Knowledge

Muskrat Falls Generating Station

Source đź“ť

36: 344:. On December 17, 2012, the provincial government announced project sanction. Emera received approval to proceed with the Maritime Link from the Nova Scotia Utility and Review Board in 2013. Financial close for the loan guarantee occurred in late 2013. On September 23, 2020, the first unit at Muskrat Falls was synced to the electricity grid in Labrador. Power from the remaining three units was originally expected to come online in the fall of 2021. However, there were delays in construction, including on the corresponding Labrador–Island Link which will transmit generated power to a converter outside 1709: 1737: 537:
that the business case, which assumed the Muskrat Falls project was the lowest-cost power option, was “questionable.” LeBlanc said that the project’s economics were not sufficiently tested and that Nalcor failed to consider all potentially viable power options. LeBlanc said that Nalcor concealed information that could have undermined the business case for the project from the public and government.
1723: 43: 536:
Dwight Ball called a public inquiry into the project, which took place between 2018 and 2020. In the inquiry report, Commissioner Richard LeBlanc concluded the government failed its duty to residents by predetermining that the megaproject would proceed no matter what. In his report, LeBlanc concluded
524:
The project is more than $ 6 billion over budget, and five years late as of 2022. Projected cost overruns exceeding 70% from $ 7.4 billion to $ 12.7 billion due to poor planning, lack of engineering experience, and related assumptions that were invalid, misleading or later turned out to be incorrect
511:
accepting. Nalcor had applied for a permit in July 2018 to carry out the approximately 13 hectares of wetland capping – essentially pouring sand and stone over a small area of wetland near the reservoir – but the permit was never approved by the Department of Municipal
464:
and the provincial government began in 2006, resulting in the New Dawn (Tshash Petapen) Agreement, finalized in 2011. This agreement included an Impacts and Benefits Agreement (IBA), a Redress Agreement related to damage caused by the Churchill Falls development, and an agreement in principle about
362:
In April 2023, Jennifer Williams, CEO of Newfoundland and Labrador Hydro, announced the completion of the final successful test of the 1100 km transmission link to Newfoundland. Commissioning by the federal government will be announced following the completion of paperwork. Originally approved
488:
Community Council) and the Government of Newfoundland and Labrador outlining the establishment of an independent committee to make recommendations on mitigating potential impacts of methylmercury on human health from the Lower Churchill Project at Muskrat Falls, Labrador. In 2018, the committee
459:
with the provincial and federal governments. The provincial and federal government agreed to a combined review process that would fulfill the requirements of both levels of government, resulting in the formation of a Joint Review Panel. In 2010, the focus shifted to Muskrat Falls only. The
551:
would provide the project with $ 5.2 billion of financial support to compensate for its large cost overrun (from $ 6.2 billion to over $ 13 billion) and to enable the province to maintain the price of power at a competitive rate (14.7 cents per kilowatt-hour). The
460:
environmental assessment for the transmission lines was done separately and was conducted in 2013. Many Indigenous peoples had serious concerns about how the land and wildlife would be changed by the development. Negotiations between the
376:
Reservoir impoundment was completed in 2019 with the flooding of 41 km of land to create the 101 km reservoir. Containment is by a two-part concrete dam totalling 757 metres long. This will power an 834 MW generating station.
1495: 1758: 35: 476:
levels in fish would rise as a result of the project. After protests led by Indigenous groups in Central Labrador in 2016, an agreement was reached by Labrador’s three Indigenous groups (
1051: 1289: 1783: 1312: 503:
at the Muskrat Falls reservoir as previously planned. The $ 30 million designated for the capping was split up and offered to all three Indigenous governments, with the
1540: 1243: 731: 1607: 772: 1401: 323:
to develop the project was announced in November 2010. On November 30, 2012, a federal loan guarantee deal for financing of the project was signed by
86: 1266: 1174: 611: 1763: 1585: 882: 794: 1773: 465:
the Innu Nation’s land claim. Upon the ratification of the New Dawn Agreement, the Innu Nation indicated that the project was acceptable to them.
