Knowledge (XXG)

J. Strom Thurmond Dam

Source 📝

543: 619: 633: 884: 661: 647: 49: 29: 44: 533:
from South Carolina. In response, a group of Georgia legislators introduced an eventually unsuccessful bill to rename the lake as "Clarks Hill" once again. On April 4, 1989 the State of Georgia legislature passed House Resolution No. 115 making "Clarks Hill" the official state name for both the dam
444:
with 124 ft. booms. In 1948, after the foundation was excavated, workers began to pour concrete on site for the spillway. In 1949, initial work on the concrete spillway was completed; the original coffer dam was removed and a second cofferdam was installed in order to restore the flow of the
469:
Since completion, the J. Strom Thurmond dam has prevented an estimated $ 185,000 annually in flood damages. In one specific case, the dam decreased the height of the March 1964 flood from 38 feet (12 m) to 25 feet (7.6 m) at Augusta, where the flood stage is 32 feet (9.8 m). The dam
465:
to transport on site. By July 1951, the reservoir began to fill as most of the embankment part of the dam was complete and filling would finish in October 1952. By November 1952, the first generator was operating and began transferring power to South Carolina early the next year. The six remaining
491:
and a subsequent low-demand for electricity. While the USACE and officials from Georgia were negotiating a plan for the dam in the mid-to-late 1930s, the SREC assured them that they would not interfere. However, during the short construction halt in late 1946, the SREC did in fact reapply for the
435:
had halted funding for many government programs in order to handle a post-Second World War depressed economy. In 1947, diversion of the Savannah River and construction of a coffer dam began while the contract for the actual dam was awarded. The construction plant for the dam was also completed in
478:
The USACE encountered several problems when constructing the Clark Hill project. The most serious was a conflict with the Savannah River Electric Company (SREC) over the power rights of the Clark Hill project. The SREC had acquired a permit from the
500:. Dondero introduced a bill that would allow the USACE to build the dam's embankment and allow SREC to build, own and operate the powerhouse. The bill was defeated and SREC announced it would no longer fight for the Clark Hill project or any other 550:
The J. Strom Thurmond Dam's power-house is a concrete-gravity structure that is flanked by embankment dams for a total length of one mile. The concrete section is 1,096 feet (334 m) long and is 200 feet (61 m) high from the Savannah's
427:
with Public Law 534 in 1944. A clerical error at the time named the project "Clark Hill" instead of "Clarks Hill". The final report on the Upper Savannah Basin was issued in 1946 and initial construction began soon thereafter on August 1.
419:'s blessing in a 1935 plan. Roosevelt ordered a feasibility study to be done on the Clark Hill Project amongst other dams in the plan. The results were sent back to the President in 1937 and other reviews were conducted until focus on the 392:. In 1933, the USACE completed the report for the entire Savannah River Basin that recommended against government flood control development of the basin but did propose two hydropower dams in the upper Savannah Basin, the Clark Hill and 944: 328:
with an installed 380 MW capacity. The Dam has prevented over $ 3.1 million in estimated flood damage annually and also provides recreation, water quality, water supply, along with fish and wildlife management.
449:
in the spillway structure. Concrete operations on the main part of the dam had halted in 1949 because of a steel-strike but resumed in 1950 and much of the spillway was completed by the end of the year.
929: 954: 497: 949: 979: 959: 344:. The USACE developed the Christopher D. Spiller pollinator trail in the site of housing for workers during the construction of the dam. They are also helping restore the 340:. Originally accepted in Georgia, the dam is named after revolutionary war hero, Elijah Clark, who is also buried on the western banks of the lake on acreage that is now 969: 585:. Each turbine weighs 300 tons and has a 30-foot (9.1 m) diameter. The generators are fed with water by seven 214-foot (65 m), 20-inch-wide (510 mm) 466:
generators went online between 1953 and 1954. The project was completed at a cost of US $ 78.5 million compared to the estimated cost of US $ 35.3 million in 1944.
984: 857: 679: 597:
that help maintaining a normal 330 ft MSL lake elevation and flooding. The dam's 700,000,000 kW·h annual production of electricity is managed by the
376:. His report was overlooked until the 1927 Rivers and Harbors Act allowed the USACE to investigate development of the Savannah River for the purpose of 423:
slowed the approval process. The next comprehensive study on the Upper Savannah Basin was not completed until 1943 but the project was authorized by
564: 674: 934: 349: 830: 788: 80: 403:
and prior efforts by local leaders in Augusta were instrumental in gaining approval. Support from the USACE along with Georgia Senators
974: 724: 767: 492:
license. In 1947, the Federal Power Commission denied the SREC the license but the company gained support from Michigan Representative
850: 604: 598: 64: 964: 939: 908: 542: 412: 324:. The concrete structure of the dam spans 1,096 feet (334 m) and rises 204 feet (62 m) above the riverbed, housing a 741: 470:
also helps maintain the 9-foot (2.7 m) navigation channel near Augusta along with reducing silt in the channel by 22%.
