26:
604:
686:
2742:
2644:
700:
672:
2632:
2656:
399:
known as
Sheringham shoal. The wind farm would be located at water depths of 16 to 22 metres (52 to 72 ft) and consist of somewhere between 45 and 108 turbines. Benefits of the site included low shipping and trawling intensities; lack of any dredging, dumping, oil/gas, or MoD practice areas, and
400:
of cables or pipelines; as well as low visual impact from the coast, and outside any nature conservation areas. The seabed at the wind farm and offshore cable route consisted of mainly gravely sand, overlying chalk. The electrical power export cable was to be connected to a switching station near
509:
compensating for wave oscillations. Delays of several months of the arrival of foundation transport vessels, coupled with wave conditions limiting the operational window of use of the transport vessels, meant that the vessel Svanen was not able to install all the foundations. The delay had an
437:
requires the developer to decommission the wind farm once out of use - the decommissioning plan submitted by the developer included: removal of wind turbines, cutting of foundations at seabed level or lower, whilst interarray cables would be left on the sea bed.
505:, halting installation due to a previously scheduled contract for the installation vessel. The foundations installed by MT Højgaard used a special method: the support of the foundation on the delivery barge had its motion steadied by a 135t sliding support with
657:
The
Sheringham Shoal windfarm operates a community benefit fund supporting local charities and community projects. Since its establishment in 2010, the Fund has made grant awards totalling £881,642. The Fund is operated by Norfolk Community Foundation.
528:
The offshore substations were installed in May 2011 by
Heerema. The remaining pile foundations, and the transition pieces and offshore substation topsides where installed by Seaway Heavy Lifting between May and August 2011 using the newly built
500:
Onshore work began in 2009, and construction of the offshore part began March 2010. Turbine foundations installation began in June 2010; MT Højgaard installed the substation piles and 17 of the turbine foundations, using the vessel
2694:
586:
was dredged to allow wind-farm maintenance vessels to be based there. A 150 metres (490 ft) pontoon jetty was also built; the work was completed early 2010. An onshore operations base was constructed at
915:
450:
was awarded a €24m contract for the supply and construction of the 145kV export cables, and was awarded a €12m ($ 15.8m) contract in April 2009 to supply 81 km of 36kV inter-array cables.
2687:
1738:
Aldersey-Williams, John; Broadbent, Ian; Strachan, Peter (2019). "Better estimates of LCOE from audited accounts – A new methodology with examples from United
Kingdom offshore wind and CCGT".
1921:
2726:
2680:
638:
took over operations and maintenance of the wind farm from Scira. Statoil took over operation from
Statkraft, beginning in 2017, while also increasing its share in the proposed
1961:
2605:
2304:
956:
725:
454:
obtained a €50 million contract to supply offshore and onshore substations in late 2008, design and project management of the offshore substations was sub-contracted to
385:
3260:
2029:
1303:
1627:
537:
for the substation installation was cancelled and transferred to Seaway due to the delays. Foundation and transition piece installation was complete by August 2011.
3250:
1914:
3230:
3235:
923:
730:
974:
1787:
899:
2648:
1951:
1907:
433:
The lease on the sea bed given by the Crown Estate has a duration of 50 years, and the (initial) wind farm has an estimated lifespan of 20 years. The
2659:
2344:
3265:
1946:
3245:
574:
in late 2011. The first turbine was installed on 3 July 2011, and began generating in August 2011; installation was complete by July 2012.
1680:
1662:
301:
56:
1153:
25:
338:
off the coast of
Norfolk. A lease for use of the sea bed was obtained in 2004 by Scira Offshore Energy (later acquired by Statoil (now
1594:
1208:
513:
Export cable installation began late 2010, under contract to Visser & Smith Marine
Contracting. Work was carried out by the ships
3160:
2389:
2354:
1046:
937:
353:
3.6MW turbines (total power 316.8 MW) spread over a 35 km (14 sq mi) area over 17 km (11 mi) from shore.
2565:
2374:
1930:
749:
715:
767:
2259:
1010:
3225:
3092:
3076:
3071:
3055:
2459:
2399:
1028:
785:
346:), the development gained offshore planning consent in 2008, and was constructed 2009–2011, being officially opened in 2012.
1226:
373:
to develop a c. 315MW wind farm. Development work for
Econventures was to be carried out by Evelop BV, both subsidiaries of
801:
2334:
2204:
409:
559:
was terminated by mutual agreement after the foundation installation delays. Turbine installation was carried out by the
2977:
2935:
2930:
2925:
2844:
2839:
1941:
408:. Two routes were considered for the export cable, one avoiding the sandbank at Sheringham shoal. The connection to the
611:
The wind farm was operational by late 2011. An official opening took place on
September 27, 2012, attended by Norway's
2874:
2434:
2059:
720:
1832:
1698:
1281:
1818:
3186:
2940:
2854:
2495:
2464:
2339:
631:
3155:
2800:
2394:
2349:
2319:
1847:
2834:
2829:
2731:
2505:
2364:
2329:
2269:
2249:
2169:
2089:
2084:
3026:
2961:
2795:
880:
627:
2945:
2859:
2610:
2536:
2244:
2209:
2179:
2079:
2064:
1633:
705:
2849:
3165:
3010:
2703:
2615:
2541:
2429:
2224:
2194:
2174:
2139:
552:
401:
126:
1304:"Seaway Heavy Lifting to Install Subsea Foundations for Offshore Wind Farm on Sheringham Shoal (UK)]"
3121:
2920:
2890:
2869:
2864:
2546:
2480:
2254:
2189:
2154:
2134:
2119:
2094:
639:
603:
427:
426:
acquired 50% of the shareholding in Scira becoming joint (50:50) owners of the development. In 2014 the
395:, just within the 12 nm UK territorial water boundary, and 5 kilometres (3.1 mi) north of the
96:
2587:
369:
site at
Sheringham shoal. Econventures together with SLP Energy (Lowestoft, UK) formed a joint venture
3150:
2424:
2239:
2229:
2109:
2074:
434:
1611:
3220:
2779:
2774:
2721:
2409:
2285:
2234:
2199:
2069:
2054:
2049:
2044:
1984:
685:
612:
556:
534:
3255:
2580:
2444:
2324:
2264:
2144:
1765:
592:
405:
350:
245:
165:
2741:
2672:
634:) acquired the electrical transmission assets of the wind farm for £193 million. In August 2013
486:
470:
391:
The planned wind farm was approximately 18 kilometres (11 mi) off the coast of Norfolk at
3191:
2636:
2573:
2490:
2485:
2414:
2404:
957:"24 million Euro submarine power cable contract for the Sheringham Shoal Offshore Wind Farm A"
366:
331:
1865:
381:
took a 50% stake in Scira, acquiring 25% shareholdings from both SLP Energy and Ecocentures.
