390:
365:
29:
1019:
Schlömer S., T. Bruckner, L. Fulton, E. Hertwich, A. McKinnon, D. Perczyk, J. Roy, R. Schaeffer, R. Sims, P. Smith, and R. Wiser, 2014: Annex III: Technology-specific cost and performance parameters. In: Climate Change 2014: Mitigation of
Climate Change. Contribution of Working Group III to the Fifth
275:
As part of project application materials, the facility was expected to require 17 full-time staff once constructed. The facility is eligible for the
Federal Solar Investment Tax Credit (ITC). MG&E assumed that the facility would receive 30% of the ITC. The ITC would be normalized over the 30 year
397:
In 2023, Badger Hollow I and II generated 176 GWh combined, approximately 0.28% of the total electric power generated in
Wisconsin (63,216 GWh) for that year. The facility had an approximate annual capacity factor of 13.2% in 2023. While presiding over the transfer of ownership stage, the PSC asked
1292:
299:
The procurement and construction of utility-scale solar has also been justified by some in
Wisconsin due to electrical generation supply concerns when several large coal-fired plants in the state will be closed in the early 2020s. Those coal-fired plant closures have since been delayed to the mid
263:
The sites covers approximately 3500 acres, with between 2000 and 2200 acres used directly for the solar panel arrays. The facility is located in the
Village of Cobb and in the towns of Mifflin, Eden, and Linden. It is located just south of Cobb and southeast of the nearby Montfort Wind Farm.
320:(PSC) on June 1, 2018. On April 18, 2019, the CPCN application to construct the facility was approved by the PSC. In its approval ruling, the PSC found that the project satisfied the requirements of Wisconsin Statute § 1.12 and 196.025(1), known as the Energy Priorities Law.
296:, the lifecycle emissions of electricity generated by utility-scale solar facilities is 48 gCO2eq/kWh (median value). By comparison, lifecycle emissions from electricity generated from coal and natural gas (combined-cycle plants) are 820 and 490 gCO2eq/kWh, respectively.
360:
Construction of Badger Hollow Phase I started in 2020 and finished in
November 2021. The project was delayed to allow the developer more time in managing the acquisition of the solar panels which was impacted by federal government changes to trade tariffs.
1338:
272:. The total cost for this agreement was $ 1,299 per KW, or $ 194.8 million for the Badger Hollow component. In March, 2020, WE Energies and MG&E purchased and acquired the remaining 150 MW of the solar farm for approximately $ 194.9 million.
267:
On April 18, 2019, WPS and MG&E purchased and acquired 150 MW of the Badger Hollow solar farm and the electrical tie in line for approximately $ 389.7 million. This purchase also included the acquisition of the 150 MW
372:
A 5.7 mile, 138 kV generator tie line was constructed to connect Badger Hollow facility with the existing electric transmission system. The tie line cost $ 15.6 million and finished full construction in
December 2021.
380:
as well as US government trade and tariff investigations into solar panel distributors and compliance on the sourcing of materials and labor to produce the panels. Phase 2 entered full operation in
December 2023.
950:"Joint Application of Madison Gas and Electric Company and Wisconsin Electric Power Company for Approval to Acquire Ownership Interests in the Badger Hollow II Solar Electric Generating Facility - Final Decision"
1126:
906:"Application for a Certificate of Public Convenience and Necessity of Badger Hollow Solar Farm, LLC to Construct a Solar Electric Generation Facility, to be Located in Iowa County, Wisconsin - Final Decision"
1223:
1055:
928:"Joint Application of Madison Gas and Electric Company and Wisconsin Public Service Corporation for Approval to Acquire Ownership Interests in Solar Electric Generating Facilities - Final Decision"
1391:
323:
Major components of Badger Hollow include the PV panels, power conversion units (PCUs), collection lines, a collector substation, and an operations and maintenance (O&M) building.
292:
charged the Office of
Sustainability and Clean Energy to achieve a goal that all electricity consumed in Wisconsin by 2050 be 100% carbon-free. According to analysis conducted by the
1317:"Joint Application of Madison Gas and Electric Company and Wisconsin Public Service Corporation for Approval to Acquire Ownership Interests in Solar Electric Generating Facilities"
313:
344:: Inverters and pad-mounted transformers convert the DC output to AC power and step up the power to a 34.5 kV voltage. The capacity of the PCUs is up to 300 MW AC.