405: 750: 1148: 1100: 990: 816: 431:, power is distributed via the existing grid. Emera hopes to sell surplus power via a proposed 563 km underwater transmission line from 1020: 1220: 533: 331: 926: 1669: 500: 574:
protested the decision stating they had not been consulted. The Innu Nation also raised concerns about the compensation claimed by the
1379: 587: 305: 1689: 704: 645: 1334: 1768: 970: 1423: 860: 676: 356: 145: 363:
in 2012 with an anticipated price tag of around $ 7.4 billion, the costs of the project increased to more than $ 13 billion.
1517: 1357: 571: 1627: 1446: 390: 578:
and how cost overruns may reduce the amount of Innu royalties received under the 2011 impact and benefits agreement.
345: 301: 172: 293: 162: 73: 55: 541: 456: 413: 324: 1742: 496:
During the Muskrat Falls inquiry in 2019, it was revealed the provincial government wouldn’t be completing
1648:"Trudeau offers $ 5.2 billion bailout for Newfoundland and Labrador's beleaguered Muskrat Falls hydro dam" 338: 1052:"Transmission link between Labrador and Newfoundland energized as Muskrat Falls project nears completion" 1778: 592: 560: 489:
recommended – among other things – wetland capping to stem the release of
452: 394: 386: 1290:"Newfoundland and Labrador government 'unintentionally' missed Muskrat Falls wetland capping deadline" 557: 553: 548: 398: 420:
with a capacity of 500 MW. Construction was a 1.2 billion dollar joint venture between Nalcor and
1647: 1562: 1380:"Government skipped methylmercury deadline then offered 'hush money,' says Nunatsiavut president" 1028: 469: 417: 247: 1313:"No time left for reservoir work prior to flooding, deputy minister tells Muskrat Falls Inquiry" 1125: 1073: 904: 838: 677:
Report on Two Generation Expansion Alternatives for the Island Interconnected Electrical System
1402:"Liberal minister dismisses call for investigation into Muskrat Falls wetland capping failure" 839:"Government of Newfoundland and Labrador Announces Sanction of the Muskrat Falls Development" 563:
protested against this subsidy, which they claimed provided unfair competition to their own
334: 516:
later said wetland capping would have only decreased methylmercury levels by two per cent.
393:
line with a capacity of 900 MW. The total length is 1,100 km, of which 30 km are
708: 260: 1608:"$ 5.2B deal reached between feds, N.L. government to stave off skyrocketing power bills" 564: 1221:"Nunatsiavut president pleads with premier to pump the brakes on Muskrat Falls flooding" 1469: 683: 544: 341: 327: 270: 240: 1752: 1714: 945: 618: 567: 490: 473: 436: 432: 316: 309: 234: 51: 1447:"Too late to mitigate: Inquiry hears how wetland capping no longer a Muskrat option" 451:
registered the generation components of the Lower Churchill Project, including both
1728: 1496:"'Project was not the right choice': Muskrat Falls estimate surpasses $ 11-billion" 352: 201: 1736: 1670:"Innu Nation repeatedly blindsided by Muskrat Falls announcements, letters show" 732:"Churchill hydro deal signals era of Atlantic co-operation – The Globe and Mail" 513: 508: 485: 481: 477: 461: 409: 1518:"Muskrat Falls: A story of unchecked oilmen and their boondoggle hydro project" 1704: 1244:"Advisory committee recommendations about Muskrat Falls deserve action: chair" 526: 971:"Nalcor Energy to be no more: Crown corporation being folded into N.L. Hydro" 101: 88: 1722: 751:"Harper signs loan guarantee deal for Muskrat Falls despite Quebec's outcry" 428: 312:
has a capacity of over 824 MW and provides 4.5 TWh of electricity per year.
