1447: 1436: 1427: 1418: 1409: 1398: 1394: 1385: 1383: 1375: 1374: 1370: 1361: 1359: 1350: 1349: 1345: 1337: 1333: 1324: 1320: 1313: 1300: 1299: 1295: 1286: 1284: 1280: 1274:Wayback Machine 1260: 1256: 1250:Wayback Machine 1236: 1232: 1220: 1216: 1208: 1204: 1195: 1193: 1189: 1181: 1177: 1168: 1166: 1162: 1153: 1151: 1147: 1138: 1136: 1132: 1124: 1120: 1110: 1108: 1098: 1097: 1093: 1083: 1081: 1067: 1066: 1062: 1054: 1050: 1045:Wayback Machine 1032: 1028: 1020: 1011: 1003: 999: 991: 987: 979: 975: 963: 959: 951: 947: 939: 930: 920: 918: 914: 903: 899: 898: 894: 885: 883: 870: 869: 865: 855: 853: 839: 838: 834: 825: 823: 810: 809: 805: 795: 793: 784: 783: 779: 770: 768: 755: 754: 750: 745: 708: 692: 679: 667: 654: 629: 618:, and most new 540: 531: 522: 513: 501: 487: 475: 456: 454:Concrete lining 451: 427: 415:Herrenknecht AG 413:, was built by 346: 317: 271:English Channel 217:Mountain Slicer 193: 188: 161:New Elbe Tunnel 152: 86: 75: 69: 66: 56:Please help to 55: 39: 35: 28: 23: 22: 15: 12: 11: 5: 2096: 2094: 2086: 2085: 2080: 2075: 2065: 2064: 2061: 2060: 2039: 2038:External links 2036: 2035: 2034: 2025: 2021:The New Yorker 2016: 2005: 2002: 2001: 2000: 1994:West, Graham. 1991: 1986: 1967: 1961: 1948: 1939: 1927: 1921:, p. 58, 1919:Mining Science 1914: 1908: 1893: 1890: 1887: 1886: 1837: 1808: 1783: 1768: 1739: 1736:on 2017-09-01. 1715: 1692:Weise, Karen. 1684: 1654: 1625: 1623: 1622: 1608: 1590: 1588: 1587: 1578: 1564: 1562: 1561: 1552: 1543: 1529: 1527: 1526: 1521: 1505: 1483: 1481: 1480: 1471: 1468: 1459: 1445: 1443: 1442: 1433: 1424: 1415: 1406: 1392: 1368: 1343: 1341:, p. 248. 1331: 1318: 1311: 1293: 1278: 1254: 1230: 1214: 1202: 1187: 1175: 1160: 1145: 1130: 1118: 1107:on 21 May 2011 1091: 1060: 1048: 1026: 1009: 997: 985: 973: 957: 945: 928: 892: 863: 832: 803: 777: 747: 746: 744: 741: 740: 739: 733: 727: 721: 715: 712:Channel Tunnel 707: 704: 691: 688: 678: 677:Backup systems 675: 666: 663: 653: 650: 628: 625: 608:Channel Tunnel 586:screw conveyor 539: 536: 530: 527: 521: 518: 512: 509: 500: 497: 486: 483: 474: 471: 455: 452: 450: 447: 426: 423: 409:TBM, known as 345: 342: 316: 313: 192: 189: 153: 151: 148: 98:Channel Tunnel 88: 87: 42: 40: 33: 26: 24: 14: 13: 10: 9: 6: 4: 3: 2: 2095: 2084: 2081: 2079: 2076: 2074: 2071: 2070: 2068: 2051: 2047: 2042: 2041: 2037: 2031: 2026: 2022: 2017: 2013: 2008: 2007: 2003: 1997: 1992: 1987: 1977: 1973: 1968: 1964: 1958: 1954: 1949: 1945: 1940: 1937: 1933: 1928: 1924: 1920: 1915: 1911: 1909:0-7110-3175-4 1905: 1901: 1896: 1895: 1891: 1882: 1876: 1861: 1857: 1856: 1851: 1844: 1842: 1838: 1827:on 2003-09-24 1826: 1822: 1815: 1813: 1809: 1798: 1794: 1787: 1784: 1780: 1775: 1773: 1769: 1758:on 2017-09-09 1757: 1753: 1749: 1743: 1740: 1735: 1731: 1730: 1725: 1719: 1716: 1704:on 2016-03-09 1703: 1699: 1695: 1688: 1685: 1672: 1668: 1664: 1658: 1655: 1643: 1639: 1635: 1629: 1626: 1621: 1617: 1614: 1609: 1607: 1603: 1599: 1598: 1597:For example: 1594: 1591: 1584: 1579: 1577:, p. 145 1576: 1575:Bancroft 1908 1573: 1572: 1568: 1565: 1558: 1553: 1549: 1544: 1541: 1540:Bancroft 