226:. It is estimated that 46,000 barrels of crude oil were spilled along the pipeline route. Many of the abandoned buildings and vehicles contain hazardous materials and telegraph wire has entangled animals such as moose and caribou. Clean-up of telegraph wire began in 2015 and most of the wire along the trail has been coiled up for removal. Remediation work began in 2018 to remove contaminants, telegraph wire and other safety hazards along the trail and expected to be completed in 2020. Remediation of the trail will allow the creation of Doi T'oh territorial park to proceed as set out in the
195:
camps and remove all personnel. Shortly after the line was declared as surplus to the war effort. Imperial Oil purchased equipment at Norman Wells for $ 3 million. Imperial also paid $ 1 million for the
Whitehorse refinery, which had been installed at a cost of $ 27 million, which they then dismantled and shipped to Alberta. The salvage rights for the remainder of the line were sold for $ 700,000 and carried out by George Price of
77:
194:
Due to its remoteness and challenging conditions the costs to provide fuel from the Canol were considerably higher than having fuel arrive via tanker. On March 8, 1945 the US War
Department made the decision to shut the project down. Work began immediately to winterize all equipment, clean and stock
174:
from Norman Wells had a pour point well below the freezing mark and could be run through a narrow pipeline without being heated. The pipeline was laid on the surface of the ground to simplify construction and maintenance. Ten pump stations were needed to move the crude oil to
Whitehorse. The pumps
35:
and the North
American west coast. The project included a section of crude petroleum transport by barge, a refinery, and a 4 inch pipeline. It was completed in two years at great cost and was abandoned less than a year later.
559:
178:
The final construction cost for the Canol
Project construction has been estimated at $ 134 million (equivalent to $ 2,319,289,225 in 2023) and may have been closer to $ 300 million when military personnel are included.
191:. The first crude oil reached the refinery in Whitehorse on April 16 and the grand opening was held on April 30. Initially only able to produce gasoline, it was finally able to produce aviation gas in November 1944.
175:
were specially designed to be able to use the Norman Wells crude as fuel. An additional 19 pump stations moved the refined fuel along the Alaska
Highway from Whitehorse as far as Watson Lake and Fairbanks.
233:
Cleanup began in 2018 at the former site of the refinery in
Whitehorse, known locally as the Marwell tar pit. Work was expected to be completed in 2020 at a cost of almost $ 7 million dollars.
219:. There are several old vehicle dumps remaining on the Yukon side and an old pipeline crossing remains in Ross River. The bridge has been used as a footbridge and was recently refurbished.
554:
99:
owned the Norman Wells field and would be responsible for the supply of oil. J. Gordon
Turnbull and Sverdrup and Parcel were chosen to the project's architect and engineer of record.
484:
91:, H. Price & Co. and W. E. Callahan Construction Co. formed a consortium to construct the project. Known as Bechtel-Price-Callahan it also included six associated companies.
569:
564:
396:
544:
277:
CANOL: The sub-Arctic
Pipeline and Refinery Project constructed by Bechtel-Price-Callahan for the Corps of Engineers United States Army 1942-1944
498:
65:
322:
388:
539:
534:
56:
to connect Alaska to the rest of the United States and conceived the CANOL (Canadian Oil) project to ensure a supply of oil from
418:
128:
432:
196:
199:. Some valuable equipment was salvaged but much of the pipeline, telegraph wire, vehicles and buildings were left in place.
138:
389:"WWII-era telephone lines snag N.W.T. moose, caribou: Abandoned 1940s Canol pipeline cleanup still a work in progress"
549:
362:
529:
188:
480:
211:
is still seasonally maintained within the Yukon and is known as
Highway 6. A ferry in the community of
247:
223:
121:
92:
81:
61:
64:. The US War Department decided to construct the project in April 1942 and it was assigned to the
107:
458:
318:
212:
144:
171:
132:
275:
53:
339:
523:
45:
96:
57:
28:
24:
216:
52:
attacking the west coast and cutting off supply lines to Alaska. They built the
242:
208:
149:
A total of 1,600 miles (2,600 km) of pipelines connecting Whitehorse to:
95:
was a consultant on the project and would operate the refinery in Whitehorse.
222:
In the Northwest Territories the road is no longer maintained and is now the
76:
499:"Whitehorse's infamous tar pit gets cleaned up after 73 years | CBC News"
392:
114:
88:
32:
483:. Sahtu Dene and Metis Comprehensive Land Claim Agreement (Report).
75:
49:
433:"One of Our Own: Jess Fortner's Canol Trail Clean Up Experience"
560:
Transport buildings and structures in the Northwest Territories
187:
The last pipeline weld was completed on February 16, 1944 near
170:
The pipeline was just 4 inches (10 cm) in diameter. The
166:
A telegraph system connecting all key points of the project
106:
An 1,100-mile-long (1,800 km) barge supply route from
228:
Sahtu Dene and Metis Comprehensive Land Claim Agreement
485:
Crown-Indigenous Relations and Northern Affairs Canada
341:
Marwell Industrial Area: Historical Research Project
120:
An 1,000-mile-long (1,600 km) winter road from
419:"Canol Trail wire cleanup project to move ahead"
555:Petroleum industry in the Northwest Territories
137:An all-weather road between Norman Wells and
31:to ensure a supply of oil for the defense of
8:
102:The eventual scope of the project included:
570:History of the petroleum industry in Canada
565:Transport buildings and structures in Yukon
363:"Ross River's historic footbridge reopens"
113:A series of ten airfields stretching from
461:. Indigenous and Northern Affairs Canada
269:
267:
265:
263:
127:A water and rail-based supply route via
80:Remains of the Canol Pipeline along the
259:
308:
306:
304:
302:
300:
298:
439:. Government of Northwest Territories
66:United States Army Corps of Engineers
7:
545:History of the Northwest Territories
16:Former pipeline in Canada and Alaska
283:. San Francisco: Ryder & Ingram
481:"17.3 Canol Trail and Dodo Canyon"
14:
459:"Canol Trail Remediation Project"
437:Industry, Tourism and Investment
399:from the original on 2014-08-16
197:Dawson Creek, British Columbia
1:
417:Kyle, Kate (11 August 2015).