1074:"New power transmission towers connect Muskrat Falls, mainland Nova Scotia" 991:"Muskrat Falls hydroelectric project in N.L. considered commissioned: CEO" 1694: 1674: 1632: 1612: 975: 905:"Speaking notes delivered December 10 by the Honourable Kathy Dunderdale" 289: 253: 187: 69: 1358:"Nalcor's $ 10M deal with NunatuKavut hammered out in a page and a half" 1628:"Ottawa to give N.L. billions of dollars to offset Muskrat Falls costs" 1175:"Methylmercury levels downstream from Muskrat Falls concern researcher" 497: 1267:"United Nations calls for methyl mercury mitigation at Muskrat Falls" 448: 297: 1541:"Newfoundland Premier announces inquiry into Muskrat Falls project" 1196: 1335:"Methylmercury deal struck with 2 of 3 Labrador Indigenous groups" 421: 320: 1690:"Muskrat Falls deal 'betrayed the Innu people,' says Innu Nation" 1586:"Final report from Muskrat Falls inquiry released to the public" 946:"Hydro Announces Completion of Muskrat Falls Generating Station" 575: 504: 276: 157: 883:"Maritime Link energy project approved by Nova Scotia's UARB" 1565:. Government of Newfoundland and Labrador. November 20, 2017 1128:. Government of Newfoundland and Labrador. November 18, 2011 907:. Government of Newfoundland and Labrador. December 17, 2012 841:. Government of Newfoundland and Labrador. December 17, 2012 355:
announced Nalcor Energy would be dismantled and folded into
525:
led Nalcor CEO Stan Marshall to say that the project was a
1015: 1013: 1011: 1759:
Hydroelectric power stations in Newfoundland and Labrador
315:
A $ 6.2 billion deal between Newfoundland and Labrador's
1424:""Last supper" held tonight by Muskrat Falls protestors" 1101:"Halifax-based Emera makes plans for $ 2B Atlantic Link" 773:"Terms of Muskrat Falls federal loan guarantee released" 300:. It comprises part of the remaining 35 per cent of the 42: 1021:"Muskrat Falls Development Generation and Transmission" 1149:"Inadequate consultation on the Muskrat Falls project" 1563:"Premier Ball Announces Muskrat Falls Public Inquiry" 16:
Hydroelectric generation station in Labrador, Canada
795:"Harper to announce Muskrat Falls deal in Labrador" 646:"Nalcor's submission to the Board of Commissioners" 269: 259: 246: 233: 228: 220: 215: 207: 196: 186: 178: 168: 156: 151: 141: 133: 125: 117: 80: 65: 24: 1197:"Timeline - Independent Expert Advisory Committee" 200:1 overflow spillway and 1 spillway with submerged 401:. Construction began in 2014 and ended in 2018. 817:"Harper 'reiterates support' for Muskrat Falls" 427:Once on Newfoundland and the mainland of the 288:is a hydroelectric generating station in the 8: 1784:Newfoundland and Labrador political scandals 861:"$ 1.5B Maritime Link approved by Emera Inc" 1650:. The Narwhal (Victoria, BC). July 29, 2021 21: 1584:McKenzie-Sutter, Holly (March 10, 2020). 