Knowledge (XXG)

Electricity sector in Bolivia

Source 📝

1009:) was proposed. Under the framework of this Law, the program called ‘Electricity for a Decent Living” has been designed to improve both rural and urban electrification. The short-term goal (2006–2010) of the program is to increase rural electrification to 53% (connection of 210,000 new households) and urban electrification to 97% (connection of 460,000 new households). The medium-term goal (2010–2015) is to achieve universal access in urban areas and a 70% access in rural ones. In the final stages, rural access would have increased to 87% by 2020 and universal coverage would be reached by 2025. The Law also mandates de creation of a Common Fund for Universal Access to Public Electricity Service (FOCO) and creates a co-financing mechanism of the National Government with Prefectures, municipalities and the private sector. However, the Law has not been approved yet, although it is expected that the Law and the mechanisms it creates will be approved soon. 983:). This new decree aims at increasing rural access through the extension and densification of electric networks, development of renewable energy and a change in the energy mix (substitution of diesel by natural gas, biomass and other renewable energies) and an increase in distribution capacity. The Rural Electrification Decree and its associated regulatory framework encourages stakeholders in the energy sector to establish partnerships with other government agencies to implement the rural electrification plan. An agreement between the Ministry of Public Works, Services and Housing and the Ministry of Education will allow for the installation of solar 696:
small organizations that serve family communities. This situation faces a legal vacuum since the consumers benefiting from these scheme, who do not consume the minimum power established legally established, cannot be considered as regulated ones. In addition, these consumers are localized outside the distribution companies’ concession areas, so they cannot receive the companies’ service. In practice, the distribution companies are reselling electricity to the mentioned organizations outside the legal framework. Accurate information on the number of organizations that operate in rural areas does not exist. However, there are approximately three in
769:
which is below the 51% average for the region. Installed hydroelectric capacity in 2016 was 494 MW, distributed amongst some 21 facilities. The largest plant is the 93 MW Saint Isabel, operated by Corani. Bolivia is working with Brazil on a huge joint project to exploit the hydro-electric potential of the Rio Madeira complex in the Amazon region. Within this project are the 800 MW Cachuela Esperanza plant sited entirely in Bolivia and the Guajara-Mirim plant (3000 MW) to be located on the border between the two countries.
22: 452: 672:(REE). As of 2013, its transmission network extended 2,850 km, representing 79% of the national total. ISA Bolivia, which runs 587 km, or 16%, of the transmission network in Bolivia, is a subsidiary of Interconexión Eléctrica S.A. (ISA), a corporation controlled by the government of Colombia. San Cristobal TESA has 172 km of transmission lines, or 5%. The number of companies is limited due to the existence of institutional entry barriers in this sector. 807: 1318:) and the Viceministry of Electricity and Alternative Energy recently signed an agreement to execute a Project for Network Densification in rural areas. Distribution cooperatives will also play an important role in this project, which is part of the program “Electricity to live with dignity”. To facilitate the access to electricity, the Viceministry and GIZ will provide a US$ 20 subsidy per household to enable their connection to the existing network. 2984: 932:) dominated the sector. In 1994, Bolivia initiated an infrastructure reform program that included the privatization of the major state owned enterprises. The Electricity Law 1994/1604 mandated the privatization of the electricity system and the unbundling of generation, transmission and distribution activities. The law aimed to increase efficiency in the sector, promote competition and encourage investment. 110: 976:
connections within five years (increasing electricity access in rural areas from 23% to 45%). It had been estimated that, by the end of the program, PLABER would have reached its goals by 70% of the initial objective. However, the model established by this program did not have significant effects in increasing coverage, expanding infrastructure and improving service quality in rural and isolated areas.
2994: 1368: 1382: 850:. One of the first overhead power lines run around 50 km between the Incachaca power station and Cochabamba. The hydroelectric station and power line were built in 1914 by a german company and served both urban electrification and the traction of the Cochabamba - Vinto - Arani railway. The ruins of the Incachaca power station are a tourist destination today. 1060:(“Dignity Tariff”) by Supreme Decree 28653. This tariff grants a 25% discount in their electricity bills to those consumers whose monthly consumption is below 70 kWh in the urban areas and 30 kWh in the rural ones. This subsidy, which will be covered for four years by the electricity companies that operate in Bolivia, will benefit about 480,000 households. 940:, a private company, which acquired exclusive rights. Finally, several distribution firms were created after the reform. All those firms operate under tariff regulation and are subject to tariff controls. CRE (Cooperative for Rural Electrification), a pre-existing distribution cooperative, maintained its position as an independent regional monopoly. CESSA ( 1110:) being the most important. Transmission in the National Interconnected System is in the hands of just two companies as entry in this sector is institutionally restricted. As for distribution, the six existing companies enjoy a geographic monopoly in their concession areas. The largest company is Electropaz, which is majority-owned by Spain's Iberdrola. 1113:
In May 2010 president Evo Morales nationalized 80% of Bolivian generation by capacity, in his Government's attempt to regain ownership of public service companies. Corani, Guarachi, and Valle Hermoso, where expropriated from their former British and French owners. In the same fashion, in May 2012 the
1072:
In the period 1995-2004, total investment in transmission represented only a modest 2% (US$ 14 million) of the total investment in the electricity sector. Generation and distribution received 58% and 40% of total investment respectively. For the year 2004 in particular, total public investment in the
916:
Electrification supplied larger cities and the mining sector, while rural area were mostly neglected. Electrification furthermore covered mainly the western parts of the country until 1941/1942, when the agricultural and hydrocarbon sector in the eastern parts of the country were developed. Though,
853:
Increasing need for electricity in the mining sector led to the construction of larger hydroelectric power stations, primarly in the western areas of the country. In the first half of the 20th century, mining companies erected first regional power grids (Foto). Because many of the larger mines were
768:
Bolivia has a considerable hydro potential, its technically feasible potential being assessed at 126 TWh/yr, of which 50 TWh/yr is considered to be economically exploitable. Only a small proportion of the total potential has been harnessed so far. The share of hydropower capacity in Bolivia is 40%,
1047:
Electricity prices charged by the distribution companies to their regulated clients include energy costs (including generation and transmission costs) and all the distribution costs, including a specific return on investment. However, as it was mentioned before, some distribution companies resell
695:
In some cases, especially in the high plateau, cooperatives and community organizations access the distribution companies’ network and sell electricity to small rural communities. Sometimes, those are organized enterprises that provide the service to middle-size towns, but in most cases, they are
601:
average in 2005. In the period November 2004 – October 2005 there were a total of 141 transmission interruptions (up from 86 in the previous period), with a total duration of 4,274 minutes. 57% of the interruptions were due to weather conditions and, while 17% derived from facility operations. In
1253:
The “Decentralized Electricity for Universal Access” project, funded by the Global Partnership on Output-based Aid, which is administered by the World Bank, plans to extend electricity access to at least 7,000 poor households, micro-enterprises and social uses in remote and dispersed rural areas
935:
As a result of privatization, three generation companies were created: Corani, Guaracachi and Valle Hermoso. Each of them received a part of ENDE's generation activities (the law limited the market share of each to 35%). Initially, these firms were granted exclusive rights, but by 1999 entry was
500:
The national government's priorities for the electricity sector include providing universal access to electricity and producing surplus energy for export. The electricity coverage in rural areas is among the lowest in Latin America and improving it represents a major challenge in the future. The
975:
In 2002, the government established Bolivia's Rural Electrification Plan (PLABER) with the objective of contributing to the socio-economic development of rural areas through access to electricity and its efficient and productive uses. The short-term goal of the program was to make 200,000 new
777:
The World Bank is financing a rural infrastructure project in Bolivia which, among others, plans to install 17,000 solar home systems by 2009. Another project funded by the Global Partnership on Out-based Aid which is administered by the World Bank intends to scale up the installations by an
759:
or PV, wind, etc.) for disperse populations was recognized by the government in the Rural Electrification Plan (PLABER). This component established that the service to households, schools and health facilities in areas of low population density would rely on locally available renewable energy
854:
in arid regions, long distances of power transmission from the hydroelectric plants needed to be covered. Several hydroelectric schemes were developed from the 1930s. Private-owned power stations at the Rivers Miguillas and Khatu (Miguillas 1931, Angostura 1936, Huaña Cota) were connected to
493:, or LAC, average hydropower capacity is 51%.) In 2014, national electricity supply of 1580.35 MW comfortably exceeded the 1298.2 MW maximum demand. Like in other countries, Bolivia's electricity sector consists of a National Interconnected System (SIN) and off-grid systems (known as the 1302:(CAF) assigned US$ 32 million and US$ 15 million respectively to the increase of electricity services coverage through the construction of two transmission lines. The first one is the 115 kV Caranavi (La Paz)-Trinidad (Beni) line, which has 374 km. The second one is the 230 kV 1068:
In the years following the privatization of 1994, investment grew considerably due to the obligations imposed on the privatized companies. Public investment remained constant, mainly directed to rural electrification, while private investment was mainly devoted to generation.
