1999 Wuppertal Schwebebahn accident

Source 📝

391:
the line was in good condition for use, despite having had the responsibility to do just that. The fitters' foreman told the court that he could not rule out the possibility of "unwittingly having made a mistake". He could not, he said, oversee all the work being done. The fitters had clearly been assigned the job of removing the claw. "I can limit myself during supervisory duties to spot checks only," he further said. He had to rely on the fitters, among whom were "experienced men", for this was, according to him, necessary. The two accused WSW inspectors who in the end had given the green light for the suspension railway to begin running on the morning in question, for their part, told the court that they had not been able to see the claw on the track because it had been too dark at the time and they had had no
29: 537: 423:) on 31 January 2002 (4 StR 289/01), the Federal Court upheld the State Court's guilty verdicts against those who were responsible for technical or building work oversight, and the foreman's acquittal. However, after an appeal from the prosecutor's office and a third party, the Federal Court overturned the fitters' acquittals, saying that the State Court had made a legal error by dividing what was an instance of collective responsibility into separate ones by applying the "principle of reliance" ( 556:) Hans Kremendahl and WSW's chairman of the board Rolf Krumsiek unveiled a memorial plaque to the victims of the accident. It can be found at Robert-Daum-Platz station. Later, on 18 April 2009, days after the accident's tenth anniversary, another memorial plaque was unveiled at a spot much nearer the accident site, on the north bank of the Wupper, a few metres (yards) from the steam pipe bridge onto which the train fell (and which has since been repaired). 545: 179: 395:. The works manager who had developed the safety scheme for the renovation work told the court, "I complied to the full extent with my duties," to which Mayer responded with a suggestion that the manager's safety scheme had been inadequate. The four fitters had nothing to say in response. Many of the surviving victims were on hand for the proceedings, including at least one who had been left with permanent 171: 129:) took place on 12 April 1999 on a stretch of track near Robert-Daum-Platz station. The accident, involving car number 4 from the WSW GTW 72 series, killed five people and injured 47, some of them seriously. It remains the worst accident in the railway's history and the only one since the railway opened in 1901 to have had a deadly outcome. 524:, began at midday on 2 June 1999. It is now established practice to do test runs after such work, even if this is still not required by law. The Schwebebahn was opened back up to the public on 8 June 1999, some eight weeks after the accident. After being examined, the piece of rolling stock damaged in the accident, car number 4, was 187:
called the emergency services to report the accident, his report was at first met with laughter from the dispatcher on the telephone, as it was considered inconceivable for a Schwebebahn train to fall off the overhead track, and nobody had ever died in an accident on this railway, which was thus said to be the world's safest.
365:
In the subsequent proceedings, it became clear that the train's fall from the track did not arise from a technical defect or a systemic error. Instead the accident had been caused by careless disassembly work towards the end of that night's shift, and deficient oversight of this work. A test run that
499:
Repair work was undertaken by WSW suspension railway workshop employees once extensive structural evaluations of overhead track support installation and of the effects wrought by the accident itself on the overhead track had been done by outside engineering consultants and other experts. Many safety
390:
company contracted to do the renovation work on Suspension Railway, that carelessness had led to the accident. He further said that the four fitters had let every care slip when they had not removed the claw fastener from the overhead track, and that the other defendants had failed to make sure that
320:
waiting on Ernststraße (street), which had been closed for the occasion. The fourth bogie, the one that had been torn off the train's roof in the accident and had fallen into the passenger compartment, had to be recovered later. The tail end of the articulated train could now be freed and lifted out
471:
was appointed to help those affected in their dealings with all questions relating to the accident's consequences. The release also dealt with questions about safety raised at the legal proceedings. While admitting that the improvements to the safety plan that had been introduced in June 1999, only
407:
by the State Court, partly for legal reasons, partly on factual grounds. The accused who were responsible for technical or building work oversight, but who nevertheless did not carry out their supervisory functions in accordance with standards, were each found guilty by the State Court of negligent