424:. The link came online in December 2017. 412:via a 200 kV 180 km sub-sea line to 1050:McKenzie-Sutter, Holly (June 27, 2018). 19:Dam in Newfoundland and Labrador, Canada 1025:Government of Newfoundland and Labrador 603: 1539:Vaughan, Andrew (September 29, 2017). 670: 668: 666: 612:"Construction schedule to first power" 1311:Fitzpatrick, Ashley (June 20, 2019). 1242:Fitzpatrick, Ashley (April 8, 2019). 1201:Independent Expert Advisory Committee 944:Callahan, Brian (November 29, 2021). 640: 638: 636: 634: 7: 730:McCarthy, Shawn (18 November 2010). 1147:Flowers, Bill (December 13, 2016). 1173:Careen, Evan (November 20, 2016). 1126:"A New Dawn for the Labrador Innu" 927:"Muskrat Falls Generating Project" 682:(Report). Vol. II. Winnipeg: 651:. Nalcor Energy. November 10, 2011 588:Churchill Falls Generating Station 306:Churchill Falls Generating Station 14: 749:Bailey, Sue (November 30, 2012). 512:Affairs and Environment. Premier 332:Newfoundland and Labrador Premier 1735: 1721: 1707: 520:Cost overruns and public inquiry 286:Muskrat Falls Generating Station 41: 34: 25:Muskrat Falls Generation Station 1764:Newfoundland and Labrador Hydro 1516:Roberts, Terry (Apr 19, 2019). 1470:"A reckoning for Muskrat Falls" 1445:Roberts, Terry (Jun 27, 2019). 1356:White, Bailery (Jul 24, 2019). 707:. Nalcor Energy. Archived from 357:Newfoundland and Labrador Hydro 319:and Halifax, Nova Scotia-based 146:Newfoundland and Labrador Hydro 1774:Roller-compacted concrete dams 1099:Withers, Paul (Jan 12, 2017). 304:that was not developed by the 1: 1288:Maher, David (July 4, 2019). 1265:Maher, David (June 7, 2019). 675:Rae, P. (January 2012). "5". 1494:Sue Bailey (June 24, 2016). 179:Elevation at crest 1468:Cox, Sarah (May 16, 2019). 1426:. The Telegram. Aug 6, 2019 391:high-voltage direct current 1800: 468:In 2016, researchers from 404:Power is transmitted from 351:On June 23, 2021, Premier 705:"Lower Churchill Project" 294:Newfoundland and Labrador 163:Roller compacted concrete 74:Newfoundland and Labrador 56:Newfoundland and Labrador 29: 1404:. CBC News. Aug 23, 2019 1382:. CBC News. Aug 11, 2019 1337:. CBC News. Jul 23, 2019 1223:. CBC News. Jul 22, 2019 885:. CBC News. Nov 29, 2013 863:. CBC News. Dec 18, 2012 819:. CBC News. Sep 24, 2012 797:. CBC News. Nov 29, 2012 457:environmental assessment 385:Power is transmitted to 1769:HVDC transmission lines 1743:Renewable energy portal 775:. CBC News. Dec 4, 2012 455:and Muskrat Falls, for 248:Installed capacity 118:Construction began 395:submarine power cables 271:Annual generation 208:Spillway capacity 134:Construction cost 593:List of HVDC projects 561:Members of Parliament 221:Normal elevation 158:Type of dam 102:53.24556°N 60.77278°W 1588:. The Globe and Mail 1543:. The Globe