Knowledge (XXG)

Prestressed concrete

Source 📝

1361: 944: 1345: 359: 978: 960: 1297: 410: 347:
concrete has been cast and set, the tendons are tensioned ("stressed") by pulling the tendon ends through the anchorages while pressing against the concrete. The large forces required to tension the tendons result in a significant permanent compression being applied to the concrete once the tendon is "locked-off" at the anchorage. The method of locking the tendon-ends to the anchorage is dependent upon the tendon composition, with the most common systems being "button-head" anchoring (for wire tendons),
259: 925: 202: 1183:
stresses generated by in-service loading. This crack-resistance also allows individual slab sections to be constructed in larger pours than for conventionally reinforced concrete, resulting in wider joint spacings, reduced jointing costs and less long-term joint maintenance issues. Initial works have also been successfully conducted on the use of precast prestressed concrete for road pavements, where the speed and quality of the construction has been noted as being beneficial for this technique.
1054: 498: 487: 324: 1313: 1016: 332: 1265: 1281: 1233: 997: 31: 1249: 816:, 2018. The Ponte Morandi was a cable-stayed bridge characterised by a prestressed concrete structure for the piers, pylons and deck, very few stays, as few as two per span, and a hybrid system for the stays constructed from steel cables with prestressed concrete shells poured on. The concrete was only prestressed to 10 MPa, resulting in it being prone to cracks and water intrusion, which caused corrosion of the embedded steel. 229: 1035: 4494: 251:) achievable between the freshly set concrete and the surface of the tendons is critical to the pre-tensioning process, as it determines when the tendon anchorages can be safely released. Higher bond strength in early-age concrete will speed production and allow more economical fabrication. To promote this, pre-tensioned tendons are usually composed of isolated single wires or strands, which provides a greater 1148:
at their far (internal) end, and have a significant "de-bonded" free-length at their external end which allows the tendon to stretch during tensioning. Tendons may be full-length bonded to the surrounding concrete or rock once tensioned, or (more commonly) have strands permanently encapsulated in corrosion-inhibiting grease over the free-length to permit long-term load monitoring and re-stressability.
1329: 1157:
tensioned, these tendons exert both axial (compressive) and radial (inward) forces onto the structure, which can directly oppose the subsequent storage loadings. If the magnitude of the prestress is designed to always exceed the tensile stresses produced by the loadings, a permanent residual compression will exist in the wall concrete, assisting in maintaining a watertight crack-free structure.
1073: 1377: 576:. Once cured, this grout can transfer the full tendon tension force to the concrete within a very short distance (approximately 1 metre). As a result, any inadvertent severing of the tendon or failure of an end anchorage has only a very localised impact on tendon performance, and almost never results in tendon ejection from the anchorage. 1400:(PTI) and the Precast/Prestressed Concrete Institute (PCI). Similar bodies include the Canadian Precast/Prestressed Concrete Institute (CPCI), the UK's Post-Tensioning Association, the Post Tensioning Institute of Australia and the South African Post Tensioning Association. Europe has similar country-based associations and institutions. 548:
strands are bundled to form a single unbonded tendon, an enveloping duct of plastic or galvanised steel is used and its interior free-spaces grouted after stressing. In this way, additional corrosion protection is provided via the grease, plastic sheathing, grout, external sheathing, and surrounding concrete layers.
843:
Building structures are typically required to satisfy a broad range of structural, aesthetic and economic requirements. Significant among these include: a minimum number of (intrusive) supporting walls or columns; low structural thickness (depth), allowing space for services, or for additional floors
564:
Both bonded and unbonded post-tensioning technologies are widely used around the world, and the choice of system is often dictated by regional preferences, contractor experience, or the availability of alternative systems. Either one is capable of delivering code-compliant, durable structures meeting
1147:
Most commonly, dam prestressing takes the form of post-tensioned anchors drilled into the dam's concrete structure and/or the underlying rock strata. Such anchors typically comprise tendons of high-tensile bundled steel strands or individual threaded bars. Tendons are grouted to the concrete or rock
778:
Following discovery of tendon corrosion in several bridges in England, the Highways Agency issued a moratorium on the construction of new internally grouted post-tensioned bridges and embarked on a 5-year programme of inspections on its existing post-tensioned bridge stock. The moratorium was lifted
1156:
Circular storage structures such as silos and tanks can use prestressing forces to directly resist the outward pressures generated by stored liquids or bulk-solids. Horizontally curved tendons are installed within the concrete wall to form a series of hoops, spaced vertically up the structure. When
547:
For individual strand tendons, no additional tendon ducting is used and no post-stressing grouting operation is required, unlike for bonded post-tensioning. Permanent corrosion protection of the strands is provided by the combined layers of grease, plastic sheathing, and surrounding concrete. Where
441:
of elements (e.g., strands or wires) placed inside a single tendon duct, with the exception of bars which are mostly used unbundled. This bundling makes for more efficient tendon installation and grouting processes, since each complete tendon requires only one set of end-anchorages and one grouting
243:
technique, where the resulting concrete element is manufactured off-site from the final structure location and transported to site once cured. It requires strong, stable end-anchorage points between which the tendons are stretched. These anchorages form the ends of a "casting bed" which may be many
684:
The durability of prestressed concrete is principally determined by the level of corrosion protection provided to any high-strength steel elements within the prestressing tendons. Also critical is the protection afforded to the end-anchorage assemblies of unbonded tendons or cable-stay systems, as
680:
Long-term durability is an essential requirement for prestressed concrete given its widespread use. Research on the durability performance of in-service prestressed structures has been undertaken since the 1960s, and anti-corrosion technologies for tendon protection have been continually improved
1165:
Prestressed concrete has been established as a reliable construction material for high-pressure containment structures such as nuclear reactor vessels and containment buildings, and petrochemical tank blast-containment walls. Using pre-stressing to place such structures into an initial state of
1182:
Heavily loaded concrete ground-slabs and pavements can be sensitive to cracking and subsequent traffic-driven deterioration. As a result, prestressed concrete is regularly used in such structures as its pre-compression provides the concrete with the ability to resist the crack-inducing tensile
1100:
Concrete is the most popular structural material for bridges, and prestressed concrete is frequently adopted. When investigated in the 1940s for use on heavy-duty bridges, the advantages of this type of bridge over more traditional designs was that it is quicker to install, more economical and
834:
Prestressed concrete is a highly versatile construction material as a result of it being an almost ideal combination of its two main constituents: high-strength steel, pre-stretched to allow its full strength to be easily realised; and modern concrete, pre-compressed to minimise cracking under
703:
Unbonded tendons comprise individual strands coated in an anti-corrosion grease or wax, and fitted with a durable plastic-based full-length sleeve or sheath. The sleeving is required to be undamaged over the tendon length, and it must extend fully into the anchorage fittings at each end of the
346:
The tendons are not placed in direct contact with the concrete, but are encapsulated within a protective sleeve or duct which is either cast into the concrete structure or placed adjacent to it. At each end of a tendon is an anchorage assembly firmly fixed to the surrounding concrete. Once the
275:
are located between the ends of the tendon to hold the tendon to the desired non-linear alignment during tensioning. Such deviators usually act against substantial forces, and hence require a robust casting-bed foundation system. Straight tendons are typically used in "linear"
1143:
Concrete dams have used prestressing to counter uplift and increase their overall stability since the mid-1930s. Prestressing is also frequently retro-fitted as part of dam remediation works, such as for structural strengthening, or when raising crest or spillway heights.
2289: 555:
process. The bare steel strand is fed into a greasing chamber and then passed to an extrusion unit where molten plastic forms a continuous outer coating. Finished strands can be cut-to-length and fitted with "dead-end" anchor assemblies as required for the project.
613:
Improved fire performance. The absence of strain redistribution in bonded tendons may limit the impact that any localised overheating has on the overall structure. As a result, bonded structures may display a higher capacity to resist fire conditions than unbonded
835:
tensile forces. Its wide range of application is reflected in its incorporation into the major design codes covering most areas of structural and civil engineering, including buildings, bridges, dams, foundations, pavements, piles, stadiums, silos, and tanks.
869:
The combination of reduced structural thickness, reduced conventional reinforcement quantities, and fast construction often results in prestressed concrete showing significant cost benefits in building structures compared to alternative structural
610:). With the tendons fixed to the concrete at each side of the crack, greater resistance to crack expansion is offered than with unbonded tendons, allowing many design codes to specify reduced reinforcement requirements for bonded post-tensioning. 506:
Unbonded slab post-tensioning. (Above) Installed strands and edge-anchors are visible, along with prefabricated coiled strands for the next pour. (Below) End-view of slab after stripping forms, showing individual strands and stressing-anchor
863:
Typically, prestressed concrete building elements are fully stressed and self-supporting within five days. At this point they can have their formwork stripped and re-deployed to the next section of the building, accelerating construction
3025: 244:
times the length of the concrete element being fabricated. This allows multiple elements to be constructed end-to-end in the one pre-tensioning operation, allowing significant productivity benefits and economies of scale to be realized.
804:
was detected in some of the prestressing tendons, necessitating initial closure of the road while additional investigations were done. Subsequent repairs and strengthening using external post-tensioning was carried out and completed in
654:
Simpler replacement and/or adjustment. Being permanently isolated from the concrete, unbonded tendons are able to be readily de-stressed, re-stressed and/or replaced should they become damaged or need their force levels to be modified
270:
Unlike those of post-tensioned concrete (see below), the tendons of pre-tensioned concrete elements generally form straight lines between end-anchorages. Where "profiled" or "harped" tendons are required, one or more intermediate
2285: 717:
and re-stressable dam anchors, will typically employ double-layer corrosion protection. Such tendons are composed of individual strands, grease-coated and sleeved, collected into a strand-bundle and placed inside encapsulating
2249: 1913: 3215: 543:
Bundled strands, individually greased-and-sheathed, forming a single tendon within an encapsulating duct that is placed either within or adjacent to the concrete (e.g., restressable anchors, external post-tensioning)
1169:
Nuclear reactor and containment vessels will commonly employ separate sets of post-tensioned tendons curved horizontally or vertically to completely envelop the reactor core. Blast containment walls, such as for
685:
the anchorages of both of these are required to retain the prestressing forces. Failure of any of these components can result in the release of prestressing forces, or the physical rupture of stressing tendons.