315:
vehicle was brought to the scene. As evening set in, the recovery scene was brightly lit. The work went on through the night into 14 April 1999. From the 22-metric-ton articulated train, the first bits to be lifted out of the river were three bogies each weighing roughly 3½ metric tons. These were
361:
was authorized to investigate and examine the whole process of the renovations on the stretch of the line from Pestalozzistraße station to Ohligsmühle station (each one stop from Robert-Daum-Platz station, the nearest to where the accident happened) from 9 to 12 April 1999 from the time when they
342:
during this work. On the night before the accident, work had ended during which parts of the overhead track, a few piers from the accident site, had been replaced. The night's work lagged so far behind schedule that the work site was left only ten minutes before the morning's first train from the
519:
Preparatory work for the repairs to the damaged parts of the overhead track at the accident site was begun on 31 May 1999, after the crane needed for replacing overhead track parts had been set up on ELBA's property a few days earlier. The actual repair work, involving the replacement of roughly
341:
Beginning in November 1997, in the course of renovation work in the leadup to the Schwebebahn's centenary in 2001, each weekend was spent completely replacing the railway's weightbearing structure. The steel claw fastener that was attached to the guide rail served to stabilize the overhead track
302:
because an underground garage presented stability problems. Across the Wupper lay the grounds of the firm ELBA, which offered an alternative, although the direct path to the accident scene was blocked by a production building. Nevertheless, during that day, the crane was positioned there and an
186:
Employees from the firm ELBA, which stood alongside the river and the track, climbed over a scaffold in the river after hearing the loud bang and began the efforts to save the victims. The train's driver, who was himself injured, also helped to rescue the passengers. According to a resident who
466:
dated 30 September 2000, the WSW acknowledged that the Wuppertal Suspension Railway accident had badly affected some people's health and psychological wellbeing, not only victims in the accident itself, but also their kin. The WSW also declared in the release that in future it would lend those
430:
The case as it related to the acquitted defendants was sent back to another chamber at the Wuppertal State Court. In these proceedings, one of the workers was sentenced to four months' probation, while the administrative fine of €500 to which the other three had been sentenced was suspended.
362:
began until the line was ready for use, and the documentation relating thereto, as well as the established organization for verifying safe suspension railway operation after completion of periodic building in which replacement work is done on sections of the overhead track.
213:
The injured were taken to two nearby buildings and a tent set up by the firefighters in an underpass. Further gathering points for the injured were set up at a factory and in a quickly built tent city at a carpark. Conference rooms on the ground floor at a bank became a
298:). The recovery of the fallen suspension railway train was readied on 13 April 1999 and proceeded only with great difficulty. It turned out that an emergency laneway next to an office-residential building could not be used for the needed 300-metric-ton 949: 500:
tests were undertaken, among them a special inspection of the whole overhead track, including supports and test runs with the five articulated trains that since the accident had been the main and secondary foci of attention among the
483: – the WSW also pointed out that questions raised in court repeatedly about the train's and the track's safety had to be seen alongside the lack of any such deficiencies that could be found by an expert consultant hired by the 467:
affected any conceivable help in the form of counselling, support and financial compensation, even after the legal proceedings were over. This included two telephone numbers at which callers could speak to advisers. An
282:. Two men were recovered from the wreck dead, while a woman's body was only recovered hours later after the river had borne it downstream from the accident site. Two other passengers later succumbed to their injuries. 402:
The accused who was responsible for the safety scheme, the works manager, and the workers who were responsible for dismantling certain equipment in the area of the accident, including the claw fitting, were each
161:
across the Wupper, breaking it in the middle. The bogie that had been torn off on impact at first remained up on the track, but quickly came off and fell down on the train, breaking through the vehicle's body.
