52:
In 1975, concerns about rapidly changing financial and energy markets as well as environmental and safety concerns led to the Darlington project becoming part of the 5-year long Ontario Royal Commission on Electric Power Planning (RCEEP) study that assessed Ontario's future energy needs for the years
71:
In 1991, problems arose first reactor unit, and it was shut down for 2 months. A similar problem occurred with the second unit, and it was shut down for 20 months. Engineers at Darlington had redesigned the heat transport system to run more efficiently and generate more power, but this woulkd cause
47:
added urgency Ontario's search for alternatives to fossil fuels to fuel its power grid. Progressive Conservative government of Premier Bill Davis became a strong advocate of Ontario Hydro's nuclear program. Planning for the new plant began in 1973. Preliminary estimates indicated that Hydro could
86:
Following the completion of Unit 2 at the Darlington Nuclear Power Station in 1990, utility revenue per kWh increased by 6 per cent in real terms on average each year from 1990 to 1993 – prompting the government to institute a rate freeze that was continued for nearly a decade. The accumulation of
56:
In July 1977 the Ontario government and Ontario Hydro announced construction of a four-unit plant that would come online in stages between 1985 and 1988 and provide 15% of Ontario's power at its completion. Because climbing interest rates of the 1970's. greatly increased the cost of borrowing,
76:
to crack and become jammed when the unit was started, forcing the shut down of the unit. A similar problem occurred with the second unit, and it too was shut down. In January 1991, an investigation into the safety of the reactors was launched to find the cause of the cracks.
57:
especially for long-term megaprojects, the projected cost of the project rose to $ 5 billion. By 1978, the cost estimate had again risen to $ 7.4 billion as Hydro began to prepare the site. Energy conservation efforts and economic slowdown
126:
announced in December 2015 the renewal of Darlington’s power reactor operating licence, for a 10 year period from Jan. 1, 2016 until Nov. 30, 2025, to allow for the refurbishment of the Darlington station, which began in October 2016.
111:(OPG) taking over all electrical generating stations. The Darlington reactors have been among the best performing in OPG's CANDU fleet, including a top year in 2008 in which the plant achieved a combined 94.5% 39:, the province's public power utility, in order to keep up with rapidly increasing demand for electrical power. The Darlington station would be the last and most powerful of a series of 542: 146:(PNNL) in Washington State and shipped to OPG's Darlington Nuclear Generating Station where they will be irradiated with neutrons inside the reactor's core to produce Pu-238. 524: 374: 219: 87:
significant electricity sector debt and the need to undertake infrastructure renewal eventually led a new government to lift the rate freeze in April 2004.
116: 305: 143: 459: 649:
Report of the Royal Commission on Electric Power Planning: Vol. 5 - Economic consideration in the planning of electric power in Ontario
626:
Report of the Royal Commission on Electric Power Planning: Vol. 5 - Economic consideration in the planning of electric power in Ontario
123: 242: 196: 175: 433: 65:
Construction began in 1981, and by 1986 was one of the largest construction sites in North America, employing 7000 workers.
572: 351: 119:(WANO) named Darlington one of the safest and top performing nuclear stations in the world - for the third time in a row. 130:
In March 2017, Ontario Power Generation (OPG) and its venture arm, Canadian Nuclear Partners, announced plans to produce
508: 234: 83:
Construction began in 1981, with unit 2 was brought online in 1990, Unit 1 in 1992, and Units 3 and 4 in 1993.
385: 108: 21: 43:
begun by Ontario Hydro in the 1960's and 1970's to meet Ontario's energy demand to the year 2000. The early
496: 648: 625: 602: 161: 313: 228: 186: 44: 213: 384:. Canadian Engineering Centennial Conference. Montreal: Canadian Nuclear Society. Archived from 227:
Kellow, Aynsley J. (1996). "Chapter 5 - Ontario: The decline and fall of the electric empire".