602:
2005, the average duration of interruptions per subscriber was 5 hours (highest since 1998 although far below the 14 hours average for LAC), while the average number of interruptions per subscriber per year was 7 (highest since 1995 but also below the 13 average for LAC).
1249:
financed by a US$ 20 m IDA credit and approved in June 2003. The project aims at improving the delivery of infrastructure services. Its first objective is the development of effective strategies to improve and accelerate electricity access, with a focus on renewable
663:
Currently, there are three transmission companies which operate the high-voltage Interconnecting Trunk System (STI), the backbone of the SIN. ENDE Corporation, ISA Bolivia, which was created in 2005, and San Cristobal TESA. The state-owned ENDE incorporates
2152: 535:. Its grid extends over 1,200 miles and covers the central and southern parts of the country. The population in the northern and western parts of the country remains largely unconnected to the national grid, either served by the off-grid system (the 913:. During that time, Bolivia had one of the longest power transmission grids in South America with a length of several hundred kilometers, though it is unknown if these power schemes were connected before creation of the national grid in 1965. 1254:(benefiting some 50,000 Bolivian citizens in these areas) through the installation of solar home systems (SHS). This is expected to be achieved through a public-private partnership under the Government's new Universal Access Policy. 553:
Bolivia's electricity export and import activities are fairly limited. Imports from Brazil amount to less than 0.01 TWh per year and have so far been devoted to supply the city of Puerto Suarez, in the Department of Santa Cruz.
716:
The departments of Beni, Pando and Tarija and the eastern region of Santa Cruz are not integrated in the SIN. As a result, there are vertically integrated operators that provide the service. The most important operators are:
642:
Currently, there are eight generation companies in the interconnected system, all of them privately owned. The three largest companies alone represent 70% of the total generation. The largest company serving the SIN is the
546:, of which 60% was thermal production, which primarily burns natural gas, and 40% hydroelectric. The contribution of other renewables is almost negligible. Total electricity production in the same year amounted to 5.29 514:
In Bolivia, the National Interconnected System (SIN) connects major population centers and represents 83% of the installed capacity. The SIN provides electricity to the largest cities and operates in the Departments of
1325:
is also financing a 5 million Euro project to improve rural access to electricity in 2005-8. The project involves the construction of six micro-hydroelectric plants and the completion of studies for another eleven.
785:
A 5.1 MW solar photovoltaic plant in Cobija, Pando, providing power to Cobija, Porvenir, Filadelfia, Bella Flor, Puerto Rico, and Chivé. The project was funded 47% by ENDE and 53% by the Danish official aid
2521: 1915: 2156: 1076:
Distribution companies acquire investment commitments for each tariff period. For the period 2003-2005, total investment by the main distribution companies was US$ 39.7 million. This was divided as follows:
1099:
The Electricity Law 1994/1604 mandated the privatization of the electricity system and the unbundling of generation, transmission and distribution activities, which had all been in the hands of ENDE (
623:
The Viceministry of Electricity and Alternative Energy, within the Ministry of Petroleum and Energy, is in charge of establishing policies and designing the regulation for the electricity sector. The
562:
Electric power consumption per capita in 2006 was 588 kWh (a 19% increase since 1996). By sector, residential consumption represents 40% of the total, followed by industrial consumption with 28%.
1315: 1758: 920:
The National Interconnected System (SIN) was created in 1965 and continued its expansion during the ‘70s and ‘80s. However, expansion decreased since the mid-1970 due economical crisis.
2546: 2530: 2514: 1073:
electricity sector was around $ US 20million which was matched by another $ US20 million from private sources. Those two figures add up to less than 0.5% of Bolivia's GDP in 2004.
501:
government envisions a major expansion of electricity generation capacity to over 8,000 MW over the decade from 2015 to 2025, primarily to export surplus generating capacity.
1229:
External assistance to the electricity sector in Bolivia is heavily focused on rural electrification with no funding for large-scale generation, which has been fully privatized.
1048:
electricity to communal organizations or rural enterprises. The price and conditions of those transactions are not regulated, which causes an important legal void in the sector.
1033:
Electricity tariffs in Bolivia are far lower than average tariffs in Latin America. The average residential tariff in 2006 was US$ 0.0614 per kWh (compared to US$ 0.115 per kWh
2123: 1663: 1246: 755:
are barely exploited in Bolivia, and their contribution to electricity generation is insignificant. However, the potential of decentralized electricity systems (i.e. solar
2507: 1341: 680:
In Bolivia, the six existing distribution companies enjoy a geographic monopoly in their concession areas. The largest company is Electropaz, majority-owned by Spain's
1275:, approved in 2004 with US$ 100,000 funding. The project aimed to develop a master plan for natural gas projects and key investment projects to optimize the network. 905:, where large mining complexes existed. The Yura river is dubbed as "Rio Eléctrico" (Electric river) because its importance for electric generation. Since 1938, the 489:
The supply is dominated by thermal generation (65%), while hydropower (35%) has a smaller share in its generation mix compared to other South American countries. (
51: 1834: 789:
The Yunchará solar photovoltaic plant in Yunchará, Tarija, which opened as a 5 MW plant in July 2017. A second phase would produce an additional 50 MW.
2375: 1012:
In 2021, the Sistema Interconectado Nacional covered most parts of the country, only in the isolated southern and eastern outskirts, isolated grids remain. In
582:
In 2005, total access to electricity in Bolivia was 67%, one of the lowest in Latin America. Urban access was 87%, while rural access remained as low as 30%.