118:
in many situations. In a prestressed concrete member, the internal stresses are introduced in a planned manner so that the stresses resulting from the imposed loads are counteracted to the desired degree.
658:
Superior overload performance. Although having a lower ultimate strength than bonded tendons, unbonded tendons' ability to redistribute strains over their full length can give them superior pre-collapse
3169: 1951: 644:. Unbonded single-strand tendons have greater handling flexibility than bonded ducting during installation, allowing them a greater ability to be deviated around service penetrations or obstructions. 2129: 102:. The essence of prestressed concrete is that once the initial compression has been applied, the resulting material has the characteristics of high-strength concrete when subject to any subsequent 1396:
Worldwide, many professional organizations exist to promote best practices in the design and construction of prestressed concrete structures. In the United States, such organizations include the
694:
Bonded tendons consist of bundled strands placed inside ducts located within the surrounding concrete. To ensure full protection to the bundled strands, the ducts must be pressure-filled with a
3045: 2360: 2048: 651:. Unbonded tendons may allow some reduction in concrete element thickness, as their smaller size and increased corrosion protection may allow them to be placed closer to the concrete surface. 3434: 393:
Casting the tendon ducts/sleeves into the concrete before any tensioning occurs allows them to be readily "profiled" to any desired shape including incorporating vertical and/or horizontal
3272: 465:, placing the tendon ducting to the required curvature profiles, and reeving (or threading) the strands or wires through the ducting. Following concreting and tensioning, the ducts are 3091: 2439: 2241: 3615: 1988: 1166:
bi-axial or tri-axial compression increases their resistance to concrete cracking and leakage, while providing a proof-loaded, redundant and monitorable pressure-containment system.
3697: 3314: 2771: 1901: 3395: 858:
For a given span, lower in-service deflections allows thinner structural sections to be used, in turn resulting in lower floor-to-floor heights, or more room for building services.
847:
The prestressing of concrete allows "load-balancing" forces to be introduced into the structure to counter in-service loadings. This provides many benefits to building structures:
572:
Reduced reliance on end-anchorage integrity. Following tensioning and grouting, bonded tendons are connected to the surrounding concrete along their full length by high-strength
844:
in high-rise construction; fast construction cycles, especially for multi-storey buildings; and a low cost-per-unit-area, to maximise the building owner's return on investment.
2476: 1360: 722:
outer ducting. The remaining void space within the duct is pressure-grouted, providing a multi-layer polythene-grout-plastic-grease protection barrier system for each strand.
825:
The flyovers were closed in September 2018 after inspections revealed poor quality concrete, tendon corrosion and signs of structural distress. They were demolished in 2019.
193:
of it (external prestressing). While pre-tensioned concrete uses tendons directly bonded to the concrete, post-tensioned concrete can use either bonded or unbonded tendons.
3648: 1646:
Post-tensioned concreted is "structural concrete in which internal stresses have been introduced to reduce potential tensile stresses in the concrete resulting from loads."
1544: 1174:(LNG) tanks, will normally utilize layers of horizontally-curved hoop tendons for containment in combination with vertically looped tendons for axial wall pre-stressing. 943: 3353: 2731: 4432: 82:
of high-strength "tendons" located within or adjacent to the concrete and is done to improve the performance of the concrete in service. Tendons may consist of single
792:
was added to the tendon grout to speed construction, leading to corrosion of the prestressing strands and the sudden collapse of one span, injuring many spectators.
2090: 1775: 853:
Load balancing results in lower in-service deflections, which allows spans to be increased (and the number of supports reduced) without adding to structural depth.
3512: 3158: 2694: 2653: 2183: 1344: 1936: 1875: 2113: 4525: 2964: 637:. The elimination of the post-stressing grouting process required in bonded structures improves the site-labour productivity of unbonded post-tensioning. 626:. Unbonded tendons can be readily prefabricated off-site complete with end-anchorages, facilitating faster installation during construction. Additional 370:
steel materials, and are classified into two main types: those where the tendon element is subsequently bonded to the surrounding concrete by internal
4170: 3880: 2999: 2349: 517:
movement relative to the concrete. This is most commonly achieved by encasing each individual tendon element within a plastic sheathing filled with a
2017: 1410:
Rules and requirements for the detailing of reinforcement and prestressing tendons are specified by individual national codes and standards such as:
401:
forces being imparted onto the hardened concrete, and these can be beneficially used to counter any loadings subsequently applied to the structure.
3479: 450:
steel, and can be either round or rectangular/oval in cross-section. The tendon sizes used are highly dependent upon the application, ranging from
3544: 2510: 977: 430:; to permanently "lock-in" the tendon pre-tension, thereby removing the long-term reliance upon the end-anchorage systems; and to improve certain 4321: 3253: 2615: 1633: 1467: 426:
of their encapsulating ducting (after tendon tensioning). This grouting is undertaken for three main purposes: to protect the tendons against
3418: 3389: 3347: 3308: 2844: 2807: 2123: 2084: 1593: 1580: 727:
In all post-tensioned installations, protection of the end-anchorages against corrosion is essential, and critically so for unbonded systems.
3068: 2416: 1116:
In short-span bridges of around 10 to 40 metres (30 to 130 ft), prestressing is commonly employed in the form of precast pre-tensioned
3995: 3607: 1977: 1296: 959: 3674: 3298: 2760: 3379: 4412: 1270: 1211: 3581: 924: 2905: 2866: 2160: 1407:
or standards, but rather exist to promote the understanding and development of prestressed concrete design, codes and best practices.
1015: 3473: 3428: 2465: 1747: 1711: 1665: 1538: 1312: 1264: 1053: 2218: 1838: 1799:"Tendons having one or more deviations from a straight line, either vertically or horizontally, between the ends of the structure" 122:
Prestressed concrete is used in a wide range of building and civil structures where its improved performance can allow for longer
4180: 3637: 2900: 2572: 1528: 4535: 3854:
Historical Patents and the Evolution of Twentieth Century Architectural Construction with Reinforced and Pre-stressed Concrete
1232: 3910: 3848: 3337: 2720: 1280: 996: 2813: 810:
One span of a 12-span viaduct collapsed on 7 July 2014, causing 4 injuries, due to corrosion of the post-tensioning tendons.
3953: 3873: 930: 895: 1376: 4530: 2323: 2074: 1764: 1382: 1223: 1072: 1034: 911: 1248: 4520: 4427: 4402: 4316: 4283: 3846:
Guidelines for Sampling, Assessing, and Restoring Defective Grout in Prestressed Concrete Bridge Post-Tensioning Ducts
3537:
Construction of a Precast Prestressed Concrete Pavement Demonstration Project on Interstate 57 near Sikeston, Missouri
3504: 1426: 1120:
or planks. Medium-length structures of around 40 to 200 metres (150 to 650 ft), typically use precast-segmental,
514: 4195: 2393: 4381: 3905: 2679: 2638: 2191: 111: 4417: 4278: 4218: 4033: 3948: 2541: 1397: 1328: 1238: 1187: 668: 588: 348: 3237:
Cavill, Brian (20 March 1997). "Very High capacity Ground Anchors Used in Strengthening Concrete Gravity Dams".
1864: 461:
Fabrication of bonded tendons is generally undertaken on-site, commencing with the fitting of end-anchorages to
3866: 783: 139: 3763: 2271: 75:) during production, in a manner that strengthens it against tensile forces which will exist when in service. 4190: 1451: 1366: 1203: 983: 891: 312: 3975: 2990: 4288: 4165: 4089: 3980: 1482: 710: 603: 513:
Unbonded post-tensioning differs from bonded post-tensioning by allowing the tendons permanent freedom of
4371: 4114: 3535: 3460: 2953: 1477: 883: 580: 442:
operation. Ducting is fabricated from a durable and corrosion-resistant material such as plastic (e.g.,
362:
Balanced-cantilever bridge under construction. Each added segment is supported by post-tensioned tendons
72: 2502: 358: 540:
Individual strand tendons placed directly into the concreted structure (e.g., buildings, ground slabs)
4407: 4308: 4303: 4175: 4038: 3853: 3789: 3129: 2870: 1462: 1457: 533:
force to the concrete, and are required to reliably perform this role for the life of the structure.
163: 2595: 1625: 1109:. By the 1960s, prestressed concrete largely superseded reinforced concrete bridges in the UK, with 1101:
longer-lasting with the bridge being less lively. One of the first bridges built in this way is the
591:
at that same location (i.e. no strain re-distribution occurs). This results in significantly higher
185:, where all strands or wires in a tendon are stressed simultaneously. Tendons may be located either 4386: 4354: 4273: 4043: 3985: 1446: 1432: 1132: 795: 714: 695: 596: 431: 127: 115: 2836: 1599: 4359: 4268: 4185: 3815: 3737: 3721: 3196:"Strengthening of existing concrete dams using post-tensioned anchors: A state-of-the-art review" 2040: 1171: 1128: 965: 875: 522: 398: 383: 123: 103: 91: 3840: 409: 258: 2152: 1131:. For the longest bridges, prestressed concrete deck structures often form an integral part of 284:; whereas profiled tendons are more commonly found in deeper precast bridge beams and girders. 4497: 4453: 4253: 4248: 4223: 4205: 4119: 4099: 3935: 3920: 3469: 3424: 3385: 3343: 3304: 2803: 2607: 2119: 2080: 1743: 1739: 1707: 1661: 1589: 1534: 1124: 1110: 755: 592: 530: 466: 232:
Pre-tensioned bridge girder in precasting bed, with single-strand tendons exiting through the
218: 107: 79: 417:
In bonded post-tensioning, tendons are permanently bonded to the surrounding concrete by the
339:
Post-tensioned concrete is a variant of prestressed concrete where the tendons are tensioned
335:
Post-tensioned tendon anchorage; four-piece "lock-off" wedges are visible holding each strand
4349: 4258: 4124: 4084: 3963: 3925: 3689: 3570: 3264: 3207: 3137: 3083: 3037: 2896: 2431: 2032: 1731: 1487: 738: 688:
Modern prestressing systems deliver long-term durability by addressing the following areas:
288: 281: 277: 263: 209:
Pre-tensioned concrete is a variant of prestressed concrete where the tendons are tensioned
35: 2874: 587:. With bonded post-tensioning, any flexure of the structure is directly resisted by tendon 4293: 4144: 4048: 3958: 1286: 1215: 1021: 899: 773: 497: 486: 304: 222: 3133: 2214: 323: 30: 4366: 4298: 4139: 4058: 4028: 4023: 3915: 2756: 1902:"Comparison of unbonded and bonded post-tensioned concrete slabs under fire conditions" 1827: 770:, leading to a progressive failure of the main bridge span and the death of one person. 759: 648: 240: 177:, which occurs after the concrete is cast. Tensioning systems may be classed as either 17: 3841:
The story of prestressed concrete from 1930 to 1945: A step towards the European Union
2564: 201: 4514: 4339: 4238: 4228: 4134: 3195: 2044: 1732: 1404: 1318: 1254: 1207: 1191: 1059: 907: 813: 623: 292: 169:
First used in the late nineteenth century, prestressed concrete has developed beyond
135: 4376: 4243: 4129: 4104: 1334: 1195: 1102: 1078: 1040: 915: 903: 719: 634: 443: 352: 331: 252: 99: 95: 2435: 3693: 3268: 3087: 3041: 2797: 2036: 4344: 4063: 4000: 3142: 3117: 1350: 1199: 1002: 879: 874:
Some notable building structures constructed from prestressed concrete include:
741:
structure constructed in 1953 with longitudinal and transverse post-tensioning.