and Mail 1498:. The Globe and Mail 1054:. The Globe and Mail 711:on November 29, 2016 554:government of Quebec 549:Government of Canada 443:Environmental impact 399:Strait of Belle Isle 261:Capacity factor 1031:on 26 December 2018 547:announced that the 408:on Newfoundland to 339:Nova Scotia Premier 107:53.24556; -60.77278 98: /  1177:. Saltwire Network 736:The Globe and Mail 470:Harvard University 418:Cape Breton Island 197:Spillway type 129:September 23, 2020 308:. The station at 282: 281: 152:Dam and spillways 126:Opening date 1791: 1745: 1740: 1739: 1731: 1726: 1725: 1717: 1712: 1711: 1710: 1700: 1699: 1686: 1680: 1679: 1666: 1660: 1659: 1657: 1655: 1644: 1638: 1637: 1636:. July 27, 2021. 1624: 1618: 1617: 1616:. July 28, 2021. 1604: 1598: 1597: 1595: 1593: 1581: 1575: 1574: 1572: 1570: 1559: 1553: 1552: 1550: 1548: 1536: 1530: 1529: 1527: 1525: 1513: 1507: 1506: 1504: 1503: 1491: 1485: 1484: 1482: 1480: 1465: 1459: 1458: 1456: 1454: 1442: 1436: 1435: 1433: 1431: 1420: 1414: 1413: 1411: 1409: 1398: 1392: 1391: 1389: 1387: 1376: 1370: 1369: 1367: 1365: 1353: 1347: 1346: 1344: 1342: 1331: 1325: 1324: 1322: 1320: 1308: 1302: 1301: 1299: 1297: 1285: 1279: 1278: 1276: 1274: 1262: 1256: 1255: 1253: 1251: 1239: 1233: 1232: 1230: 1228: 1217: 1211: 1210: 1208: 1207: 1193: 1187: 1186: 1184: 1182: 1170: 1164: 1163: 1161: 1159: 1144: 1138: 1137: 1135: 1133: 1122: 1116: 1115: 1113: 1111: 1096: 1090: 1089: 1087: 1085: 1080:. August 2, 2018 1070: 1064: 1063: 1061: 1059: 1047: 1041: 1040: 1038: 1036: 1027:. Archived from 1017: 1006: 1005: 1003: 1002: 997:. April 12, 2023 987: 981: 980: 979:. June 23, 2021. 967: 961: 960: 958: 956: 941: 935: 934: 923: 917: 916: 914: 912: 901: 895: 894: 892: 890: 879: 873: 872: 870: 868: 857: 851: 850: 848: 846: 835: 829: 828: 826: 824: 813: 807: 806: 804: 802: 791: 785: 784: 782: 780: 769: 763: 762: 760: 758: 746: 740: 739: 727: 721: 720: 718: 716: 701: 695: 694: 692: 691: 681: 672: 661: 660: 658: 656: 650: 642: 629: 628: 626: 625: 616: 608: 335:Kathy Dunderdale 113: 112: 110: 109: 108: 103: 99: 96: 95: 94: 91: 45: 44: 38: 22: 1799: 1798: 1794: 1793: 1792: 1790: 1789: 1788: 1749: 1748: 1741: 1734: 1727: 1720: 1713: 1708: 1706: 1703: 1688: 1687: 1683: 1678:. Oct 14, 2021. 1668: 1667: 1663: 1653: 1651: 1646: 1645: 1641: 1626: 1625: 1621: 1606: 1605: 1601: 1591: 1589: 1583: 1582: 1578: 1568: 1566: 1561: 1560: 1556: 1546: 1544: 1538: 1537: 1533: 1523: 1521: 1515: 1514: 1510: 1501: 1499: 1493: 1492: 1488: 1478: 1476: 1467: 1466: 1462: 1452: 1450: 1444: 1443: 1439: 1429: 1427: 1422: 1421: 1417: 1407: 1405: 1400: 1399: 1395: 1385: 1383: 1378: 1377: 1373: 1363: 1361: 1355: 1354: 1350: 1340: 1338: 1333: 1332: 1328: 1318: 1316: 1310: 1309: 1305: 1295: 1293: 1287: 1286: 1282: 1272: 1270: 1264: 1263: 1259: 1249: 1247: 1241: 