1908 1538: 1537: 1533: 1530: 1525: 1522: 1520: 1516: 1513: 1509: 1506: 1503: 1499: 1496: 1492: 1491: 1487: 1484: 1477: 1472: 1469: 1465: 1460: 1457: 1456:Bancroft 1908 1454: 1453: 1449: 1446: 1439: 1434: 1430: 1425: 1421: 1416: 1412: 1407: 1404: 1403:Bancroft 1908 1401: 1400: 1396: 1393: 1382: 1378: 1372: 1369: 1358: 1354: 1347: 1344: 1340: 1335: 1332: 1328: 1322: 1319: 1314: 1312:0-00-255539-5 1308: 1304: 1297: 1294: 1289: 1282: 1279: 1275: 1271: 1268: 1264: 1258: 1255: 1251: 1247: 1244: 1240: 1234: 1231: 1228: 1224: 1218: 1215: 1211: 1206: 1203: 1198: 1191: 1188: 1184: 1179: 1176: 1171: 1164: 1161: 1156: 1149: 1146: 1141: 1134: 1131: 1128:, p. 65. 1127: 1126:Bancroft 1908 1122: 1119: 1106: 1102: 1095: 1092: 1079: 1075: 1071: 1068:Smith, Gary. 1064: 1061: 1057: 1052: 1049: 1046: 1042: 1039: 1037: 1030: 1027: 1023: 1022:Hemphill 2013 1018: 1016: 1014: 1010: 1006: 1001: 998: 994: 989: 986: 983:, p. 58. 982: 981:Bancroft 1908 977: 974: 970: 966: 961: 958: 955:, p. 65. 954: 949: 946: 942: 937: 935: 933: 929: 913: 909: 902: 896: 893: 881: 877: 873: 867: 864: 851: 847: 843: 836: 833: 821: 817: 813: 807: 804: 791: 787: 781: 778: 766: 762: 758: 752: 749: 742: 737: 734: 731: 728: 725: 722: 719: 716: 713: 710: 709: 705: 703: 699: 697: 689: 687: 685: 676: 674: 672: 664: 662: 660: 651: 649: 646: 641: 637: 635: 627:Slurry shield 626: 624: 621: 617: 613: 609: 604: 602: 597: 595: 591: 587: 583: 579: 571: 566: 560: 555: 549: 544: 537: 535: 528: 526: 520:Double shield 519: 517: 511:Single shield 510: 508: 504: 498: 496: 493: 484: 482: 480: 472: 470: 467: 460: 453: 448: 446: 442: 436: 431: 424: 422: 420: 416: 412: 408: 401: 396: 392: 390: 385: 383: 379: 375: 371: 367: 364:TBM known as 363: 355: 350: 343: 341: 339: 335: 334:Niagara Falls 331: 326: 323: 314: 312: 309: 304: 302: 298: 294: 289: 285: 281: 276: 272: 268: 263: 259: 257: 253: 249: 248:Hoosac Tunnel 244: 242: 238: 234: 230: 226: 222: 218: 214: 209: 206: 205:Thames Tunnel 202: 198: 190: 185: 181: 176: 168: 162: 157: 149: 147: 143: 141: 137: 132: 128: 126: 121: 119: 115: 111: 107: 99: 94: 84: 81: 73: 70:November 2010 63: 59: 53: 52: 46: 41: 32: 31: 19: 2053:. Retrieved 2049: 2029: 2020: 2011: 1995: 1979:. Retrieved 1975: 1952: 1943: 1936:pp. 191-194. 1931: 1918: 1899: 1875:cite journal 1864:. Retrieved 1859: 1853: 1829:. Retrieved 1825:the original 1819:Walters, D. 1800:. Retrieved 1796: 1786: 1760:. Retrieved 1756:the original 1751: 1748:"CREG | EPB" 1742: 1734:the original 1727: 1718: 1706:. Retrieved 1702:the original 1697: 1687: 1675:. Retrieved 1666: 1657: 1646:. Retrieved 1637: 1628: 1601: 1593: 1567: 1532: 1507: 1486: 1448: 1395: 1384:. Retrieved 1380: 1371: 1360:. Retrieved 1357:www.asce.org 1356: 1346: 1334: 1326: 1321: 1302: 1296: 1281: 1262: 1257: 1238: 1233: 1222: 1217: 1205: 1190: 1178: 1163: 1148: 1133: 1121: 1109:. Retrieved 1105:the original 1094: 1082:. Retrieved 1078:the original 1073: 1063: 1058:, p. 1. 1051: 1035: 1029: 1000: 988: 976: 965:Drinker 1883 960: 948: 919:. Retrieved 910:. Kawasaki. 