648:. The activities of the sinking cycle (excavation, installation of temporary ground support, placement of the shaft lining and extending shaft services) all take place in this phase of construction. In a shaft where there are to be multiple working levels, shaft stations and station stubs (short lengths of a horizontal tunnel leading away from the station) will be developed by the sinkers on the way down. As the equipment to excavate these stations must be small enough to fit through the openings in the Galloway, the rate of advance in developing the station stubs is typically low, compared to what can be achieved with full-size mining equipment, so station stubs are typically kept as short as possible.
604:. The pre-sink is the excavation and support of the first 60 – 100 metres of the shaft barrel, often completed with smaller equipment such as handheld, pneumatic drilling equipment to drill holes for basting and ground support and mini-excavators for mucking. During the pre-sink, hoisting of muck and equipment is usually performed by a mobile crane on the surface. It is necessary to sink this part of the shaft first so that the Galloway, a multi-level working platform may be installed with enough vertical distance to the shaft bottom that it will not be damaged by
218:
27:
354:
38:
308:
636:
means of winches, which move slowly and are rated for significant loads, while the sinking buckets (or kibbles) are moved in the shaft by the sinking hoist, which moves quickly and is rated for less load than the winches. To protect the hoist(s) and winches and the sensitive electronics which are used to control their operation they are normally installed inside a build called a hoist (or winder) house.
440:
589:
down to bedrock, inside which the shaft collar will be constructed. Having the loads imposed by the collar, headframe and hoisting plant transferred into solid rock is necessary to prevent unplanned subsidence. Where the depth of bedrock is too great to for a box cut to be economically viable, or the
559:
as the project team repeats the same series of activities over and over in what is called "the sinking cycle", eventually approaching the theoretical maximum rate for that sinking set up over time. The use of experienced shaft sinkers is necessary to reduce the length of this learning curve and thus
654:
Once the shaft reaches the final design depth, the shaft is stripped of any temporary services, the
Galloway cut up or modified to suit the installation of the permanent shaft set-up, the shaft sets (if required) installed and the headframe / winders modified to allow for permanent hoisting. Any
635:
With the collar constructed and the
Galloway installed the headframe and hoist (or winder) houses may be constructed and the hoist and winch ropes installed. Headframes may be either steel or concrete and their design will determine how they are constructed. The Galloway is moved in the shaft by
410:
The shaft liner does not reach right to the bottom of the shaft during sinking, but lags behind by a fixed distance. This distance is determined by the methodology of excavation and the design thickness of the permanent liner. To ensure the safety of persons working on the shaft bottom temporary
676:
Traditionally, sinking contractors would build a temporary headframe for the sinking set-up, which would then be dismantled to make way for a permanent headframe. With the growth in complexity and duration of shaft sinking projects over time it has become more common to incorporate more of the
426:
For this reason, and to minimise the number of persons on the shaft bottom a number of projects have successfully switched to shotcrete for this temporary lining. Research and development in this area is focusing on the robotic application of shotcrete and the commercialisation of thin sprayed
628:
located on the surface. The
Galloway allows sinkers to efficiently work on different levels as required by the various tasks of the sinking cycle. It is typical for the Galloway to be constructed off to one side of the shaft and lowered into the pre-sink with a crane in as complete a state as
247:
At ground level beneath and around the headframe is the Shaft Collar (also called the Bank or Deck), which provides the foundation necessary to support the weight of the headframe and provides a means for workers, materials and services to enter and exit the shaft. Collars are usually massive
680:
With the advancements made in raise boring technology, raise borers have been used to create a pilot hole for shaft sinking, where access exists at the bottom of the new shaft, in this case the sinking phase is dedicated to enlarging this pilot hole to full diameter (a process usually called
509:
to the surface. Smaller mining operations use a skip mounted underneath the cage, rather than a separate device, while some large mines have separate shafts for the cage and skips. The third compartment is used for an emergency exit; it may house an auxiliary cage or a system of ladders. An
372:
Final choice of shaft lining is dependent on the geology of the rock which the shaft passes through, some shafts have several liners sections as required Where shafts are sunk in very competent rock there may be no requirement for lining at all, or just the installation of welded mesh and
369:. The shaft lining performs several functions; it is first and foremost a safety feature preventing loose or unstable rock from falling into the shaft, then a place for shaft sets to bolt into, and lastly a smooth surface to minimise resistance to airflow for ventilation.