1240: 1236: 1226: 1224: 1219: 1218: 1214: 1205: 1203: 1195: 1194: 1190: 1180: 1178: 1172: 1171: 1167: 1157: 1155: 1146: 1145: 1141: 1131: 1129: 1124: 1123: 1119: 1109: 1107: 1098: 1097: 1093: 1083: 1081: 1072: 1071: 1067: 1057: 1055: 1049: 1048: 1044: 1034: 1032: 1019: 1018: 1009: 1000: 998: 989: 988: 984: 969: 968: 964: 954: 952: 943: 942: 938: 925: 924: 920: 910: 908: 903: 902: 898: 888: 886: 881: 880: 876: 866: 864: 859: 858: 854: 844: 842: 837: 836: 832: 822: 820: 815: 814: 810: 800: 798: 793: 792: 788: 778: 776: 771: 770: 766: 756: 754: 748: 747: 743: 729: 728: 724: 714: 712: 703: 702: 698: 689: 687: 679: 674: 673: 664: 654: 652: 648: 644: 643: 632: 623: 621: 614: 610: 609: 605: 601: 584: 522: 472:suggested that 445: 383: 374: 369: 302:Churchill River 241:Kaplan turbines 173:Churchill River 106: 104: 100: 97: 92: 89: 87: 85: 84: 61: 60: 59: 58: 48: 47: 46: 20: 17: 12: 11: 5: 1797: 1795: 1787: 1786: 1781: 1776: 1771: 1766: 1761: 1751: 1750: 1747: 1746: 1732: 1718: 1702: 1701: 1698:. Aug 3, 2021. 1681: 1661: 1639: 1619: 1599: 1576: 1554: 1531: 1508: 1486: 1460: 1437: 1415: 1393: 1371: 1348: 1326: 1315:. The Telegram 1303: 1292:. The Telegram 1280: 1269:. The Telegram 1257: 1246:. The Telegram 1234: 1212: 1188: 1165: 1153:Policy Options 1139: 1117: 1091: 1065: 1042: 1007: 982: 962: 936: 918: 896: 874: 852: 830: 808: 786: 764: 741: 722: 696: 684:Manitoba Hydro 662: 630: 602: 600: 597: 596: 595: 590: 583: 580: 558:Bloc QuĂ©bĂ©cois 545:Justin Trudeau 542:Prime Minister 540:In July 2021, 521: 518: 447:In late 2006, 444: 441: 382: 379: 373: 370: 368: 367:Technical plan 365: 342:Darrell Dexter 328:Stephen Harper 325:Prime Minister 280: 279: 273: 267: 266: 263: 257: 256: 250: 244: 243: 237: 231: 230: 226: 225: 222: 218: 217: 213: 212: 209: 205: 204: 198: 194: 193: 190: 184: 183: 180: 176: 175: 170: 166: 165: 160: 154: 153: 149: 148: 143: 139: 138: 137:$ 12.7 billion 135: 131: 130: 127: 123: 122: 119: 115: 114: 82: 78: 77: 67: 63: 62: 49: 40: 39: 33: 32: 31: 30: 27: 26: 18: 15: 13: 10: 9: 6: 4: 3: 2: 1796: 1785: 1782: 1780: 1777: 1775: 1772: 1770: 1767: 1765: 1762: 1760: 1757: 1756: 1754: 1744: 1738: 1733: 1730: 1724: 1719: 1716: 1715:Canada portal 1705: 1697: 1696: 1691: 1685: 1682: 1677: 1676: 1671: 1665: 1662: 1649: 1643: 1640: 1635: 1634: 1629: 1623: 1620: 1615: 1614: 1609: 1603: 1600: 1587: 1580: 1577: 1564: 1558: 1555: 1542: 1535: 1532: 1519: 1512: 1509: 1497: 1490: 1487: 1475: 1471: 1464: 1461: 1448: 1441: 1438: 1425: 1419: 1416: 1403: 1397: 1394: 1381: 1375: 1372: 1359: 1352: 1349: 1336: 1330: 1327: 1314: 1307: 1304: 1291: 1284: 1281: 1268: 1261: 1258: 1245: 1238: 1235: 1222: 1216: 1213: 1202: 1198: 1192: 1189: 1176: 1169: 1166: 1154: 1150: 1143: 1140: 1127: 1121: 1118: 1106: 1102: 1095: 1092: 1079: 1075: 1069: 1066: 1053: 1046: 1043: 