539:) or having no access to electricity at all. The off-grid system consists of numerous self producers and independent power plants in rural or isolated areas. 550:. This figure does not include electricity produced in rural areas from biomass facilities, which are unorganized, decentralized, and difficult to quantify. 2744: 1632: 2486: 630:
The companies that belong to the National Interconnected System (SIN) must be vertically unbundled. However, the companies in the off-grid system (the
1286: 1279: 1272: 1182:
The Viceministry of Land Planning and Environment, within the Planning and Development Ministry, holds the environmental responsibilities in Bolivia.
917:
second world war slowed down the development of the electricity sector, because machinery and spare parts mostly came from Europe and North america.
3023: 1798: 1724: 838:
mine. The first hydroelectric power plant was built in 1902 in Landara. Soon after more hydroelectric plants were built around the urban centers of
1585: 1976: 1769: 1938: 1213:-registered projects in Bolivia, one of them in the electricity sector. That is the Rio Taquesi Hydroelectric Power Project, in the province of 2855: 2704: 2691: 1400: 1169:(*) 53% of the transmission network is operated by ISA Bolivia, a subsidiary of ISA Colombia, which is controlled by the Colombian government. 574:(SE), the generation capacity reserve will be insufficient by 2009 as it will fall below the recommended 10% if no new capacity is developed. 2902: 2253: 634:) are allowed to perform more than one of the activities defined in the electricity industry (i.e. generation, transmission, distribution). 2987: 2928: 2923: 1987: 1816: 67: 936:
liberalized and some other small companies entered the market. In regards to transmission, network operation was transferred from ENDE to
2769: 2659: 2023: 692:
until 2007. The third place is occupied by the Rural Electrification Cooperative (CRE), which operates in the Department of Santa Cruz.
486:
and privatized in the 1990s, but most of the sector was re-nationalized in 2010 (generation) and 2012 (transmission and distribution).
3018: 2217: 2348: 610:
During the 1990s and up to 2005, distribution losses have always been close to 10%, which is below the 13.6% average for the region.
2368: 2131: 1671: 91: 2581: 1859: 2476: 1884: 2933: 2599: 2453: 2398: 1264: 1037: 956:), which operated both in generation and distribution, gave rise, after its divestiture, to Electropaz (in La Paz) and ELFEO ( 952:), which was a municipal company previously to privatization, started to operate as a private firm. Lastly, the private COBEE ( 598: 490: 292: 278: 236: 158: 1336: 2887: 2759: 2634: 2604: 2576: 2433: 2418: 2954: 2918: 2754: 2654: 2629: 2448: 2309: 2054: 1435: 2481: 2969: 2892: 2860: 2779: 2669: 2649: 2639: 2556: 2428: 2408: 2361: 1472:"La demanda máxima coincidental en 2014 fue de 1298.2 MW y la generación disponible en ese periodo fue de 1580.35 MW." 2850: 2820: 2815: 2810: 2805: 2739: 2729: 2719: 2714: 2699: 2674: 2571: 2566: 2413: 1303: 1210: 434: 426: 2327: 2079: 1351: 43: 2443: 1106:
Three of the eight generation companies in the interconnected system represent 70% of total generation, with COBEE (
2959: 2938: 2897: 2882: 2845: 2835: 2830: 2825: 2789: 2774: 2734: 2724: 2664: 2614: 2609: 2538: 2438: 2423: 669: 1285:
The IDB also approved a funding of US$ 138,900 in 2005 for a project to stimulate the development of CDM projects
47: 2964: 2784: 2764: 2749: 2644: 2624: 2619: 2561: 2551: 438: 208: 1639: 827: 56: 2591: 2390: 2282: 2190: 1500: 881:(Landara 1902, Kilpani 1936, Punutuma 1963). Two 69 kV power lines connected these hydroelectric stations with 483: 479: 2322: 963:
All these reforms, together with the introduction of a load dispatch coordination office, shaped a wholesale
2997: 1217:, with an effective capacity of 89.5 megawatts and estimated emission reductions of 141,691 metric tonnes CO 781:
In the mid-2010s, ENDE began building and operating large-scale solar power plants including the following:
2340: 2335: 1952: 792:
The Uyuni solar photovoltaic plant in Uyuni, Potosí, scheduled to open as a 50 MW plant in March 2017.
1114:
transmission company Transmisora de Electricidad S.A., from Spanish capitals, was similarly expropriated.
475: 2314: 1795: 1731: 32: 2840: 1988:
https://fundacion-milenio.org/energia-bolivia-cobee-un-extrano-caso-de-autonomia-en-el-sector-electrico/
1697:
Benchmarking data of the electricity distribution sector in Latin America and Caribbean Region 1995-2005
1593: 532: 520: 516: 2109: 36: 1461: 878: 528: 2464: 1926: 1885:"Planta solar de Uyuni se entregará en marzo; se alista la instalación de otra en Oruro - La Razón" 886: 2993: 2241: 1040:), while the average tariff for the industry was US$ 0.044 per kWh (compared to US$ 0.107 per kWh 451: 60: 2261: 964: 882: 948:), two pre-existing municipal distribution firms also maintained their monopolies while ELFEC ( 806: 71: 2030: 2709: 2499: 1613: 1573: 701: 524: 189: 2221: 1835:"Planta solar de Yunchará inyectará energía al sistema interconectado desde el 20 de julio" 1696: 810:
Old 69 kV transmission power line, which connects the Miguillas hydroelectric station with
2194: 2176: 1964: 1802: 1345: 890: 989: 123:
Please help update this article to reflect recent events or newly available information.