1172:
1030:
293:
1020:
Assessment Report of the
Intergovernmental Panel on Climate Change . Cambridge University Press, Cambridge, United Kingdom and New York, NY, USA.
317:
66:
1198:
245:
334:. The panels measure approximately 2 meters by 1 meter and are rated between 335 and 445 Watts (i.e. maximum output). The total
300:
2020s with major utility companies citing electricity reliability concerns and the delay in constructing new grid-scale solar.
1173:"Badger Hollow Network Upgrades project in service, connecting solar capacity to the grid | American Transmission Co"
1080:"Application for Certificate of Public Convenience and Necessity – Badger Hollow Solar Farm – Docket # 9697-CE-100"
398:
the owners to use an 18% capacity factor for their Electric Generation Expansion Analysis System (EGEAS) analysis.
241:
1247:
376:
Construction of Badger Hollow Phase 2 (remaining 150 MW) faced time delays and cost overruns due to impacts from
1268:
277:
249:
1362:
995:
269:
257:
108:
1316:
971:
194:
1150:
1079:
949:
927:
905:
878:
389:
364:
253:
972:"Press Release: Gov. Evers Signs Executive Order #38 Relating to Clean Energy in Wisconsin"
1101:
204:
28:
330:
The facility will consist of approximately 900,000 to 1,200,000 PV panels on single-axis
335:
214:
1385:
705:
405:
331:
156:
996:"Table A.III.2 | Emissions of selected electricity supply technologies gCO2eq/kWh)"
1224:"Labor, materials shortages blamed for $ 32M cost bump at Iowa County solar farm"
1269:"Wisconsin's largest solar park is now fully operational, featuring 830K panels"
1056:"Wisconsin coal plants to keep running amid reliability, supply chain concerns"
1127:"Tariffs blamed for delay in one of Wisconsin's first large-scale solar farms"
289:
81:
68:
309:
226:
377:
1031:"Carbon Dioxide Emissions From Electricity - World Nuclear Association"
244:
in Iowa County in southwestern, Wisconsin. Ownership is shared between
388:
363:
260:
utility-scale solar plant approved and constructed in Wisconsin.
356:
A 34.5 kV/138 kV power collector substation is located on site.
1199:"Council Post: The Impact Of Covid-19 On The PV Supply Chain"
213:
203:
193:
170:
162:
152:
147:
139:
127:
117:
107:
97:
60:
50:
42:
21:
368:Electrical Substation at Badger Hollow Solar Farm
1392:Photovoltaic power stations in the United States
350:Approximately 55 miles of lines with 15 feeders.
314:Certificate of Public Convenience and Necessity
308:Badger Hollow Solar Farm, LLC, an affiliate of
256:, with each utility owning 100 MW. It was the
254:Wisconsin Electric Power Company (WE Energies)
8:
1151:"Final Decision Signed ad Served 04-18-19"
246:Wisconsin Public Service Corporation (WPS)
18:
700:
400:
338:output rating of the facility is 408 MW.
870:
318:Public Services Commission of Wisconsin
276:life of the project as required by the
294:International Panel on Climate Change
288:Through an executive order, Governor
7:
900:
898:
896:
250:Madison Gas and Electric (MG&E)
879:"Minor Siting Adjustment Approval"
14:
242:solar photovoltaic energy station
16:Solar photovoltaic energy station
27:
393:A solar array at Badger Hollow
123:$ 390 (Project Estimate, 2018)
56:Towns of Eden, Mifflin, Linden
1:
1102:"Wisconsin Legislature: 1.12"
709:) Badger Hollow II Solar Farm
121:$ 422 Million (As of 1/14/23)
409:) Badger Hollow I Solar Farm
103:Phase 2 - Under Construction
215:Annual net output
1408:
1363:"Electricity Data Browser"
1339:"Electricity Data Browser"
1293:"Electricity Data Browser"
1267:Schulz, Joe (2024-01-05).