338:Arts, Midnight (April 1999).
183:Operation and decommissioning
158:Watson Lake (Canol No.3), and
27:project constructed during
586:
152:Norman Wells (Canol No. 1)
139:Johnson's Crossing, Yukon
315:A walk on the Canol Road
274:Finnie, Richard (1945).
44:During World War II the
540:Oil pipelines in Alaska
535:Oil pipelines in Canada
161:Fairbanks (Canol No. 4)
85:
215:is used to cross the
172:low gravity crude oil
79:
487:. 15 September 2010.
248:Canol Heritage Trail
224:Canol Heritage Trail
155:Skagway (Canol No.2)
122:Peace River, Alberta
93:Standard Oil Company
82:Canol Heritage Trail
62:Northern Territories
48:was concerned about
313:Gage, S.R. (1990).
108:Waterways, Alberta
86:
213:Ross River, Yukon
145:Whitehorse, Yukon
577:
550:History of Yukon
514:
513:
511:
509:
495:
489:
488:
477:
471:
470:
468:
466:
455:
449:
448:
446:
444:
429:
423:
422:
414:
408:
407:
405:
404:
385:
379:
378:
376:
374:
359:
353:
352:
350:
348:
335:
329:
328:
317:. Mosaic Press.
310:
293:
292:
290:
288:
282:
271:
60:in the Canadian
585:
584:
580:
579:
578:
576:
575:
574:
520:
519:
518:
517:
507:
505:
497:
496:
492:
479:
478:
474:
464:
462:
457:
456:
452:
442:
440:
431:
430:
426:
416:
415:
411:
402:
400:
387:
386:
382:
372:
370:
361:
360:
356:
346:
344:
337:
336:
332:
325:
312:
311:
296:
286:
284:
280:
273:
272:
261:
256:
239:
205:
185:
133:Skagway, Alaska
124:to Norman Wells
117:to Norman Wells
110:to Norman Wells
89:W.A. Bechtel Co
74:
42:
17:
12:
11:
5:
583:
581:
573:
572:
567:
562:
557:
552:
547:
542:
537:
532:
522:
521:
516:
515:
490:
472:
450:
424:
409:
395:. 2014-07-08.
380:
369:. 11 June 2018
354:
330:
323:
294:
258:
257:
255:
252:
251:
250:
245:
238:
235:
204:
203:Current status
201:
189:Macmillan Pass
184:
181:
168:
167:
164:
163:
162:
159:
156:
153:
147:
143:A refinery in
141:
135:
125:
118:
111:
73:
70:
54:Alaska Highway
41:
38:
15:
13:
10:
9:
6:
4:
3:
2:
582:
571:
568:
566:
563:
561:
558:
556:
553:
551:
548:
546:
543:
541:
538:
536:
533:
531:
530:Oil pipelines
528:
527:
525:
504:
500:
494:
491:
486:
482:
476:
473:
460:
454:
451:
438:
434:
428:
425:
420:
413:
410:
398:
394:
390:
384:
381:
368:
364:
358:
355:
343:
342:
334:
331:
326:
324:0-88962-439-9
320:
316:
309:
307:
305:
303:
301:
299:
295:
279:
278:
270:
268:
266:
264:
260:
253:
249:
246:
244:
241:
240:
236:
234:
231:
229:
225:
220:
218:
214:
210:
202:
200:
198:
192:
190:
182:
180:
176:
173:
165:
160:
157:
154:
151:
150:
148:
146:
142:
140:
136:
134:
130:
129:Prince Rupert
126:
123:
119:
116:
112:
109:
105:
104:
103:
100:
98:
94:
90:
83:
78:
71:
69:
67:
63:
59:
55:
51:
47:
46:United States
39:
37:
34:
30:
26:
22:
21:Canol Project
506:. Retrieved
502:
493:
475:
463:. Retrieved
453:
441:. Retrieved
436:
427:
412:
401:. Retrieved
383:
371:. Retrieved
366:
357:
345:. Retrieved
340:
333:
314:
285:. Retrieved
276:
232:
227:
221:
206:
193:
186:
177:
169:
101:
97:Imperial Oil
87:
72:Construction
58:Norman Wells
43:
29:World War II
25:oil pipeline
20:
18:
508:11 December
465:10 December
443:24 November
421:. CBC News.
373:11 December
347:11 December
287:21 December
217:Pelly River
524:Categories
403:2014-08-19
367:Yukon News
254:References
243:Canol Road
209:Canol Road
397:Archived
393:CBC News
237:See also
115:Edmonton
40:History
23:was an
321:
84:, 2020
33:Alaska
281:(PDF)
50:Japan
510:2020
467:2020
445:2019
375:2020
349:2020
319:ISBN
289:2020
207:The
131:and
19:The
503:CBC
526::
501:.
435:.
391:.
365:.
297:^
262:^
230:.
68:.
512:.
469:.
447:.
406:.
377:.
351:.
327:.
291:.
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.