Knowledge (XXG)

Cantref Reservoir

Source 📝

323:, on which work did not start until 1911, it ran along the valley floor. At first, it may have crossed over the river near Nant-Ddu lodge, and run along its eastern bank to the foot of the dam, but it later stayed on the western bank to reach the top of the dam. The track was built by William Jones, the first contractor for the reservoir, on the basis that it would be taken over by the Corporation. Work began on it around April 1886, and it was largely finished by October, although storm damage meant that some of the ballasting was delayed. After Jones' reservoir contract had been revoked, the railway was valued at £3,395 in December 1888 as part of the settlement litigation. A temporary incline was constructed in June 1889 to the north of the dam, but it is not clear whether this began at the lower level and was used to raise materials, or began at the higher level and was used to lower them to the worksite. 274:
sites, and by the time the first sod was cut for the reservoir by the Mayor on 4 May 1886, around 2 miles (3.2 km) of the railway had already been completed. Jones succeeded in cutting the embankment trench and filling the bottom with a concrete key, but he lacked funds, and did not have enough pumping plant to keep the workings dry. Many of his labourers left the job, and progress became very slow. The Town Clerk took possession of the works on 29 October 1888, which included Jones' plant, tools and implements. Jones then took out a writ against the Corporation, and an agreement was not reached until June 1889, with the Corporation paying £10,000 to the court in July.
339:
for free. When the railway was no longer needed, the land would be reinstated, or the landowner could buy it. However, around 1.04 miles (1.67 km) of track were lifted in March 1892, after a disagreement developed. This was probably a new section which was part of the northern extension, but the difficulties were eventually resolved, and the track was reinstated in April 1893. The Board of Trade approved the plans for the extension on 27 April 1893 and by June, two timber viaducts had been built, to carry the railway over ravines on the west bank of the reservoir, and the Beacons site was reached, creating a railway that was 7.25 miles (11.67 km) in length.
278:
progress was slow, with the extremely wet weather of 1890 being a significant factor. He struggled to retain his workforce, and wrote to J A B Williams explaining the difficulties. By February 1891 he had completed about half of the job, and on 18 March 1891 the Water Committee relieved him of his contract, paid for the work that had been done, and took possession of his plant, railways, a quarry and a clay field from which the puddle clay was extracted. Mackay's involvement with the project ceased on 13 June 1891.
31: 44: 282:
Committee, and impounding of water began on the same day. A plaque to commemorate the event named the Waterworks Engineer, J A B Williams, but failed to mention either of the contractors. The weir and the steps of the overflow channel on the western side of the dam were faced in granite obtained from Cornwall, but the rest of the stone was obtained from a quarry near Cefn Coed, served by sidings on the railway, at which extraction began while Jones was fulfilling his contract.
252:, who also recommended the Taff Fawr scheme in June 1882 as the one most likely to meet the needs for water at the lowest cost. They presented a bill to Parliament in November 1883, which was considered by a House of Commons Committee between 1 May and 20 May 1884. There were 16 petitions against it and serious opposition from riparian landowners, but several influential civil engineers was called to give evidence, notably Bateman, 613: 51: 354:)-gauge railway was used to transfer the clay from the field to the main line railway. It was then moved to the Corporation sidings at Cefn Coed, from where the private locomotives hauled it up the valley to Cantref. One narrow gauge locomotive is known to have worked at the clay pit, an 0-4-0 saddle tank named 277:
Meanwhile, a new contract was awarded in March 1889 to John Mackay of Newport, who had previously completed work on Llanishen Reservoir and the balancing reservoirs at Blackbrook, Cefn and Rhubina for the Corporation. The contract was for £89,619, and he had two years to complete the work, but again