316:(CPCN) application to the
223:
179:
175:
38:
33:42°56'25.8"N 90°18'44.6"W
26:
1106:docs.legis.wisconsin.gov
238:Badger Hollow Solar Farm
22:Badger Hollow Solar Farm
1228:Wisconsin State Journal
1131:Wisconsin State Journal
1060:Wisconsin State Journal
195:Nameplate capacity
101:Phase 1 - Commissioned
394:
385:Electricity production
369:
184:Units operational
118:Construction cost
1035:www.world-nuclear.org
392:
367:
270:Two Creeks Solar Park
171:Power generation
82:42.94028°N 90.31222°W
1248:"MGE Solar Projects"
881:. September 30, 2021
205:Capacity factor
109:Commission date
711:
411:
312:, LLC, submitted a
87:42.94028; -90.31222
78: /
1197:Hackbarth, Joern.
976:State of Wisconsin
701:
401:
395:
370:
163:Solar tracker
1319:. August 10, 2018
863:
862:
837:
832:
819:
814:
809:
804:
799:
794:
789:
784:
779:
774:
769:
764:
699:
698:
673:
668:
655:
650:
645:
640:
635:
630:
625:
620:
615:
610:
605:
600:
587:
582:
577:
572:
567:
562:
557:
552:
547:
542:
537:
532:
519:
514:
509:
504:
499:
494:
489:
484:
479:
474:
469:
464:
234:
233:
1399:
1377:
1376:
1374:
1373:
1359:
1353:
1352:
1350:
1349:
1335:
1329:
1328:
1326:
1324:
1313:
1307:
1306:
1304:
1303:
1289:
1283:
1282:
1280:
1279:
1264:
1258:
1257:
1255:
1254:
1244:
1238:
1237:
1235:
1234:
1222:Hubbuch, Chris.
1219:
1213:
1212:
1210:
1209:
1194:
1188:
1187:
1185:
1184:
1169:
1163:
1162:
1160:
1158:
1153:. April 18, 2019
1147:
1141:
1140:
1138:
1137:
1125:Hubbuch, Chris.
1122:
1116:
1115:
1113:
1112:
1098:
1092:
1091:
1089:
1087:
1076:
1070:
1069:
1067:
1066:
1054:Hubbuch, Chris.
1051:
1045:
1044:
1042:
1041:
1027:
1021:
1017:
1011:
1010:
1008:
1006:
1000:
992:
986:
985:
983:
982:
968:
962:
961:
959:
957:
946:
940:
939:
937:
935:
930:. April 18, 2019
924:
918:
917:
915:
913:
908:. April 18, 2019
902:
891:
890:
888:
886:
875:
835:
830:
817:
812:
807:
802:
797:
792:
787:
782:
777:
772:
767:
762:
712:
671:
666:
653:
648:
643:
638:
633:
628:
623:
618:
613:
608:
603:
598:
585:
580:
575:
570:
565:
560:
555:
550:
545:
540:
535:
530:
517:
512:
507:
502:
497:
492:
487:
482:
477:
472:
467:
462:
412:
348:Collector Lines:
332:tracking systems
227:edit on Wikidata
189:Phase 2 - 150 MW
187:Phase 1 - 150 MW
148:Solar farm
93:
92:
90:
89:
88:
83:
79:
76:
75:
74:
71:
54:Village of Cobb
31:
19:
1407:
1406:
1402:
1401:
1400:
1398:
1397:
1396:
1382:
1381:
1380:
1371:
1369:
1361:
1360:
1356:
1347:
1345:
1337:
1336:
1332:
1322:
1320:
1315:
1314:
1310:
1301:
1299:
1291:
1290:
1286:
1277:
1275:
1266:
1265:
1261:
1252:
1250:
1246:
1245:
1241:
1232:
1230:
1221:
1220:
1216:
1207:
1205:
1196:
1195:
1191:
1182:
1180:
1171:
1170:
1166:
1156:
1154:
1149:
1148:
1144:
1135:
1133:
1124:
1123:
1119:
1110:
1108:
1100:
1099:
1095:
1085:
1083:
1078:
1077:
1073:
1064:
1062:
1053:
1052:
1048:
1039:
1037:
1029:
1028:
1024:
1018:
1014:
1004:
1002:
998:
994:
993:
989:
980:
978:
970:
969:
965:
955:
953:
952:. March 6, 2020