1030: 1026: 1022: 1016: 1014: 1012: 1008: 996: 995:Globalnews.ca 992: 986: 983: 978: 977: 972: 966: 963: 951: 947: 940: 937: 932: 931:Nalcor Energy 928: 922: 919: 906: 900: 897: 884: 878: 875: 862: 856: 853: 840: 834: 831: 818: 812: 809: 796: 790: 787: 774: 768: 765: 753:. Global News 752: 745: 742: 737: 733: 726: 723: 710: 706: 700: 697: 686:International 685: 678: 671: 669: 667: 663: 647: 641: 639: 637: 635: 631: 620: 619:Nalcor Energy 613: 607: 604: 598: 594: 591: 589: 586: 585: 581: 579: 577: 573: 569: 568:power company 566: 562: 559: 555: 550: 546: 543: 538: 535: 530: 528: 519: 517: 515: 510: 506: 502: 499: 494: 492: 491:methylmercury 487: 483: 479: 475: 474:methylmercury 471: 466: 463: 458: 454: 450: 442: 440: 438: 437:Massachusetts 434: 433:New Brunswick 430: 425: 423: 419: 415: 411: 407: 402: 400: 396: 392: 389:via a 350 kV 388: 380: 378: 371: 366: 364: 360: 358: 354: 349: 347: 343: 340: 336: 333: 329: 326: 322: 318: 317:Nalcor Energy 313: 311: 310:Muskrat Falls 307: 303: 299: 295: 291: 287: 278: 274: 272: 268: 264: 262: 258: 255: 251: 249: 245: 242: 238: 236: 232: 229:Power Station 227: 223: 219: 214: 210: 206: 203: 199: 195: 191: 189: 185: 181: 177: 174: 171: 167: 164: 161: 159: 155: 150: 147: 144: 140: 136: 132: 128: 124: 120: 116: 111: 83: 79: 75: 71: 68: 64: 57: 53: 52:Muskrat Falls 37: 28: 23: 1779:Megaprojects 1729:Water portal 1693: 1684: 1673: 1664: 1652:. Retrieved 1642: 1631: 1622: 1611: 1602: 1590:. Retrieved 1579: 1567:. Retrieved 1557: 1545:. Retrieved 1534: 1522:. Retrieved 1511: 1500:. Retrieved 1489: 1477:. Retrieved 1473: 1463: 1451:. Retrieved 1440: 1428:. Retrieved 1418: 1406:. Retrieved 1396: 1384:. Retrieved 1374: 1362:. Retrieved 1351: 1339:. Retrieved 1329: 1317:. Retrieved 1306: 1294:. Retrieved 1283: 1271:. Retrieved 1260: 1248:. Retrieved 1237: 1225:. Retrieved 1215: 1204:. Retrieved 1200: 1191: 1179:. Retrieved 1168: 1156:. Retrieved 1152: 1142: 1130:. Retrieved 1120: 1108:. Retrieved 1104: 1094: 1082:. Retrieved 1077: 1068: 1056:. Retrieved 1045: 1033:. Retrieved 1029:the original 1024: 999:. Retrieved 994: 985: 974: 965: 953:. Retrieved 949: 939: 930: 921: 911:December 10, 909:. Retrieved 899: 887:. Retrieved 877: 865:. Retrieved 855: 843:. Retrieved 833: 821:. Retrieved 811: 799:. Retrieved 789: 777:. Retrieved 767: 755:. Retrieved 744: 735: 725: 713:. Retrieved 709:the original 699: 688:. Retrieved 655:December 27, 653:. Retrieved 622:. Retrieved 606: 565:Hydro QuĂ©bec 539: 531: 523: 495: 480:Government, 467: 446: 426: 406:Stephenville 403: 387:Newfoundland 384: 381:Transmission 375: 361: 353:Andrew Furey 350: 314: 285: 283: 202:radial gates 50:Location of 1474:The Narwhal 1078:Global News 572:Innu Nation 514:Dwight Ball 509:NunatuKavut 505:Innu Nation 486:NunatuKavut 482:Innu Nation 478:Nunatsiavut 462:Innu Nation 453:Gull Island 414:Point Aconi 410:Nova Scotia 239:4 x 206 MW 105: / 81:Coordinates 1753:Categories 1520:. CBC News 1502:2016-06-24 1449:. CBC News 1360:. CBC News 1206:2018-10-30 1001:2023-04-16 955:24 January 738:. Toronto. 