117:), dimensions and depth of mine shafts vary greatly in response to the specific needs of the mine they are part of and the geology they are sunk through. For example, in North and South America, smaller shafts are designed to be rectangular in plan view with
467:
and top hat sections. Top hat sections offer a number of advantages over hollow structural sections including simpler installation, improved corrosion resistance and increased stiffness. Mine conveyances run on the guides in a similar way to how a
67:
Shaft sinking is one of the most difficult of all mining development methods: restricted space, gravity, groundwater and specialized procedures make the task quite formidable. Shafts may be sunk by conventional drill and blast or mechanised means.
677:
permanent shaft set-up into the sinking phase. This results in a reduced overall project duration, as for example, if the service piping used to sink the shaft does not need to be stripped out to make way for permanent piping.
178:
A shaft may be either vertical or inclined (between 80 and 90 degrees to the horizontal), although most modern mine shafts are vertical. If access exists at the bottom of the proposed shaft, and ground conditions allow, then
577:
Although significant emphasis is placed on the rate of progress of a project sinking cycle by shaft sinkers, sinking is only one of a number of phases in the conventional construction of a new shaft, as follows;
547:
The lowest point in a sinking shaft is known as the "shaft bottom". Shaft projects differ from some other forms of mine development in that all activities that take place on the shaft bottom become part of the
198:". Many other global mining jurisdictions have adopted this rule and shafts are therefore often found in pairs (although there are multiple alternative methods of providing a second means of egress).
194:
where the single shaft at the mine became blocked, the United
Kingdom made single shaft mines illegal in 1862, establishing the practice that all underground mines must have a "
529:. One or more of the compartments discussed above may be used for air intake, while others may be used for exhaust. Where this is the case a steel or concrete wall called a
94:
The modern shaft sinking industry is gradually shifting further towards greater mechanisation. Recent innovations in the form of full-face shaft boring (akin to a vertical
494:, a conveyance used for moving workers and supplies below the surface, which is suspended from the hoist on steel wire rope. It functions in a similar manner to an
244:
wheel (with the hoist motor mounted on the ground). The headframe will also typically contain bins for storing ore being transferred to the processing facility.
278:, sometimes for many kilometers. The lowest shaft station is most often the point where rock leaves the mine levels and is transferred to the shaft, if so a
128:
Mine shafts may be used for a variety of purposes, including as a means of escape in the event of an emergency underground and allowing for the movement of:
1018:
274:(or inset) which allows men, materials and services to enter and exit the shaft. From the station tunnels (drifts, galleries or levels) extend towards the
629:
possible. Once in place, the
Galloway is "chaired" (suspended from the shaft collar) while the headframe is built above, often protected by a bulkhead.
665:
As with the depth and design of shafts, significant variations may exist in this sequence depending on local conditions. For example, shafts in the
555:
It is typical for progress (the "sinking rate") in the sinking phase (that is excavation, ground support and lining) of a shaft project to follow a
71:
Historically, mine shaft sinking has been among the most dangerous of all the mining occupations and the preserve of mining contractors called
293:
typically connects the bottom of the shaft with the rest of the mine, this ramp often contains the mine's water handling facility, called the
169:. Small shafts may be excavated upwards from within an existing mine as long as there is access at the bottom, in which case they are called
661:
The
Permanent set-up must then be commissioned to ensure that all parts are operating as planned before being handed over to the new owner.
41:
A plan-view schematic of a mine shaft showing cage and skip compartments. Services may be housed in either of the four open compartments.
735:
498:. Cages may be single-, double-, or rarely triple-deck, always having multiple redundant safety systems in case of unexpected failure.
535:
is installed between the two compartments to separate the air flow. At many mines there are one or more complete additional separate
884:
789:
1011:
1102:
1097:
730:
725:
866:
685:(waste rock) from sinking falls down the pilot hole and is handled using existing mine infrastructure off critical path.
624:
The
Galloway (also known as a Sinking Stage or Scaffold) is a multi-level working platform, suspended in the shaft from
526:
403:
and even squash balls have been required by specific circumstances. In extreme cases, particularly when sinking through
195:
217:
1232:
1227:
945:
du Judeel, G; Keyter and Harte (April 2012). "Shaft Lining design for a potash shaft in rock salts at large depths".