3240:
2500:
2454:
2449:
2290:
2159:
1755:
1747:
975:"Nexans wins 12 million Euro infield cable contract for Sheringham Shoal Offshore Wind Farm"
588:
482:
1119:
619:. The cost of development has been estimated at 10billion Norwegian krona ($ 1.8 billion).
465:. The two foundations for the substations and foundations for 88 turbines were supplied by
2995:
2707:
2379:
2369:
2164:
2114:
2104:
2009:
506:
645:
By September 2013 the wind farm had generated 1.2TWh in its first year of operation. Its
2750:
2526:
2359:
2149:
2124:
2004:
1999:
691:
677:
646:
466:
413:
261:
237:
1720:
993:
3214:
3040:
2214:
2099:
2019:
1989:
1769:
620:
583:
1834:
Sheringham Shoal Offshore Wind Farm Onshore Grid Connection -Environmental Statement
1011:"Areva T&D to provide substations for StatoilHydro's Sheringham Shoal wind farm"
2991:
2531:
2510:
2384:
1899:
1071:
362:
1121:
Siemens awarded major offshore wind power contract worth more than 450 Million EUR
469:. Manufacture of the turbine monopiles and transition pieces was subcontracted to
2905:
2184:
1751:
699:
378:
901:
Eversheds advises Statkraft on acquisition of 50% of Sheringham Shoal wind farm
3135:
2551:
2419:
2219:
2129:
1969:
667:
560:
497:
obtained a €450 million contract to supply 88 wind turbines to the wind farm.
455:
392:
71:
58:
3106:
635:
423:
396:
343:
335:
157:
2631:
1576:
1558:
1540:
1522:
1504:
1486:
1468:
1450:
1432:
1414:
1396:
1378:
1360:
1339:
1321:
1260:
1242:
1189:
1171:
1135:
1613:
Statkraft: Norway's Crown Prince opens Sheringham Shoal offshore wind farm
1289:
616:
490:
474:
374:
461:
Design work on the turbine and substation foundations was contracted to
310:
2759:
1974:
1109:, § Substations, Inter-Array & Export Cables - Offshore Substation.
494:
478:
462:
339:
142:
121:
1760:
1172:"Construction work begins on Sheringham Shoal Offshore Wind Farm site"
477:. The substation superstructure and foundations were subcontracted to
2014:
1979:
1340:"Foundation installation complete at Sheringham Shoal Wind Farm site"
447:
1209:"Gigantisk rulleskøjte gør det lettere at rejse havmøllefundamenter"
1866:"Sheringham Shoal Offshore Wind Farm, Greater Wash, United Kingdom"
916:"UK Green Investment Bank invests £240m in UK offshore wind sector"
602:
451:
1663:"UK: Ofgem Awards Sheringham Shoal Offshore Transmission Licence"
2814:
1793:
286:
2676:
1903:
1559:"Construction progresses at Scira's new permanent O&M base"
1154:"Construction work began on Sheringham Shoal offshore windfarm"
419:
Planning consent for the wind farm was given on 8 August 2008.
1994:
1415:"New turbine installation vessel to start at Sheringham Shoal"
1211:[Giant roller skate raises wind turbine foundations],
607:
Sheringham Shoal Offshore Wind Farm from Sheringham west cliff
416:
via a 132kV 21.3 kilometres (13.2 mi) underground cable.
1541:"Swaffham company wins wind farm base construction contract"
768:"Crown Estate awards Scira Offshore Energy a Wind Farm Site"
1645:
1643:
1807:
1681:"Statkraft to operate Sheringham Shoal offshore wind farm"
1243:"Trio of vessels to install Sheringham Shoal export cable"
1892:
1322:"Substation and foundation installation contract awarded"
412:
was planned to be made at an electrical substation near
994:"Areva wins €60m Statoil contract for Sheringham Shoal"
582:
As part of the development, the harbour and channel at
1282:"Foundation installation complete at Sheringham Shoal"
544:, and installed under the sea bed by water jetting by
384:
In 2006 Scira submitted a planning application to the
365:
awarded Econventures (Utrecht, NL) the lease of the
3179:
3143:
3134:
3114:
3105:
3085:
3064:
3048:
3039:
3019:
3003:
2990:
2970:
2954:
2913:
2904:
2883:
2822:
2813:
2788:
2767:
2758:
2749:
2714:
2598:
2564:
2519:
2473:
2312:
2303:
2278:
2037:
2028:
1960:
1469:"Turbine installation complete at Sheringham Shoal"
623:is used as the operational base for the wind farm.
510:estimated additional cost of 600 million NOK.
297:
281:
276:
260:
244:
212:
204:
190:
182:
174:
156:
151:
135:
111:
95:
87:
50:
36:
18:
802:"Application for 315 MW off east coast of England"
2606:List of offshore wind farms in the United Kingdom
1029:"Wood Group branches out as winds of change blow"
922:(press release), 27 November 2014, archived from
726:List of offshore wind farms in the United Kingdom
1261:"Sheringham Shoal offshore substations in place"
1190:"First foundation installed at Sheringham Shoal"
1048:SUBSTATION DESIGN FOR SHERINGHAM SHOAL WIND FARM
626:In June 2013 a consortium, "Blue Transmission" (
430:took a £240 million 20% stake in the wind farm.