690:2014-07-26 624:2014-07-26 599:References 527:boondoggle 397:under the 372:Generation 346:St. John's 292:region of 93:60°46′22″W 90:53°14′44″N 532:In 2017, 429:Maritimes 216:Reservoir 211:5930 m/s 188:Spillways 1695:CBC News 1675:CBC News 1633:CBC News 1613:CBC News 976:CBC News 582:See also 484:and the 290:Labrador 235:Turbines 169:Impounds 142:Owner(s) 76:, Canada 70:Labrador 66:Location 1654:Oct 16, 1592:Nov 29, 1569:Nov 29, 1547:Nov 29, 1524:Nov 29, 1479:21 July 1453:Nov 29, 1430:Nov 29, 1408:Nov 29, 1386:Nov 29, 1364:Nov 29, 1341:Nov 29, 1319:Nov 29, 1296:Nov 29, 1273:Nov 29, 1250:Nov 29, 1227:Nov 29, 1181:Nov 29, 1158:Nov 29, 1132:Nov 29, 1110:21 July 1084:Nov 29, 1058:Nov 29, 1035:21 July 889:Nov 29, 867:Nov 29, 845:Nov 29, 823:Nov 29, 801:Nov 29, 779:Nov 29, 757:Nov 29, 715:June 8, 534:Premier 501:capping 498:wetland 570:. The 449:Nalcor 298:Canada 182:39.5 m 680:(PDF) 649:(PDF) 615:(JPG) 422:Emera 321:Emera 265:62.3% 224:39 m 121:2013 1656:2022 1594:2020 1571:2020 1549:2020 1526:2020 1481:2019 1455:2020 1432:2020 1410:2020 1388:2020 1366:2020 1343:2020 1321:2020 1298:2020 1275:2020 1252:2020 1229:2020 1183:2020 1160:2020 1134:2020 1112:2019 1086:2020 1060:2020 1037:2019 957:2022 950:VOCM 913:2013 891:2020 869:2020 847:2020 825:2020 803:2020 781:2020 759:2020 717:2013 657:2011 576:Innu 556:and 507:and 337:and 284:The 275:4.5 252:824 1105:CBC 435:to 416:on 277:TWh 54:in 1755:: 1692:. 1672:. 1630:. 1610:. 1472:. 1199:. 1151:. 1103:. 1076:. 1023:. 1010:^ 993:. 973:. 948:. 929:. 734:. 665:^ 633:^ 617:. 529:. 493:. 439:. 359:. 348:. 330:, 296:, 254:MW 72:, 1658:. 1596:. 1573:. 1551:. 1528:. 1505:. 1483:. 1457:. 1434:. 1412:. 1390:. 1368:. 1345:. 1323:. 1300:. 1277:. 1254:. 1231:. 1209:. 1185:. 1162:. 1136:. 1114:. 1088:. 1062:. 1039:. 1004:. 959:. 933:. 915:. 893:. 871:. 849:. 827:. 805:. 783:. 761:. 719:. 693:. 659:. 627:. 192:2

Index

Muskrat Falls Generating Station is located in Newfoundland and Labrador
Muskrat Falls
Newfoundland and Labrador
Labrador
Newfoundland and Labrador
53°14′44″N 60°46′22″W / 53.24556°N 60.77278°W / 53.24556; -60.77278
Newfoundland and Labrador Hydro
Type of dam
Roller compacted concrete
Churchill River
Spillways
radial gates
Turbines
Kaplan turbines
Installed capacity
MW
Capacity factor
Annual generation
TWh
Labrador
Newfoundland and Labrador
Canada
Churchill River
Churchill Falls Generating Station
Muskrat Falls
Nalcor Energy
Emera
Prime Minister
Stephen Harper
Newfoundland and Labrador Premier

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.

↑