1373: 200: 2353: 1267:
provides technical assistance through three projects in the energy sector in Bolivia:
3012: 1387: 1041: 1034: 984: 756: 689: 178: 2205: 470:(Empresa Nacional de Electricidad), although the private Bolivian Power Company ( 1666:
Informe Anual de Comportamiento de los Sistemas de Transmision Nov-2004/Oct-2005
1002: 906: 2058: 474:; COBEE) is also a major producer of electricity. ENDE had been unbundled into 1363: 1338:
Capitalization and Privatization in Bolivia. An approximation to an Evaluation
1238: 1214: 847: 752: 1381: 863: 815: 681: 547: 1990:
ENERGÍA BOLIVIA: COBEE, un extraño caso de autonomía en el sector eléctrico
1436:"Once plantas de energías alternas producirán 420 MW hasta 2020 - La Razón" 894: 839: 705: 2086: 1197:
emissions from electricity production in 2003 were 1.73 million tons of CO
987:
systems in rural areas in conjunction with the literacy program, “I can” (
980: 1013: 993:). Under the pilot phase, 500 solar panels are expected to be installed. 902: 871: 831: 778:
additional 7000 in the next three years. (see External Assistance below)
543: 170: 1953:
http://pronostico-erv.org.bo/frontend/pdf/MapasistemaElectricoBolvia.pdf
1929:
Bolivia en el primer centenario de su independencia, p. 106-108, 116-122
1278:
A technical cooperation project approved in 2004 aimed at developing an
1201:, which represents 22 percent of total emissions for the energy sector. 1395: 1017: 859: 647:(COBEE), which serves the region surrounding La Paz. The other two are 462: 142: 597:
Service quality as measured by interruptions was much better than the
910: 898: 867: 843: 697: 2286: 2187: 1087:
Electropaz: US$ 10.4 million (11% below initially approved amount)
855: 811: 805: 450: 1999: 1927:
https://archive.org/details/gri_33125008089084/page/106/mode/2up
728: 467: 2503: 2357: 1817:"Planta solar en Pando generará 5,1 megavatios de electricidad" 1322: 823: 224: 103: 15: 1241:
is involved in two projects in the energy sector in Bolivia:
1761:
Diagnostico del Sector Eléctrico en el Area Rural de Bolivia
1090:
Elfeo: US$ 1.53 million (3% below initially approved amount)
1084:
ELFEC: US$ 10.2 million (5% below initially approved amount)
928:
Until 1994, the vertically integrated public utility, ENDE (
1193:(Organización Latinoamericana de Energía) estimated that CO 1081:
CRE: US$ 17.5 million (22% below initially approved amount)
1501:"Bolivia quiere exportar 8.000 megavatios de electricidad" 1095:
Summary of private participation in the electricity sector
1916:
Potencial y aprovechamiento de la hidroenergía en Bolivia
979:
A new Rural Electrification Decree was approved in 2005 (
54:
and tools are available to assist in formatting, such as
2153:"Bolivia "nacionaliza" empresas de generación eléctrica" 834:, which provided energy to his nearby residence and the 2177:
http://www.losandes.com.pe/Economia/20120501/62591.html
1965:
https://www.evh.bo/index.php/portfolio/18-rio-electrico
1190: 1939:
Proyectan realzar el parque eco-turístico de Incachaca
1273:
Support for the Bolivian Rural Electrification Program
1967:
Río Eléctrico: Centrales Hidroeléctricas del Río Yura
1247:
Decentralized Infrastructure for Rural Transformation
2283:"Viceministry of Electricity and Alternative Energy" 1860:"ENDE instalará planta solar en Yunchará - La Razón" 1633:"Viceministry of Electricity and Alternative Energy" 866:
by a 69 kV line, with minor lines connecting Uncía,
570:
According to the demand projections prepared by the
2947: 2911: 2875: 2798: 2690: 2683: 2590: 2537: 2462: 2389: 2349:
Inter-American Development Bank projects in Bolivia
1020:, 69 kV connections to the Argentinian grid exist. 425: 424: 416: 408: 400: 392: 384: 376: 365: 360: 352: 344: 336: 328: 320: 315: 307: 299: 285: 271: 266: 258: 250: 243: 231: 219: 198: 187: 176: 165: 153: 148: 2310:Viceministry of Electricity and Alternative Energy 396:Viceministry of Electricity and Alternative Energy 1911: 1909: 1907: 1905: 1314:The German Agency for International Cooperation ( 1160:Generation, transmission and distribution (2004) 1005:, a new Law for Universal Access to Electricity ( 627:(SE) is responsible for applying the regulation. 204:emissions from electricity generation (1994) 1271:A technical cooperation project directed at the 1056:In March 2006, the Bolivian government approved 332:100% (in the SIN-National Interconnected System) 1692: 1690: 1688: 1627: 1625: 1623: 1621: 1457: 1455: 967:that seeks to simulate competitive conditions. 877:Another set of power stations was built at the 589:for more information on electrification plans) 380:2 (Transportadora de Electricidad, ISA Bolivia) 2126:Superintendencia de Electricidad. Memoria 2005 1791: 1789: 1753: 1751: 430:transactions related to the electricity sector 2515: 2369: 822:Electricity in Bolivia started in 1899, when 8: 2488:South Georgia and the South Sandwich Islands 1282:received US$ 149,800 in funds from the IADB. 1103:) the vertically integrated public utility. 686:Empresa de Luz y Fuerza Eléctrica Cochabamba 140: 35:, which are uninformative and vulnerable to 1955:Mapa del Sistema Eléctrico Bolivia Nacional 404:Land Planning and Environment Vice-Ministry 50:and maintains a consistent citation style. 