Knowledge (XXG)

Kapoor Tunnel

Source 📝

240:(TBM), which was built in Vancouver at a cost of $ 258,000. Excavation was undertaken from both ends with the intention of meeting in the middle. The machine was later abandoned and excavation was carried out manually due to the soft rock clogging the teeth and gears and causing motor burn outs. The contractor quit and the water district completed the task in 1967. On completion, the tunnel was an engineering success. Even without modern laser technology, the tunnel was joined only 6 in (152 mm) off line. The project was almost incident free with the only major injury occurring when a worker's eye was damaged while drilling into a hole containing an undetonated stick of dynamite. 31: 227:
would no longer meet the region's needs, the decision was made to excavate the tunnel. Prior to construction of the flowline, Arthur Adams, the consultant for the flowline construction, had proposed the Kapoor Tunnel be built. However, that era's technology was not yet up to the task.
287:
This tunnel can convey 580 million litres/day, 10 times greater than the Sooke Flowline, and provides water to all municipalities, except Sooke and the Highlands. Its final cost was $ 5.6 million. The Sooke Flowline had been leaking and was vulnerable to blow downs and rock slides.
291:
Every January, the tunnel is shut off and the city transfers over to the district's secondary Goldstream system. Workers walk the 8.8 km (5.5 mi) route to look for cracks and other defects.
262:
The narrow gauge railway restricted how much cement could be sent into the tunnel and slowed the lining process to 24 m (79 ft) per day.
352: 357: 272: 198: 207:
is a straight 8.8 km (5.5 mi) subterranean route which is the main transport of water from the Sooke Lake to the
87: 48: 256:
The tight space meant that only three men could work at the rock face, limiting progress to 7 metres (23 feet) per day
216: 276: 212: 208: 130: 271:
The tunnel runs from the head tank near Sooke Lake, which maintains a constant pressure to the Japan Gulch
237: 313: 220: 224: 346: 102: 89: 63: 50: 253:
Close quarters meant that only one cart could travel in the tunnel at a time
30: 317: 259:
Fresh air needed to be pumped in from the surface deep into the tunnel
247:
The rock the tunnel was being bored through was a crumbly, unstable
35:
The Kapoor Tunnel passes 1,000 ft (305 m) below two lakes.
248: 243:
The project was a challenging feat due to a variety of factors:
187: 179: 174: 166: 158: 150: 142: 137: 126: 118: 79: 40: 21: 170:580,000 m/d (20,000,000 cu ft/d) 8: 335:. Victoria: Greater Victoria Water District. 18: 331:Greater Victoria Water District (1991). 300: 162:2.1 m (6 ft 11 in) max. 154:2.1 m (6 ft 11 in) max. 310:At The End of the Trail From Victoria 236:The tunnel was formed by a miniature 7: 312:. Victoria: Cougar Press Editions. 16:Water transport route in BC, Canada 223:. When it was determined that the 14: 199:Timeline of the CRD Water System 29: 333:History and General Information 1: 353:Tunnels in British Columbia 374: 277:Goldstream Provincial Park 196: 358:Tunnels completed in 1970 146:8.8 km (5.5 mi) 133:Integrated Water Services 131:Capital Regional District 28: 103:48.460766°N 123.573069°W 64:48.509520°N 123.691286°W 108:48.460766; -123.573069 69:48.509520; -123.691286 238:tunnel boring machine 44:Sooke Lake Head Tank 99: /  60: /  308:Hall, Del (1989). 180:Construction start 221:Saanich Peninsula 195: 194: 365: 337: 336: 328: 322: 321: 305: 213:City of Victoria 114: 113: 111: 110: 109: 104: 100: 97: 96: 95: 92: 75: 74: 72: 71: 70: 65: 61: 58: 57: 56: 53: 33: 19: 373: 372: 368: 367: 366: 364: 363: 362: 343: 342: 341: 340: 330: 329: 325: 307: 306: 302: 297: 285: 269: 234: 201: 138:Characteristics 107: 105: 101: 98: 93: 90: 88: 86: 85: 84: 68: 66: 62: 59: 54: 51: 49: 47: 46: 45: 36: 24: 17: 12: 11: 5: 371: 369: 361: 360: 355: 345: 344: 339: 338: 323: 299: 298: 296: 293: 284: 281: 268: 265: 264: 263: 260: 257: 254: 251: 233: 230: 225:Sooke Flowline 197:Main article: 193: 192: 189: 185: 184: 181: 177: 176: 172: 171: 168: 164: 163: 160: 156: 155: 152: 148: 147: 144: 140: 139: 135: 134: 128: 124: 123: 120: 116: 115: 81: 77: 76: 42: 38: 37: 34: 26: 25: 22: 15: 13: 10: 9: 6: 4: 3: 2: 370: 359: 356: 354: 351: 350: 348: 334: 327: 324: 319: 315: 311: 304: 301: 294: 292: 289: 282: 280: 278: 274: 266: 261: 258: 255: 252: 250: 246: 245: 244: 241: 239: 231: 229: 226: 222: 218: 214: 210: 206: 205:Kapoor Tunnel 200: 190: 186: 182: 178: 173: 169: 165: 161: 157: 153: 149: 145: 141: 136: 132: 129: 127:Maintained by 125: 122:Kapoor Tunnel 121: 119:Official name 117: 112: 82: 78: 73: 43: 39: 32: 27: 23:Kapoor Tunnel 20: 332: 326: 309: 303: 290: 286: 270: 242: 235: 232:Construction 204: 202: 143:Total length 283:Maintenance 275:Plant near 106: / 94:123°34′23″W 83:Japan Gulch 67: / 55:123°41′29″W 347:Categories 318:B002IGIN76 295:References 219:, and the 91:48°27′39″N 52:48°30′34″N 217:Esquimalt 209:Westshore 167:Capacity 175:History 316:  188:Opened 159:Height 41:Begins 267:Route 249:shale 151:Width 314:ASIN 203:The 191:1970 183:1960 80:Ends 349:: 279:. 273:UV 215:, 211:, 320:.

Index


48°30′34″N 123°41′29″W / 48.509520°N 123.691286°W / 48.509520; -123.691286
48°27′39″N 123°34′23″W / 48.460766°N 123.573069°W / 48.460766; -123.573069
Capital Regional District
Timeline of the CRD Water System
Westshore
City of Victoria
Esquimalt
Saanich Peninsula
Sooke Flowline
tunnel boring machine
shale
UV
Goldstream Provincial Park
ASIN
B002IGIN76
Categories
Tunnels in British Columbia
Tunnels completed in 1970

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.