260:
The catchment of the upper Taff Fawr was 10,400 acres (42 km) but it was split into an upper area of 4,000 acres (16 km) and a lower one of 6,400 acres (26 km). Any works had to provide compensation water to maintain the flow in the Taff Fawr, and working on the upper area first meant
365:
Tracing the history of the standard gauge locomotives used on the construction project is a little more difficult. Jones, the first contractor, is known to have had one locomotive, and possibly a second. When Mackay took over the contract, he bought four more with him, and so there were five or six
338:
to be built. In 1891 the Corporation negotiated with Lewis to allow the railway to remain in place for another six years, and it was agreed, providing that the route was properly fenced, gates were provided at level crossings where necessary, and goods for local farms could be transported from Cefn
247:
in 1879, and in March 1881 asked their Borough Engineer, John Avery Brandon Williams, to produce a report on all possible sources of water for Cardiff, so that they could plan for the future. Williams presented his reports in May and August 1881, suggesting that the best scheme was to impound the
273:
Initially the contract for construction of the earth dam, which was about 600 feet (180 m) long with a puddle clay core, was awarded to William Jones of Neath. To provide access to the site, a standard gauge railway, some 6 miles (9.7 km) long, was built from Cefn Coed to the reservoir
285:
As built, the crest of the dam was 120 feet (37 m) above the foundations, and 90 feet (27 m) above the level of the river. At its maximum, the water is 73 feet (22 m) deep, and the dam created a reservoir which is 0.75 miles (1.21 km) long, holding 323 million imperial
281:
Completion of the reservoir was achieved by using direct labour. J T Jones was the first site manager, but became ill, and this role was taken over by F Orton in November 1881. The reservoir was formally opened on 14 September 1892 by Alderman David Jones, who was chairman of the Waterworks
318:
station, and passed through a rocky gorge, where a trestle bridge was built to carry it over the Taff Fawr. The bridge was 150 feet (46 m) long, and some 50 feet (15 m) above the river. After that, it ran on a ledge to the west of the river, and by the time it reached the site of
256:
James Mansergh, and George H. Hill. J A B Williams, their own Engineer, and the meteorologist George James Symonds also gave evidence, and although it cost the Corporation £3,652 to fight the case, Royal Assent was obtained for the Cardiff Corporation Act 1884 on 7 August.
358:, which was obtained second-hand from the Bargoed Coal Company of Fochriw around 1885. It was probably obtained by Mackay, but passed into Corporation ownership when his contract was terminated, and was sold to the Crawshay Brothers in early 1897 for £150, becoming their 261:
that they only had to supply 3 million imperial gallons (14 Ml) per day of compensation flow until work started on the lower area. Cantref Reservoir, at the time known as Cantreff, was the first to be built, together with a 32-mile (51 km) pipeline to
269:
and intermediate balancing reservoirs at Blackbrook, Cefn, and Rhubina. Work on the pipeline was completed in September 1888, and on the balancing reservoirs in November 1888. Construction or the reservoir was not so straight forward.
370:, the identity of which is less certain. There were three sales of plant and equipment in 1897 and 1898, at which eight locomotives were listed, so it is possible that some were offered for sale more than once. One locomotive, named 366:
operating during this period. The Corporation bought a second-hand locomotive in 1891, and two new ones in 1891 and 1894. Four 0-6-0 and two 0-4-0 saddle tanks have been positively identified, and there was a locomotive named
683: 306:
The remote location of Cantref Reservoir and the huge amount of material needed to construct the dam resulted in plans for a standard gauge railway to be built. This left the
625: 311: 693: 86: 374:
was definitely auctioned at the final sale on 2 September 1898 and subsequently worked in the Northamptonshire ironstone industry until 1962.
