Knowledge

Rocky Mountain Hydroelectric Plant

Source 📝

281:, roads and bridges. Construction was suspended in 1985 when the project was 20 percent complete. In 1987, Oglethorpe Power, who was in need of a pumped-storage plant, began negotiations with Georgia Power to complete the power plant. On 15 December 1988, the two power companies reached an agreement after Oglethorpe received a US$ 706.8 million loan guarantee. The agreement allowed Oglethorpe to operate the plant and have a 75 percent stake in ownership. Construction on the power plant restarted shortly after the agreement. In 1995 the power plant was completed and the generators commissioned. The project cost $ 1 billion and it was dedicated on 9 October 1995. An upgrade of the power station was completed in 2011 which increased the installed generating capacity of each turbine-generator from 283 megawatts (380,000 hp) to 365 megawatts (489,000 hp). This increased the installed capacity of the plant from 849 megawatts (1,139,000 hp) to 1,095 MW. The power of the pumps was also increased as well. The upgrade may seem early for the young power plant but the turbines, pumps and inlet valves were purchased before construction was suspended and sat in storage. 306:. The other two embankment dams serve as auxiliary dams. The lower reservoir can store up to 18,800 acre-feet (23,200,000 m) of water and it covers an area of 600 acres (240 ha). Two other auxiliary reservoirs are located adjacent to the lower reservoir and they serve to provide additional water during periods of drought. Auxiliary Pool I is located just north of the lower reservoir and covers an area of 400 acres (160 ha). It is created by four embankment dams. Auxiliary Pool II is located west of the lower reservoir and covers an area of 200 acres (81 ha). It is created by an embankment dam and an outlet structure. Both Auxiliary Pool I and II are normally maintained at 715 feet (218 m), a water level 5 feet (1.5 m) above the lower reservoir. They provide an additional 5,800 acre-feet (7,200,000 m) of water to the lower reservoir. The Auxiliary Pools are also used to sustain wildlife and provide for recreation. 29: 492: 370: 520: 506: 290:
Water from the power plant is then discharged into the lower reservoir. When energy demand is low, usually at night, water is pumped from the lower reservoir back up to the upper reservoir. The upper reservoir can be replenished in as little as 7.2 hours. The same turbine-generators that are used to generate electricity reverse into pumps during pumping mode.
289:
As a pumped-storage power plant, it uses two reservoirs to produce electricity and store energy. The upper reservoir stores water (energy) for periods when electricity demand is high. During these periods, water from the upper reservoir is released down to the power plant to produce hydroelectricity.
293:
The upper reservoir is formed on Rocky Mountain above the lower reservoir by a 120-foot (37 m) tall and 12,895-foot (3,930 m) long continuous earth and rock-fill dam. It can store up to 10,650 acre-feet (13,140,000 m) of water and its surface area covers 221 acres (89 ha). The
256:
on top of which the plant's upper reservoir is located. Construction on the plant began in 1977 and it was commissioned in 1995. After upgrades were completed in 2011, the plant has an installed capacity of 1,095 megawatts (1,468,000 hp). It is owned by both
277:(FERC) license to operate the plant in 1972, they began to carry out design studies and plans for land acquisition. Construction on the project began in 1977 after the FERC license was granted. The initial phase included the tunnels, 566: 535: 334: 561: 576: 294:
upper reservoir lies at an elevation of 1,392 feet (424 m) while the lower reservoir is at 710.5 feet (216.6 m). The lower reservoir impounds Heath Creek and is created by two
309:
The upper reservoir and power plant are connected by an 889-foot (271 m) long penstock which splits into three separate penstocks prior to reaching each of the three 365 MW
571: 551: 338: 436: 69: 556: 274: 392: 414: 298:
and one gravity/embankment composite dam. The composite dam is 120 feet (37 m) tall and the gravity section features a
28: 440: 581: 497: 313:-generators. The difference in elevation between the upper and lower reservoirs affords the power plant a minimum net 586: 525: 253: 53: 310: 249: 218: 225: 258: 136: 314: 295: 241: 204: 545: 262: 245: 141: 57: 34: 511: 303: 519: 487: 84: 71: 505: 299: 278: 462: 567:
Pumped-storage hydroelectric power stations in the United States
437:"Rocky Mountain Pumped Storage Hydropower Project and Upgrade" 371:"Upgrade of The Rocky Mountain hydroelectric plant: part one" 265:
which have 75 percent and 25 percent stakes, respectively.
415:"Oglethorpe Power Dedicates Rocky Mountain Hydro Plant" 244:
power plant located 10 miles (16 km) northwest of