948:
947:
943:
933:
931:
926:
925:
921:
911:
909:
904:
903:
894:
884:
882:
877:
876:
872:
868:
754:Annual (Total)
454:Annual (Total)
387:
306:
286:
230:
188:
134:
132:
122:
102:
86:
84:
80:
77:
72:
69:
67:
65:
64:
55:
34:
17:
12:
11:
5:
1405:
1403:
1395:
1394:
1384:
1383:
1379:
1378:
1354:
1330:
1308:
1284:
1259:
1239:
1214:
1189:
1177:www.atcllc.com
1164:
1142:
1117:
1093:
1082:. June 1, 2018
1071:
1046:
1022:
1012:
987:
963:
941:
919:
892:
869:
867:
864:
861:
860:
858:
856:
854:
852:
850:
848:
846:
844:
842:
840:
838:
833:
828:
824:
823:
820:
815:
810:
805:
800:
795:
790:
785:
780:
775:
770:
765:
760:
756:
755:
752:
749:
746:
743:
740:
737:
734:
731:
728:
725:
722:
719:
716:
697:
696:
694:
692:
690:
688:
686:
684:
682:
680:
678:
676:
674:
669:
664:
660:
659:
656:
651:
646:
641:
636:
631:
626:
621:
616:
611:
606:
601:
596:
592:
591:
588:
583:
578:
573:
568:
563:
558:
553:
548:
543:
538:
533:
528:
524:
523:
520:
515:
510:
505:
500:
495:
490:
485:
480:
475:
470:
465:
460:
456:
455:
452:
449:
446:
443:
440:
437:
434:
431:
428:
425:
422:
419:
416:
386:
383:
358:
357:
351:
345:
339:
305:
302:
285:
282:
232:
231:
224:
221:
220:
219:176 GWh (2023)
217:
211:
210:
207:
201:
200:
197:
191:
190:
185:
181:
180:
177:
176:
173:
172:
168:
167:
164:
160:
159:
154:
150:
149:
145:
144:
141:
137:
136:
129:
125:
124:
119:
115:
114:
111:
105:
104:
99:
95:
94:
62:
58:
57:
52:
48:
47:
44:
40:
39:
36:
35:
32:
24:
23:
15:
13:
10:
9:
6:
4:
3:
2:
1404:
1393:
1390:
1389:
1387:
1368:
1364:
1358:
1355:
1344:
1340:
1334:
1331:
1318:
1312:
1309:
1298:
1294:
1288:
1285:
1274:
1270:
1263:
1260:
1249:
1243:
1240:
1229:
1225:
1218:
1215:
1204:
1200:
1193:
1190:
1178:
1174:
1168:
1165:
1152:
1146:
1143:
1132:
1128:
1121:
1118:
1107:
1103:
1097:
1094:
1081:
1075:
1072:
1061:
1057:
1050:
1047:
1036:
1032:
1026:
1023:
1016:
1013:
997:
991:
988:
977:
973:
967:
964:
951:
945:
942:
929:
923:
920:
907:
901:
899:
897:
893:
880:
874:
871:
865:
859:
857:
855:
853:
851:
849:
847:
845:
843:
841:
839:
834:
829:
826:
825:
821:
816:
811:
806:
801:
796:
791:
786:
781:
776:
771:
766:
761:
758:
757:
753:
750:
747:
744:
741:
738:
735:
732:
729:
726:
723:
720:
717:
714:
713:
710:
707:
704:
695:
693:
691:
689:
687:
685:
683:
681:
679:
677:
675:
670:
665:
662:
661:
657:
652:
647:
642:
637:
632:
627:
622:
617:
612:
607:
602:
597:
594:
593:
589:
584:
579:
574:
569:
564:
559:
554:
549:
544:
539:
534:
529:
526:
525:
521:
516:
511:
506:
501:
496:
491:
486:
481:
476:
471:
466:
461:
458:
457:
453:
450:
447:
444:
441:
438:
435:
432:
429:
426:
423:
420:
417:
414:
413:
410:
407:
404:
399:
391:
384:
382:
379:
374:
366:
362:
355:
352:
349:
346:
343:
340:
337:
333:
329:
326:
325:
324:
321:
319:
315:
311:
303:
301:
297:
295:
291:
283:
281:
279:
273:
271:
265:
261:
259:
255:
251:
247:
243:
239:
228:
222:
218:
216:
212:
208:
206:
202:
198:
196:
192:
186:
183:
182:
178:
174:
169:
165:
161:
158:
157:Flat-panel PV
155:
151:
146:
142:
138:
130:
126:
120:
116:
113:November 2021
112:
110:
106:
100:
96:
91:
63:
59:
53:
49:
45:
41:
37:
30:
25:
20:
1370:. Retrieved
1366:
1357:
1346:. Retrieved
1342:
1333:
1321:. Retrieved
1311:
1300:. Retrieved
1296:
1287:
1276:. Retrieved
1272:
1262:
1251:. Retrieved
1242:
1231:. Retrieved
1227:
1217:
1206:. Retrieved
1202:
1192:
1181:. Retrieved
1179:. 2022-01-14
1176:
1167:
1155:. Retrieved
1145:
1134:. Retrieved
1130:
1120:
1109:. Retrieved
1105:
1096:
1084:. Retrieved
1074:
1063:. Retrieved
1059:
1049:
1038:. Retrieved
1034:
1025:
1015:
1003:. Retrieved
990:
979:. Retrieved
975:
966:
954:. Retrieved
944:
932:. Retrieved
922:
910:. Retrieved
883:. Retrieved
873:
708:
703:Generation (
702:
408:
403:Generation (
402:
396:
375:
371:
359:
353:
347:
341:
327:
322:
307:
298:
287:
274:
266:
262:
240:is a 300 MW
237:
235:
209:13.2% (2023)
1367:www.eia.gov
1343:www.eia.gov
1323:January 14,
1297:www.eia.gov
1157:January 14,
1086:January 14,
1005:January 14,
956:January 14,
934:January 14,
912:January 14,
885:January 14,
354:Substation:
166:Single-axis
85: /
61:Coordinates
1372:2024-05-14
1348:2024-05-14
1302:2024-05-14
1278:2024-05-14
1253:2024-05-14
1233:2023-01-15
1208:2023-01-15
1183:2023-01-15
1136:2023-01-15
1111:2023-01-15
1065:2023-01-15
1040:2023-01-15
981:2023-01-15
866:References
290:Tony Evers
284:Background
73:90°18′44″W
70:42°56′25″N
310:Invenergy
140:Employees
1386:Category
658:174,544
590:197,465
378:COVID-19
131:MG&E
128:Owner(s)
51:Location
328:Panels:
304:History
43:Country
1203:Forbes
1001:. 2014
836:14,755
822:1,261
672:15,081
644:12,588
639:13,539
634:25,914
629:28,019
624:20,397
619:19,515
609:13,159
604:14,061
576:15,890
571:17,389
566:22,936
561:27,763
556:25,066
551:19,528
546:16,418
541:14,136
536:14,055
531:10,525
522:8,249
258:second
252:, and
199:300 MW
98:Status
999:(PDF)
831:5,319
827:2024
818:1,261
759:2023
715:Year
667:6,432
663:2024
654:4,651
649:8,548
614:7,511
599:6,642
595:2023
586:4,776
581:8,983
527:2022
518:3,094
513:5,155
459:2021
415:Year
225:[
133:WEPCO
1325:2023
1159:2023
1088:2023
1007:2023
958:2023
936:2023
914:2023
887:2023
751:Dec
748:Nov
745:Oct
742:Sep
739:Aug
736:Jul
733:Jun
730:May
727:Apr
724:Mar
721:Feb
718:Jan
451:Dec
448:Nov
445:Oct
442:Sep
439:Aug
436:Jul
433:Jun
430:May
427:Apr
424:Mar
421:Feb
418:Jan
342:PCUs
236:The
153:Type
1273:WPR
706:MWh
406:MWh
278:IRS
135:WPS
46:USA
1388::
1365:.
1341:.
1295:.
1271:.
1226:.
1201:.
1175:.
1129:.
1104:.
1058:.
1033:.
974:.
895:^
813:--
808:--
803:--
798:--
793:--
788:--
783:--
778:--
773:--
768:--
763:--
508:--
503:--
498:--
493:--
488:--
483:--
478:--
473:--
468:--
463:--
336:DC
280:.
248:,
143:17
1375:.
1351:.
1327:.
1305:.
1281:.
1256:.
1236:.
1211:.
1186:.
1161:.
1139:.
1114:.
1090:.
1068:.
1043:.
1009:.
984:.
960:.
938:.
916:.
889:.
229:]
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.