394: 342:
Puddle clay for the construction of the core of the dam was obtained from land owned by the Crawshay Brothers, part of their ironworks near
290:. Unlike the other two reservoirs in the chain, the size as built was that specified by the original Act of 1884, whereas the capacity of 43: 220: 632: 327: 307: 244: 186: 286:
gallons (1,470 Ml). It covers an area of 42.85 acres (17.34 ha) and its surface level is 1,073 feet (327 m)
673: 201: 194: 617: 30: 205: 678: 249: 248:
waters of the upper Taff Fawr. The Corporation were a little hesitant, but consulted the water engineer
287: 688: 405: 266: 232: 415: 320: 315: 295: 213: 390: 335: 291: 262: 427: 253: 343: 130: 667: 331: 118: 658: 330:
to the south of Cantref, and was later extended northwards over land belonging to
209: 190: 659:
www.geograph.co.uk : photos of the Cantref reservoir and surrounding area
228: 178: 346:. It was located near the Six Bells public house at Pen-yr-Heolgerrig, and a 101: 88: 174: 123: 612: 651: 198: 182: 72: 224: 523: 521: 496: 494: 407:
History of the Cardiff Corporation Waterworks Undertaking
189:
between 1886 and 1892, but since 1973 has been owned by
160: 152: 144: 140: 129: 117: 78: 68: 23: 79: 684:Reservoirs in the Brecon Beacons National Park 8: 596: 584: 572: 560: 527: 512: 500: 385:Bowtell, Harold D; Hill, Geoffrey (2006). 312:Brecon and Merthyr Tydfil Junction Railway 212:. Part of the south west corner is in the 20: 50: 539: 485: 473: 461: 449: 442: 326:The railway was built on land owned by 243:Cardiff Corporation had bought out the 423: 413: 298:was doubled when construction began. 7: 14: 551:Ordnance Survey, 1:2500 map, 1904 387:Reservoir Builders of South Wales 611: 308:London and North Western Railway 49: 42: 29: 404:Wheatley, Joseph Larke (1905). 159: 151: 143: 694:Cardiff Corporation Waterworks 626:"Welsh Water Recreation Guide" 389:. Industrial Railway Society. 187:Cardiff Corporation Waterworks 1: 67: 195:Brecon Beacons National Park 334:to enable the reservoir at 173:is the middle of the three 156:42.85 acres (17.34 ha) 710: 245:Cardiff Waterworks Company 206:historic county boundaries 410:. British History Online. 148:0.75 miles (1.21 km) 37: 28: 216:unitary authority area. 597:Bowtell & Hill 2006 585:Bowtell & Hill 2006 573:Bowtell & Hill 2006 561:Bowtell & Hill 2006 528:Bowtell & Hill 2006 513:Bowtell & Hill 2006 501:Bowtell & Hill 2006 193:. It is located in the 164:1,073 feet (327 m) 250:John Frederick Bateman 202:unitary authority area 620:at Wikimedia Commons 638:on 28 September 2011 288:Above Ordnance Datum 102:51.83194°N 3.46111°W 674:Reservoirs in Powys 476:, pp. 462–463. 464:, pp. 461–462. 267:Llanishen Reservoir 227:and links with the 98: /  575:, pp. 11, 13. 321:Llwyn-on Reservoir 316:Cefn-coed-y-cymmer 214:Rhondda Cynon Taff 185:. It was built by 107:51.83194; -3.46111 18:Reservoir in Wales 618:Cantref Reservoir 616:Media related to 599:, pp. 14–18. 563:, pp. 10–11. 396:978-0-9540726-2-9 328:Sir William Lewis 263:Lisvane Reservoir 171:Cantref Reservoir 168: 167: 161:Surface elevation 57:Cantref Reservoir 24:Cantref Reservoir 701: 655: 647: 645: 643: 637: 631:. Archived from 630: 615: 600: 594: 588: 582: 576: 570: 564: 558: 552: 549: 543: 537: 531: 525: 516: 515:, pp. 9–10. 