2687: 2522: 2508: 2500: 2376: 2362: 2354: 1948: 1946: 1245:A project to assist the implementation of 614:Responsibilities in the electricity sector 542:Total installed capacity in 2006 was 1.43 2531:Renewable energy by country and territory 2342:Empresa Luz y Fuerza Eléctrica Cochabamba 950:Empresa Luz y Fuerza Eléctrica Cochabamba 688:(ELFEC), which was owned by the American 308:Share of government financing (2004) 92:Learn how and when to remove this message 2009: 2007: 1551: 1549: 1547: 1545: 1543: 1541: 1116: 830:built a Diesel-generated power plant in 586: 455:Bolivia electricity production by source 2055:"of Electricity and Alternative Energy" 1539: 1537: 1535: 1533: 1531: 1529: 1527: 1525: 1523: 1521: 1411: 1306:and Santibáñez line, with 225 km. 1108:Compañía Boliviana de Energía Eléctrica 954:Compañía Boliviana de Energía Eléctrica 645:Compañia Boliviana de Energía Eléctrica 472:Compañia Boliviana de Energía Eléctrica 353:Competitive supply to residential users 337:Share of private sector in distribution 1401:Water supply and sanitation in Bolivia 751:Renewable energy resources other than 199: 139: 1569: 1567: 1565: 1563: 1561: 348:No (regional distribution monopolies) 329:Share of private sector in generation 7: 1024:Tariffs, cost recovery and subsidies 958:Empresa Luz y Fuerza Eléctrica Oruro 740:Cooperativa Regional de Electricidad 606:Distribution and transmission losses 2384:Electricity sector in South America 1335:Barja, G. & Urquiola, M. 2003. 593:Interruption frequency and duration 220:Average electricity use (2006) 42:Please consider converting them to 1178:Responsibility for the environment 735:): 16.65 MW, serves 28,554 clients 668:(TDE), which was owned by Spain's 401:Responsibility for the environment 14: 2323:Planning and Development Ministry 1280:Rural Electrification Master Plan 946:Servicios Eléctricos Potosí S.A. 797:History of the electricity sector 742:): 14.53 MW, serves 4,940 clients 723:Servicios Eléctricos Tarija, S.A. 625:Superintendencia de Electricidad 393:Responsibility for policy-setting 345:Competitive supply to large users 2992: 2983: 2982: 2547:Democratic Republic of the Congo 1815:Lazcano, Miguel (25 July 2015). 1588:Superintendencia de Electricidad 1380: 1366: 1101:Empresa Nacional de Electricidad 942:Compañía Eléctrica de Sucre S.A. 930:Empresa Nacional de Electricidad 893:, with minor lines branching to 733:Empresa Nacional de Electricidad 712:Operators in the off-grid system 572:Superintendencia de Electricidad 466:is dominated by the state-owned 372:3 (generation), 3 (distribution) 300:Annual investment in electricity 154:Electricity coverage (2003) 108: 20: 3024:Electric power in South America 2316:Superintedencia de Electricidad 1265:Inter-American Development Bank 1173:Electricity and the environment 725:): 44 MW, serves 56,885 clients 491:Latin America and the Caribbean 388:Multi-sector national regulator 377:Responsibility for transmission 232:Distribution losses (2005) 1434:Vásquez, Wálter (2015-07-27). 1209:Currently, there are just two 938:Transportadora de Electricidad 666:Transportadora de Electricidad 366: 166:Installed capacity (2006) 46:to ensure the article remains 1: 2000:ELFEC: Historia de la empresa 1300:Corporación Andina de Fomento 971:Rural electrification efforts 505:Electricity supply and demand 385:Responsibility for regulation 1321:The German development bank 1287:Development of CDM Projects 924:Unbundling and privatization 566:Demand and supply projection 2329:Interconexion Eléctrica S.A 2024:"Intelligent Energy Europe" 1353:Sector Eléctrico, 2000-2004 1205:CDM projects in electricity 814:and the mining industry in 445:annual emissions reductions 161:total average in 2007: 92%) 157:67% (total), 28% (rural); ( 3040: 1841:(in Spanish). 12 July 2017 1155:Private participation (%) 1123:Private participation (%) 909:is used for the supply of 747:Renewable energy resources 649:Empresa Eléctrica Guarachi 272:Average residential tariff 3019:Electric power in Bolivia 2978: 2013:Barja & Urquiola 2003 1001:In 2006, under President 286:Average industrial tariff 117:This article needs to be 1507:. Cochabamba. 2015-06-21 1186:Greenhouse gas emissions 1064:Investment and financing 981:Supreme Decree No. 28567 653:Empresa Eléctrica Corani 1007:Ley de Acceso Universal 670:Red Electrica de España 295:average in 2005: 0.107) 281:average in 2005: 0.115) 239:average in 2005: 13.6%) 2080:"Supreme Decree 28653" 1298:In 2005 and 2007, the 819: 461:electricity sector in 456: 409:Electricity sector law 288:(US$ /kW·h, 2006) 274:(US$ /kW·h, 2006) 141:Electricity sector of 1977:Map of the power grid 809: 619:Policy and regulation 578:Access to electricity 454: 267:Tariffs and financing 244:Consumption by sector 417:Renewable energy law 369:of service providers 1614:CIA World Fact Book 1225:External assistance 997:Recent developments 828:Simón Iturri Patiño 587:Recent Developments 437:project; 141,691 t 145: 2193:2007-09-28 at the 1801:2018-12-01 at the 1796:Bolivia hydropower 1710:Memoria Anual 2013 1708:ENDE Corporación, 1574:EIA Bolivia Report 1487:Memoria Anual 2013 1485:ENDE Corporación, 1421:Memoria Anual 2013 1419:ENDE Corporación, 1344:2006-07-20 at the 1035:weighted averagein 965:electricity market 820: 510:Installed capacity 457: 3006: 3005: 2871: 2870: 2497: 2496: 2469:other territories 2111:Noticias Sociedad 1839:lavozdetarija.com 1167: 1166: 449: 448: 340:100% (in the SIN) 321:Sector unbundling 138: 137: 102: 101: 94: 52:Several templates 3031: 2996: 2986: 2985: 2929:French Polynesia 2688: 2524: 2517: 2510: 2501: 2489: 2477:Falkland Islands 2391:Sovereign states 2378: 2371: 2364: 2355: 2298: 2297: 2295: 2294: 2285:. Archived from 2279: 2273: 2272: 2270: 2269: 2260:. Archived from 2250: 2244: 2239: 2233: 2232: 2230: 2229: 