641: 551:
Individually greased-and-sheathed tendons are usually fabricated off-site by an
308: 155: 131: 788:
A multi-span steel and concrete structure constructed in 1995. An unauthorised
287:
Pre-tensioned concrete is most commonly used for the fabrication of structural
217:, following which the end-anchoring of the tendons is released, and the tendon 4448: 4233: 4213: 4005: 1186:
Some notable civil structures constructed using prestressed concrete include:
618:
The benefits that unbonded post-tensioning can offer over bonded systems are:
568:
The benefits that bonded post-tensioning can offer over unbonded systems are:
447: 367: 2611: 2312: 4479: 1472: 820: 800:
Sixteen-span prestressed structure constructed in 1961. Corrosion from road
767: 742: 660: 627: 552: 518: 470: 427: 394: 159: 126:, reduced structural thicknesses, and material savings compared with simple 87: 228: 4463: 4458: 4094: 4053: 4015: 3897: 3889: 1419: 1302: 1219: 887: 801: 789: 763: 664: 565:
the structural strength and serviceability requirements of the designer.
462: 454:
works typically using between 2 and 6 strands per tendon, to specialized
451: 248: 233: 214: 68: 2385: 4422: 3990: 3118:"Rock-engineering design of post-tensioned anchors for dams - A review" 1706:(2nd ed.). Melbourne, Australia: Longman Cheshire. pp. 1–13. 1415: 595:
strains in the tendons than if they were unbonded, allowing their full
584: 526: 437:
Bonded post-tensioning characteristically uses tendons each comprising
419: 296: 51:
After concrete solidifies, tendons apply compressive stress to concrete
3423:(Second ed.). New York: John Wiley & Sons. pp. 472–494. 2927: 2843:. Vol. 123. Simmons-Boardman Publishing Company. pp. 54–58. 2533: 1865:"Nonprestresed Bonded Reinforcement in Post-Tensioned Building Design" 1828:"Unbonded and bonded post-tensioning systems in building construction" 1660:. South Melbourne, Australia: Addison Welsley Longman. pp. 8–19. 48:
Before concrete solidifies, tendons embedded in concrete are tensioned
4149: 4109: 3943: 3845: 3381:
Structures for Nuclear Facilities – Analysis, Design and Construction
1117: 667:-type action instead of pure flexure, allowing significantly greater 300: 143: 3336:
Gilbert, R. I.; Mickleborough, N. C.; Ranzi, G. (17 February 2016).
3254:"Analysis and Design of Prestressed Circular Concrete Storage Tanks" 3211: 378:
post-tensioning); and those where the tendon element is permanently
213:
to the concrete being cast. The concrete bonds to the tendons as it
3759: 2115:
Bridge Management 4: Inspection, Maintenance, Assessment and Repair
4068: 3970: 1656:
Warner, R. F.; Rangan, B. V.; Hall, A. S.; Faulkes, K. A. (1988).
607: 606:, bonded tendons respond similarly to conventional reinforcement ( 573: 423: 408: 371: 357: 330: 322: 257: 227: 200: 181:, where each tendon's strand or wire is stressed individually, or 29: 3534:
Merritt, David; Rogers, Richard; Rasmussen, Robert (March 2008).
151: 83: 3862: 327:
Forces on post-tensioned concrete with profiled (curved) tendon
2311:
Australian Society for History of Engineering and Technology.
698:
grout, without leaving any voids, following strand-tensioning.
599:
to be realised, and producing a higher ultimate load capacity.
455: 147: 2415:
Knoll, Franz; Prosser, M. John; Otter, John (May–June 1976).
1978:"Survey on the Durability of Prestressed Concrete Structures" 366:
Tendon encapsulation systems are constructed from plastic or
2184:"Corrosdion Failures: Lowe's Motor Speedway Bridge Collapse" 745:
attacked the under-protected tendons where they crossed the
397:. When the tendons are tensioned, this profiling results in 382:
bonded from the surrounding concrete, usually by means of a
3858: 3571:"Design of the Main Spans, Second Gateway Bridge, Brisbane" 2837:"Prestressed Concrete Bridge Beams Being Tested in England" 1106: 808:
Petrulla Viaduct ("Viadotto Petrulla"), Sicily, Italy, 2014
3811: 3785: 2350:"Structural Design of the 84 Storey World Tower in Sydney" 2992:
Bridge Construction Practices Using Incremental Launching
1429:: Building Code Requirements for Reinforced Concrete; and 910:, Madrid; Guoco Tower (Tanjong Pagar Centre), Singapore; 529:
based. Anchorages at each end of the tendon transfer the
110:. This can result in improved structural capacity and/or 71:
used in construction. It is substantially "prestressed" (
38:(top) and prestressed concrete beam (bottom) under load: 3569:
Connall, John; Wheeler, Paul; Pau, Andrew; Mihov, Miho.
2215:"TfL report warned of Hammersmith Flyover collapse risk" 749:
joints between the segments, leading to sudden collapse.
1533:(Third ed.). New York, US: John Wiley & Sons. 3733: 560:
Comparison between bonded and unbonded post-tensioning
189:
the concrete volume (internal prestressing) or wholly
3675:"1300-Ton-Capacity Prestressed Anchors Stabilize Dam" 3122:
Journal of Rock Mechnanics and Geological Engineering
2799:
Prestressed Concrete bridges: design and Construction
2018:"Corrosion of Prestressing Steels and its Mitigation" 1837:(5). Phoenix, Arizona US: Post-Tensioning Institute. 2272:"Giù il viadotto Petrulla, panico sulla Statale 626" 1579:
Federation Internationale du Beton (February 2005).
731:
Several durability-related events are listed below:
630:
may need to be allowed for this fabrication process.
602:
Improved crack-control. In the presence of concrete
4472: 4441: 4395: 4332: 4204: 4158: 4077: 4014: 3934: 3896: 2313:"An Engineering Walk around the Sydney Opera House" 106:and of ductile high-strength steel when subject to 1937:"Two way post-tensioned slabs with bonded tendons" 343:the surrounding concrete structure has been cast. 221:are transferred to the concrete as compression by 90:or threaded bars that are most commonly made from 3734:"Canadian Precast/Prestressed Concrete Institute" 3241:. London UK: Institution of Civil Engineers: 262. 4433:International Federation for Structural Concrete 3468:(Fourth ed.). New Delhi: Tata McGraw Hill. 3026:"Cable Stayed Bridges with Prestressed Concrete" 663:. In extremes, unbonded tendons can resort to a 3420:Construction of Prestressed Concrete Structures 3303:(Third ed.). CRC Press. pp. 149–165. 2359:. Council on Tall Buildings and Urban Habitat. 1403:These organizations are not the authorities of 735:Ynys-y-Gwas bridge, West Glamorgan, Wales, 1985 536:Unbonded post-tensioning can take the form of: 2466:"Kai Tak Cruise Terminal Building - Hong Kong" 2286:"Churchill Way Flyovers Deconstruction Scheme" 2112:Ryall, M. J.; Woodward, R.; Milne, D. (2000). 1738:(6th ed.). Phoenix, AZ US: PTI. pp.  3874: 3673:Eberhardt, A.; Veltrop, J. A. (August 1965). 3339:Design of Prestressed Concrete to AS3600-2009 2386:"The Tower, One St. George Wharf, London, UK" 2213:Ed Davey and Rebecca Cafe (3 December 2012). 1582:fib Bulletin 31: Post-tensioning in Buildings 469:and the tendon stressing-ends sealed against 8: 2594:Martinez, Julio; Gomez, Miguel (July 2008). 2565:"Eureka Tower, Melbourne Victoria Australia" 2118:. London: Thomas Telford. pp. 170–173. 174: 3812:"South African Post Tensioning Association" 2242:"Extending the Life of Hammersmith Flyover" 1105:, a railway bridge constructed 1946 in the 681:since the earliest systems were developed. 170: 3881: 3867: 3859: 3373: 3371: 2011: 2009: 1725: 1723: 1697: 851:Longer spans for the same structural depth 752:Scheldt River bridge, Melle, Belgium, 1991 676:Tendon durability and corrosion protection 3543:. US DOT Federal Highway Administration. 