510: 504: 498: 489: 483: 477: 471: 465: 459: 453: 447: 431: 425: 421: 419: 411: 400: 353: 349: 314:joint line near 197:, mostly in the 113: 112: 110: 109: 108: 103: 99: 96: 95: 94: 91: 81: 53: 52: 46: 33: 21: 709: 708: 704: 703: 702: 700: 699: 698: 664: 663: 649: 641: 639: 635: 628: 624: 609: 604: 603: 595: 591: 583: 579: 571: 567: 559: 555: 550: 546: 538: 534: 526: 519: 511: 507: 499: 492: 484: 480: 472: 468: 460: 456: 448: 444: 439: 434: 422: 412: 403: 397: 384: 380: 351: 347: 304: 254:Thomas Hawksley 241: 221:public footpath 204:and within the 133: countries 106: 104: 100: 97: 92: 89: 87: 85: 84: 64: 63: 62: 61: 60: 59: 58: 54: 19: 12: 11: 5: 707: 705: 697: 696: 691: 686: 681: 676: 666: 665: 662: 661: 656: 608: 607:External links 605: 602: 601: 589: 577: 565: 553: 544: 542:, p. 464. 532: 517: 505: 490: 488:, p. 463. 478: 466: 454: 452:, p. 459. 441: 440: 438: 435: 433: 432: 401: 395: 381: 379: 376: 344:Merthyr Tydfil 303: 300: 240: 237: 166: 165: 162: 158: 157: 154: 150: 149: 146: 142: 141: 138: 137: 136:United Kingdom 134: 127: 126: 121: 115: 114: 82: 76: 75: 70: 66: 65: 56: 55: 48: 47: 41: 40: 39: 38: 35: 34: 26: 25: 17: 13: 10: 9: 6: 4: 3: 2: 706: 695: 692: 690: 687: 685: 682: 680: 679:Dams in Powys 677: 675: 672: 671: 669: 660: 657: 653: 634: 627: 623: 622: 621: 619: 614: 606: 598: 593: 590: 587:, p. 18. 586: 581: 578: 574: 569: 566: 562: 557: 554: 548: 545: 541: 540:Wheatley 1905 536: 533: 530:, p. 10. 529: 524: 522: 518: 514: 509: 506: 502: 497: 495: 491: 487: 486:Wheatley 1905 482: 479: 475: 474:Wheatley 1905 470: 467: 463: 462:Wheatley 1905 458: 455: 451: 450:Wheatley 1905 446: 443: 436: 429: 417: 409: 408: 402: 398: 392: 388: 383: 382: 377: 375: 373: 369: 363: 361: 357: 345: 340: 337: 333: 332:Lord Tredegar 329: 324: 322: 317: 313: 309: 301: 299: 297: 293: 289: 283: 279: 275: 271: 268: 264: 258: 255: 251: 246: 238: 236: 234: 230: 226: 222: 217: 215: 211: 207: 203: 200: 196: 192: 188: 184: 180: 176: 172: 163: 155: 147: 139: 135: 132: 128: 125: 122: 120: 116: 111: 83: 77: 74: 71: 45: 36: 32: 27: 22: 16: 640:. Retrieved 633:the original 610: 592: 580: 568: 556: 547: 535: 508: 503:, p. 9. 481: 469: 457: 445: 406: 386: 378:Bibliography 371: 367: 364: 360:Cyfarthfa 14 359: 355: 341: 325: 305: 284: 280: 276: 272: 259: 242: 233:Navvies Line 223:crosses the 218: 170: 169: 153:Surface area 15: 424:|work= 352:914 mm 210:Breconshire 191:Welsh Water 145:Max. length 105: / 80:Coordinates 689:River Taff 668:Categories 650:(409  437:References 229:Taff Trail 181:valley in 175:reservoirs 90:51°49′55″N 426:ignored ( 416:cite book 348:3 ft 179:Taff Fawr 124:reservoir 93:3°27′40″W 372:Cantreff 302:Railways 296:Llwyn-on 231:and the 69:Location 642:31 July 368:Swansea 356:Darrell 336:Beacons 292:Beacons 239:History 235:paths. 177:in the 648:  393:  636:(PDF) 629:(PDF) 199:Powys 183:Wales 131:Basin 73:Wales 644:2011 428:help 391:ISBN 294:and 265:and 119:Type 652:KiB 225:dam 208:of 670:: 520:^ 493:^ 420:: 418:}} 414:{{ 362:. 219:A 654:) 646:. 430:) 399:. 350:( 310:/

Index


Cantref Reservoir is located in Wales
Wales
51°49′55″N 3°27′40″W / 51.83194°N 3.46111°W / 51.83194; -3.46111
Type
reservoir
Basin
reservoirs
Taff Fawr
Wales
Cardiff Corporation Waterworks
Welsh Water
Brecon Beacons National Park
Powys
unitary authority area
historic county boundaries
Breconshire
Rhondda Cynon Taff
public footpath
dam
Taff Trail
Navvies Line
Cardiff Waterworks Company
John Frederick Bateman
Thomas Hawksley
Lisvane Reservoir
Llanishen Reservoir
Above Ordnance Datum
Beacons
Llwyn-on

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.