903: 843: 457:
had been awarded a year prior. Construction on the powerhouse would lag initially because materials were needed for the
365: 309: 139: 624: 400: 52: 480: 60: 522:. In 1987, however, the U.S. Congress passed a South Carolina-sponsored bill to rename the dam and lake after 666: 461:
but by July 1952, 60% of the powerhouse was complete. Each generator required for the power house needed 32
353: 341: 301: 56: 487:
dam at the Clark Hill site. In 1932, the SREC surrendered the license because of conditions imposed by the
893: 572: 424: 416: 638: 582: 530: 337: 289: 261: 453:
In late 1950, contracts for construction of the powerhouse were awarded and the contracts for the 7
556: 513: 408: 293: 189: 764: 527: 454: 368:(USACE) Savannah Office issued a survey report that recommended the construction of dams on the 229: 785: 567:. The dam is 239.5 miles (385.4 km) upstream of the Savannah's mouth and combines with the 493: 721: 579: 488: 484: 420: 404: 377: 373: 317: 277: 792: 728: 432: 870: 560: 523: 501: 369: 333: 297: 285: 281: 273: 242: 196: 154: 923: 771: 385: 345: 313: 219: 68: 888: 652: 594: 568: 441: 393: 698:
U.S. Geological Survey Geographic Names Information System: J. Strom Thurmond Dam
660: 446: 440:
that would be transported anywhere on the construction site via three-revolving
325: 697: 614: 458: 389: 381: 321: 835: 399:
Construction on the Clarks Hill project was not authorized until 1944 by the
95: 82: 646: 804: 590: 586: 437: 269: 235: 28: 552: 462: 165: 578:
The dam helps provide electricity during peak-hours with seven 40-MW
765:
Clarks Hill or Lake Thurmond? The answer depends on your home state
541: 431:
Construction was at first ceased until November 1946 as President
786:
Army Corps of Engineers J. Strom Thurmond Lake and Dam Hydropower
839: 575:(1985) in order to form over 120 miles (190 km) of lakes. 866: 722:
Army Corps of Engineers J. Strom Thurmond Lake and Dam History
305: 248: 445:
Savannah River to its original channel but now through eight-
945:
Buildings and structures in McCormick County, South Carolina
742:"USACE opens new trail for pollinators and longleaf pines" 498:
U.S. House Committee on Public Works and Transportation
304:
on the Georgia side of the state line) cross it. The
930:
Buildings and structures in Columbia County, Georgia
555:. The dam created the 71,000-acre (29,000 ha) 241: 228: 218: 213: 205: 195: 185: 180: 172: 160: 150: 145: 135: 127: 119: 111: 74: 38: 21: 955:Hydroelectric power plants in Georgia (U.S. state) 332:Since 1988, the official name of the dam is after 559:which stretches 29.4 miles (47.3 km) up the 805:"Generation – Southeastern Power Administration" 348:on the site and around the dam which includes 851: 680:List of dams and reservoirs in South Carolina 364:In 1890, Lieutenant Oberlin M. Carter of the 8: 950:Hydroelectric power plants in South Carolina 603:Electricity from the dam is marketed by the 980:1954 establishments in Georgia (U.S. state) 514:Lake Strom Thurmond § Renaming of lake 342:Elijah Clark State Park and Recreation Area 960:United States Army Corps of Engineers dams 858: 844: 836: 781: 779: 717: 715: 713: 711: 709: 707: 705: 312:between 1946 and 1954 for the purposes of 27: 18: 415:were important towards getting President 483:in 1928 to construct, own and operate a 970:Energy infrastructure completed in 1954 690: 276:located 22 miles (35 km) north of 675:List of dams and reservoirs in Georgia 201:6,144 