3141: 1900:Bailey, Colin G.; Ellobody, Ehab (2009). 1695: 1693: 1691: 1689: 1687: 1685: 1683: 1681: 1679: 1677: 1530:Design of Prestressed Concrete Structures 709:Prestressing tendons requiring permanent 458:works using up to 91 strands per tendon. 255:for bonding than bundled-strand tendons. 3786:"Post Tensioning Institute of Australia" 3505:"Building Post-Tensioned Slabs on Grade" 1950:(2). US: Post-Tensioning Institute: 44. 1821: 1819: 1817: 1815: 1813: 1811: 1809: 1807: 1805: 3454: 3452: 3194:Xu, Haixue; Benmokrane, Brahim (1996). 2867:"History of Prestressed Concrete in UK" 1574: 1572: 1570: 1568: 1566: 1564: 1562: 1522: 1520: 1518: 1516: 1514: 1512: 1510: 1508: 1506: 1504: 1500: 1228: 920: 3792:from the original on 25 September 2016 3766:from the original on 19 September 2016 3722:Precast/Prestressed Concrete Institute 3703:from the original on 16 September 2016 3587:from the original on 17 September 2016 3550:from the original on 15 September 2016 3515:from the original on 18 September 2016 3485:from the original on 11 September 2016 3278:from the original on 16 September 2016 3175:from the original on 14 September 2016 3097:from the original on 16 September 2016 3069:"Prestressed Concrete Dams: 1936–1964" 2970:from the original on 16 September 2016 2954:"Structures Engineering Design Manual" 2777:from the original on 17 September 2016 2700:from the original on 22 September 2016 2659:from the original on 22 September 2016 2544:from the original on 24 September 2016 2482:from the original on 14 September 2016 2445:from the original on 15 September 2016 2252:from the original on 15 September 2016 2054:from the original on 16 September 2016 1994:from the original on 16 September 2016 1916:from the original on 17 September 2016 1702:Warner, R. F.; Faulkes, K. A. (1988). 1632:. Farmington Hills, Michigan US: ACI. 1468:Glossary of prestressed concrete terms 3654:from the original on 26 February 2017 3200:Canadian Journal of Civil Engineering 3005:from the original on 30 November 2016 2835:R. L. M'ilmoyle (20 September 1947). 2721:"Case Study: Capital Gate, Abu Dhabi" 2575:from the original on 13 February 2012 2513:from the original on 4 September 2016 2503:"International Commerce Centre (ICC)" 1844:from the original on 23 November 2016 1826:Aalami, Bijan O. (5 September 1994). 1636:from the original on 11 December 2016 758:constructed in the 1950s. Inadequate 27:Form of concrete used in construction 7: 3996:Ground granulated blast-furnace slag 3608:"Incheon Bridge, Seoul, South Korea" 3417:Gerwick, Ben C. (13 February 1997). 3384:. London: Springer. pp. 36–37. 3157:Institution of Engineers Australia. 2618:from the original on 8 February 2017 2329:from the original on 8 February 2017 2221:from the original on 3 December 2012 1881:from the original on 8 February 2017 1781:from the original on 8 February 2017 1547:from the original on 8 February 2017 351:anchoring (for strand tendons), and 78:This compression is produced by the 4413:Institution of Structural Engineers 3618:from the original on 10 August 2016 3067:Roemermann, A. C. (February 1965). 3024:Leonhardt, Fritz (September 1987). 2596:"Torre Espacio. Building Structure" 1957:from the original on 28 August 2016 1935:Bondy, Kenneth B. (December 2012). 413:Multi-strand post-tensioning anchor 3437:from the original on 17 April 2021 3398:from the original on 17 April 2021 3356:from the original on 17 April 2021 3317:from the original on 17 April 2021 2989:LaViolette, Mike (December 2007). 2906:National Heritage List for England 2847:from the original on 17 April 2021 2816:from the original on 17 April 2021 2396:from the original on 30 April 2021 2366:from the original on 14 April 2016 2132:from the original on 17 April 2021 2093:from the original on 17 April 2021 2073:De Schutter, Geert (10 May 2012). 2016:Podolny, Walter (September 1992). 1863:Aalami, Bijan O. (February 2001). 1730:Post-Tensioning Institute (2006). 1435:AS 3600-2009: Concrete Structures. 25: 4526:Concrete buildings and structures 3459:Raju, Krishna (1 December 2006). 3300:Circular Storage Tasnks and Silos 3252:Priestley, M. J. N. (July 1985). 3218:from the original on 29 June 2021 2932:Concrete Bridge Development Group 2737:from the original on 30 July 2016 2680:"Gateway to South Eastern Europe" 2292:from the original on 9 April 2021 2163:from the original on 11 June 2016 1976:Szilard, Rudolph (October 1969). 1626:"CT-13: ACI Concrete Terminology" 1527:Lin, T.Y.; Burns, Ned H. (1981). 1422:2: Design of Concrete Structures; 713:and/or force adjustment, such as 701:Tendon coating (unbonded tendons) 434:of the final concrete structure. 280:elements, such as shallow beams, 42:Non-prestressed beam without load 4493: 4492: 3818:from the original on 25 May 2016 2761:"Evolution of Bridge Technology" 1375: 1359: 1343: 1327: 1311: 1295: 1279: 1263: 1247: 1231: 1071: 1052: 1033: 1014: 995: 976: 958: 942: 923: 692:Tendon grouting (bonded tendons) 496: 485: 386:sheath over the tendon strands ( 3740:from the original on 5 May 2021 1392:Design agencies and regulations 130:. Typical applications include 3911:Roman architectural revolution 3849:Federal Highway Administration 3342:(Second ed.). CRC Press. 3116:Brown, E. T. (February 2015). 2998:. AASHTO. p. Appendix A. 2952:Main Roads Western Australia. 1129:incrementally-launched designs 164:nuclear containment structures 45:Non-prestressed beam with load 34:Comparison of non-prestressed 1: 3760:"Post-Tensioning Association" 3166:www.engineersaustralia.org.au 2928:"History of Concrete Bridges" 2606:(249). Madrid, Spain: 19–43. 2436:10.15554/pcij.05011976.84.111 2079:. CRC Press. pp. 31–33. 2076:Damage to Concrete Structures 1624:American Concrete Institute. 896:International Commerce Centre 374:of the duct after stressing ( 355:anchoring (for bar tendons). 114:compared with conventionally 54:Prestressed beam without load 3694:10.15554/pcij.08011965.18.36 3509:www.concreteconstruction.net 3269:10.15554/pcij.07011985.64.85 3088:10.15554/pcij.02011965.76.88 3042:10.15554/pcij.09011987.52.80 2534:"Ocean Heights 2, Dubai UAE" 2532:CM Engineering Consultants. 2037:10.15554/pcij.09011992.34.55 1765:"CFCC Pre-tensioning Manual" 912:Zagreb International Airport 856:Reduced structural thickness 4428:Portland Cement Association 4403:American Concrete Institute 3647:. SRG Limited. p. 10. 3297:Ghali, Amin (12 May 2014). 3143:10.1016/j.jrmge.2014.08.001 2768:IABSE Symposium Proceedings 2569:www.designbuild-network.com 2417:"Prestressing the CN Tower" 2348:Martin, Owen; Lal, Nalean. 1872:ADAPT Technical Publication 1630:American Concrete Institute 766:resulted in tie-down cable 239:Pre-tensioning is a common 4552: 3906:Ancient Roman architecture 3378:Bangash, M. Y. H. (2011). 786:, North Carolina, US, 2000 707:Double-layer encapsulation 671:before structural failure. 57:Prestressed beam with load 4488: 4418:Indian Concrete Institute 3511:. Concrete Construction. 2796:Hewson, Nigel R. (2012). 2153:"Post-Tensioning Systems" 1398:Post-Tensioning Institute 1113:being the dominant form. 754:A three-span prestressed 3159:"Catagunya Dam Tasmania" 2963:. MRWA. pp. 17–23. 2901:"Adam Viaduct (1061327)" 2719:Schofield, Jeff (2012). 2639:"Reaching for the Skies" 2571:. Design Build Network. 