866:
2688:
1915:
1433:"First turbine installed at Sheringham Shoal"
8:
2727:Pre-nationalisation electric power companies
1649:
1599:(press release), Statkraft, 22 November 2011
1596:The first energy delivery from offshore wind
731:List of offshore wind farms in the North Sea
555:in December 2010, the initial contract with
1397:"New turbine installation contract awarded"
1379:"Cable laying complete at Sheringham Shoal"
750:"UK Green Light for 15 Offshore Wind Farms"
595:, with building work taking place in 2012.
551:The turbine installation was contracted to
548:. Installation was complete by March 2012.
3140:
3111:
3045:
3000:
2910:
2819:
2764:
2755:
2695:
2681:
2673:
2309:
2034:
1922:
1908:
1900:
1361:"More vessels join Sheringham Shoal fleet"
15:
1952:Offshore wind power in the United Kingdom
1759:
1505:"New outer harbour at Wells taking shape"
1276:
1274:
2345:European Offshore Wind Deployment Centre
1487:"Historic cooperation agreement signed."
904:(press release), Eversheds, 3 April 2009
3261:Energy infrastructure completed in 2012
1699:"Statoil increases in UK offshore wind"
1355:
1353:
1066:
1064:
741:
302:Related media on Commons
1947:Renewable energy in the United Kingdom
3251:Power stations in the East of England
1848:"Sheringham Shoal Offshore Wind Farm"
1523:"Wells Harbour construction complete"
1072:"Sheringham Shoal Offshore Wind Farm"
879:Barclay, Christopher (17 July 2012),
388:for a 108 turbine, 315 MW wind farm.
7:
3231:Offshore wind farms in the North Sea
2655:
1629:Opening of Sheringham Shoal windfarm
1097:, § Turbine, Tower and Substructure.
945:, Statoil, 14 February 2014, §2, p.6
787:Signs offshore wind power deal in UK
3236:Buildings and structures in Norfolk
1789:Sheringham Shoal Offshore Wind Farm
1632:, 27 September 2012, archived from
1228:A 135 ton "shock absorber" on rails
888:, House of Commons Library, §4, p.5
328:Sheringham Shoal Offshore Wind Farm
19:Sheringham Shoal Offshore Wind Farm
1367:(press release), 22 September 2011
1249:(press release), 17 September 2010
992:Berrill, Paul (23 December 2008),
854:
842:
830:
818:
14:
1529:(press release), 16 February 2010
2740:
2654:
2643:
2642:
2630:
1931:Wind power in the United Kingdom
1583:(press release), 18 October 2012
1511:(press release), 4 February 2010
1421:(press release), 7 December 2011
1288:, 24 August 2011, archived from
1207:Krøyer, Kent (9 November 2010),
1106:
1094:
716:Wind power in the United Kingdom
698:
684:
670:
649:has been estimated at £150/MWh.
540:Inter-array cables were laid by
386:Department of Trade and Industry
24:
1831:Royal Haskoning (August 2007),
1610:Statkraft (27 September 2012),
1346:(press release), 23 August 2011
208:35 km (14 sq mi)
3266:2012 establishments in England
1547:(press release), 15 March 2012
1457:(press release), 2 August 2011
1385:(press release), 21 March 2012
1328:(press release), 11 March 2011
1231:, MT Højgaard, 3 November 2010
963:(press release), 16 April 2008
1:
1721:"Sheringham pumps out 1.2TWh"
1577:"Egmere base almost complete"
1565:(press release), 20 June 2012
1493:(press release), 24 June 2009
1475:(press release), 10 July 2012
1196:(press release), 28 June 2010
1178:(press release), 9 March 2010
1142:(press release), 30 June 2009
981:(press release), 2 April 2009
882:Wind Farm consents - offshore
632:Barclays Infrastructure Funds
183:Distance from shore
1942:Energy in the United Kingdom
1439:(press release), 4 July 2011
1267:(press release), 13 May 2011
920:/www.greeninvestmentbank.com
570:, with SEA JACK replaced by
178:15–22 m (49–72 ft)
3246:Round 2 offshore wind farms
1752:10.1016/j.enpol.2018.12.044
721:List of offshore wind farms
533:. A previous contract with
262:Annual net output
3282:
615:and UK Secretary of State
175:Max. water depth
2738:
2624:
1937:
1685:www.windpoweroffshore.com
1451:"First power to the Grid"
1136:"Onshore work commences."
939:Decommissioning Programme
857:, §2.9.1; Fig.2.17, p.70.
307:
221:
217:
32:
23:
2732:Renewable Energy Systems
2506:Sofia Offshore Wind Farm
1870:www.power-technology.com
1616:(press release), Reuters
806:www.windpowermonthly.com
485:(transition pieces) and
234:Make and model
197:107 m (351 ft)
2611:North Sea Offshore Grid
1820:Environmental Statement
1124:, Siemens, 1 April 2009
754:www.maritimejournal.com
706:Renewable energy portal
628:Macquarie Capital Group
246:Nameplate capacity
186:17 km (11 mi)
2704:Electricity generation
2616:Wind power in Scotland
2390:Lynn and Inner Dowsing
1286:www.wellsharbour.co.uk
608:
402:Muckleburgh Collection
226:Units operational
127:Green Investment Group
3226:Wind farms in England
2637:Wind power portal
790:, Hydro, 28 June 2005
640:Dogger Bank Wind Farm
606:
428:Green Investment Bank
371:Scira Offshore Energy
349:The wind farm has 88
269:1,200 GWh (2013)
213:Power generation
2566:Installation vessels
2460:West of Duddon Sands
1667:www.offshorewind.biz
1158:www.offshorewind.biz
998:www.rechargenews.com
867:ES onshore grid 2007
737:References and notes
553:Gulf Marine Services
404:, via landfall near
97:Commission date
2722:Eastern Electricity
2305:Offshore wind farms
2205:Little Cheyne Court
1727:, 27 September 2013
1636:on 17 December 2012
1308:subseaworldnews.com
613:Crown Prince Haakon
591:, 3 miles south of
517:(route clearance),
277:External links
191:Rotor diameter
68: /
2030:Onshore wind farms
1852:www.4coffshore.com
1808:"Sheringham Shoal"
1403:, 22 December 2010
845:, §2.2.1, 2.2.1.4.