1074:
1004:
110:, which are "sunk" as a means of accessing an underground ore body, during the development of an underground mine.
20:
618:. From the bottom of the box cut, the shaft collar is constructed bottom up in a planned series of concrete pours.
673:
is both strong and close to the surface. This reduces the amount of time required to establish the shaft collar.
464:
209:, which has a depth of 2991 meters. Along with its twin ventilation shafts, it took ten years to sink and equip.
191:
53:
552:
for the project schedule. The infrastructure required to sink a shaft is referred to as "the sinking set-up".
52:
is the action of excavating a mine shaft from the top down, where there is initially no access to the bottom.
419:) is among the most physically challenging parts of the shaft sinking cycle as bolts must be installed using
366:
986:
285:
Beneath the lowest shaft station the shaft continues on for some distance, this area is referred to as the
1156:
609:
586:
95:
26:
549:
469:
260:
or casing is incorporated into the collar to ensure the proper flow of air into and out of the mine.
901:
740:
249:
236:(or winding tower, poppet head or pit head) which stands above the shaft. Depending on the type of
206:
353:
991:
876:
282:
is excavated on one side of the shaft at this location to allow transfer facilities to be built.
447:
Where the shaft is to be used for hoisting it is frequently split into multiple compartments by
365:
Many (although not all) shafts are lined following excavation and the installation of temporary
336:
37:
642:
The
Sinking set-up must then be commissioned to ensure that all parts are operating as planned.
341:
880:
805:
785:
57:
567:
Getting the various components of the sinking set-up correct and installed at the right time.
1191:
1069:
964:
Sanders, D. (April 2012). "New
Waterproofing Technologies for Vertical Shaft Construction".
502:
399:
segments have all been used at one time or another. Additionally, the use of materials like
396:
358:
253:
307:
201:
Currently, the deepest continuous single-lift mine shaft in the world is the main shaft at
1196:
1161:
1138:
1044:
666:
226:
202:
72:
1186:
1166:
1054:
1036:
872:
595:
591:
556:
318:
263:
Beneath the collar the part of the shaft which continues into the ground is called the
237:
170:
138:
Mine services (such as compressed air, water, backfill, power, communications and fuel)
1221:
1206:
1059:
720:
682:
31:
928:"Sinking Contractor's Close Out Presentation on the completion of South Deep Shafts"
1123:
1118:
700:
695:
681:"slashing"). This methodology can be considerably faster than full face sinking as
511:
257:
88:
831:
585:. A box cut is a large square or rectangular excavation typically completed using
377:. The material of choice for shaft lining is mass concrete which is poured behind
60:
projects, differ greatly in execution method from deep shafts, typically sunk for
1201:
1064:
715:
519:
240:(or winder) used, the top of the headframe will either house a hoist motor or a
180:
98:) have shown promise but the use of this method is, as of 2019, not widespread.
475:
Some shafts do not use guide beams but instead utilize steel wire rope (called
439:
710:
515:
183:
may be used to excavate the shaft from the bottom up; such shafts are called
155:
When the top of the excavation is the ground surface, it is referred to as a
705:
420:
412:
392:
384:
374:
323:
233:
114:
570:
Having experienced people involved from as early in the project as possible
16:
Process of excavating a vertical or near vertical tunnel from the top down
1133:
531:
495:
472:
runs on its rails, both having wheels which keep them securely in place.
270:
At locations where the shaft barrel meets horizontal workings there is a
122:
573:
Using the available time on the shaft bottom as efficiently as possible.
407:, composite liners consisting of two or more materials may be required.
1148:
766:
670:
605:
484:
428:
400:
225:, Katowice. Currently functioning as observation tower and part of the
80:
1049:
1027:
404:
331:
275:
241:
118:
107:
76:
61:
996:
927:
232:
The most visible feature of a traditionally-built mine shaft is the
590:
bedrock is not strong enough, civil engineering techniques such as
411:
ground support is installed, usually consisting of welded mesh and
625:
452:
438:
388:
306:
216:
161:
84:
25:
487:
or wheel of cheese) as these are easier to maintain and replace.
932:
Proceedings of the Third South
African Conference on Base Metals
669:
generally do not need a deep and complex shaft collar since the
299:, as water will naturally flow to the lowest point in the mine.
