43:. On March 12, 2004 the Big Bay dam embankment failed through piping in the vicinity of the principal spillway 12 years after construction. A peak breach flow of 147,000 ft/s (4,200 m/s) was estimated from the breach geometry, breach timing and the reservoir volume. The Big Bay embankment, which is largely intact, is approximately 1890 feet long and 51.3 feet high. The failure occurred with an initial water surface about 6 inches (0.15 m) above the normal pool elevation of 278.0 ft (84.73 m), releasing 14,200 ac-ft (17,500,000 m) of water and inundating 14.3 miles (23.0 km) of valley to depths of up to 33 ft (10 m) from the dam to the Pearl River. Woody material was stripped from the stream valley for a length of 2300 ft (700 m) immediately below the dam, after which velocities decreased to such an extent that little vegetation was uprooted. 55:
regard to the breach timing, increased discharge from a pre-existing seep was first noticed on Thursday, March 11. The seep gradually increased its discharge, with the flow carrying material by the next morning. At mid-morning on March 12 the seep was inspected and was noticed that it had about a ½ inch of head height. By 12:15 water “shot up out of the hole”. Shortly after this the seep was observed to be “spouting approximately 2 to 3 ft in height, with a diameter of about 18 inches”. The area around the boil then collapsed and the embankment began to rapidly erode. This is the point where the breach is assumed to start, at about 12:20. The final breach dimensions occurred from about 13:10. Full formation is assumed to occur at 13:15—the breach formation time is estimated to be 55 minutes.
59: 17: 51:
damage, 1 mobile home was destroyed, 3 mobile homes had major damage, 3 mobile homes had minor damage, Pine Burr Church suffered major damage, Hub Chapel Church had minor damage, and the Pinebur Volunteer Fire Department suffered major damage. In all, 104 structures were documented as damaged or destroyed. There were no deaths.
54:
The dam breach characteristics, specifically the breach geometry and formation time, were estimated by Yochum et al. 2008. The breach width was measured to be 230 ft (70 m), with a top width of 315 ft (96 m), right side slope of 0.61 and a left side slope of 1.3 (horizontal/vertical). In
50:
Counties. A damage assessment indicated that, within Lamar County, 26 homes were destroyed, 8 homes had major damage, 8 homes had minor damage, 25 mobile homes were destroyed and 1 mobile home had minor damage. In Marion County, 1 home was destroyed, 13 homes had major damage, 12 homes had minor
198: 213: 208: 183: 144: 115:
MEMA. 2004. “NEWS: Governor Barbour requests federal assistance.” News release, Mississippi Emergency Management Agency, March 22, 2004.
89:
Yochum, S.E.; Goertz, L.A.; Jones, P.H. (2008). "Case Study of the Big Bay Dam Failure: Accuracy and Comparison of Breach Predictions".
193: 203: 188: 40: 102: 124:
Burge, T.R. (2004) Big Bay Dam: Evaluation of Failure Land Partners Limited Partnership, Hattiesburg, MS.
133: 47: 36: 98: 134:
Report from National Oceanographic and Atmospheric Administration (NOAA) in Jackson, MS
177: 32: 159: 146: 46:
The inundation impacted Bay Creek and Lower Little Creek in Lamar and
58: 16: 57: 63: 21: 199:
Buildings and structures in Lamar County, Mississippi
8: 66:photo shows some damage caused by the flood 103:10.1061/(ASCE)0733-9429(2008)134:9(1285) 84: 82: 80: 15: 76: 20:The breach is clearly visible in this 214:2004 disestablishments in Mississippi 7: 209:1991 establishments in Mississippi 14: 184:Dam failures in the United States 91:Journal of Hydraulic Engineering 1: 230: 35:located 11 miles west of 194:Disasters in Mississippi 204:Dams completed in 1991 67: 25: 61: 19: 189:Dams in Mississippi 160:31.1826°N 89.5712°W 156: /  37:Purvis, Mississippi 68: 26: 165:31.1826; -89.5712 221: 171: 170: 168: 167: 166: 161: 157: 154: 153: 152: 149: 136: 131: 125: 122: 116: 113: 107: 106: 97:(9): 1285–1293. 86: 229: 228: 224: 223: 222: 220: 219: 218: 174: 173: 164: 162: 158: 155: 150: 147: 145: 143: 142: 140: 139: 132: 128: 123: 119: 114: 110: 88: 87: 78: 73: 12: 11: 5: 227: 225: 217: 216: 211: 206: 201: 196: 191: 186: 176: 175: 138: 137: 126: 117: 108: 75: 74: 72: 69: 13: 10: 9: 6: 4: 3: 2: 226: 215: 212: 210: 207: 205: 202: 200: 197: 195: 192: 190: 187: 185: 182: 181: 179: 172: 169: 135: 130: 127: 121: 118: 112: 109: 104: 100: 96: 92: 85: 83: 81: 77: 70: 65: 60: 56: 52: 49: 44: 42: 38: 34: 30: 23: 18: 141: 129: 120: 111: 94: 90: 53: 45: 41:Lamar County 28: 27: 163: / 33:earthen dam 29:Big Bay Dam 178:Categories 151:89°34′16″W 148:31°10′57″N 71:References 24:photograph 62:Another 31:was an 48:Marion 64:NOAA 22:NOAA 99:doi 95:134 39:in 180:: 93:. 79:^ 105:. 101::

Index


NOAA
earthen dam
Purvis, Mississippi
Lamar County
Marion

NOAA



doi
10.1061/(ASCE)0733-9429(2008)134:9(1285)
Report from National Oceanographic and Atmospheric Administration (NOAA) in Jackson, MS
31°10′57″N 89°34′16″W / 31.1826°N 89.5712°W / 31.1826; -89.5712
Categories
Dam failures in the United States
Dams in Mississippi
Disasters in Mississippi
Buildings and structures in Lamar County, Mississippi
Dams completed in 1991
1991 establishments in Mississippi
2004 disestablishments in Mississippi

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.

↑