774:, 18 December 2003
609:
593:Wells-next-the-Sea
572:Sea Jack Leviathan
351:Siemens Wind Power
72:53.1167°N 1.1333°E
3208:
3207:
3204:
3203:
3200:
3199:
3192:East Anglia Array
3130:
3129:
3101:
3100:
3035:
3034:
2986:
2985:
2900:
2899:
2809:
2808:
2670:
2669:
2560:
2559:
2299:
2298:
2060:Askam and Ireleth
515:Atlantic Guardian
493:(piles). In 2009
367:Round 2 wind farm
332:Round 2 wind farm
318:
317:
3273:
3171:Sheringham Shoal
3141:
3112:
3046:
3001:
2911:
2820:
2765:
2756:
2744:
2697:
2690:
2683:
2674:
2658:
2657:
2646:
2645:
2635:
2634:
2501:Neart Na Gaoithe
2465:Westermost Rough
2440:Sheringham Shoal
2310:
2035:
1924:
1917:
1910:
1901:
1896:
1895:
1893:Official website
1879:
1878:
1876:
1861:
1860:
1858:
1841:
1839:
1827:
1825:
1814:
1803:
1802:
1800:
1774:
1773:
1763:
1735:
1729:
1728:
1717:
1711:
1710:
1708:
1706:
1695:
1689:
1688:
1687:, 15 August 2013
1677:
1671:
1670:
1659:
1653:
1650:Power Technology
1647:
1638:
1637:
1624:
1618:
1617:
1607:
1601:
1600:
1591:
1585:
1584:
1573:
1567:
1566:
1555:
1549:
1548:
1537:
1531:
1530:
1519:
1513:
1512:
1501:
1495:
1494:
1483:
1477:
1476:
1465:
1459:
1458:
1447:
1441:
1440:
1429:
1423:
1422:
1411:
1405:
1404:
1393:
1387:
1386:
1375:
1369:
1368:
1357:
1348:
1347:
1336:
1330:
1329:
1318:
1312:
1311:
1300:
1294:
1293:
1292:on 19 April 2012
1278:
1269:
1268:
1257:
1251:
1250:
1239:
1233:
1232:
1223:
1217:
1216:
1204:
1198:
1197:
1186:
1180:
1179:
1168:
1162:
1161:
1150:
1144:
1143:
1132:
1126:
1125:
1116:
1110:
1104:
1098:
1092:
1086:
1085:
1084:
1082:
1068:
1059:
1058:
1057:
1055:
1043:
1037:
1036:
1033:www.scotsman.com
1025:
1019:
1018:
1017:, 8 January 2009
1007:
1001:
1000:
989:
983:
982:
971:
965:
964:
953:
947:
946:
944:
934:
928:
927:
912:
906:
905:
896:
890:
889:
887:
876:
870:
869:, pp. 2, 7.
864:
858:
852:
846:
840:
834:
828:
822:
816:
810:
809:
798:
792:
791:
782:
776:
775:
764:
758:
757:
756:, 1 January 2004
746:
708:
703:
702:
694:
689:
688:
680:
675:
674:
673:
578:Operations bases
507:hydraulic motors
483:Bladt Industries
322:Wind farm layout
311:edit on Wikidata
293:
290:
288:
240:SWT-3.6-107 (88)
229:88 × 3.6 MW
83:
82:
80:
79:
78:
73:
69:
66:
65:
64:
61:
28:
16:
3281:
3280:
3276:
3275:
3274:
3272:
3271:
3270:
3211:
3210:
3209:
3196:
3175:
3156:Greater Gabbard
3126:
3097:
3081:
3060:
3031:
3015:
2982:
2966:
2950:
2896:
2879:
2805:
2784:
2745:
2736:
2710:
2708:East of England
2701:
2671:
2666:
2629:
2620:
2594:
2556:
2515:
2469:
2370:Hywind Scotland
2350:Greater Gabbard
2295:
2274:
2165:Goonhilly Downs
2024:
2010:Talisman Energy
1956:
1933:
1928:
1891:
1890:
1887:
1882:
1874:
1872:
1864:
1856:
1854:
1846:
1837:
1830:
1823:
1817:
1812:www.scira.co.uk
1806:
1798:
1796:
1786:
1782:
1777:
1737:
1736:
1732:
1719:
1718:
1714:
1704:
1702:
1697:
1696:
1692:
1679:
1678:
1674:
1661:
1660:
1656:
1648:
1641:
1626:
1625:
1621:
1609:
1608:
1604:
1593:
1592:
1588:
1575:
1574:
1570:
1557:
1556:
1552:
1539:
1538:
1534:
1521:
1520:
1516:
1503:
1502:
1498:
1485:
1484:
1480:
1467:
1466:
1462:
1449:
1448:
1444:
1431:
1430:
1426:
1413:
1412:
1408:
1395:
1394:
1390:
1377:
1376:
1372:
1359:
1358:
1351:
1338:
1337:
1333:
1320:
1319:
1315:
1310:, 11 March 2011
1302:
1301:
1297:
1280:
1279:
1272:
1259:
1258:
1254:
1241:
1240:
1236:
1225:
1224:
1220:
1206:
1205:
1201:
1188:
1187:
1183:
1170:
1169:
1165:
1152:
1151:
1147:
1134:
1133:
1129:
1118:
1117:
1113:
1105:
1101:
1093:
1089:
1080:
1078:
1070:
1069:
1062:
1053:
1051:
1045:
1044:
1040:
1027:
1026:
1022:
1009:
1008:
1004:
991:
990:
986:
973:
972:
968:
955:
954:
950:
942:
936:
935:
931:
914:
913:
909:
898:
897:
893:
885:
878:
877:
873:
865:
861:
853:
849:
841:
837:
829:
825:
817:
813:
800:
799:
795:
784:
783:
779:
766:
765:
761:
748:
747:
743:
739:
712:
711:
704:
697:
690:
683:
676:
671:
669:
664:
655:
601:
580:
444:
435:2004 Energy Act
359:
325:
324:
323:
314:
287:sheringhamshoal
285:
272:
256:
200:
170:
152:Wind farm
147:
131:
107:
77:53.1167; 1.1333
76:
74:
70:
67:
62:
59:
57:
55:
54:
46:
12:
11:
5:
3279:
3277:
3269:
3268:
3263:
3258:
3253:
3248:
3243:
3238:
3233:
3228:
3223:
3213:
3212:
3206:
3205:
3202:
3201:
3198:
3197:
3195:
3194:
3189:
3183:
3181:
3177:
3176:
3174:
3173:
3168:
3163:
3161:Gunfleet Sands
3158:
3153:
3147:
3145:
3138:
3132:
3131:
3128:
3127:
3125:
3124:
3118:
3116:
3109:
3103:
3102:
3099:
3098:
3096:
3095:
3089:
3087:
3083:
3082:
3080:
3079:
3074:
3068:
3066:
3062:
3061:
3059:
3058:
3052:
3050:
3043:
3037:
3036:
3033:
3032:
3030:
3029:
3023:
3021:
3017:
3016:
3014:
3013:
3007:
3005:
2998:
2988:
2987:
2984:
2983:
2981:
2980:
2974:
2972:
2968:
2967:
2965:
2964:
2958:
2956:
2952:
2951:
2949:
2948:
2943:
2938:
2936:Little Barford
2933:
2928:
2926:Great Yarmouth
2923:
2917:
2915:
2908:
2902:
2901:
2898:
2897:
2895:
2894:
2887:
2885:
2881:
2880:
2878:
2877:
2872:
2867:
2862:
2857:
2852:
2847:
2845:Little Barford
2842:
2840:Great Yarmouth
2837:
2832:
2826:
2824:
2817:
2811:
2810:
2807:
2806:
2804:
2803:
2798:
2792:
2790:
2786:
2785:
2783:
2782:
2777:
2771:
2769:
2762:
2753:
2751:Power stations
2747:
2746:
2739:
2737:
2735:
2734:
2729:
2724:
2718:
2716:
2712:
2711:
2702:
2700:
2699:
2692:
2685:
2677:
2668:
2667:
2665:
2664:
2652:
2640:
2625:
2622:
2621:
2619:
2618:
2613:
2608:
2602:
2600:
2596:
2595:
2593:
2592:
2585:
2582:MPI Resolution
2578:
2570:
2568:
2562:
2561:
2558:
2557:
2555:
2554:
2549:
2544:
2539:
2534:
2529:
2527:Atlantic Array
2523:
2521:
2517:
2516:
2514:
2513:
2508:
2503:
2498:
2493:
2488:
2483:
2477:
2475:
2471:
2470:
2468:
2467:
2462:
2457:
2452:
2447:
2442:
2437:
2432:
2427:
2422:
2417:
2412:
2407:
2402:
2397:
2392:
2387:
2382:
2377:
2372:
2367:
2365:Humber Gateway
2362:
2357:
2355:Gunfleet Sands
2352:
2347:
2342:
2337:
2332:
2327:
2322:
2316:
2314:
2307:
2301:
2300:
2297:
2296:
2294:
2293:
2288:
2282:
2280:
2276:
2275:
2273:
2272:
2270:Winscales Moor
2267:
2262:
2257:
2252:
2250:Trimdon Grange
2247:
2242:
2237:
2232:
2227:
2222:
2217:
2212:
2207:
2202:
2197:
2192:
2187:
2182:
2177:
2172:
2170:Great Eppleton
2167:
2162:
2157:
2152:
2147:
2142:
2137:
2132:
2127:
2125:Cold Northcott
2122:
2117:
2112:
2107:
2102:
2097:
2092:
2090:Brechfa Forest
2087:
2085:Braes of Doune
2082:
2077:
2072:
2067:
2065:Beinn an Tuirc
2062:
2057:
2052:
2047:
2041:
2039:
2032:
2026:
2025:
2023:
2022:
2017:
2012:
2007:
2005:SSE Renewables
2002:
2000:Siemens Gamesa
1997:
1992:
1987:
1982:
1977:
1972:
1966:
1964:
1958:
1957:
1955:
1954:
1949:
1944:
1938:
1935:
1934:
1929:
1927:
1926:
1919:
1912:
1904:
1898:
1897:
1886:
1885:External links
1883:
1881:
1880:
1862:
1844:
1843:
1842:
1828:
1804:
1783:
1781:
1778:
1776:
1775:
1730:
1712:
1690:
1672:
1669:, 28 June 2013
1654:
1639:
1619:
1602:
1586:
1568:
1550:
1532:
1514:
1496:
1478:
1460:
1442:
1424:
1406:
1388:
1370:
1349:
1331:
1313:
1295:
1270:
1252:
1234:
1218:
1199:
1181:
1163:
1160:, 9 March 2010
1145:
1127:
1111:
1099:
1087:
1060:
1038:
1020:
1002:
984:
979:www.nexans.com
966:
961:www.nexans.com
948:
929:
907:
891:
871:
859:
847:
835:
823:
811:
793:
777:
759:
740:
738:
735:
734:
733:
728:
723:
718:
710:
709:
695:
692:Weather portal
681:
678:England portal
666:
665:
663:
660:
654:
653:Community Fund
651:
647:levelised cost
600:
597:
579:
576:
561:jackup vessels
531:Oleg Strashnov
521:(laying), and
446:In April 2008
443:
440:
414:Salle, Norfolk
406:Weybourne Hope
358:
355:
321:
320:
319:
316:
315:
308:
305:
304:
299:
295:
294:
283:
279:
278:
274:
273:
271:
270:
266:
264:
258:
257:
255:
254:
250:
248:
242:
241:
238:Siemens Gamesa
235:
231:
230:
227:
223:
222:
219:
218:
215:
214:
210:
209:
206:
205:Site area
202:
201:
199:
198:
194:
192:
188:
187:
184:
180:
179:
176:
172:
171:
169:
168:
162:
160:
154:
153:
149:
148:
146:
145:
139:
137:
133:
132:
130:
129:
124:
119:
115:
113:
109:
108:
106:
105:
104:September 2012
101:
99:
93:
92:
89:
85:
84:
52:
48:
47:
45:
44:
43:United Kingdom
40:
38:
34:
33:
30:
29:
21:
20:
13:
10:
9:
6:
4:
3:
2:
3278:
3267:
3264:
3262:
3259:
3257:
3254:
3252:
3249:
3247:
3244:
3242:
3239:
3237:
3234:
3232:
3229:
3227:
3224:
3222:
3219:
3218:
3216:
3193:
3190:
3188:
3185:
3184:
3182:
3178:
3172:
3169:
3167:
3164:
3162:
3159:
3157:
3154:
3152:
3149:
3148:
3146:
3142:
3139:
3137:
3133:
3123:
3120:
3119:
3117:
3113:
3110:
3108:
3104:
3094:
3091:
3090:
3088:
3084:
3078:
3075:
3073:
3070:
3069:
3067:
3063:
3057:
3054:
3053:
3051:
3047:
3044:
3042:
3038:
3028:
3025:
3024:
3022:
3018:
3012:
3009:
3008:
3006:
3002:
2999:
2997:
2993:
2989:
2979:
2978:King's Lynn B
2976:
2975:
2973:
2969:
2963:
2960:
2959:
2957:
2953:
2947:
2944:
2942:
2939:
2937:
2934:
2932:
2929:
2927:
2924:
2922:
2919:
2918:
2916:
2912:
2909:
2907:
2903:
2892:
2889:
2888:
2886:
2882:
2876:
2875:West Thurrock
2873:
2871:
2868:
2866:
2863:
2861:
2858:
2856:
2853:
2851:
2848:
2846:
2843:
2841:
2838:
2836:
2833:
2831:
2828:
2827:
2825:
2821:
2818:
2816:
2812:
2802:
2801:Tilbury Docks
2799:
2797:
2794:
2793:
2791:
2787:
2781:
2778:
2776:
2773:
2772:
2770:
2766:
2763:
2761:
2757:
2754:
2752:
2748:
2743:
2733:
2730:
2728:
2725:
2723:
2720:
2719:
2717:
2713:
2709:
2705:
2698:
2693:
2691:
2686:
2684:
2679:
2678:
2675:
2663:
2662:
2653:
2651:
2650:
2641:
2639:
2638:
2633:
2627:
2626:
2623:
2617:
2614:
2612:
2609:
2607:
2604:
2603:
2601:
2597:
2591:
2590:
2589:MPI Discovery
2586:
2584:
2583:
2579:
2577:
2576:
2575:MPI Adventure
2572:
2571:
2569:
2567:
2563:
2553:
2550:
2548:
2545:
2543:
2540:
2538:
2537:Docking Shoal
2535:
2533:
2530:
2528:
2525:
2524:
2522:
2518:
2512:
2509:
2507:
2504:
2502:
2499:
2497:
2494:
2492:
2489:
2487:
2484:
2482:
2479:
2478:
2476:
2472:
2466:
2463:
2461:
2458:
2456:
2453:
2451:
2448:
2446:
2443:
2441:
2438:
2436:
2433:
2431:
2428:
2426:
2423:
2421:
2418:
2416:
2413:
2411:
2408:
2406:
2403:
2401:
2398:
2396:
2393:
2391:
2388:
2386:
2383:
2381:
2378:
2376:
2375:Kentish Flats
2373:
2371:
2368:
2366:
2363:
2361:
2358:
2356:
2353:
2351:
2348:
2346:
2343:
2341:
2338:
2336:
2333:
2331:
2328:
2326:
2323:
2321:
2318:
2317:
2315:
2311:
2308:
2306:
2302:
2292:
2289:
2287:
2284:
2283:
2281:
2277:
2271:
2268:
2266:
2263:
2261:
2258:
2256:
2253:
2251:
2248:
2246:
2245:Slieve Rushen
2243:
2241:
2238:
2236:
2233:
2231:
2228:
2226:
2223:
2221:
2218:
2216:
2215:Moel Maelogan
2213:
2211:
2210:Milton Keynes
2208:
2206:
2203:
2201:
2198:
2196:
2193:
2191:
2188:
2186:
2183:
2181:
2180:Holmside Hall
2178:
2176:
2173:
2171:
2168:
2166:
2163:
2161:
2158:
2156:
2153:
2151:
2148:
2146:
2143:
2141:
2138:
2136:
2133:
2131:
2128:
2126:
2123:
2121:
2118:
2116:
2113:
2111:
2108:
2106:
2103:
2101:
2100:Carland Cross
2098:
2096:
2093:
2091:
2088:
2086:
2083:
2081:
2080:Blyth Harbour
2078:
2076:
2073:
2071:
2068:
2066:
2063:
2061:
2058:
2056:
2053:
2051:
2048:
2046:
2043:
2042:
2040:
2036:
2033:
2031:
2027:
2021:
2020:ScottishPower
2018:
2016:
2013:
2011:
2008:
2006:
2003:
2001:
1998:
1996:
1993:
1991:
1990:REG WindPower
1988:
1986:
1983:
1981:
1978:
1976:
1973:
1971:
1968:
1967:
1965:
1963:
1959:
1953:
1950:
1948:
1945:
1943:
1940:
1939:
1936:
1932:
1925:
1920:
1918:
1913:
1911:
1906:
1905:
1902:
1894:
1889:
1888:
1884:
1871:
1867:
1863:
1853:
1849:
1845:
1836:
1835:
1829:
1826:, Scira, 2006
1822:
1821:
1816:
1815:
1813:
1809:
1805:
1795:
1791:
1790:
1785:
1784:
1779:
1771:
1767:
1762:
1757:
1753:
1749:
1745:
1741:
1740:Energy Policy
1734:
1731:
1726:
1722:
1716:
1713:
1700:
1694:
1691:
1686:
1682:
1676:
1673:
1668:
1664:
1658:
1655:
1651:
1646:
1644:
1640:
1635:
1631:
1630:
1623:
1620:
1615:
1614:
1606:
1603:
1598:
1597:
1590:
1587:
1582:
1578:
1572:
1569:
1564:
1560:
1554:
1551:
1546:
1542:
1536:
1533:
1528:
1524:
1518:
1515:
1510:
1506:
1500:
1497:
1492:
1488:
1482:
1479:
1474:
1470:
1464:
1461:
1456:
1452:
1446:
1443:
1438:
1434:
1428:
1425:
1420:
1416:
1410:
1407:
1402:
1398:
1392:
1389:
1384:
1380:
1374:
1371:
1366:
1362:
1356:
1354:
1350:
1345:
1341:
1335:
1332:
1327:
1323:
1317:
1314:
1309:
1305:
1299:
1296:
1291:
1287:
1283:
1277:
1275:
1271:
1266:
1262:
1256:
1253:
1248:
1244:
1238:
1235:
1230:
1229:
1222:
1219:
1214:
1210:
1203:
1200:
1195:
1191:
1185:
1182:
1177:
1173:
1167:
1164:
1159:
1155:
1149:
1146:
1141:
1137:
1131:
1128:
1123:
1122:
1115:
1112:
1108:
1103:
1100:
1096:
1091:
1088:
1077:
1073:
1067:
1065:
1061:
1050:
1049:
1042:
1039:
1035:, 2 June 2009
1034:
1030:
1024:
1021:
1016:
1012:
1006:
1003:
999:
995:
988:
985:
980:
976:
970:
967:
962:
958:
952:
949:
941:
940:
933:
930:
926:on 2016-02-17
925:
921:
917:
911:
908:
903:
902:
895:
892:
884:
883:
875:
872:
868:
863:
860:
856:
851:
848:
844:
839:
836:
832:
827:
824:
820:
815:
812:
808:, 1 July 2006
807:
803:
797:
794:
789:
788:
781:
778:
773:
772:www.eeegr.com
769:
763:
760:
755:
751:
745:
742:
736:
732:
729:
727:
724:
722:
719:
717:
714:
713:
707:
701:
696:
693:
687:
682:
679:
668:
661:
659:
652:
650:
648:
643:
641:
637:
633:
629:
624:
622:
621:Wells Harbour
618:
614:
605:
598:
596:
594:
590:
585:
584:Wells Harbour
577:
575:
573:
569:
568:GMS Endeavour
565:
562:
558:
557:Master Marine
554:
549:
547:
546:Toisa Warrior
543:
538:
536:
535:Master Marine
532:
526:
525:(trenching).
524:
520:
516:
511:
508:
504:
498:
496:
492:
488:
484:
480:
476:
472:
468:
464:
459:
457:
453:
449:
441:
439:
436:
431:
429:
425:
420:
417:
415:
411:
410:National Grid
407:
403:
398:
394:
389:
387:
382:
380:
376:
372:
368:
364:
356:
354:
352:
347:
345:
341:
337:
333:
329:
312:
306:
303:
300:
296:
292:
284:
280:
275:
268:
267:
265:
263:
259:
252:
251:
249:
247:
243:
239:
236:
233:
232:
228:
225:
224:
220:
216:
211:
207:
203:
196:
195:
193:
189:
185:
181:
177:
173:
167:
164:
163:
161:
159:
155:
150:
144:
141:
140:
138:
134:
128:
125:
123:
120:
117:
116:
114:
110:
103:
102:
100:
98:
94:
90:
86:
81:
53:
49:
42:
41:
39:
35:
31:
27:
22:
17:
3170:
3166:Scroby Sands
3027:Peterborough
2992:Incinerators
2941:Peterborough
2893:(clean coal)
2855:Peterborough
2796:Peterborough
2660:
2647:
2628:
2588:
2581:
2574:
2542:First Flight
2532:Celtic Array
2511:Triton Knoll
2439:
2430:Scroby Sands
2385:London Array
2225:Ovenden Moor
2195:Langley Park
2175:Hadyard Hill
1873:, retrieved
1869:
1855:, retrieved
1851:
1833:
1819:
1811:
1797:, retrieved
1788:
1743:
1739:
1733:
1724:
1715:
1703:. Retrieved
1693:
1684:
1675:
1666:
1657:
1634:the original
1628:
1622:
1612:
1605:
1595:
1589:
1580:
1571:
1562:
1553:
1544:
1535:
1526:
1517:
1508:
1499:
1490:
1481:
1472:
1463:
1454:
1445:
1436:
1427:
1418:
1409:
1400:
1391:
1382:
1373:
1364:
1343:
1334:
1325:
1316:
1307:
1298:
1290:the original
1285:
1264:
1255:
1246:
1237:
1227:
1221:
1212:
1202:
1193:
1184:
1175:
1166:
1157:
1148:
1139:
1130:
1120:
1114:
1102:
1090:
1079:, retrieved
1075:
1052:, retrieved
1047:
1041:
1032:
1023:
1014:
1005:
997:
987:
978:
969:
960:
951:
938:
932:
924:the original
919:
910:
900:
894:
881:
874:
862:
850:
838:
826:
814:
805:
796:
786:
780:
771:
762:
753:
744:
656:
644:
625:
610:
581:
571:
567:
563:
550:
545:
541:
539:
530:
527:
523:VOS Sympathy
522:
518:
514:
512:
502:
499:
460:
445:
442:Construction
432:
421:
418:
390:
383:
370:
363:Crown Estate