307:
was lowered into the Wupper. To prepare for the actual recovery, the steel truss carrying the steam pipes, onto which the suspension railway train had fallen, had to be taken apart. Meanwhile, several
321:
of the riverbed. In work that took until evening, the whole train was lifted out of the Wupper after having been taken apart into three pieces. These were then transported to one of the halls at the
141:
involved in the accident was travelling near kilometre 7 on the suspension railway's route at about 5:45 am local time at a speed of roughly 50 km/h (30 mph) when it struck a
813: 333:, Wuppertal's highest hill. The section of rail from the overhead track onto which the fateful claw fastener was attached was removed to a place for safekeeping on Friday 16 April 1999. 258:), all routine operations were postponed and all available doctors were pressed into emergency service. Within three hours of the accident, all 47 of the injured, suffering from 1007: 911: 615: 928: 997: 958: 383: 629: 472:
two months after the accident, could not yet properly be evaluated – the responsibility for that lay with the Technical Oversight Authority (
1022: 182:
A view of the accident scene from the riverbank in 2016 looking towards Pestalozzistraße station, in the direction from which the train came.
761: 1002: 707: 408:
homicide in five legally concurrent cases in coincidence with negligent bodily harm in 37 legally concurrent cases, and sentenced to
145:
component (a "claw fastener") that had temporarily been attached to the running rail on the overhead track. The impact tore the lead
895: 600: 738: 513: 462:. The total cost to the Corporation from the Wuppertal Suspension Railway accident ran to well over DM 8 million. In a 1012: 28: 869: 484: 291: 779: 491:). The release ended with the WSW stating that it would not comment on the court’s guilty verdicts against the accused. 677: 536: 195: 346:
direction came along. The workers were apparently in such a hurry that they forgot to remove the claw fastener.
1017: 416: 845: 290:
First, the affected stretch of the overhead track and the trainwreck in the river were seized by order of the
477: 509: 343: 207: 116: 867:
Kühlwetter, Hans-Jürgen (June 2001). "Das erstinstanzliche Urteil im Wuppertaler Schwebebahnprozess".
459: 455: 247: 905: 443: 378:), the prosecutor, Ralf Meyer, put it to the defendants, three Wuppertal City Works Corporation ( 317: 202:, to rescue and treat the injured at the site, which could only be reached with difficulty. Even 69: 544: 178: 932: 891: 874: 609: 596: 235: 648: 158: 715: 505: 299: 138: 122: 239: 798: 215: 746: 991: 573: 552:
On 12 April 2000, the first anniversary of the fateful day, Wuppertal's chief mayor (
501: 463: 435: 387: 259: 149:, the first of four, off the train's roof. The vehicle next leant over to the right, 827: 382:, or WSW for short) employees along with four fitters and their foreman from Lavis 308: 170: 925:
Landgericht Wuppertal, Az.: 21 KLs 411 Js 533/99 - 2/00 – (first-instance ruling)
780:"Unfall der Wuppertaler Schwebebahn – Freisprüche von vier Monteuren aufgehoben" 330: 231: 191: 888:
Eisenbahnunfälle bei der Deutschen Bahn. Ursachen – Hintergründe – Konsequenzen
174:
The accident site in 2005; the steam pipe bridge can be seen in the background.
521: 396: 392: 316:
lifted with the crane during the day over the ELBA work buildings and onto an
312: 150: 973: 960: 878: 366:
could have prevented the accident was neither planned nor prescribed by law.
468: 409: 404: 304: 275: 271: 199: 230:), was the first to admit patients from the accident scene. Meanwhile, the 685: 326: 279: 219: 828:"Als das unfassbare geschah - das Schwebebahnunglück vom 12. April 1999" 458:
to help the bereaved and others affected by the accident overcome their
447: 439: 243: 206:
were called into service to minister to those who were suffering from
451: 263: 203: 154: 354: 543: 535: 525: 267: 177: 169: 146: 142: 79:
Train struck maintenance equipment left on tracks by rail workers.
950:|article RP Online – Pictures of the Suspension Railway accident 33:
Scene of the incident, where a train fell onto a steam pipeline.