1452:Dyckerhoff & Widmann 1226:, Videbergshamn Sweden. 1224:Ringhals nuclear reactor 1178:Hardstands and pavements 819:Churchill Way flyovers, 784:Charlotte Motor Speedway 477:Unbonded post-tensioning 2961:www.mainroads.wa.gov.au 1906:The Structural Engineer 1763:Tokyo Rope Mfg Co Ltd. 1222:, Toronto, Canada; and 1214:, Itz Valley, Germany; 892:Kai Tak Cruise Terminal 319:Post-tensioned concrete 262:Pre-tensioned, precast 247:The amount of bond (or 18:Post-tensioned concrete 4536:Structural engineering 4196:Alkali–silica reaction 3954:Energetically modified 3239:Conference Proceedings 2873:. 2004. Archived from 2563:Design Build Network. 2190:. NACE. Archived from 1734:Post-Tensioning Manual 1483:Properties of concrete 1383:Ringhals nuclear plant 1190:, Brisbane Australia; 949:Guoco Tower, Singapore 867:Reduced material costs 640:Improved installation 414: 405:Bonded post-tensioning 363: 336: 328: 267: 236: 206: 205:Pre-tensioning process 197:Pre-tensioned concrete 61: 3645:www.srglimited.com.au 3638:"SRG Remote Projects" 3612:www.dywidag-systems.a 1478:Prestressed structure 1386:Videbergshamn, Sweden 1206:, South Hook, Wales; 884:St George Wharf Tower 861:Faster stripping time 814:Genoa bridge collapse 798:London, England, 2011 412: 361: 334: 326: 295:, hollow-core slabs, 261: 231: 204: 33: 4181:Environmental impact 4039:Reversing drum mixer 3462:Prestressed Concrete 3048:on 16 September 2016 2871:Cambridge University 2678:BBR Network (2016). 2637:BBR Network (2016). 2217:. BBC News, London. 2194:on 24 September 2016 1704:Prestressed Concrete 1463:Freyssinet Test Arch 1133:cable-stayed designs 756:cantilever structure 725:Anchorage protection 696:corrosion-inhibiting 432:structural behaviors 160:industrial pavements 65:Prestressed concrete 4531:Reinforced concrete 3134:2015JRMGE...7....1B 1835:PTI Technical Notes 1658:Concrete Structures 1447:Cable stayed bridge 1433:Australian Standard 1274:Itz Valley, Germany 1212:Autobahn A73 bridge 1125:balanced-cantilever 839:Building structures 796:Hammersmith Flyover 782:Pedestrian bridge, 132:high-rise buildings 128:reinforced concrete 116:reinforced concrete 92:high-tensile steels 4521:Building materials 4284:Self-consolidating 3976:Water–cement ratio 2246:www.freyssinet.com 1605:on 8 February 2017 1414:European Standard 1218:, Moscow, Russia; 1202:, Washington, US; 1172:liquid natural gas 966:Sydney Opera House 876:Sydney Opera House 774:UK Highways Agency 415: 390:post-tensioning). 364: 337: 329: 268: 237: 207: 140:foundation systems 104:compression forces 62: 4506: 4505: 4498:Category:Concrete 4279:Roller-compacting 4100:Climbing formwork 3949:Calcium aluminate 3921:Roman engineering 3391:978-3-642-12560-7 3349:978-1-4665-7277-5 3310:978-1-4665-7104-4 2877:on 25 August 2018 2809:978-0-7277-4113-4 2125:978-0-7277-2854-8 2086:978-0-415-60388-1 1595:978-2-88394-071-0 1458:Eugène Freyssinet 1370:South Hook, Wales 1338:Ad Damazin, Sudan 1210:, Brevik Norway; 1161:Nuclear and blast 918:, Abu Dhabi UAE. 739:precast-segmental 581:ultimate strength 282:hollow-core slabs 16:(Redirected from 4543: 4496: 4495: 4408:Concrete Society 4219:Fiber-reinforced 4034:Volumetric mixer 3926:Roman technology 3883: 3876: 3869: 3860: 3828: 3827: 3825: 3823: 3808: 3802: 3801: 3799: 3797: 3782: 3776: 3775: 3773: 3771: 3756: 3750: 3749: 3747: 3745: 3730: 3724: 3719: 3713: 3712: 3710: 3708: 3702: 3679: 3670: 3664: 3663: 3661: 3659: 3653: 3642: 3634: 3628: 3627: 3625: 3623: 3603: 3597: 3596: 3594: 3592: 3586: 3575: 3566: 3560: 3559: 3557: 3555: 3549: 3542: 3531: 3525: 3524: 3522: 3520: 3501: 3495: 3494: 3492: 3490: 3484: 3467: 3456: 3447: 3446: 3444: 3442: 3414: 3408: 3407: 3405: 3403: 3375: 3366: 3365: 3363: 3361: 3333: 3327: 3326: 3324: 3322: 3294: 3288: 3287: 3285: 3283: 3277: 3258: 3249: 3243: 3242: 3234: 3228: 3227: 3225: 3223: 3206:(6): 1151–1171. 3191: 3185: 3184: 3182: 3180: 3174: 3163: 3154: 3148: 3147: 3145: 3113: 3107: 3106: 3104: 3102: 3096: 3073: 3064: 3058: 3057: 3055: 3053: 3044:. Archived from 3021: 3015: 3014: 3012: 3010: 3004: 2997: 2986: 2980: 2979: 2977: 2975: 2969: 2958: 2949: 2943: 2942: 2940: 2938: 2924: 2918: 2917: 2915: 2913: 2897:Historic England 2893: 2887: 2886: 2884: 2882: 2863: 2857: 2856: 2854: 2852: 2832: 2826: 2825: 2823: 2821: 2793: 2787: 2786: 2784: 2782: 2776: 2765: 2753: 2747: 2746: 2744: 2742: 2736: 2725: 2716: 2710: 2709: 2707: 2705: 2699: 2684: 2675: 2669: 2668: 2666: 2664: 2658: 2643: 2634: 2628: 2627: 2625: 2623: 2600:Hormigon y Acero 2591: 2585: 2584: 2582: 2580: 2560: 2554: 2553: 2551: 2549: 2529: 2523: 2522: 2520: 2518: 2498: 2492: 2491: 2489: 2487: 2481: 2470: 2461: 2455: 2454: 2452: 2450: 2444: 2421: 2412: 2406: 2405: 2403: 2401: 2382: 2376: 2375: 2373: 2371: 2365: 2354: 2345: 2339: 2338: 2336: 2334: 2328: 2317: 2308: 2302: 2301: 2299: 2297: 2282: 2276: 2275: 2268: 2262: 2261: 2259: 2257: 2237: 2231: 2230: 2228: 2226: 2210: 2204: 2203: 2201: 2199: 2179: 2173: 2172: 2170: 2168: 2148: 2142: 2141: 2139: 2137: 2109: 2103: 2102: 2100: 2098: 2070: 2064: 2063: 2061: 2059: 2053: 2022: 2013: 2004: 2003: 2001: 1999: 1993: 1982: 1973: 1967: 1966: 1964: 1962: 1956: 1941: 1932: 1926: 1925: 1923: 1921: 1897: 1891: 1890: 1888: 1886: 1880: 1869: 1860: 1854: 1853: 1851: 1849: 1843: 1832: 1823: 1800: 1797: 1791: 1790: 1788: 1786: 1780: 1769: 1760: 1754: 1753: 1737: 1727: 1718: 1717: 1699: 1672: 1671: 1653: 1647: 1645: 1643: 1641: 1621: 1615: 1614: 1612: 1610: 1604: 1598:. Archived from 1587: 1576: 1557: 1556: 1554: 1552: 1524: 1488:Segmental bridge 1379: 1363: 1347: 1331: 1315: 1299: 1283: 1267: 1251: 1235: 1091:Civil structures 1075: 1056: 1037: 1018: 999: 984:Kai Tak Terminal 980: 962: 946: 927: 500: 489: 467:pressure-grouted 278:precast concrete 264:hollow-core slab 21: 4551: 4550: 4546: 4545: 4544: 4542: 4541: 4540: 4511: 4510: 4507: 4502: 4484: 4468: 4437: 4391: 4328: 4200: 4154: 4073: 4049:Flow table test 4010: 3930: 3892: 3887: 3837: 3832: 3831: 3821: 3819: 3810: 3809: 3805: 3795: 3793: 3784: 3783: 3779: 3769: 3767: 3758: 3757: 3753: 3743: 3741: 3732: 3731: 3727: 3720: 3716: 3706: 3704: 3700: 3677: 3672: 3671: 3667: 3657: 3655: 3651: 3640: 3636: 3635: 3631: 3621: 3619: 3605: 3604: 3600: 3590: 3588: 3584: 3578:www.cmnzl.co.nz 3573: 3568: 3567: 3563: 3553: 3551: 3547: 3540: 3533: 3532: 3528: 3518: 3516: 3503: 3502: 3498: 3488: 3486: 3482: 3476: 3465: 3458: 3457: 3450: 3440: 3438: 3431: 3416: 3415: 3411: 3401: 3399: 3392: 3377: 3376: 3369: 3359: 3357: 3350: 3335: 3334: 3330: 3320: 3318: 3311: 3296: 3295: 3291: 3281: 3279: 3275: 3256: 3251: 3250: 3246: 3236: 3235: 3231: 3221: 3219: 3212:10.1139/l96-925 3193: 3192: 3188: 3178: 3176: 3172: 3161: 3156: 3155: 3151: 3115: 3114: 3110: 3100: 3098: 3094: 3071: 3066: 3065: 3061: 3051: 3049: 3023: 3022: 3018: 3008: 3006: 3002: 2995: 2988: 2987: 2983: 2973: 2971: 2967: 2956: 2951: 2950: 2946: 2936: 2934: 2926: 2925: 2921: 2911: 2909: 2895: 2894: 2890: 2880: 2878: 2865: 2864: 2860: 2850: 2848: 2834: 2833: 2829: 2819: 2817: 2810: 2795: 2794: 2790: 2780: 2778: 2774: 2763: 2757:Tang, Man-Chung 2755: 2754: 2750: 2740: 2738: 2734: 2723: 2718: 2717: 2713: 2703: 2701: 2697: 2682: 2677: 2676: 2672: 2662: 2660: 2656: 2641: 2636: 2635: 2631: 2621: 2619: 2593: 2592: 2588: 2578: 2576: 2562: 2561: 2557: 2547: 2545: 2531: 2530: 2526: 2516: 2514: 2500: 2499: 2495: 2485: 2483: 2479: 2468: 2463: 2462: 2458: 2448: 2446: 2442: 2419: 2414: 