sq mi (15,910 km) 985:1954 establishments in South Carolina 436:1947, containing equipment to create 7: 831:USACE J. Strom Thurmond Dam and Lake 538:Dam and power plant characteristics 14: 605:Southeastern Power Administration 599:Southeastern Power Administration 563:and 17 miles (27 km) up the 882: 659: 645: 631: 617: 372:in order to prevent flooding in 65:McCormick County, South Carolina 47: 42: 899:J. Strom Thurmond (Clarks Hill) 518:Until 1988, the dam was called 1: 209:71,100 acres (28,800 ha) 935:Dams in Georgia (U.S. state) 740:Hale, Riley (May 21, 2021). 496:who was the chairman of the 366:U.S. Army Corps of Engineers 310:U.S. Army Corps of Engineers 140:U.S. Army Corps of Engineers 625:Georgia (U.S. state) portal 1001: 975:Dams on the Savannah River 534:and associated reservoir. 511: 16:Dam in South Carolina, USA 877: 26: 481:Federal Power Commission 411:and Georgia Congressman 360:History and construction 61:Columbia County, Georgia 667:Renewable energy portal 302:Georgia State Route 150 230:Installed capacity 112:Construction began 965:Dams completed in 1954 940:Dams in South Carolina 573:Richard B. Russell Dam 547: 508:Dam naming controversy 474:Construction obstacles 243:Annual generation 128:Construction cost 545: 417:Franklin D. Roosevelt 354:longleaf pine habitat 258:J. Strom Thurmond Dam 96:33.66083°N 82.19972°W 33:J. Strom Thurmond Dam 22:J. Strom Thurmond Dam 639:United States portal 557:Lake Strom Thurmond 294:Lake Strom Thurmond 197:Catchment area 190:Lake Strom Thurmond 101:33.66083; -82.19972 92: /  894:Richard B. Russell 791:2009-12-05 at the 727:2009-12-27 at the 548: 917: 916: 494:George A. Dondero 308:was built by the 284:at the border of 255: 254: 206:Surface area 164:200 feet (61 m) ( 146:Dam and spillways 120:Opening date 992: 887: 886: 885: 860: 853: 846: 837: 819: 818: 816: 815: 801: 795: 783: 774: 762: 756: 755: 753: 752: 737: 731: 719: 700: 695: 669: 664: 663: 655: 650: 649: 641: 636: 635: 634: 627: 622: 621: 620: 589:, and the dam's 580:hydroelectricity 504:Basin projects. 489:Great Depression 485:hydroelectricity 421:Second World War 405:Walter F. George 378:hydroelectricity 374:Augusta, Georgia 350:Piedmont prairie 318:hydroelectricity 278:Augusta, Georgia 260:, also known in 176:1 mile (1.73 km) 107: 106: 104: 103: 102: 97: 93: 90: 89: 88: 85: 51: 50: 46: 45: 31: 19: 1000: 999: 995: 994: 993: 991: 990: 989: 920: 919: 918: 913: 883: 881: 873: 864: 827: 822: 813: 811: 803: 802: 798: 793:Wayback Machine 784: 777: 763: 759: 750: 748: 739: 738: 734: 729:Wayback Machine 720: 703: 696: 692: 688: 665: 658: 651: 644: 637: 632: 630: 623: 618: 616: 613: 571:(1962) and the 540: 520:Clarks Hill Dam 516: 510: 476: 433:Harry S. Truman 409:Richard Russell 362: 320:and downstream 266:Clarks Hill Dam 100: 98: 94: 91: 86: 83: 81: 79: 78: 48: 43: 34: 17: 12: 11: 5: 998: 996: 988: 987: 982: 977: 972: 967: 962: 957: 952: 947: 942: 937: 932: 922: 921: 915: 914: 912: 911: 906: 901: 896: 891: 878: 875: 874: 871:Savannah River 865: 863: 862: 855: 848: 840: 834: 833: 826: 825:External links 823: 821: 820: 796: 775: 770:2012-07-18 at 757: 732: 701: 689: 687: 684: 683: 682: 677: 671: 670: 656: 642: 628: 612: 609: 561:Savannah River 539: 536: 528:segregationist 526:, a long-time 524:Strom Thurmond 509: 506: 502:Savannah River 475: 472: 370:Savannah River 361: 358: 334:Strom Thurmond 298:U.S. Route 221 286:South Carolina 282:Savannah River 274:embankment dam 253: 252: 245: 239: 238: 