153:, and then fell almost 10 m (30 ft) into the River 814:"Wuppertaler Stadtwerke AG zum Urteil im Schwebebahnprozess" 799:"Verfahren gegen Monteure im Schwebebahnprozeß eingestellt" 157:. The train's front section came down on a bridge carrying 434:
The WSW, as the suspension railway's operator, paid some
678:"Nach dem Schwebebahnunfall in Elberfeld vom 12.04.1999" 520:
5 m (16 ft) of rail support, running rail and
784:
Bundesgerichtshof, Pressestelle des Bundesgerichtshofes
630:"Schwebebahn-Unglück: Ein schwarzer Tag für Wuppertal" 762:"Schwebebahn-Unglück: Jeder hat eine Entschuldigung" 104: 96: 88: 83: 75: 65: 47: 42: 21: 797:Bretschneider, Frank; Busch, Wibke (5 June 2003). 595:(in German) (1 ed.), Odenthal, p. 13, 311:were mounted on the overhead track and a police 508:work was necessary at the line's two termini, 8: 812:Wuppertaler Stadtwerke (30 September 2000). 540:Memorial plaque at Robert-Daum-Platz station 1008:Railway accidents and incidents in Germany 910:: CS1 maint: location missing publisher ( 737:Friedrichsen, Gisela (18 September 2000). 714:(in German). 15 April 1999. Archived from 684:(in German). 15 April 2000. Archived from 614:: CS1 maint: location missing publisher ( 198:were on hand, along with twelve emergency 18: 739:"Man kann doch nicht alles selbst machen" 516:to bring the trains into working order. 254:(another hospital, now also part of the 935:: ruling of the 4th criminal division ( 846:"10. Jahrestag des Schwebebahn-Unglück" 649:"Gespenstische Stille nach dem Unglück" 565: 399:arising from injuries in the accident. 100:5 (3 in wreck; 2 succumbed to injuries) 903: 672: 670: 668: 666: 664: 662: 607: 939:) from 31 January 2002 – 4 StR 417/01 256:Helios Universitätsklinikum Wuppertal 228:Helios Universitätsklinikum Wuppertal 7: 548:Memorial plaque at the accident site 270:, found themselves at hospitals in 22:1999 Wuppertal Schwebebahn accident 647:Iven, Jens Peter (12 April 1999). 14: 998:History of North Rhine-Westphalia 415:In the ruling handed down by the 27: 890:. Stuttgart. pp. 120–128. 242:427 cross, became an emergency 852:(in German). 31 December 2014. 760:Meinke, Ulf (24 August 2000). 593:Jahrhundertbauwerk Schwebebahn 374:At the Wuppertal State Court ( 351:Technischer Überwachungsverein 1: 870:Eisenbahn-Revue International 786:(in German). 31 January 2002. 323:Generaloberst-Hoepner-Kaserne 224:Ferdinand-Sauerbruch-Klinikum 1023:April 1999 events in Germany 816:(Press release) (in German). 591:Oertel, Marie Luise (2001), 359:Rheinland/Berlin-Brandenburg 834:(in German). 12 April 1999. 745:(in German). Archived from 636:(in German). 12 April 2004. 578:Die Wuppertaler Schwebebahn 474:Technische Aufsichtsbehörde 252:Städtisches Klinikum Barmen 16:Railway accident in Germany 1039: 929:juris.bundesgerichtshof.de 708:"WSW-Presse-Info Nr. 2/99" 485:public prosecutor's office 438: 1.3 million in 380:WSW Wuppertaler Stadtwerke 292:public prosecutor's office 190:In the end, more than 150 1003:Railway accidents in 1999 574:"Unfälle der Schwebebahn" 234:Robert-Daum-Platz, where 38: 26: 417:Federal Court of Justice 549: 541: 495:Technical consequences 454:costs, as well as for 183: 175: 53:; 25 years ago 1013:Wuppertal Schwebebahn 886:Preuß, Erich (2004). 