2413: 2409: 2399: 2397: 2384: 2383: 2379: 2369: 2367: 2363: 2352: 2347: 2346: 2342: 2332: 2330: 2326: 2315: 2310: 2309: 2305: 2295: 2293: 2284: 2283: 2279: 2270: 2269: 2265: 2255: 2253: 2239: 2238: 2234: 2224: 2222: 2212: 2211: 2207: 2197: 2195: 2181: 2180: 2176: 2166: 2164: 2157:www.ukcares.com 2150: 2149: 2145: 2135: 2133: 2126: 2111: 2110: 2106: 2096: 2094: 2087: 2072: 2071: 2067: 2057: 2055: 2051: 2020: 2015: 2014: 2007: 1997: 1995: 1991: 1980: 1975: 1974: 1970: 1960: 1958: 1954: 1939: 1934: 1933: 1929: 1919: 1917: 1899: 1898: 1894: 1884: 1882: 1878: 1867: 1862: 1861: 1857: 1847: 1845: 1841: 1830: 1825: 1824: 1803: 1798: 1794: 1784: 1782: 1778: 1767: 1762: 1761: 1757: 1750: 1729: 1728: 1721: 1714: 1701: 1700: 1675: 1668: 1655: 1654: 1650: 1639: 1637: 1623: 1622: 1618: 1608: 1606: 1602: 1596: 1585: 1578: 1577: 1560: 1550: 1548: 1541: 1526: 1525: 1502: 1497: 1492: 1442: 1394: 1387: 1385: 1380: 1371: 1369: 1364: 1355: 1353: 1348: 1339: 1337: 1332: 1323: 1321: 1316: 1307: 1306:Toronto, Canada 1305: 1300: 1291: 1289: 1287:Ostankino Tower 1284: 1275: 1273: 1268: 1259: 1257: 1252: 1243: 1242:Brisbane, Aust. 1241: 1236: 1216:Ostankino Tower 1194:, South Korea; 1180: 1163: 1154: 1152:Silos and tanks 1141: 1098: 1093: 1086: 1082: 1076: 1067: 1063: 1057: 1048: 1044: 1038: 1029: 1025: 1022:Ocean Heights 2 1019: 1010: 1006: 1000: 991: 986: 981: 972: 968: 963: 954: 950: 947: 938: 934: 928: 914:, Croatia; and 900:Ocean Heights 2 868: 862: 857: 852: 841: 832: 824: 809: 799: 787: 777: 753: 737:A single-span, 736: 726: 708: 702: 693: 678: 562: 511: 510: 509: 508: 503: 502: 501: 492: 491: 490: 479: 407: 321: 223:static friction 199: 175:post-tensioning 60: 28: 23: 22: 15: 12: 11: 5: 4549: 4547: 4539: 4538: 4533: 4528: 4523: 4513: 4512: 4504: 4503: 4501: 4500: 4489: 4486: 4485: 4483: 4482: 4476: 4474: 4470: 4469: 4467: 4466: 4461: 4456: 4451: 4445: 4443: 4439: 4438: 4436: 4435: 4430: 4425: 4420: 4415: 4410: 4405: 4399: 4397: 4393: 4392: 4390: 4389: 4384: 4379: 4374: 4369: 4367:Concrete block 4364: 4363: 4362: 4357: 4355:voided biaxial 4352: 4347: 4336: 4334: 4330: 4329: 4327: 4326: 4325: 4324: 4319: 4311: 4306: 4301: 4296: 4291: 4286: 4281: 4276: 4271: 4266: 4261: 4256: 4251: 4246: 4241: 4236: 4231: 4226: 4221: 4216: 4210: 4208: 4202: 4201: 4199: 4198: 4193: 4188: 4183: 4178: 4173: 4168: 4162: 4160: 4156: 4155: 4153: 4152: 4147: 4142: 4137: 4132: 4127: 4122: 4117: 4112: 4107: 4102: 4097: 4092: 4087: 4081: 4079: 4075: 4074: 4072: 4071: 4066: 4061: 4059:Concrete cover 4056: 4051: 4046: 4041: 4036: 4031: 4029:Concrete mixer 4026: 4020: 4018: 4012: 4011: 4009: 4008: 4003: 3998: 3993: 3988: 3983: 3978: 3973: 3968: 3967: 3966: 3961: 3956: 3951: 3940: 3938: 3932: 3931: 3929: 3928: 3923: 3918: 3916:Roman concrete 3913: 3908: 3902: 3900: 3894: 3893: 3888: 3886: 3885: 3878: 3871: 3863: 3857: 3856: 3851: 3843: 3836: 3835:External links 3833: 3830: 3829: 3803: 3777: 3751: 3725: 3714: 3665: 3629: 3598: 3561: 3526: 3496: 3474: 3448: 3429: 3409: 3390: 3367: 3348: 3328: 3309: 3289: 3244: 3229: 3186: 3149: 3108: 3059: 3016: 2981: 2944: 2919: 2888: 2858: 2827: 2808: 2788: 2748: 2711: 2670: 2629: 2586: 2555: 2524: 2493: 2473:vslvietnam.com 2456: 2407: 2377: 2340: 2303: 2277: 2274:. 8 July 2014. 2263: 2248:. Freyssinet. 2232: 2205: 2174: 2143: 2124: 2104: 2085: 2065: 2005: 1968: 1927: 1892: 1855: 1801: 1792: 1755: 1748: 1719: 1712: 1673: 1666: 1648: 1616: 1594: 1558: 1539: 1499: 1498: 1496: 1493: 1491: 1490: 1485: 1480: 1475: 1470: 1465: 1460: 1455: 1449: 1443: 1441: 1438: 1437: 1436: 1430: 1423: 1405:building codes 1393: 1390: 1389: 1388: 1381: 1374: 1372: 1365: 1358: 1356: 1354:Washington, US 1349: 1342: 1340: 1333: 1326: 1324: 1322:Brevik, Norway 1317: 1310: 1308: 1301: 1294: 1292: 1290:Moscow, Russia 1285: 1278: 1276: 1269: 1262: 1260: 1255:Incheon Bridge 1253: 1246: 1244: 1239:Gateway Bridge 1237: 1230: 1192:Incheon Bridge 1188:Gateway Bridge 1179: 1176: 1162: 1159: 1153: 1150: 1140: 1137: 1097: 1094: 1092: 1089: 1088: 1087: 1077: 1070: 1068: 1058: 1051: 1049: 1039: 1032: 1030: 1020: 1013: 1011: 1001: 994: 992: 982: 975: 973: 964: 957: 955: 948: 941: 939: 929: 922: 872: 871: 865: 864:"cycle-times". 859: 854: 840: 837: 831: 828: 827: 826: 817: 811: 806: 802:de-icing salts 793: 780: 771: 760:concrete cover 750: 729: 728: 723: 705: 699: 677: 674: 673: 672: 656: 652: 649:concrete cover 645: 638: 633:Improved site 631: 622:Ability to be 616: 615: 611: 600: 597:yield strength 577: 561: 558: 545: 544: 541: 505: 504: 495: 494: 493: 484: 483: 482: 481: 480: 478: 475: 406: 403: 320: 317: 241:prefabrication 219:tension forces 198: 195: 171:pre-tensioning 136:concrete slabs 134:, residential 112:serviceability 108:tension forces 59: 58: 55: 52: 49: 46: 43: 39: 26: 24: 14: 13: 10: 9: 6: 4: 3: 2: 4548: 4537: 4534: 4532: 4529: 4527: 4524: 4522: 4519: 4518: 4516: 4509: 4499: 4491: 4490: 4487: 4481: 4478: 4477: 4475: 4471: 4465: 4462: 4460: 4457: 4455: 4452: 4450: 4447: 4446: 4444: 4440: 4434: 4431: 4429: 4426: 4424: 4421: 4419: 4416: 4414: 4411: 4409: 4406: 4404: 4401: 4400: 4398: 4396:Organizations 4394: 4388: 4385: 4383: 4380: 4378: 4375: 4373: 4370: 4368: 4365: 4361: 4360:slab on grade 4358: 4356: 4353: 4351: 4348: 4346: 4343: 4342: 4341: 4338: 4337: 4335: 4331: 4323: 4320: 4318: 4315: 4314: 4312: 4310: 4307: 4305: 4302: 4300: 4297: 4295: 4292: 4290: 4289:Self-leveling 4287: 4285: 4282: 4280: 4277: 4275: 4272: 4270: 4267: 4265: 4262: 4260: 4257: 4255: 4252: 4250: 4247: 4245: 4242: 4240: 4237: 4235: 4232: 4230: 4227: 4225: 4222: 4220: 4217: 4215: 4212: 4211: 4209: 4207: 4203: 4197: 4194: 4192: 4189: 4187: 4184: 4182: 4179: 4177: 4174: 4172: 4169: 4167: 4164: 4163: 4161: 4157: 4151: 4148: 4146: 4143: 4141: 4138: 4136: 4133: 4131: 4128: 4126: 4123: 4121: 4118: 4116: 4113: 4111: 4108: 4106: 4103: 4101: 4098: 4096: 4093: 4091: 4090:Cast-in-place 4088: 4086: 4083: 4082: 4080: 4076: 4070: 4067: 4065: 4062: 4060: 4057: 4055: 4052: 4050: 4047: 4045: 4042: 4040: 4037: 4035: 4032: 4030: 4027: 4025: 4022: 4021: 4019: 4017: 4013: 4007: 4004: 4002: 3999: 3997: 3994: 3992: 3989: 3987: 3986:Reinforcement 3984: 3982: 3979: 3977: 3974: 3972: 3969: 3965: 3962: 3960: 3957: 3955: 3952: 3950: 3947: 3946: 3945: 3942: 3941: 3939: 3937: 3933: 3927: 3924: 3922: 3919: 3917: 3914: 3912: 3909: 3907: 3904: 3903: 3901: 3899: 3895: 3891: 3884: 3879: 3877: 3872: 3870: 3865: 3864: 3861: 3855: 3852: 3850: 3847: 3844: 3842: 3839: 3838: 3834: 3817: 3813: 3807: 3804: 3791: 3787: 3781: 3778: 3765: 3761: 3755: 3752: 3739: 3735: 3729: 3726: 3723: 3718: 3715: 3699: 3695: 3691: 3687: 3683: 3676: 3669: 3666: 3650: 3646: 3639: 3633: 3630: 3617: 3613: 3609: 3602: 3599: 3583: 3579: 3572: 3565: 3562: 3546: 3539: 3538: 3530: 3527: 3514: 3510: 3506: 3500: 3497: 3481: 3477: 3475:0-07-063444-0 3471: 3464: 3463: 3455: 3453: 3449: 3436: 3432: 3430:0-471-53915-5 3426: 3422: 3421: 3413: 3410: 3397: 3393: 3387: 3383: 3382: 3374: 3372: 3368: 3355: 3351: 3345: 3341: 3340: 3332: 3329: 3316: 3312: 3306: 3302: 3301: 3293: 3290: 3274: 3270: 3266: 3262: 3255: 3248: 3245: 3240: 3233: 3230: 3217: 3213: 3209: 3205: 3201: 3197: 3190: 3187: 3171: 3167: 3160: 3153: 3150: 3144: 3139: 3135: 3131: 3127: 3123: 3119: 3112: 3109: 3093: 3089: 3085: 3081: 3077: 3070: 3063: 3060: 3047: 3043: 3039: 3035: 3031: 3027: 3020: 3017: 3001: 2994: 2993: 2985: 2982: 2966: 2962: 2955: 2948: 2945: 2933: 2929: 2923: 2920: 2908: 2907: 2902: 2898: 2892: 2889: 2876: 2872: 2868: 2862: 2859: 2846: 2842: 2838: 2831: 2828: 2815: 2811: 2805: 2801: 2800: 2792: 2789: 2773: 2769: 2762: 2758: 2752: 2749: 2733: 2729: 2728:CTBUH Journal 2722: 2715: 2712: 2696: 2692: 2688: 2681: 2674: 2671: 2655: 2651: 2647: 2640: 2633: 2630: 2617: 2613: 2609: 2605: 2601: 2597: 2590: 2587: 2574: 2570: 2566: 2559: 2556: 2543: 2539: 2535: 2528: 2525: 2512: 2508: 2504: 2497: 2494: 2478: 2474: 2467: 2460: 2457: 2441: 2437: 2433: 2430:(3): 84–111. 