2220:. Archived from 2214: 2208: 2203: 2197: 2185: 2179: 2174: 2168: 2167: 2165: 2164: 2155:. Archived from 2149: 2143: 2142: 2140: 2139: 2130:. Archived from 2120: 2114: 2107: 2101: 2100: 2098: 2097: 2091: 2085:. Archived from 2084: 2076: 2070: 2069: 2067: 2066: 2057:. Archived from 2051: 2045: 2044: 2042: 2041: 2035: 2029:. Archived from 2028: 2020: 2014: 2011: 2002: 1997: 1991: 1985: 1979: 1974: 1968: 1962: 1956: 1950: 1941: 1936: 1930: 1924: 1918: 1913: 1900: 1899: 1897: 1896: 1889:www.la-razon.com 1881: 1875: 1874: 1872: 1871: 1864:www.la-razon.com 1856: 1850: 1849: 1847: 1846: 1831: 1825: 1824: 1812: 1806: 1793: 1784: 1783: 1781: 1780: 1774: 1768:. Archived from 1767: 1755: 1746: 1745: 1743: 1742: 1736: 1730:. Archived from 1729: 1721: 1715: 1713: 1712:, pp. 27–28 1705: 1699: 1694: 1683: 1682: 1680: 1679: 1670:. Archived from 1660: 1654: 1653: 1651: 1650: 1644: 1638:. Archived from 1637: 1629: 1616: 1611: 1605: 1604: 1602: 1601: 1592:. Archived from 1582: 1576: 1571: 1556: 1553: 1516: 1515: 1513: 1512: 1497: 1491: 1490: 1482: 1476: 1475: 1470: 1464: 1459: 1450: 1449: 1447: 1446: 1431: 1425: 1424: 1423:, pp. 3, 11 1416: 1390: 1385: 1384: 1376: 1371: 1370: 1369: 1117: 1042:weighted average 883:Agua de Castilla 468:ENDE Corporation 429: 368: 203: 190:renewable energy 146: 133: 130: 124: 112: 111: 104: 97: 90: 86: 83: 77: 75: 64: 24: 23: 16: 3039: 3038: 3034: 3033: 3032: 3030: 3029: 3028: 3009: 3008: 3007: 3002: 2974: 2943: 2907: 2867: 2794: 2679: 2586: 2533: 2528: 2498: 2493: 2487: 2470: 2468: 2458: 2385: 2382: 2306: 2301: 2292: 2290: 2281: 2280: 2276: 2267: 2265: 2252: 2251: 2247: 2240: 2236: 2227: 2225: 2216: 2215: 2211: 2204: 2200: 2195:Wayback Machine 2186: 2182: 2175: 2171: 2162: 2160: 2151: 2150: 2146: 2137: 2135: 2122: 2121: 2117: 2108: 2104: 2095: 2093: 2089: 2082: 2078: 2077: 2073: 2064: 2062: 2053: 2052: 2048: 2039: 2037: 2033: 2026: 2022: 2021: 2017: 2012: 2005: 1998: 1994: 1986: 1982: 1975: 1971: 1963: 1959: 1951: 1944: 1937: 1933: 1925: 1921: 1914: 1903: 1894: 1892: 1883: 1882: 1878: 1869: 1867: 1858: 1857: 1853: 1844: 1842: 1833: 1832: 1828: 1814: 1813: 1809: 1803:Wayback Machine 1794: 1787: 1778: 1776: 1772: 1765: 1757: 1756: 1749: 1740: 1738: 1734: 1727: 1723: 1722: 1718: 1707: 1706: 1702: 1695: 1686: 1677: 1675: 1662: 1661: 1657: 1648: 1646: 1642: 1635: 1631: 1630: 1619: 1612: 1608: 1599: 1597: 1584: 1583: 1579: 1572: 1559: 1554: 1519: 1510: 1508: 1499: 1498: 1494: 1484: 1483: 1479: 1473: 1471: 1467: 1460: 1453: 1444: 1442: 1433: 1432: 1428: 1418: 1417: 1413: 1409: 1386: 1379: 1372: 1367: 1365: 1362: 1346:Wayback Machine 1332: 1312: 1296: 1261: 1237:Currently, the 1235: 1227: 1220: 1207: 1200: 1196: 1188: 1180: 1175: 1097: 1066: 1058:Tarifa Dignidad 1054: 1031: 1026: 999: 973: 926: 804: 799: 775: 766: 749: 714: 678: 661: 640: 621: 616: 608: 595: 580: 568: 560: 512: 507: 442: 287: 273: 245: 212: 134: 128: 125: 122: 113: 109: 98: 87: 81: 78: 66: 55: 41: 25: 21: 12: 11: 5: 3037: 3035: 3027: 3026: 3021: 3011: 3010: 3004: 3003: 3001: 3000: 2990: 2979: 2976: 2975: 2973: 2972: 2967: 2962: 2957: 2951: 2949: 2945: 2944: 2942: 2941: 2936: 2931: 2926: 2921: 2915: 2913: 2909: 2908: 2906: 2905: 2900: 2895: 2890: 2885: 2879: 2877: 2873: 2872: 2869: 2868: 2866: 2865: 2864: 2863: 2856:United Kingdom 2853: 2848: 2843: 2838: 2833: 2828: 2823: 2818: 2813: 2808: 2802: 2800: 2796: 2795: 2793: 2792: 2787: 2782: 2777: 2772: 2767: 2762: 2757: 2752: 2747: 2742: 2737: 2732: 2727: 2722: 2717: 2712: 2707: 2705:Czech Republic 2702: 2696: 2694: 2692:European Union 2685: 2681: 2680: 2678: 2677: 2672: 2667: 2662: 2657: 2652: 2647: 2642: 2637: 2632: 2627: 2622: 2617: 2612: 2607: 2602: 2596: 2594: 2588: 2587: 2585: 2584: 2579: 2574: 2569: 2564: 2559: 2554: 2549: 2543: 2541: 2535: 2534: 2529: 2527: 2526: 2519: 2512: 2504: 2495: 2494: 2492: 2491: 2484: 2479: 2473: 2471: 2463: 2460: 2459: 2457: 2456: 2451: 2446: 2441: 2436: 2431: 2426: 2421: 2416: 2411: 2406: 2401: 2395: 2393: 2387: 2386: 2383: 2381: 2380: 2373: 2366: 2358: 2352: 2351: 2346: 2338: 2333: 2325: 2320: 2312: 2305: 2304:External links 2302: 2300: 2299: 2274: 2245: 2234: 2209: 2198: 2180: 2169: 2144: 2115: 2102: 2071: 2046: 2015: 2003: 1992: 1980: 1969: 1957: 1942: 1931: 1919: 1901: 1876: 1851: 1826: 1807: 1785: 1747: 1716: 1700: 1684: 1655: 1617: 1606: 1577: 1557: 1517: 1492: 1477: 1474:"Los Tiempos". 1465: 1462:EIA Statistics 1451: 1426: 1410: 1408: 1405: 1404: 1403: 1398: 1392: 1391: 1377: 1374:Bolivia portal 1361: 1358: 1357: 1356: 1348: 1331: 1328: 1311: 1308: 1295: 1292: 1291: 1290: 1283: 1276: 1260: 1257: 1256: 1255: 1251: 1234: 1231: 1226: 1223: 1218: 1206: 1203: 1198: 1194: 1187: 1184: 1179: 1176: 1174: 1171: 1165: 1164: 1161: 1157: 1156: 1153: 1149: 1148: 1145: 1141: 1140: 1137: 1133: 1132: 1129: 1125: 1124: 1121: 1096: 1093: 1092: 1091: 1088: 1085: 1082: 1065: 1062: 1053: 1050: 1030: 1027: 1025: 1022: 998: 995: 972: 969: 960:) (in Oruro). 