547: 539: 370:Judicial consequences 181: 173: 117:Wuppertal Schwebebahn 873:. pp. 283–287. 832:Bahnen im Bergischen 749:on 27 February 2011. 460:psychological trauma 970: /  425:Vertrauensgrundsatz 309:halogen floodlights 208:psychological shock 196:ambulance personnel 159:steam heating pipes 974:51.2518°N 7.1327°E 550: 542: 528:and not replaced. 489:Staatsanwaltschaft 444:pain and suffering 296:Staatsanwaltschaft 248:rescue helicopters 184: 176: 70:Wuppertal, Germany 51:12 April 1999 933:Bundesgerichtshof 718:on 16 August 2021 554:Oberbürgermeister 448:medical treatment 421:Bundesgerichtshof 318:articulated truck 139:articulated train 127:Schwebebahnunfall 112: 111: 1030: 985: 984: 982: 981: 980: 975: 971: 968: 967: 966: 963: 915: 909: 901: 882: 854: 853: 842: 836: 835: 824: 818: 817: 809: 803: 802: 794: 788: 787: 776: 770: 769: 757: 751: 750: 734: 728: 727: 725: 723: 712:www.home.wtal.de 704: 698: 697: 695: 693: 682:www.home.wtal.de 674: 657: 656: 653:Der Tagesspiegel 644: 638: 637: 626: 620: 619: 613: 605: 588: 582: 581: 570: 532:Public memorials 480:Regierungsbezirk 286:Recovery efforts 226:(now called the 61: 59: 54: 31: 19: 1038: 1037: 1033: 1032: 1031: 1029: 1028: 1027: 1018:1999 in Germany 988: 987: 979:51.2518; 7.1327 978: 976: 972: 969: 964: 961: 959: 957: 956: 955: 946: 922: 902: 898: 885: 866: 863: 861:Further reading 858: 857: 844: 843: 839: 826: 825: 821: 811: 810: 806: 796: 795: 791: 778: 777: 773: 759: 758: 754: 736: 735: 731: 721: 719: 706: 705: 701: 691: 689: 688:on 4 March 2016 676: 675: 660: 646: 645: 641: 628: 627: 623: 606: 603: 590: 589: 585: 572: 571: 567: 562: 534: 497: 397:mobility issues 372: 339: 288: 168: 135: 57: 55: 52: 34: 17: 12: 11: 5: 1036: 1034: 1026: 1025: 1020: 1015: 1010: 1005: 1000: 990: 989: 953: 952: 945: 944:External links 942: 941: 940: 926: 921: 918: 917: 916: 896: 883: 862: 859: 856: 855: 837: 819: 804: 789: 771: 752: 729: 699: 658: 639: 621: 601: 583: 564: 563: 561: 558: 533: 530: 496: 493: 393:portable light 371: 368: 338: 337:Investigations 335: 287: 284: 236:Bundesstraße 7 216:field hospital 167: 166:Rescue efforts 164: 134: 131: 110: 109: 106: 102: 101: 98: 94: 93: 90: 86: 85: 81: 80: 77: 73: 72: 67: 63: 62: 49: 45: 44: 40: 39: 36: 35: 32: 24: 23: 15: 13: 10: 9: 6: 4: 3: 2: 1035: 1024: 1021: 1019: 1016: 1014: 1011: 1009: 1006: 1004: 1001: 999: 996: 995: 993: 986: 983: 951: 948: 947: 943: 938: 934: 930: 927: 924: 923: 920:Court rulings 919: 913: 907: 899: 897:3-613-71229-6 893: 889: 884: 880: 876: 872: 871: 865: 864: 860: 851: 847: 841: 838: 833: 829: 823: 820: 815: 808: 805: 800: 793: 790: 785: 781: 775: 772: 767: 763: 756: 753: 748: 744: 740: 733: 730: 717: 713: 709: 703: 700: 687: 683: 679: 673: 671: 669: 667: 665: 663: 659: 