361:In 2004 the
360:
348:
327:
326:
2931:King's Lynn
2547:Navitus Bay
2486:East Anglia
2481:Dogger Bank
2400:North Hoyle
2360:Gwynt y Môr
2255:West Durham
2190:Knabs Ridge
2185:Kilgallioch
2155:Fraisthorpe
2135:Crystal Rig
2120:Coal Clough
2095:Burton Wold
1875:16 February
1857:16 February
1799:16 February
1705:9 September
1581:scira.co.uk
1563:scira.co.uk
1545:scira.co.uk
1527:scira.co.uk
1509:scira.co.uk
1491:scira.co.uk
1473:scira.co.uk
1455:scira.co.uk
1437:scira.co.uk
1419:scira.co.uk
1401:scira.co.uk
1383:scira.co.uk
1365:scira.co.uk
1344:scira.co.uk
1326:scira.co.uk
1265:scira.co.uk
1247:scira.co.uk
1215:(in Danish)
1194:scira.co.uk
1176:scira.co.uk
1140:scira.co.uk
1081:16 February
1054:16 February
1015:tdworld.com
481:(topside),
467:MT Højgaard
375:Econcern BV
253:317 MW
136:Operator(s)
91:Operational
75: /
51:Coordinates
3221:Sheringham
3215:Categories
3151:Blood Hill
3093:Sizewell C
3077:Sizewell A
3056:Sizewell B
2962:Letchworth
2835:Goldington
2830:Cliff Quay
2780:Wissington
2552:Shell Flat
2496:Moray East
2425:Robin Rigg
2420:Rhyl Flats
2335:Burbo Bank
2240:Scout Moor
2230:Pates Hill
2220:Out Newton
2130:Conisholme
2110:Cefn Croes
2075:Blood Hill
1970:Ecotricity
1761:10059/3298
1725:renews.biz
456:Wood Group
393:Sheringham
377:. In 2005
60:53°07′00″N
3256:Statkraft
3122:Tilbury A
2946:Rye House
2865:Tilbury B
2860:Rye House
2715:Companies
2520:Cancelled
2410:Race Bank
2286:Den Brook
2235:Royd Moor
2200:Lindhurst
2070:Black Law
2055:Arecleoch
2050:Ardrossan
2045:Alltwalis
1962:Companies
1770:158158724
1746:: 25–35.
1701:. Statoil
833:, §2.4.2.
821:, §1.3.2.
636:Statkraft
599:Operation
542:Team Oman
519:Team Oman
487:Sif Group
471:Sif Group
424:Statkraft
397:sand bank
344:Statkraft
336:North Sea
63:1°08′00″E
3180:Proposed
3086:Proposed
3072:Bradwell
3011:Thetford
2884:Proposed
2649:Category
2474:Proposed
2445:Teesside
2435:Seagreen
2325:Beatrice
2279:Proposed
2265:Whitelee
2260:Westmill
2145:Delabole
2140:Dagenham
662:See also
617:Ed Davey
564:Sea Jack
491:Smulders
475:Smulders
422:In 2009
166:Offshore
112:Owner(s)
3241:Equinor
3187:Dudgeon
3041:Nuclear
2921:Coryton
2891:Tilbury
2870:Watford
2850:Norwich
2760:Biomass
2706:in the
2661:Commons
2491:Hornsea
2415:Rampion
2405:Ormonde
2340:Dudgeon
1975:Equinor
1840:, Scira
1780:Sources
1076:mth.com
855:ES 2006
843:ES 2006
831:ES 2006
819:ES 2006
495:Siemens
479:Heerema
463:Ramboll
357:History
340:Equinor
298:Commons
282:Website
143:Equinor
122:Equinor
118:Equitix
37:Country
3144:Active
3115:Closed
3065:Closed
3049:Active
3020:Future
3004:Active
2971:Future
2955:Closed
2914:Active
2823:Closed
2789:Future
2768:Active
2455:Walney
2450:Thanet
2395:Methil
2320:Barrow
2313:Active
2291:Viking
2160:Garves
2038:Active
2015:Vestas
1985:Ørsted
1980:Innogy
1768:
1213:ing.dk
589:Egmere
503:Svanen
448:Nexans
342:) and
88:Status
2996:waste
2775:Elean
2599:Other
2380:Lincs
2330:Blyth
2115:Clyde
2105:Carno
1838:(PDF)
1824:(PDF)
1766:S2CID
943:(PDF)
886:(PDF)
452:Areva
379:Hydro
330:is a
309:[
3136:Wind
2815:Coal
2150:Farr
1877:2016
1859:2016
1801:2016
1794:LORC
1707:2016
1107:Lorc
1095:Lorc
1083:2016
1056:2016
566:and
489:and
473:and
158:Type
3107:Oil
2906:Gas
1995:RWE
1756:hdl
1748:doi
1744:128
334:in
291:.uk
289:.co
3217::
1868:,
1850:,
1810:,
1792:,
1764:.
1754:.
1742:.
1723:,
1683:,
1665:,
1642:^
1579:,
1561:,
1543:,
1525:,
1507:,
1489:,
1471:,
1453:,
1435:,
1417:,
1399:,
1381:,
1363:,
1352:^
1342:,
1324:,
1306:,
1284:,
1273:^
1263:,
1245:,
1192:,
1174:,
1156:,
1138:,
1074:,
1063:^
1031:,
1013:,
996:,
977:,
959:,
918:,
804:,
770:,
752:,
642:.
630:,
458:.
2994:/
2696:e
2689:t
2682:v
1923:e
1916:t
1909:v
1772:.
1758::
1750::
1709:.
1652:.
313:]
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.