295:
159:; when the top of the excavation is underground, it is called a
1000:
506:
252:
structures with more than one level. If the shaft is used for
145:
479:) kept in tension by massive weights at shaft bottom called
415:. The installation of the temporary ground support (called
832:"Case Study - Blind Shaft Sinking for BHP Jansen Project"
622:
Galloway (Sinking Stage) Construction & Installation.
741:
Repurposing old mine shafts for energy storage purposes
655:
permanent conveyances will be installed at this stage.
75:. Today shaft sinking contractors are concentrated in
849:
Gleeson, D (September 2018). "That Sinking Feeling".
381:
in lifts of 6 m as the shaft advances (gets deeper).
510:
additional compartment houses mine services such as
1179:
1147:
1111:
1090:
1083:
1035:
463:. For steel shaft guides, the main two options are
490:The largest compartment is typically used for the
443:Typical mine cage, located in Harzbergbau, Germany
121:supports. Larger shafts are round in plan and are
560:the duration of the project as much as possible.
598:may be used to create a deep foundation instead.
19:"Mineshaft" redirects here. For other uses, see
563:Key to a successful shaft sinking project are:
501:The second compartment is used for one or more
806:"A Glossary of Mining Terms used in mid 1800s"
784:. John Wiley and Sons Inc. pp. 282, 284.
1012:
455:. Vertical members in a shaft set are called
8:
652:Shaft Equipping & Headframe Changeover.
525:A second reason to divide the shaft is for
1087:
1019:
1005:
997:
106:Mine shafts are vertical or near-vertical
763:Underground Drilling and Loading Handbook
633:Headframe & Hoist House Construction.
451:, these may be made of either timber or
352:
36:
753:
782:Introductory Mining Engineering 2nd ed
7:
879:: McIntosh Engineering. p. 92.
144:Broken rock (in the form of payable
987:Abandoned Mine Shafts & Tunnels
902:"Work: The Hartley Mining Disaster"
736:Glossary of coal mining terminology
539:with separate head gear and cages.
483:(because of their resemblance to a
864:De la Vergne, Jack (August 2003).
14:
514:and pipes for transfer of water,
459:, horizontal members are called
934:: 455 – via Academia.edu.
659:Commissioning Permanent Set Up.
151:Or any combination of the above
731:Underground mining (soft rock)
726:Underground mining (hard rock)
1:
966:Shaft Design and Construction
947:Shaft Design and Construction
640:Commissioning Sinking Set-Up.
769:: Tamrock Corp. p. 173.
761:Puhakka, Tuula, ed. (1997).
780:Hartman, Howard L. (2002).
1249:
867:Hard Rock Miner's Handbook
465:hollow structural sections
205:in South Africa, owned by
21:Mineshaft (disambiguation)
18:
192:Hartley Colliery disaster
30:Abandoned mine shafts in
196:a second means of egress
148:, or non payable waste)
836:SDC 2019 - Proceedings
444:
362:
350:
229:
42:
34:
900:BBC (February 2004),
587:earthmoving equipment
442:
423:powered rock drills.
356:
310:
220:
213:Parts of a mine shaft
96:tunnel boring machine
56:, typically sunk for
40:
29:
851:International Mining
830:Rennkamp, P (2019).
470:steel roller coaster
289:. A tunnel called a
1075:Mountaintop removal
926:Douglas, A (2005).