907: 895: 884:. Retrieved 875: 866: 856:February 27, 854:. Retrieved 845: 835: 824:. Retrieved 815: 806: 794:. Retrieved 790:the original 780: 769:. Retrieved 760: 751: 700: 693: 680: 668: 655: 642: 638: 630: 605: 598: 575: 532: 523: 514: 505: 502: 499:Open/Gripper 491: 488: 485:Shield types 476: 468: 465: 443: 439: 406: 404: 389:Kuala Lumpur 386: 359: 327: 318: 305: 301:Mersey River 264: 260: 251: 245: 216: 210: 194: 184:Sydney Metro 182:line of the 144: 133: 129: 122: 109: 105: 103: 76: 67: 48: 18:Bored tunnel 967:, pp.  953:Bagust 2006 941:Potter 2023 876:Komatsu Ltd 665:Tunnel size 256:disc harrow 138:methods or 62:introducing 2067:Categories 2055:2023-10-18 1981:2023-10-08 1892:References 1866:2008-10-08 1831:2008-10-08 1802:2023-10-29 1797:The Si-Eng 1779:Stack 1995 1762:2020-11-03 1648:2023-02-04 1386:2023-10-17 1362:2023-10-17 1099:Howes, M. 921:2 November 886:2021-10-02 826:2021-10-02 796:2 November 771:2020-02-27 730:Subterrene 724:Roadheader 696:subsidence 572:in Nevada. 380:, for its 378:Washington 293:Birkenhead 213:Henri Maus 45:references 2044:Robbins. 1339:West 1988 1210:West 1988 1183:West 1988 993:West 1988 684:pipelines 634:bentonite 594:bentonite 479:shotcrete 473:Main Beam 407:hard rock 338:Adam Beck 322:hole saws 297:Liverpool 1671:Archived 1642:Archived 1616:Archived 1515:Archived 1498:Archived 1270:Archived 1246:Archived 1041:Archived 912:Archived 880:Archived 850:Archived 820:Archived 765:Archived 706:See also 288:Sangatte 273:and the 2050:Robbins 1708:21 July 1677:21 July 1512:p. 275. 1495:AditNow 1267:p. 169. 1243:p. 247. 1227:p. 182. 1111:14 July 1084:14 July 969:191-194 645:caisson 492:shields 411:Martina 374:Seattle 150:History 114:tunnels 58:improve 1959:  1906:  1309:  610:, the 590:slurry 366:Bertha 47:, but 1923:65-68 1571:See: 1536:See: 1490:See: 1452:See: 1399:See: 915:(PDF) 904:(PDF) 743:Notes 620:metro 582:spoil 425:Types 344:2000s 315:1900s 233:Turin 191:1800s 1957:ISBN 1904:ISBN 1881:link 1710:2017 1679:2017 1307:ISBN 1113:2011 1086:2011 923:2021 858:2020 798:2021 578:muck 306:The 295:and 229:Alps 195:The 118:sand 360:An 215:'s 110:TBM 2069:: 2048:. 1974:. 1877:}} 1873:{{ 1860:32 1858:. 1852:. 1840:^ 1811:^ 1795:. 1771:^ 1750:. 1726:. 1696:. 1669:. 1665:. 1640:. 1636:. 1379:. 1355:. 1072:. 1012:^ 931:^ 906:. 878:. 874:. 848:. 844:. 818:. 814:. 763:. 759:. 643:A 376:, 303:. 243:. 104:A 2058:. 2032:. 2023:. 1984:. 1965:. 1912:. 1883:) 1869:. 1834:. 1805:. 1781:. 1765:. 1681:. 1651:. 1504:. 1389:. 1365:. 1315:. 1276:) 1252:) 1115:. 1088:. 1024:. 1007:. 995:. 971:. 943:. 925:. 889:. 860:. 829:. 800:. 774:. 108:( 83:) 77:( 72:) 68:( 54:. 20:)

Index

Bored tunnel
references
inline citations
improve
introducing
Learn how and when to remove this message

Channel Tunnel
tunnels
sand
drilling and blasting
trenchless construction
horizontal directional drilling

New Elbe Tunnel


City & Southwest
Sydney Metro
first successful tunnelling shield
Marc Isambard Brunel
Thames Tunnel
Henri Maus
King of Sardinia
Fréjus Rail Tunnel
Alps
Turin
Revolutions of 1848
pneumatic drills
Hoosac Tunnel

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.