925: 922: 803: 800: 798: 795: 794: 793: 790: 787: 774: 771: 765: 762: 748: 745: 744: 743: 736: 726: 713: 710: 684:; followed by 677: 674: 660: 657: 639: 636: 620: 617: 615: 612: 607: 604: 594: 591: 579: 576: 567: 564: 559: 556: 511: 508: 506: 503: 447: 446: 440: 431: 422: 421: 418: 414: 413: 410: 406: 405: 402: 398: 397: 394: 390: 389: 386: 382: 381: 378: 374: 373: 370: 363: 362: 358: 357: 354: 350: 349: 346: 342: 341: 338: 334: 333: 330: 326: 325: 322: 318: 317: 313: 312: 309: 305: 304: 303:US$ 40 million 301: 297: 296: 289: 283: 282: 275: 269: 268: 264: 263: 260: 256: 255: 252: 248: 247: 241: 240: 233: 229: 228: 221: 217: 216: 210: 205: 196: 195: 192: 185: 184: 181: 174: 173: 167: 163: 162: 155: 151: 150: 136: 135: 116: 114: 107: 100: 99: 82:September 2022 44:full citations 28: 26: 19: 13: 10: 9: 6: 4: 3: 2: 3036: 3025: 3022: 3020: 3017: 3016: 3014: 2999: 2995: 2991: 2989: 2981: 2980: 2977: 2971: 2968: 2966: 2963: 2961: 2958: 2956: 2953: 2952: 2950: 2948:South America 2946: 2940: 2937: 2935: 2932: 2930: 2927: 2925: 2922: 2920: 2917: 2916: 2914: 2910: 2904: 2903:United States 2901: 2899: 2896: 2894: 2891: 2889: 2886: 2884: 2881: 2880: 2878: 2876:North America 2874: 2862: 2859: 2858: 2857: 2854: 2852: 2849: 2847: 2844: 2842: 2839: 2837: 2834: 2832: 2829: 2827: 2824: 2822: 2819: 2817: 2814: 2812: 2809: 2807: 2804: 2803: 2801: 2797: 2791: 2788: 2786: 2783: 2781: 2778: 2776: 2773: 2771: 2768: 2766: 2763: 2761: 2758: 2756: 2753: 2751: 2748: 2746: 2743: 2741: 2738: 2736: 2733: 2731: 2728: 2726: 2723: 2721: 2718: 2716: 2713: 2711: 2708: 2706: 2703: 2701: 2698: 2697: 2695: 2693: 2689: 2686: 2682: 2676: 2673: 2671: 2668: 2666: 2663: 2661: 2658: 2656: 2653: 2651: 2648: 2646: 2643: 2641: 2638: 2636: 2633: 2631: 2628: 2626: 2623: 2621: 2618: 2616: 2613: 2611: 2608: 2606: 2603: 2601: 2598: 2597: 2595: 2593: 2589: 2583: 2580: 2578: 2575: 2573: 2570: 2568: 2565: 2563: 2560: 2558: 2555: 2553: 2550: 2548: 2545: 2544: 2542: 2540: 2536: 2532: 2525: 2520: 2518: 2513: 2511: 2506: 2505: 2502: 2490: 2485: 2483: 2482:French Guiana 2480: 2478: 2475: 2474: 2472: 2466: 2461: 2455: 2452: 2450: 2447: 2445: 2442: 2440: 2437: 2435: 2432: 2430: 2427: 2425: 2422: 2420: 2417: 2415: 2412: 2410: 2407: 2405: 2402: 2400: 2397: 2396: 2394: 2392: 2388: 2379: 2374: 2372: 2367: 2365: 2360: 2359: 2356: 2350: 2347: 2345: 2343: 2339: 2337: 2334: 2332: 2330: 2326: 2324: 2321: 2319: 2317: 2313: 2311: 2308: 2307: 2303: 2289:on 2007-11-10 2288: 2284: 2278: 2275: 2264:on 2007-11-03 2263: 2259: 2257: 2249: 2246: 2243: 2238: 2235: 2224:on 2007-06-14 2223: 2219: 2213: 2210: 2207: 2202: 2199: 2196: 2192: 2189: 2184: 2181: 2178: 2173: 2170: 2159:on 2016-03-04 2158: 2154: 2148: 2145: 2134:on 2007-07-05 2133: 2129: 2127: 2119: 2116: 2113: 2112: 2106: 2103: 2092:on 2007-03-07 2088: 2081: 2075: 2072: 2061:on 2007-09-21 2060: 2056: 2050: 2047: 2036:on 2011-07-23 2032: 2025: 2019: 2016: 2010: 2008: 2004: 2001: 1996: 1993: 1989: 1984: 1981: 1978: 1973: 1970: 1966: 1961: 1958: 1954: 1949: 1947: 1943: 1940: 1935: 1932: 1928: 1923: 1920: 1917: 1912: 1910: 1908: 1906: 1902: 1890: 1886: 1880: 1877: 1865: 1861: 1855: 1852: 1840: 1836: 1830: 1827: 1822: 1818: 1811: 1808: 1804: 1800: 1797: 1792: 1790: 1786: 1775:on 2007-07-02 1771: 1764: 1762: 1754: 1752: 1748: 1737:on 2011-07-20 1733: 1726: 1725:"ECLAC, 2005" 1720: 1717: 1711: 1704: 1701: 1698: 1693: 1691: 1689: 1685: 1674:on 2007-10-28 1673: 1669: 1667: 1659: 1656: 1645:on 2012-02-08 1641: 1634: 1628: 1626: 1624: 1622: 1618: 1615: 1610: 1607: 1596:on 2007-10-28 1595: 1591: 1589: 1581: 1578: 1575: 1570: 1568: 1566: 1564: 1562: 1558: 1552: 1550: 1548: 1546: 1544: 1542: 1540: 1538: 1536: 1534: 1532: 1530: 1528: 1526: 1524: 1522: 1518: 1506: 1502: 1496: 1493: 1488: 1481: 1478: 1469: 1466: 1463: 1458: 1456: 1452: 1441: 1437: 1430: 1427: 1422: 1415: 1412: 1406: 1402: 1399: 1397: 1394: 1393: 1389: 1388:Energy portal 1383: 1378: 1375: 1364: 1359: 1355: 1354: 1350:UDAPE, 2004. 1349: 1347: 1343: 1340: 1339: 1334: 1333: 1329: 1327: 1324: 1319: 1317: 1309: 1307: 1305: 1301: 1293: 1288: 1284: 1281: 1277: 1274: 1270: 1269: 1268: 1266: 1258: 1252: 1248: 1244: 1243: 1242: 1240: 1232: 1230: 1224: 1222: 1221:e per annum 1216: 1212: 1204: 1202: 1192: 1185: 1183: 1177: 1172: 1170: 1162: 1159: 1158: 1154: 1151: 1150: 1146: 1144:Distribution 1143: 1142: 1138: 1136:Transmission 1135: 1134: 1130: 1127: 1126: 1122: 1119: 1118: 1115: 1111: 1109: 1104: 1102: 1094: 1089: 1086: 1083: 1080: 1079: 1078: 1074: 1070: 1063: 1061: 1059: 1051: 1049: 1045: 1043: 1039: 1036: 1028: 1023: 1021: 1019: 1015: 1010: 1008: 1004: 996: 994: 992: 991: 986: 982: 977: 970: 968: 966: 961: 959: 955: 951: 947: 944:) and SEPSA ( 943: 939: 933: 931: 923: 921: 918: 914: 912: 908: 904: 900: 896: 892: 888: 887:Tasna Rosario 884: 880: 875: 873: 869: 865: 861: 857: 851: 849: 845: 841: 837: 833: 829: 825: 817: 813: 808: 802:Early history 801: 796: 791: 788: 784: 783: 782: 779: 772: 770: 763: 761: 758: 757:photovoltaics 754: 746: 741: 737: 734: 730: 727: 724: 720: 719: 718: 711: 709: 707: 704:and three in 703: 699: 693: 691: 687: 683: 675: 673: 671: 667: 658: 656: 654: 650: 646: 637: 635: 633: 628: 626: 618: 613: 611: 605: 603: 600: 592: 590: 588: 583: 577: 575: 573: 565: 563: 557: 555: 551: 549: 545: 540: 538: 534: 530: 526: 522: 518: 509: 504: 502: 498: 496: 492: 487: 485: 481: 477: 473: 469: 465: 464: 453: 444: 436: 433:1 registered 432: 428: 423: 419: 415: 411: 407: 403: 399: 395: 391: 387: 383: 379: 375: 371: 364: 359: 355: 351: 347: 343: 339: 335: 331: 327: 323: 319: 314: 310: 306: 302: 298: 294: 290: 284: 280: 276: 270: 265: 261: 257: 253: 249: 242: 238: 234: 230: 226: 222: 218: 214: 206: 202: 197: 193: 191: 186: 182: 180: 179:fossil energy 175: 172: 168: 164: 160: 156: 152: 147: 144: 132: 129:November 2015 120: 115: 106: 105: 96: 93: 85: 73: 72:documentation 69: 62: 61:documentation 58: 53: 49: 45: 40: 38: 34: 29:This article 27: 18: 17: 2924:Cook Islands 2582:South Africa 2465:Dependencies 2403: 2341: 2328: 2315: 2291:. Retrieved 2287:the original 2277: 2266:. Retrieved 2262:the original 2255: 2248: 2237: 2226:. Retrieved 2222:the original 2212: 2201: 2183: 2172: 2161:. Retrieved 2157:the