616:Collar Construction
512:high voltage cables
361:in Wodzisław Śląski
250:reinforced concrete
207:Gold Fields Limited
1233:Mining engineering
1228:Underground mining
583:Box Cut Excavation
543:Shaft construction
445:
435:Shaft compartments
363:
351:
230:
43:
35:
1215:
1214:
1175:
1174:
58:civil engineering
1240:
1088:
1070:Hydraulic mining
1021:
1014:
1007:
998:
992:Top Hat Sections
974:
973:
961:
955:
954:
942:
936:
935:
923:
917:
916:
915:
913:
897:
891:
890:
861:
855:
854:
846:
840:
839:
827:
821:
820:
818:
816:
802:
796:
795:
777:
771:
770:
758:
537:auxiliary shafts
505:, used to hoist
397:precast concrete
359:1 Maja Coal Mine
357:Sheave wheel of
254:mine ventilation
1248:
1247:
1243:
1242:
1241:
1239:
1238:
1237:
1218:
1217:
1216:
1211:
1197:Deep sea mining
1171:
1157:Room and pillar
1143:
1107:
1079:
1031:
1025:
983:
978:
977:
963:
962:
958:
944:
943:
939:
925:
924:
920:
911:
909:
906:Legacies – Tyne
899:
898:
894:
887:
863:
862:
858:
848:
847:
843:
829:
828:
824:
814:
812:
804:
803:
799:
792:
779:
778:
774:
760:
759:
755:
750:
745:
691:
667:Canadian Shield
592:diaphragm walls
545:
437:
349:
305:
227:Silesian Museum
221:Mine Headframe
215:
203:South Deep Mine
185:borehole shafts
141:Ventilation air
104:
24:
17:
12:
11:
5:
1246:
1244:
1236:
1235:
1230:
1220:
1219:
1213:
1212:
1210:
1209:
1204:
1199:
1194:
1189:
1183:
1181:
1177:
1176:
1173:
1172:
1170:
1169:
1164:
1159:
1153:
1151:
1145:
1144:
1142:
1141:
1136:
1131:
1126:
1121:
1115:
1113:
1109:
1108:
1106:
1105:
1100:
1094:
1092:
1085:
1081:
1080:
1078:
1077:
1072:
1067:
1062:
1057:
1052:
1047:
1041:
1039:
1033:
1032:
1026:
1024:
1023:
1016:
1009:
1001:
995:
994:
989:
982:
981:External links
979:
976:
975:
956:
937:
918:
892:
885:
856:
841:
822:
797:
790:
772:
752:
751:
749:
746:
744:
743:
738:
733:
728:
723:
718:
713:
708:
703:
698:
692:
690:
687:
663:
662:
656:
649:
643:
637:
630:
619:
613:
599:
596:concrete piles
575:
574:
571:
568:
557:learning curve
544:
541:
516:compressed air
481:cheese weights
436:
433:
387:, fibrecrete,
367:ground support
348:
347:
344:
339:
334:
329:
326:
321:
315:
304:
301:
280:loading pocket
214:
211:
190:Following the
153:
152:
149:
142:
139:
136:
133:
113:The shape (in
103:
100:
54:Shallow shafts
15:
13:
10:
9:
6:
4:
3:
2:
1245:
1234:
1231:
1229:
1226:
1225:
1223:
1208:
1207:Seabed mining
1205:
1203:
1200:
1198:
1195:
1193:
1190:
1188:
1185:
1184:
1182:
1178:
1168:
1165:
1163:
1160:
1158:
1155:
1154:
1152:
1150:
1146:
1140:
1137:
1135:
1132:
1130:
1127:
1125:
1122:
1120:
1117:
1116:
1114:
1110:
1104:
1101:
1099:
1096:
1095:
1093:
1089:
1086:
1082:
1076:
1073:
1071:
1068:
1066:
1063:
1061:
1058:
1056:
1053:
1051:
1048:
1046:
1043:
1042:
1040:
1038:
1034:
1029:
1022:
1017:
1015:
1010:
1008:
1003:
1002:
999:
993:
990:
988:
985:
984:
980:
971:
967:
960:
957:
952:
948:
941:
938:
933:
929:
922:
919:
907:
903:
896:
893:
888:
886:0-9687006-1-6
882:
878:
874:
870:
868:
860:
857:
853:. p. 28.
