1846:," was studied to meet the mobility needs of the city of Palermo; commissioned by Italconsult S.p.A. and Groupe Scetauroute, it underwent a revision in 1998. Responsible for the revision and executive design was engineer Vinicio Brandani. The system included three lines: one from the Roccella industrial area to the Central Station, one from the Borgo Nuovo district to the Notarbartolo railway station, and one from the San Giovanni Apostolo district (former Cep) to the Notarbartolo station, passing through Sicilian Region Avenue to the Corso Calatafimi interchange. The project included numerous ancillary works such as three pedestrian overpasses along the Sicilian Region avenue between Einstein Square and Corso Calatafimi; roadway improvements; two rolling stock depots with adjoining workshops, in the Roccella industrial area and on Via Castellana; and the routes on protected lanes entirely separate from the roadways. The planned in-service trains: 17 bi-directional 250-seat trainsets (of which 62 seated), with 6 accesses on each side and equipped with information systems with screens and internal audio. Commercial speed was expected to be about 20 km/h. The overall development of the system of just over 15 km, with 40 stops (almost every 400 meters) had a total cost of about 192 million euros. It was planned to be completed within 5 years from the start of construction (October 2006) with the three lines completed approximately 44, 48, and 52 months from the start date. On 30 December 2005 the contract was awarded to a temporary association of companies consisting of the Turin-based "Sis" consortium, the Rome-based firms "Bombardier Transportation Italy" and "Mosco & Associati," Messina-based "Edil Scavi," Milan-based "Amec Spie Rail," and the Berlin-based, "Seib Ingenieur-Consult," IngenieurbĂĽro Wosnitza e Knappe" and "ETC Transport Consultants." The construction sites opened in October 2006 and began work in June 2007.
378:. Such a route was expected to drastically cut down the connection time between the two metropolitan cities but triggered controversy from Enna and Caltanissetta institutions that preferred a line that would penetrate as far as both cities by retracing a merely modernized version of the current route. The two cities at the time of the railroad's construction were joined mainly because of the richness of their sulfur basins; following the abandonment of ore mining since the late 1960s, rail freight became marginal, both because of market crises and, since the late 1980s, as a result of the FS's decision to abandon small batch transport in favor of full train. Diverting the route planned for the A.V. line with stops in the two cities, however, would totally nullify its construction given that stops below 100 km would drastically lower the commercial speed.
1079:. Variants have been proposed over the years that, while crossing the territories of central Sicily, would involve increases in travel time and require less financial resources. The "institutional contract" of 28 February 2013, partly accepted what had previously been proposed, elaborating on the contested aspects regarding the central section of the line, on which a decision will still have to be made in a rather short time frame; regarding this section, the point of detachment from the old route has been modified, taking it from Catenanuova to Raddusa/Agira. The contract seems to have laid the groundwork for a start on the modernization of the important route, so much so that the government the following year earmarked more than 800 million for the Palermo-Messina-Catania rail axis to carry out part of the work.
740:
1832:
284:
Caltagirone from the Etnean capital was also completed, however, it was not until 1931 that this locality was connected to the station of
Dittaino, near Enna, (but on a narrow gauge) and it was necessary to wait a good half century, that is, until 1979, for the continuation of the line to Gela to come into operation, which would probably never have been connected to the Catania-Caltagirone line without the emergence of the Gela petrochemical hub. Instead, the direct connection between Caltagirone and Canicattì, which would have shortened the distance between Catania and Agrigento, remained unfinished, although much of the work had already been completed.
1440:
916:, clearly visible to those who travel the network of state and provincial roads where they cause severe unevenness of the road surface to be traveled at walking pace. On the railroad network, whose road surface is, in many cases, still that of the last century with embankments in poor condition and never resolved ballast drainage problems, such events often cause traffic disruptions or in less severe cases slowdowns that disrupt the regularity of train travel. (The heavy costs of ongoing rehabilitation work, eventually globally outweighing those of any modernization, contributed to the decision to close the extensive FS narrow-gauge network.)
276:
1094:
Trapani - Palermo via Milo sections, closed since 8 May 2011 and 25 February 2013 respectively, for a total of more than 130 km in total, are unusable due to structural failure or landslides. Added to this is the fact that many areas, especially inland, lack rail links altogether, despite the precarious condition of the road system and the tourism potential they express: reference can usefully be made to the southern coast of
Agrigento and the inland areas of the province of Enna, which were traversed by narrow-gauge railways that were closed in the second half of the 20th century.
1824:
98:
1494:, it is a double-track section, with considerable commuter and tourist traffic between the air terminal and the Sicilian capital. The line operates from 4:45 a.m. to 10 p.m. in the direction of the Airport and from 5:30 a.m. to 11 p.m. in the direction of the Central Station every day of the week, with reduced number of runs on holidays. The frequency is one run every 30 minutes in the urban area from Central Station to Tommaso Natale and every 60 minutes for the Trinacria Express service to the airport. These stations are:
1647:
participation in the ministry's notice on "Submission of applications for access to resources earmarked for Mass Rapid
Transit with Fixed Installations," with a deadline of 31 December 2019, in order to obtain at least funding for the first functional Oreto-Notarbartolo lot, about 6 kilometers long with 8 stations, whose costs are around 850 million euros. On 6 August 2020 it was announced that the City of Palermo had submitted the funding application for the design adjustment of the work, with a total amount of €300000.