410: 238: 192: 171: 92: 411:
Shaping the future - First report by the Ontario Royal Commission on Electric Power Planning
17: 167: 112: 157: 131: 96: 40: 36: 382:
Proceedings of the nuclear power and fusion programs of the Canadian Nuclear Society
438: 73: 483: 580: 359: 107:
In April 1999 Ontario Hydro was split into 5 component Crown corporations with
91:
The facility was constructed in stages between 1981 and 1993 by the provincial
35:
Construction of the Darlington plant was first proposed in the late 1960's by
543:"A Historical and Comparative Perspective on Ontario's Electricity Rates" 72:
impellers in the cooling system to send pressure pulses . This caused a
68:
A decrease in the projected level of energy consumption led the Ontario
497:
United States to ship neptunium to Canada as part of Pu-238 production
139: 629:(Report). Toronto: Royal Commission on Electric Power Planning. 1980 606:(Report). Toronto: Royal Commission on Electric Power Planning. 1978 484:"CNSC renews the Darlington Nuclear Power Reactor Operating Licence" 414:(Report). Toronto: Royal Commission on Electric Power Planning. 1976 306:"The costs of power: Ontario Hydro customers face the consequences" 525:
NASA Doesn't Have Enough Nuclear Fuel For Its Deep Space Missions
135: 230:
Transforming power : the politics of electricity planning
499:. International Panel on Fissile Materials. 5 March 2017. 188:
Hydro: the decline and fall of Ontario's electric empire
460:"Darlington Nuclear Plant Rated Among the World's Best" 163:
Public power: The fight for publicly owned electricity
652:(Report). Toronto: Ontario Ministry of Energy. 1980 647: 624: 601: 409: 434:"'Tune-up' for Pickering, Overhaul at Darlington" 509:NASA Re-starts PU-238 Production at Two Sites 8: 345: 343: 603:Interim report on nuclear power in Ontario 299: 297: 295: 293: 291: 218:: CS1 maint: location missing publisher ( 304:Wickens, Barbara (September 21, 1992). 275: 282: 211: 117:World Association of Nuclear Operators 334: 144:Pacific Northwest National Laboratory 7: 573:"Utility Nuclear Program Draws Fire" 48:build the plant for $ 2.5 billion. 350:J.A.L. Robertson (August 3, 2022). 571:Langan, Fred (September 9, 1992). 124:Canadian Nuclear Safety Commission 28: 160:(2003). "10 - Nuclear Ontario". 541:Fremeth, Adam (December 2018). 356:Can CANDU estimates be trusted? 1: 375:"Domestic project management" 432:Ferguson, Rob (9 Feb 2010). 373:J. McCredie (May 18, 1987). 547:Energy Regulation Quarterly 122:After public hearings, the 678: 235:Cambridge University Press 577:Christian Science Monitor 312:. Toronto. Archived from 109:Ontario Power Generation 134:as a second source for 142:will be fabricated by 185:Swift, Jamie (2004). 115:. In June 2016, the 531:. 13 December 2018. 45:1970s energy crisis 138:. Rods containing 93:Crown corporation 669: 661: 660: 658: 657: 651: 644: 638: 637: 635: 634: 628: 621: 615: 614: 612: 611: 605: 598: 592: 591: 589: 588: 579:. Archived from 568: 562: 561: 559: 558: 538: 532: 527:. Ethan Siegel, 522: 516: 506: 500: 494: 488: 487: 480: 474: 473: 471: 470: 456: 450: 449: 447: 446: 429: 423: 422: 420: 419: 413: 406: 400: 399: 397: 396: 390: 379: 370: 364: 363: 358:. Archived from 352:"Darlington NGS" 347: 338: 332: 326: 325: 323: 321: 301: 286: 280: 255: 253: 251: 223: 217: 209: 207: 205: 181: 18:User:Soulscanner 677: 676: 672: 671: 670: 668: 667: 666: 665: 664: 655: 653: 646: 645: 641: 632: 630: 623: 622: 618: 609: 607: 600: 