2429: 2425: 2418: 2411: 2408: 2395: 2391: 2387: 2381: 2378: 2362: 2358: 2351: 2344: 2341: 2325: 2321: 2314: 2307: 2304: 2291: 2287: 2281: 2278: 2273: 2267: 2264: 2251: 2247: 2243: 2236: 2233: 2220: 2216: 2209: 2206: 2193: 2189: 2185: 2178: 2175: 2162: 2158: 2154: 2147: 2144: 2131: 2127: 2121: 2117: 2116: 2108: 2105: 2092: 2088: 2082: 2078: 2077: 2069: 2066: 2050: 2046: 2042: 2038: 2034: 2030: 2026: 2019: 2012: 2010: 2006: 1990: 1986: 1979: 1972: 1969: 1953: 1949: 1945: 1938: 1931: 1928: 1915: 1911: 1907: 1903: 1896: 1893: 1877: 1873: 1866: 1859: 1856: 1840: 1836: 1829: 1822: 1820: 1818: 1816: 1814: 1812: 1810: 1808: 1806: 1802: 1796: 1793: 1777: 1773: 1766: 1759: 1756: 1751: 1749:0-9778752-0-2 1745: 1741: 1736: 1735: 1726: 1724: 1720: 1715: 1713:0-582-71225-4 1709: 1705: 1698: 1696: 1694: 1692: 1690: 1688: 1686: 1684: 1682: 1680: 1678: 1674: 1669: 1667:0-582-80247-4 1663: 1659: 1652: 1649: 1635: 1631: 1627: 1620: 1617: 1601: 1597: 1591: 1584: 1583: 1575: 1573: 1571: 1569: 1567: 1565: 1563: 1559: 1546: 1542: 1540:0-471-01898-8 1536: 1532: 1531: 1523: 1521: 1519: 1517: 1515: 1513: 1511: 1509: 1507: 1505: 1501: 1494: 1489: 1486: 1484: 1481: 1479: 1476: 1474: 1471: 1469: 1466: 1464: 1461: 1459: 1456: 1453: 1450: 1448: 1445: 1444: 1439: 1434: 1431: 1428: 1424: 1421: 1417: 1413: 1412: 1411: 1408: 1406: 1401: 1399: 1391: 1384: 1378: 1373: 1368: 1362: 1357: 1352: 1346: 1341: 1336: 1330: 1325: 1320: 1314: 1309: 1304: 1298: 1293: 1288: 1282: 1277: 1272: 1266: 1261: 1256: 1250: 1245: 1240: 1234: 1229: 1227: 1225: 1221: 1217: 1213: 1209: 1205: 1201: 1197: 1193: 1189: 1184: 1177: 1175: 1173: 1167: 1160: 1158: 1151: 1149: 1145: 1138: 1136: 1134: 1130: 1126: 1123: 1119: 1114: 1112: 1108: 1104: 1095: 1090: 1085: 1084:18° lean 2010 1080: 1074: 1069: 1066: 1061: 1060:Torre Espacio 1055: 1050: 1047: 1042: 1036: 1031: 1028: 1023: 1017: 1012: 1009: 1004: 998: 993: 990: 985: 979: 974: 971: 967: 961: 956: 953: 945: 940: 937: 932: 926: 921: 919: 917: 913: 909: 908:Torre Espacio 906:, Melbourne; 905: 901: 898:, Hong Kong; 897: 893: 889: 885: 881: 877: 866: 860: 855: 850: 849: 848: 845: 838: 836: 829: 822: 818: 815: 812: 807: 803: 797: 794: 791: 785: 781: 775: 772: 769: 765: 761: 757: 751: 748: 744: 740: 734: 733: 732: 724: 721: 716: 712: 706: 700: 697: 691: 690: 689: 686: 682: 675: 670: 666: 662: 657: 653: 650: 646: 643: 639: 636: 632: 629: 625: 624:prefabricated 621: 620: 619: 612: 609: 605: 601: 598: 594: 590: 586: 582: 578: 575: 571: 570: 569: 566: 559: 557: 554: 549: 542: 539: 538: 537: 534: 532: 528: 524: 520: 516: 499: 488: 476: 474: 472: 468: 464: 459: 457: 453: 449: 445: 440: 435: 433: 429: 425: 422: 421: 411: 404: 402: 400: 396: 391: 389: 385: 381: 377: 373: 369: 360: 356: 354: 350: 344: 342: 333: 325: 318: 316: 314: 311:and concrete 310: 306: 302: 298: 294: 290: 285: 283: 279: 274: 265: 260: 256: 254: 250: 245: 242: 235: 230: 226: 224: 220: 216: 212: 203: 196: 194: 192: 188: 184: 180: 176: 172: 167: 165: 161: 157: 153: 149: 145: 141: 137: 133: 129: 125: 120: 117: 113: 109: 105: 101: 97: 93: 89: 86:, multi-wire 85: 81: 76: 74: 70: 67:is a form of 66: 56: 53: 50: 47: 44: 41: 40: 37: 32: 19: 4508: 4372:Step barrier 4333:Applications 4263: 4244:Nanoconcrete 4130:Power trowel 4115:Power screed 4105:Slip forming 4078:Construction 3822:12 September 3820:. Retrieved 3806: 3796:12 September 3794:. Retrieved 3780: 3770:12 September 3768:. Retrieved 3754: 3744:12 September 3742:. Retrieved 3728: 3717: 3705:. Retrieved 3688:(4): 18–43. 3685: 3681: 3668: 3656:. Retrieved 3644: 3632: 3620:. Retrieved 3611: 3601: 3589:. Retrieved 3577: 3564: 3552:. Retrieved 3536: 3529: 3517:. Retrieved 3508: 3499: 3487:. Retrieved 3461: 3439:. Retrieved 3419: 3412: 3400:. Retrieved 3380: 3358:. Retrieved 3338: 3331: 3319:. Retrieved 3299: 3292: 3280:. Retrieved 3260: 3247: 3238: 3232: 3220:. Retrieved 3203: 3199: 3189: 3177:. Retrieved 3165: 3152: 3125: 3121: 3111: 3099:. Retrieved 3079: 3075: 3062: 3050:. Retrieved 3046:the original 3036:(5): 52–80. 3033: 3029: 3019: 3007:. Retrieved 2991: 2984: 2972:. Retrieved 2960: 2947: 2935:. Retrieved 2931: 2922: 2910:. Retrieved 2904: 2891: 2879:. Retrieved 2875:the original 2861: 2849:. Retrieved 2840: 2830: 2818:. Retrieved 2798: 2791: 2779:. Retrieved 2767: 2751: 2739:. Retrieved 2727: 2714: 2702:. Retrieved 2690: 2686: 2673: 2661:. Retrieved 2649: 2645: 2632: 2620:. Retrieved 2603: 2599: 2589: 2577:. Retrieved 2568: 2558: 2546:. Retrieved 2538:www.cmecs.co 2537: 2527: 2515:. Retrieved 2507:www.arup.com 2506: 2496: 2484:. Retrieved 2472: 2459: 2447:. Retrieved 2427: 2423: 2410: 2398:. Retrieved 2389: 2380: 2368:. Retrieved 2356: 2343: 2331:. Retrieved 2320:ashet.org.au 2319: 2306: 2294:. Retrieved 2280: 2266: 2254:. Retrieved 2245: 2240:Freyssinet. 2235: 2223:. Retrieved 2208: 2196:. Retrieved 2192:the original 2188:www.nace.org 2187: 2177: 2165:. Retrieved 2156: 2146: 2134:. Retrieved 2114: 2107: 2095:. Retrieved 2075: 2068: 2056:. Retrieved 2031:(5): 34–55. 2028: 2024: 1996:. Retrieved 1984: 1971: 1959:. Retrieved 1947: 1943: 1930: 1918:. Retrieved 1909: 1905: 1895: 1883:. Retrieved 1871: 1858: 1846:. Retrieved 1834: 1795: 1783:. Retrieved 1771: 1758: 1733: 1703: 1657: 1651: 1638:. Retrieved 1629: 1619: 1607:. Retrieved 1600:the original 1581: 1549:. Retrieved 1529: 1454:AG (Dywidag) 1425:US Standard 1409: 1402: 1395: 1335:Roseires Dam 1319:Norcem silos 1271:Autobahn A73 1208:Cement silos 1196:Roseires Dam 1185: 1181: 1168: 1164: 1155: 1146: 1142: 1121: 1115: 1103:Adam Viaduct 1099: 1083: 1079:Capital Gate 1064: 1045: 1041:Eureka Tower 1026: 1007: 988: 969: 951: 935: 916:Capital Gate 904:Eureka Tower 873: 846: 842: 833: 830:Applications 762:in the side 746: 730: 720:polyethylene 687: 683: 679: 635:productivity 617: 567: 563: 550: 546: 535: 521:-inhibiting 515:longitudinal 512: 460: 444:polyethylene 438: 436: 418: 416: 392: 387: 379: 375: 365: 345: 340: 338: 286: 272: 269: 266:being placed 253:surface area 246: 238: 210: 208: 190: 186: 183:multi-strand 182: 178: 168: 150:structures, 121: 100:aramid fiber 96:carbon fiber 77: 64: 63: 4350:hollow-core 4309:Waste light 4304:Translucent 4264:Prestressed 4191:Segregation 4176:Degradation 4064:Cover meter 4001:Silica fume 3936:Composition 3707:6 September 3682:PCI Journal 3658:6 September 3622:2 September 3614:. DYWIDAG. 3591:2 September 3554:5 September 3519:5 September 3489:5 September 3441:5 September 3402:5 September 3360:5 September 3321:5 September 3282:5 September 3261:PCI Journal 3222:2 September 3179:2 September 3128:(1): 1–13. 