852:
845:
842:
837:
833:
826:
823:
811:
807:
801:
798:
793:
791:0-471-34851-1
787:
783:
776:
773:
768:
764:
757:
754:
747:
742:
739:
737:
734:
732:
729:
727:
724:
722:
721:Salt-concrete
719:
717:
714:
712:
709:
707:
704:
702:
699:
697:
694:
693:
688:
686:
684:
678:
674:
672:
668:
660:
657:
653:
650:
647:
644:
641:
638:
634:
631:
627:
623:
620:
617:
614:
611:
607:
603:
600:
597:
593:
588:
584:
581:
580:
579:
572:
569:
566:
565:
564:
561:
558:
553:
551:
550:critical path
542:
540:
538:
534:
533:
528:
523:
521:
517:
513:
508:
504:
499:
497:
493:
488:
486:
482:
478:
473:
471:
466:
462:
458:
454:
450:
441:
434:
432:
430:
424:
422:
418:
414:
408:
406:
402:
398:
394:
390:
386:
382:
380:
376:
370:
368:
360:
355:
345:
343:
340:
338:
335:
333:
330:
327:
325:
322:
320:
317:
316:
314:
311:Schematic of
309:
302:
300:
298:
297:
292:
288:
283:
281:
277:
273:
272:shaft station
268:
266:
261:
259:
255:
251:
245:
243:
239:
235:
228:
224:
219:
212:
210:
208:
204:
199:
197:
193:
188:
186:
182:
176:
175:
173:
168:
164:
163:
158:
150:
147:
143:
140:
137:
134:
131:
130:
129:
126:
124:
120:
116:
111:
109:
101:
99:
97:
92:
90:
86:
82:
78:
74:
69:
65:
63:
59:
55:
51:
50:shaft sinking
47:
39:
33:
32:Marl, Germany
28:
22:
1128:
969:
965:
959:
950:
946:
940:
931:
921:
910:, retrieved
905:
895:
865:
859:
850:
844:
835:
825:
813:. Retrieved
809:
800:
781:
775:
762:
756:
701:Engine shaft
696:Drift mining
679:
675:
664:
658:
651:
645:
639:
632:
621:
615:
601:
582:
576:
562:
554:
546:
536:
530:
524:
500:
491:
489:
480:
476:
474:
460:
456:
448:
446:
425:
416:
409:
395:tubing, and
383:
378:
371:
364:
312:
303:Shaft lining
294:
290:
287:shaft bottom
286:
284:
279:
271:
269:
265:shaft barrel
264:
262:
258:plenum space
246:
231:
222:
200:
189:
184:
181:raise boring
177:
171:
166:
160:
156:
154:
127:
112:
105:
93:
89:South Africa
70:
66:
49:
46:Shaft mining
45:
44:
1202:Prospecting
1084:Sub-surface
972:(1): 90–92.
953:(1): 51–54.
869:, Edition 3
765:. Tampere,
716:Raise borer
527:ventilation
520:diesel fuel
379:shaft forms
102:Mine shafts
1222:Categories
1112:Directions
1030:techniques
748:References
711:Man engine
477:guide rope
449:shaft sets
413:rock bolts
375:rock bolts
337:false edge
64:projects.
1192:Automated
1187:Abandoned
1103:Soft rock
1098:Hard rock
1050:Quarrying
912:3 October
877:North Bay
706:Headframe
646:Full Sink
492:mine cage
421:pneumatic
393:cast iron
385:Shotcrete
346:mineshaft
342:hoistroom
313:headframe
234:headframe
167:sub-shaft
135:Materials
115:plan view
1162:Longwall
1139:Borehole
1134:Bell pit
1065:Dredging
1045:Open-pit
815:10 April
689:See also
610:blasting
606:fly rock
602:Pre-Sink
532:brattice
496:elevator
431:liners.
276:ore body
223:Warszawa
123:concrete
1167:Retreat
1149:Stoping
1091:Classes
1037:Surface
767:Finland
671:bedrock
626:winches
608:during
485:truckle
461:buntons
429:polymer
417:bolting
401:bitumen
125:lined.
108:tunnels
81:Germany
73:sinkers
1060:Placer
1028:Mining
883:
810:GENUKI
788:
457:guides
405:halite
242:sheave
172:raises
132:People
119:timber
77:Canada
62:mining
1180:Other
1129:Shaft
1124:Slope
1119:Drift
1055:Strip
908:, BBC
873:Tempe
838:: 42.
503:skips
453:steel
389:brick
332:sheer
328:wheel
324:cable
319:hoist
238:hoist
165:or a
162:winze
157:shaft
85:China
914:2013
881:ISBN
817:2017
786:ISBN
683:muck
296:sump
291:ramp
256:, a
87:and
594:or
518:or
507:ore
146:ore
48:or
1224::
968:.
949:.
930:.
904:,
871:.
834:.
808:.
522:.
391:,
267:.
187:.
91:.
83:,
79:,
1020:e
1013:t
1006:v
970:1
951:1
889:.
875:/
819:.
794:.
612:.
174:.
23:.
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.