599: 595: 586: 584: 570: 569: 565: 556: 554: 540: 539: 535: 523: 519: 515:, March 5, 2017 507: 503: 495: 491: 482: 481: 477: 468: 466: 464:www.newswire.ca 458: 457: 453: 444: 442: 431: 430: 426: 417: 415: 408: 407: 403: 394: 392: 388: 377: 372: 371: 367: 349: 348: 341: 333: 329: 319: 317: 303: 302: 289: 281: 277: 272: 258: 249: 247: 245: 226: 210: 203: 201: 199: 184: 178: 168:Insomniac Press 156: 152: 113:capacity factor 105: 90: 80: 63: 51: 33: 26: 25: 24: 12: 11: 5: 675: 673: 663: 662: 639: 616: 593: 563: 533: 517: 501: 489: 475: 451: 424: 401: 365: 362:on 2022-08-03. 339: 327: 287: 274: 273: 271: 268: 243: 197: 176: 158:Howard Hampton 151: 148: 104: 101: 62: 59: 41:CANDU reactors 32: 29: 27: 15: 14: 13: 10: 9: 6: 4: 3: 2: 674: 650: 643: 640: 627: 620: 617: 604: 597: 594: 583:on 2021-04-11 582: 578: 574: 567: 564: 552: 548: 544: 537: 534: 530: 526: 521: 518: 514: 513:Neutron Bytes 510: 505: 502: 498: 493: 490: 485: 479: 476: 465: 461: 455: 452: 441: 440: 435: 428: 425: 412: 405: 402: 391:on 2016-03-16 387: 383: 376: 369: 366: 361: 357: 353: 346: 344: 340: 337:, p. 32. 336: 331: 328: 316:on 2020-09-24 315: 311: 307: 300: 298: 296: 294: 292: 288: 285:, p. 32. 284: 279: 276: 269: 267: 265: 263: 261: 259: 256: 246: 244:0-521-47122-2 240: 236: 233:. Cambridge: 232: 231: 224: 221: 215: 200: 198:1-896357-88-1 194: 190: 189: 182: 179: 177:1-894663-44-6 173: 169: 165: 164: 159: 154: 149: 147: 145: 141: 137: 133: 132:Plutonium-238 128: 125: 120: 118: 114: 110: 102: 100: 98: 97:Ontario Hydro 94: 88: 84: 81: 78: 75: 69: 66: 60: 58: 54: 49: 46: 42: 38: 37:Ontario Hydro 30: 23: 19: 654:. Retrieved 642: 631:. Retrieved 619: 608:. Retrieved 596: 585:. Retrieved 581:the original 576: 566: 555:. Retrieved 550: 546: 536: 528: 520: 512: 504: 492: 478: 467:. Retrieved 463: 454: 443:. Retrieved 439:Toronto Star 437: 427: 416:. Retrieved 404: 393:. Retrieved 386:the original 381: 368: 360:the original 355: 330: 318:. Retrieved 314:the original 309: 278: 266: 264: 262: 260: 257: 248:. Retrieved 229: 225: 202:. Retrieved 187: 183: 162: 155: 153: 150:Bibliography 129: 121: 106: 89: 85: 82: 79: 70: 67: 64: 61:Construction 55: 53:1983-1993. 50: 34: 283:Kellow 1996 191:. Toronto. 166:. Toronto: 74:fuel bundle 656:2022-08-04 633:2022-08-04 610:2022-08-04 587:2022-08-03 557:2022-08-05 469:2016-07-22 445:2010-02-10 418:2022-08-04 395:2022-08-04 335:Swift 2004 310:Macleans's 270:References 320:August 3, 214:cite book 103:Operation 553:(4 2018) 250:6 August 204:6 August 31:Planning 20:‎ | 22:Sandbox 529:Forbes 241:  195:  174:  140:Np-237 389:(pdf) 378:(PDF) 16:< 322:2022 252:2022 239:ISBN 220:link 206:2022 193:ISBN 172:ISBN 136:NASA 575:. 549:. 545:. 511:, 462:. 436:. 380:. 354:. 342:^ 308:. 290:^ 237:. 216:}} 212:{{ 170:. 99:. 95:, 659:. 636:. 613:. 590:. 560:. 551:6 486:. 472:. 448:. 421:. 398:. 324:. 254:. 222:) 208:. 180:.

Index

User:Soulscanner
Sandbox
Ontario Hydro
CANDU reactors
1970s energy crisis
fuel bundle
Crown corporation
Ontario Hydro
Ontario Power Generation
capacity factor
World Association of Nuclear Operators
Canadian Nuclear Safety Commission
Plutonium-238
NASA
Np-237
Pacific Northwest National Laboratory
Howard Hampton
Public power: The fight for publicly owned electricity
Insomniac Press
ISBN
1-894663-44-6
Hydro: the decline and fall of Ontario's electric empire
ISBN
1-896357-88-1
cite book
link
Transforming power : the politics of electricity planning
Cambridge University Press
ISBN
0-521-47122-2