original 2147: 2136:. Retrieved 2132:the original 2125: 2118: 2110: 2105: 2094:. Retrieved 2087:the original 2074: 2063:. Retrieved 2059:the original 2049: 2038:. Retrieved 2031:the original 2018: 1995: 1983: 1972: 1960: 1934: 1922: 1893:. Retrieved 1891:(in Spanish) 1888: 1879: 1868:. Retrieved 1866:(in Spanish) 1863: 1854: 1843:. Retrieved 1838: 1829: 1820: 1810: 1777:. Retrieved 1770:the original 1760: 1739:. Retrieved 1732:the original 1719: 1709: 1703: 1676:. Retrieved 1672:the original 1665: 1658: 1647:. Retrieved 1640:the original 1609: 1598:. Retrieved 1594:the original 1587: 1580: 1509:. Retrieved 1504: 1495: 1489:, p. 11 1486: 1480: 1468: 1443:. Retrieved 1439: 1429: 1420: 1414: 1352: 1337: 1320: 1313: 1299: 1297: 1262: 1236: 1228: 1208: 1189: 1181: 1168: 1112: 1107: 1105: 1100: 1098: 1075: 1071: 1067: 1057: 1055: 1046: 1032: 1011: 1006: 1000: 990:Yo, sí puedo 988: 978: 974: 962: 957: 953: 949: 945: 941: 937: 934: 929: 927: 919: 915: 876: 852: 835: 821: 780: 776: 767: 750: 739: 732: 722: 715: 700:, twenty in 694: 685: 679: 676:Distribution 665: 662: 659:Transmission 652: 648: 644: 641: 631: 629: 624: 622: 609: 596: 584: 581: 571: 569: 561: 552: 541: 536: 513: 499: 494: 488: 484:distribution 480:transmission 471: 460: 458: 361:Institutions 246:(% of total) 126: 118: 88: 79: 68:Citation bot 30: 2934:New Zealand 2841:Switzerland 2770:Netherlands 2660:Philippines 2600:Afghanistan 2256:Los Tiempos 1805:01/12/2018. 1152:Investment 1128:Generation 1003:Evo Morales 907:Zongo River 651:(EGSA) and 251:Residential 194:40% (hydro) 3013:Categories 2888:Costa Rica 2760:Luxembourg 2635:Kazakhstan 2605:Bangladesh 2577:Seychelles 2336:Electropaz 2293:2007-09-19 2268:2007-09-19 2228:2007-09-19 2163:2013-04-10 2138:2007-09-19 2096:2007-09-19 2065:2007-09-19 2040:2007-09-19 1895:2018-01-09 1870:2018-01-09 1845:2018-01-09 1779:2007-09-19 1741:2008-04-24 1678:2007-09-19 1649:2007-09-19 1600:2007-09-19 1555:UDAPE 2004 1511:2015-11-04 1445:2015-11-04 1239:World Bank 1233:World Bank 1215:Sud Yungas 879:Yura River 848:Cochabamba 836:Miraflores 764:Hydropower 753:hydropower 690:PPL Global 655:(CORANI). 638:Generation 533:Chuquisaca 521:Santa Cruz 517:Cochabamba 476:generation 412:Yes (1994) 259:Industrial 227:per capita 215:per capita 48:verifiable 2955:Argentina 2919:Australia 2755:Lithuania 2655:Palestine 2630:Indonesia 2454:Venezuela 2399:Argentina 1120:Activity 1052:Subsidies 1044:in LAC). 901:and even 864:Llallagua 816:Llallagua 760:sources. 682:Iberdrola 277:0.0614; ( 188:Share of 177:Share of 33:bare URLs 2988:Category 2970:Colombia 2893:Honduras 2861:Scotland 2780:Portugal 2670:Thailand 2650:Pakistan 2640:Malaysia 2557:Ethiopia 2444:Suriname 2434:Paraguay 2419:Colombia 2191:Archived 1821:La Razón 1799:Archived 1440:La Razón 1360:See also 1342:Archived 1304:Carrasco 1250:sources. 1014:Villazon 903:Pulacayo 891:Telamayu 872:Colquiri 826:magnate 316:Services 291:0.0404 ( 37:link rot 2912:Oceania 2851:Ukraine 2821:Iceland 2816:Belarus 2811:Armenia 2806:Albania 2745:Ireland 2740:Hungary 2730:Germany 2720:Finland 2715:Denmark 2700:Austria 2675:Vietnam 2572:Nigeria 2567:Morocco 2449:Uruguay 2424:Ecuador 2404:Bolivia 1505:Opinión 1396:Bolivia 1330:Sources 1029:Tariffs 1018:Yacuiba 860:Huanuni 786:agency. 721:SETAR ( 632:Aislado 537:Aislado 495:Aislado 463:Bolivia 207:0.19 t 143:Bolivia 119:updated 2998:Portal 2960:Brazil 2939:Tuvalu 2898:Mexico 2883:Canada 2846:Turkey 2836:Russia 2831:Norway 2826:Kosovo 2790:Sweden 2775:Poland 2735:Greece 2725:France 2710:Cyprus 2684:Europe 2665:Taiwan 2615:Brunei 2610:Bhutan 2539:Africa 2429:Guyana 2409:Brazil 2331:(ISA) 2206:UNFCCC 1310:Others 911:La Paz 899:Tatasi 895:Potosí 868:Catavi 844:La Paz 840:Potosí 706:Potosi 698:La Paz 558:Demand 529:Potosí 235:10%; ( 57:reFill 2965:Chile 2799:Other 2785:Spain 2765:Malta 2750:Italy 2645:Nepal 2625:India 2620:China 2562:Kenya 2552:Egypt 2414:Chile 2344:ELFEC 2218:"CAF" 2188:OLADE 2090:(PDF) 2083:(PDF) 2034:(PDF) 2027:(PDF) 1773:(PDF) 1766:(PDF) 1735:(PDF) 1728:(PDF) 1643:(PDF) 1636:(PDF) 1407:Notes 1191:OLADE 1147:100% 1139:53%* 856:Oruro 832:Uncía 812:Oruro 773:Solar 738:CRE ( 702:Oruro 585:(See 525:Oruro 169:1.43 31:uses 2592:Asia 2439:Peru 1263:The 1163:50% 1131:20% 1016:and 889:and 870:and 862:and 846:and 729:ENDE 531:and 482:and 459:The 223:588 149:Data 65:and 2467:and 2242:CAF 1323:KfW 1316:GIZ 1294:CAF 1259:IDB 1211:CDM 1038:LAC 824:tin 599:LAC 548:TWh 497:). 435:CDM 427:CDM 367:No. 324:Yes 311:50% 293:LAC 279:LAC 262:28% 254:40% 237:LAC 225:kWh 201:GHG 183:60% 159:LAC 3015:: 2318:SE 2006:^ 1945:^ 1904:^ 1887:. 1862:. 1837:. 1819:. 1788:^ 1750:^ 1687:^ 1620:^ 1560:^ 1520:^ 1503:. 1454:^ 1438:. 985:PV 897:, 885:, 874:. 858:, 842:, 708:. 544:GW 527:, 523:, 519:, 478:, 439:CO 420:No 356:No 209:CO 171:GW 2523:e 2516:t 2509:v 2377:e 2370:t 2363:v 2296:. 2271:. 2258:" 2254:" 2231:. 2166:. 2141:. 2128:" 2124:" 2099:. 2068:. 2043:. 1898:. 1873:. 1848:. 1823:. 1782:. 1763:" 1759:" 1744:. 1714:. 1681:. 1668:" 1664:" 1652:. 1603:. 1590:" 1586:" 1514:. 1448:. 1289:. 1219:2 1199:2 1195:2 818:. 731:( 443:e 441:2 213:e 211:2 131:) 127:( 121:. 95:) 89:( 84:) 80:( 76:. 74:) 70:( 63:) 59:( 39:.

Index

bare URLs
link rot
full citations
verifiable
Several templates
reFill
documentation
Citation bot
documentation
Learn how and when to remove this message
Bolivia
LAC
GW
fossil energy
renewable energy
GHG
CO2e
kWh
LAC
LAC
LAC
CDM
CDM
CO2e

Bolivia
ENDE Corporation
generation
transmission
distribution

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.