373:. Gerencia de Inteligencia e Información Tecnológica 224: 213: 203: 198: 190: 182: 177: 169: 161: 156: 148: 132: 124: 116: 108: 100: 63: 49: 41: 21: 562:Hydroelectric power plants in Georgia (U.S. state) 577:Buildings and structures in Floyd County, Georgia 439:. Ogelthorpe Power Corporation. Archived from 8: 572:1995 establishments in Georgia (U.S. state) 27: 18: 393:"Oglethorpe Power Corporation - History" 552:Energy infrastructure completed in 1995 364: 362: 360: 358: 356: 337:. Oglethorpe Power Corp. Archived from 326: 194:18,800 acre⋅ft (23,200,000 m) 173:10,650 acre⋅ft (13,140,000 m) 369:Israelsen, R.E.; R.C. Hayes; A. Ware. 209:613 ft (187 m) (minimum net) 7: 335:"Rocky Mountain Hydroelectric Plant" 275:Federal Energy Regulatory Commission 536:Rocky Mountain Hydroelectric Plant 463:"Pumped-Storage Plants in the USA" 273:After Georgia Power applied for a 238:Rocky Mountain Hydroelectric Plant 217:3 x 365 MW (489,000 hp) 22:Rocky Mountain Hydroelectric Plant 14: 230:1,095 MW (1,468,000 hp) 518: 504: 490: 1: 557:Dams in Georgia (U.S. state) 417:. PRNewswire. 9 October 1995 498:Georgia (U.S. state) portal 603: 317:of 613 feet (187 m). 26: 16:Dam in near Rome, Georgia 526:Renewable energy portal 226:Installed capacity 109:Construction began 125:Construction cost 248:in the U.S. state of 219:Francis pump-turbines 85:34.35556°N 85.30389°W 311:Francis pump-turbine 285:Design and operation 252:. It is named after 186:Rocky Mountain Lower 165:Rocky Mountain Upper 538:at Oglethorpe Power 341:on 25 February 2012 191:Total capacity 170:Total capacity 90:34.35556; -85.30389 81: /  582:Georgia Power dams 395:. Funding Universe 234: 233: 117:Opening date 594: 587:Oglethorpe Power 528: 523: 522: 514: 509: 508: 500: 495: 494: 493: 475: 474: 472: 470: 459: 453: 452: 450: 448: 433: 427: 426: 424: 422: 411: 405: 404: 402: 400: 389: 383: 382: 380: 378: 366: 351: 350: 348: 346: 331: 259:Oglethorpe Power 152:Oglethorpe Power 137:Oglethorpe Power 96: 95: 93: 92: 91: 86: 82: 79: 78: 77: 74: 31: 19: 602: 601: 597: 596: 595: 593: 592: 591: 542: 541: 532: 531: 524: 517: 510: 503: 496: 491: 489: 484: 479: 478: 468: 466: 461: 460: 456: 446: 444: 435: 434: 430: 420: 418: 413: 412: 408: 398: 396: 391: 390: 386: 376: 374: 368: 367: 354: 344: 342: 333: 332: 328: 323: 296:embankment dams 287: 271: 214:Pump-generators 178:Lower reservoir 157:Upper reservoir 140: 89: 87: 83: 80: 75: 72: 70: 68: 67: 37: 17: 12: 11: 5: 600: 598: 590: 589: 584: 579: 574: 569: 564: 559: 554: 544: 543: 540: 539: 530: 529: 515: 501: 486: 485: 483: 482:External links 480: 477: 476: 454: 443:on 20 May 2012 428: 406: 384: 352: 325: 324: 322: 319: 315:hydraulic head 286: 283: 270: 267: 242:pumped-storage 232: 231: 228: 222: 221: 215: 211: 210: 207: 205:Hydraulic head 201: 200: 196: 195: 192: 188: 187: 184: 180: 179: 175: 174: 171: 167: 166: 163: 159: 158: 154: 153: 150: 146: 145: 134: 130: 129: 126: 122: 121: 118: 114: 113: 110: 106: 105: 102: 98: 97: 65: 61: 60: 51: 47: 46: 43: 39: 38: 32: 24: 23: 15: 13: 10: 9: 6: 4: 3: 2: 599: 588: 585: 583: 580: 578: 575: 573: 570: 568: 565: 563: 560: 558: 555: 553: 550: 549: 547: 537: 534: 533: 527: 521: 516: 513: 507: 502: 499: 488: 481: 465:. IndustCards 464: 458: 455: 442: 438: 432: 429: 416: 410: 407: 394: 388: 385: 372: 365: 363: 361: 359: 357: 353: 340: 336: 330: 327: 320: 318: 316: 312: 307: 305: 304:tainter gates 301: 297: 291: 284: 282: 280: 276: 268: 266: 264: 263:Georgia Power 260: 255: 254:Rock Mountain 251: 247: 243: 239: 229: 227: 223: 220: 216: 212: 208: 206: 202: 199:Power Station 197: 193: 189: 185: 181: 176: 172: 168: 164: 160: 155: 151: 147: 143: 142:Georgia Power 138: 135: 131: 127: 123: 119: 115: 111: 107: 103: 99: 94: 66: 62: 59: 58:Rome, Georgia 55: 52: 48: 45:United States 44: 40: 36: 35:power station 30: 25: 20: 512:Water portal 467:. Retrieved 457: 445:. Retrieved 441:the original 431: 419:. Retrieved 409: 397:. Retrieved 387: 375:. Retrieved 343:. Retrieved 339:the original 329: 308: 292: 288: 272: 237: 235: 54:Floyd County 33:View of the 149:Operator(s) 128:$ 1 billion 104:Operational 88: / 64:Coordinates 546:Categories 469:4 February 447:4 February 421:4 February 399:4 February 377:4 February 345:4 February 321:References 269:Background 76:85°18′14″W 73:34°21′20″N 302:with two 279:penstocks 300:spillway 133:Owner(s) 50:Location 250:Georgia 183:Creates 162:Creates 56:, near 42:Country 101:Status 240:is a 144:(25%) 139:(75%) 471:2012 449:2012 423:2012 401:2012 379:2012 347:2012 261:and 246:Rome 236:The 120:1995 112:1977 548:: 355:^ 473:. 451:. 425:. 403:. 381:. 349:.

Index


power station
Floyd County
Rome, Georgia
34°21′20″N 85°18′14″W / 34.35556°N 85.30389°W / 34.35556; -85.30389
Oglethorpe Power
Georgia Power
Hydraulic head
Francis pump-turbines
Installed capacity
pumped-storage
Rome
Georgia
Rock Mountain
Oglethorpe Power
Georgia Power
Federal Energy Regulatory Commission
penstocks
embankment dams
spillway
tainter gates
Francis pump-turbine
hydraulic head
"Rocky Mountain Hydroelectric Plant"
the original




Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.