3101:2 September 3076:PCI Journal 3052:7 September 3030:PCI Journal 3009:7 September 2974:2 September 2937:22 February 2841:Railway Age 2820:2 September 2781:5 September 2741:2 September 2704:2 September 2663:2 September 2622:1 September 2579:1 September 2548:1 September 2517:2 September 2486:1 September 2449:2 September 2424:PCI Journal 2400:1 September 2370:1 September 2333:1 September 2256:7 September 2198:7 September 2167:7 September 2136:7 September 2097:7 September 2058:7 September 2025:PCI Journal 1998:7 September 1985:PCI Journal 1944:PTI Journal 1351:Wanapum Dam 1258:South Korea 1200:Wanapum Dam 1111:box girders 1081:, Abu Dhabi 1043:, Melbourne 1003:World Tower 933:, Hong Kong 890:, Toronto; 880:World Tower 715:stay-cables 669:deformation 655:in-service. 642:flexibility 349:split-wedge 309:water tanks 293:floor slabs 173:to include 4515:Categories 4449:Eurocode 2 4387:Structures 4274:Reinforced 4234:Lunarcrete 4214:AstroCrete 4171:Durability 4166:Properties 4044:Slump test 4016:Production 4006:Metakaolin 3168:. IEAust. 2390:cclint.com 2225:3 December 1495:References 1418:-2:2005 – 987:Hong Kong 886:, London; 882:, Sydney; 870:materials. 711:monitoring 579:Increased 531:tensioning 525:, usually 448:galvanised 368:galvanised 179:monostrand 80:tensioning 73:compressed 4480:Hempcrete 4442:Standards 4269:Ready-mix 4186:Recycling 3981:Aggregate 3964:Rosendale 3606:DYWIDAG. 3263:: 64–85. 3082:: 76–88. 2912:25 August 2881:25 August 2851:25 August 2693:: 37–41. 2612:0439-5689 2540:. CMECS. 2357:ctbuh.org 2322:. ASHET. 2159:. CARES. 2045:109223938 1987:: 62–73. 1961:25 August 1920:22 August 1885:25 August 1848:23 August 1785:19 August 1640:25 August 1609:26 August 1551:24 August 1473:PC strand 1367:LNG tanks 1204:LNG tanks 1198:, Sudan; 1065:230m 2008 1046:297m 2006 1027:335m 2016 1008:230m 2004 952:290m 2016 936:484m 2010 931:ICC tower 902:, Dubai; 823:, England 821:Liverpool 768:corrosion 764:abutments 743:Corrosion 661:ductility 628:lead time 553:extrusion 519:corrosion 507:recesses. 471:corrosion 428:corrosion 395:curvature 303:, driven 297:balconies 273:deviators 4473:See also 4464:EN 10080 4459:EN 206-1 4454:EN 197-1 4313:Aerated 4254:Polished 4249:Pervious 4224:Filigree 4120:Finisher 4095:Formwork 3959:Portland 3890:Concrete 3816:Archived 3790:Archived 3764:Archived 3738:Archived 3698:Archived 3649:Archived 3616:Archived 3582:Archived 3545:Archived 3513:Archived 3480:Archived 3435:Archived 3396:Archived 3354:Archived 3315:Archived 3273:Archived 3216:Archived 3170:Archived 3092:Archived 3000:Archived 2965:Archived 2845:Archived 2814:Archived 2772:Archived 2759:(2007). 2732:Archived 2695:Archived 2687:Connaect 2654:Archived 2646:Connaect 2616:Archived 2573:Archived 2542:Archived 2511:Archived 2509:. ARUP. 2477:Archived 2440:Archived 2394:Archived 2361:Archived 2324:Archived 2290:Archived 2250:Archived 2219:Archived 2161:Archived 2130:Archived 2091:Archived 2049:Archived 1989:Archived 1952:Archived 1914:Archived 1876:Archived 1874:(2–01). 1839:Archived 1776:Archived 1772:MaineDOT 1634:Archived 1545:Archived 1440:See also 1420:Eurocode 1303:CN Tower 1220:CN Tower 1062:, Madrid 1005:, Sydney 888:CN Tower 790:chemical 779:in 1996. 665:catenary 647:Reduced 604:cracking 463:formwork 452:building 424:grouting 399:reaction 388:unbonded 372:grouting 353:threaded 249:adhesion 234:formwork 69:concrete 4423:Nanocem 4382:Columns 4259:Polymer 4159:Science 4125:Grinder 4085:Precast 3991:Fly ash 3898:History 3130:Bibcode 2802:. ICE. 2475:. VSL. 2392:. CCL. 2296:8 April 2151:CARES. 1588:. FIB. 1416:EN 1992 1122:in-situ 1118:girders 1096:Bridges 1024:, Dubai 747:in-situ 704:tendon. 593:tensile 589:strains 585:flexure 527:lithium 439:bundles 420:in situ 384:greased 301:lintels 191:outside 88:strands 4345:waffle 4294:Sulfur 4150:Tremie 4145:Sealer 4110:Screed 4054:Curing 3944:Cement 3472:  3427:  3388:  3346:  3307:  2806:  2730:(11). 2652:: 51. 2610:  2501:ARUP. 2182:NACE. 2122:  2083:  2043:  1912:(19). 1746:  1710:  1664:  1592:  1537:  1427:ACI318 776:, 1992 523:grease 376:bonded 187:within 144:bridge 4377:Roads 4299:Tabby 4206:Types 4140:Float 4069:Rebar 4024:Plant 3971:Water 3701:(PDF) 3678:(PDF) 3652:(PDF) 3641:(PDF) 3585:(PDF) 3574:(PDF) 3548:(PDF) 3541:(PDF) 3483:(PDF) 3466:(PDF) 3276:(PDF) 3257:(PDF) 3173:(PDF) 3162:(PDF) 3095:(PDF) 3072:(PDF) 3003:(PDF) 2996:(PDF) 2968:(PDF) 2957:(PDF) 2775:(PDF) 2770:: 7. 2764:(PDF) 2735:(PDF) 2724:(PDF) 2698:(PDF) 2683:(PDF) 2657:(PDF) 2642:(PDF) 2480:(PDF) 2469:(PDF) 2464:VSL. 2443:(PDF) 2420:(PDF) 2364:(PDF) 2353:(PDF) 2327:(PDF) 2316:(PDF) 2052:(PDF) 2041:S2CID 2021:(PDF) 1992:(PDF) 1981:(PDF) 1955:(PDF) 1940:(PDF) 1879:(PDF) 1868:(PDF) 1842:(PDF) 1831:(PDF) 1779:(PDF) 1768:(PDF) 1742:–54. 1603:(PDF) 1586:(PDF) 805:2015. 614:ones. 608:rebar 574:grout 446:) or 341:after 313:pipes 305:piles 289:beams 215:cures 211:prior 156:tanks 152:silos 124:spans 84:wires 4340:Slab 4322:RAAC 4239:Mass 4229:Foam 4135:Pump 3824:2016 3798:2016 3772:2016 3746:2016 3709:2016 3660:2016 3624:2016 3593:2016 3556:2016 3521:2016 3491:2016 3470:ISBN 3443:2016 3425:ISBN 3404:2016 3386:ISBN 3362:2016 3344:ISBN 3323:2016 3305:ISBN 3284:2016 3224:2016 3181:2016 3103:2016 3054:2016 3011:2016 2976:2016 2939:2024 2914:2018 2883:2018 2853:2018 2822:2016 2804:ISBN 2783:2016 2743:2016 2706:2016 2665:2016 2624:2016 2608:ISSN 2581:2016 2550:2016 2519:2016 2488:2016 2451:2016 2402:2016 2372:2016 2335:2016 2298:2021 2258:2016 2227:2012 2200:2016 2169:2016 2138:2016 2120:ISBN 2099:2016 2081:ISBN 2060:2016 2000:2016 1963:2016 1922:2016 1887:2016 1850:2016 1787:2016 1744:ISBN 1708:ISBN 1662:ISBN 1642:2016 1611:2016 1590:ISBN 1553:2016 1535:ISBN 1139:Dams 1127:and 989:2013 970:1973 894:and 878:and 162:and 154:and 146:and 36:beam 4317:AAC 3690:doi 3265:doi 3208:doi 3138:doi 3084:doi 3038:doi 2432:doi 2033:doi 583:in 456:dam 148:dam 98:or 4517:: 3814:. 3788:. 3762:. 3736:. 3696:. 3686:10 3684:. 3680:. 3643:. 3610:. 3580:. 3576:. 3507:. 3478:. 3451:^ 3433:. 3394:. 3370:^ 3352:. 3313:. 3271:. 3259:. 3214:. 3204:23 3202:. 3198:. 3164:. 3136:. 3124:. 3120:. 3090:. 3080:10 3078:. 3074:. 3034:32 3032:. 3028:. 2959:. 2930:. 2903:. 2899:. 2869:. 2839:. 2812:. 2766:. 2726:. 2691:10 2689:. 2685:. 2650:10 2648:. 2644:. 2614:. 2604:59 2602:. 2598:. 2567:. 2536:. 2505:. 2471:. 2438:. 2428:21 2426:. 2422:. 2388:. 2355:. 2318:. 2288:. 2244:. 2186:. 2155:. 2128:. 2089:. 2047:. 2039:. 2029:37 2027:. 2023:. 2008:^ 1983:. 1946:. 1942:. 1910:87 1908:. 1904:. 1870:. 1833:. 1804:^ 1774:. 1770:. 1722:^ 1676:^ 1628:. 1561:^ 1543:. 1503:^ 1135:. 1107:UK 473:. 380:de 315:. 307:, 299:, 291:, 225:. 166:. 158:, 142:, 138:, 94:, 3882:e 3875:t 3868:v 3826:. 3800:. 3774:. 3748:. 3711:. 3692:: 3662:. 3626:. 3595:. 3558:. 3523:. 3493:. 3445:. 3406:. 3364:. 3325:. 3286:. 3267:: 3226:. 3210:: 3183:. 3146:. 3140:: 3132:: 3126:7 3105:. 3086:: 3056:. 3040:: 3013:. 2978:. 2941:. 2916:. 2885:. 2855:. 2824:. 2785:. 2745:. 2708:. 2667:. 2626:. 2583:. 2552:. 2521:. 2490:. 2453:. 2434:: 2404:. 2374:. 2337:. 2300:. 2260:. 2229:. 2202:. 2171:. 2140:. 2101:. 2062:. 2035:: 2002:. 1965:. 1948:8 1924:. 1889:. 1852:. 1789:. 1752:. 1740:5 1716:. 1670:. 1644:. 1613:. 1555:. 20:)

Index

Post-tensioned concrete
six figures showing forces and resulting deflection of beam
beam
concrete
compressed
tensioning
wires
strands
high-tensile steels
carbon fiber
aramid fiber
compression forces
tension forces
serviceability
reinforced concrete
spans
reinforced concrete
high-rise buildings
concrete slabs
foundation systems
bridge
dam
silos
tanks
industrial pavements
nuclear containment structures
pre-tensioning
post-tensioning
three figures; darker green slab is pre-tensioned in lighter green casting bed
cures

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.