654: 650: 643: 640: 635: 631: 625: 622: 617: 611: 604: 602:3-00-008291-3 598: 594: 587: 584: 579: 575: 569: 566: 559: 557: 555: 546: 538: 531: 529: 527: 523: 517: 515: 511: 507: 503: 502:rolling stock 494: 492: 490: 486: 482: 481: 475: 470: 465: 464:press release 461: 457: 453: 449: 445: 441: 437: 432: 428: 426: 422: 418: 413: 411: 406: 400: 398: 394: 389: 388:Aschaffenburg 385: 381: 377: 369: 367: 363: 360: 356: 352: 347: 345: 336: 334: 332: 328: 324: 319: 314: 310: 306: 301: 297: 293: 285: 283: 281: 277: 273: 269: 265: 261: 257: 253: 249: 245: 241: 237: 233: 229: 225: 221: 217: 211: 209: 205: 201: 197: 193: 188: 180: 172: 165: 163: 160: 156: 152: 148: 144: 140: 133:Circumstances 132: 130: 128: 124: 120: 118: 107: 103: 99: 95: 91: 87: 82: 78: 74: 71: 68: 64: 50: 46: 41: 37: 30: 25: 20: 954: 936: 887: 868: 849: 840: 831: 822: 807: 801:(in German). 792: 783: 774: 768:(in German). 765: 755: 747:the original 742: 732: 720:. Retrieved 716:the original 711: 702: 690:. Retrieved 686:the original 681: 655:(in German). 652: 642: 633: 624: 592: 586: 580:(in German). 577: 568: 553: 551: 522:current rail 518: 504:. Extensive 498: 488: 479: 473: 433: 429: 424: 420: 414: 401: 379: 375: 373: 364: 358: 350: 348: 340: 322: 295: 289: 260:broken bones 255: 251: 240:Landesstraße 227: 223: 212: 192:firefighting 189: 185: 136: 126: 115: 113: 977: / 743:Der Spiegel 722:24 November 692:24 November 456:specialists 376:Landgericht 331:Lichtscheid 268:lacerations 244:landing pad 232:city square 218:. A nearby 992:Categories 962:51°15′06″N 937:Strafsenat 560:References 514:Oberbarmen 313:light mast 246:for three 200:physicians 84:Statistics 58:1999-04-12 965:7°07′58″E 906:cite book 879:1421-2811 634:RP Online 510:Vohwinkel 476:) in the 469:ombudsman 410:probation 405:acquitted 344:Vohwinkel 305:excavator 276:Remscheid 272:Wuppertal 250:. At the 204:clergymen 610:citation 526:scrapped 506:shunting 450:and for 327:barracks 280:Solingen 220:hospital 151:derailed 119:accident 66:Location 440:damages 264:bruises 105:Injured 56: ( 43:Details 894:  877:  599:  478:local 452:burial 446:, for 442:, for 386:, the 222:, the 155:Wupper 123:German 97:Deaths 89:Trains 329:) on 300:crane 147:bogie 143:steel 76:Cause 912:link 892:ISBN 875:ISSN 766:Welt 724:2017 694:2017 616:link 597:ISBN 512:and 384:GmbH 349:The 278:and 266:and 238:and 194:and 137:The 114:The 48:Date 850:RGA 427:). 355:TÜV 994:: 931:, 908:}} 904:{{ 848:. 830:. 782:. 764:. 741:. 710:. 680:. 661:^ 651:. 632:. 612:}} 608:{{ 576:. 436:DM 412:. 357:) 274:, 262:, 210:. 125:: 108:47 914:) 900:. 881:. 726:. 696:. 618:) 487:( 419:( 353:( 325:( 294:( 121:( 92:1 60:)

Index


Wuppertal, Germany
Wuppertal Schwebebahn
German
articulated train
steel
bogie
derailed
Wupper
steam heating pipes


firefighting
ambulance personnel
physicians
clergymen
psychological shock
field hospital
hospital
city square
Bundesstraße 7
Landesstraße
landing pad
rescue helicopters
broken bones
bruises
lacerations
Wuppertal
Remscheid
Solingen