232: 226: 225: 222: 216: 215: 211: 210: 207: 203: 202: 199: 193: 192: 187: 183: 182: 178: 177: 174: 170: 169: 162: 158: 157: 155:Savannah River 152: 148: 147: 143: 142: 137: 133: 132: 131:$ 78.5 million 129: 125: 124: 121: 117: 116: 113: 109: 108: 76: 72: 71: 40: 36: 35: 32: 24: 23: 15: 13: 10: 9: 6: 4: 3: 2: 997: 986: 983: 981: 978: 976: 973: 971: 968: 966: 963: 961: 958: 956: 953: 951: 948: 946: 943: 941: 938: 936: 933: 931: 928: 927: 925: 910: 907: 905: 904:Stevens Creek 902: 900: 897: 895: 892: 890: 880: 879: 876: 872: 868: 861: 856: 854: 849: 847: 842: 841: 838: 832: 829: 828: 824: 810: 806: 800: 797: 794: 790: 787: 782: 780: 776: 773: 772:archive.today 769: 766: 761: 758: 747: 743: 736: 733: 730: 726: 723: 718: 716: 714: 712: 710: 708: 706: 702: 699: 694: 691: 685: 681: 678: 676: 673: 672: 668: 662: 657: 654: 648: 643: 640: 629: 626: 615: 610: 608: 606: 601: 600: 596: 595:tainter gates 592: 588: 584: 581: 576: 574: 570: 566: 562: 558: 554: 544: 537: 535: 532: 529: 525: 521: 515: 507: 505: 503: 499: 495: 490: 486: 482: 473: 471: 467: 464: 460: 456: 451: 448: 443: 442:gantry cranes 439: 434: 429: 426: 422: 418: 414: 410: 406: 402: 401:78th Congress 397: 395: 394:Hartwell Dams 391: 387: 386:flood control 383: 379: 375: 371: 367: 359: 357: 355: 351: 347: 346:longleaf pine 343: 339: 336:, a longtime 335: 330: 327: 323: 319: 315: 314:flood control 311: 307: 303: 299: 295: 291: 287: 283: 279: 275: 272:-gravity and 271: 267: 263: 259: 250: 246: 244: 240: 237: 233: 231: 227: 223: 221: 217: 214:Power Station 212: 208: 204: 200: 198: 194: 191: 188: 184: 179: 175: 171: 167: 163: 159: 156: 153: 149: 144: 141: 138: 134: 130: 126: 122: 118: 114: 110: 105: 77: 73: 70: 66: 62: 58: 54: 41: 37: 30: 25: 20: 909:New Savannah 898: 812:. Retrieved 808: 799: 760: 749:. Retrieved 745: 735: 693: 653:Water portal 602: 593:contains 23 577: 569:Hartwell Dam 565:Little River 549: 519: 517: 477: 468: 452: 447:sluice gates 430: 398: 363: 331: 265: 257: 256: 247:700,000,000 546:Power plant 326:power plant 292:, creating 136:Operator(s) 99: / 75:Coordinates 57:SR 150 53:US 221 924:Categories 814:2023-03-20 809:Energy.gov 751:2021-05-22 686:References 583:generators 512:See also: 459:Korean War 455:generators 413:Paul Brown 390:irrigation 382:navigation 322:navigation 87:82°11′59″W 84:33°39′39″N 587:penstocks 181:Reservoir 889:Hartwell 789:Archived 768:Archived 725:Archived 611:See also 591:spillway 463:railcars 438:concrete 425:Congress 270:concrete 251:annually 220:Turbines 151:Impounds 55: / 39:Location 869:on the 553:thalweg 531:Senator 338:Senator 290:Georgia 280:on the 268:, is a 262:Georgia 186:Creates 166:thalweg 173:Length 161:Height 300:(and 867:Dams 746:WRDW 407:and 388:and 352:and 288:and 234:380 123:1954 115:1946 306:dam 264:as 249:kWh 69:USA 926:: 807:. 778:^ 744:. 704:^ 607:. 396:. 384:, 380:, 356:. 316:, 296:. 236:MW 67:, 63:/ 59:, 859:e 852:t 845:v 817:. 754:. 224:7 168:)

Index


US 221
SR 150
Columbia County, Georgia
McCormick County, South Carolina
USA
33°39′39″N 82°11′59″W / 33.66083°N 82.19972°W / 33.66083; -82.19972
U.S. Army Corps of Engineers
Savannah River
thalweg
Lake Strom Thurmond
Catchment area
Turbines
Installed capacity
MW
Annual generation
kWh
Georgia
concrete
embankment dam
Augusta, Georgia
Savannah River
South Carolina
Georgia
Lake Strom Thurmond
U.S. Route 221
Georgia State Route 150
dam
U.S. Army Corps of Engineers
flood control

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.