1657:
1718:
1745:, the so-called Metroferrovia came into operation on 15 June 2009, to connect the city center to the southern suburbs with a dedicated train service, making use of the double-track route of the Messina-Catania railway, for a total of 16 km in the urban section of Messina; 11 stops were established. The service is operated by RFI through a service contract and uses a Minuetto electric train shuttling round trips daily. The service was suspended from 1 October 2009 due to the
845:. However, plans dated back to the 1920s and some of the work had already been done before the war. Many works executed or started were finally abandoned in the 1950s such as the continuation towards Palermo of the Regalbuto - Nicosia section or the Canicattì - Caltagirone. At present, the regional network would need a profound redesign of the routes according to new mobility needs, and the connection with, and between, airports and intermodal freight transport.
403:
268:
85:
127:
Caltanissetta-Licata (for the embarkation at the port of Licata from that of
Caltanissetta). A short time later the Institute for the Promotion of Agriculture, Arts and Crafts in Palermo announced a competition for the study of a rail network of Sicily; in this context a project that set as a priority the construction of the Palermo-Girgenti railroad with a branch line to Caltanissetta and Licata arose. With the proclamation of
1878:
614:
973:
399:
times occurred as a result of the so-called stately decree. In 2008, the network was paradoxically configured to resemble that of the early 20th century, with slightly less extension, but in 2010 additional rail routes were suspended and uncertainty remains about the fate of important lines such as the
Syracuse-Gela-Canicattì and the Alcamo-Castelvetrano-Trapani.
885:
731:, developed as an extension and complement to two main lines: the north-south transversal Palermo-Corleone-San Carlo and the longitudinal coastal Castelvetrano-Porto Empedocle. Most of the others stood at intermediate or terminal stations of the first two. Exceptions were the lines in the central hinterland that arose in support of the Palermo-Catania.
299:, which instead remained without railroads. By the time the picturesque Catania-Motta Sant'Anastasia-Regalbuto railway was finally completed in the 1950s, it was too late for the purposes for which it had been designed, but nevertheless it was intensively used until the 1970s to transport oranges from Leto, Mandarano, Carcaci (in the territory of
589:
entrance of
Catania; the Acireale section is, since the 1980s, almost entirely in tunnels following the construction of the double track. The section of the line through Catania is currently being buried with work scheduled for completion in 2016. From Catania's Acquicella station it runs alongside the double-track
908:
As of 22 November 2009, between
Messina and Patti on the Palermo-Messina, speeds of up to 220 km/h can be reached, while 150 km/h maximum speeds remain attainable only on two short sections of the Messina-Catania and near Palermo. On the rest of the lines, the maximum speeds that can be reached, only
772:
of lines since the 1950s has not resulted in the design and construction of new tracks, leaving the areas of central and southwestern Sicily without rail connections: the southern area of the province of Enna, of great tourist-archaeological interest, and the coast from
Castelvetrano to Agrigento and
771:
The
Sicilian railways, while still quite extensive are, except for a few newly built sections near the areas of the three largest Sicilian cities, generally of obsolete design and layout and therefore inadequate to the changing economic needs of the Sicilian territory. The closure of more than 700 km
588:
it passes through densely inhabited areas and alternates between sections in the open and in tunnels; the line penetrates further, continuing on Giarre (where there is a connection with the FCE) and
Acireale becoming double-track again shortly after the station of Fiumefreddo di Sicilia and up to the
531:
The Ionian is the second major line in the region. It is 182 km long from central Messina to Syracuse. It was the first line in the region to be built in its entirety between 1867 and 1871, with the present layout except for the modern double-track variant sections between Fiumefreddo and Catania and
1705:
The Catania rail link is being built, of which the urban section between Cannizzaro, Ognina and Catania Centrale is already active, while the one between Catania and Bicocca (whose station will be underground) is still in the executive design phase, as is the entire RFI track of the affected section
1062:
to the Peloritan capital completed, construction has begun on the doubling of the section between Fiumetorto and CefalĂą Ogliastrillo. The intermediate Patti-Castelbuono section has remained single-track, but there is a feasibility study as well as a preliminary project for doubling between Patti and
621:
The central Sicilian backbone that began in 1863 with the Palermo-Bagheria was completed in 1885, with the opening of the Marianopoli tunnel that allowed direct trains between Palermo and Catania to take the so-called Vallelunga line, avoiding the long round trip of the one, opened in 1881, that ran
1093:
Moreover, the lines cross areas that are geologically unstable, which undermine the delicate rail and road structure of Sicily, further penalizing rail transport, given the long times and high costs required to restore the damaged sections: suffice it to say that to date, the Caltagirone - Gela and
414:
and to Trapani is attached westward; and the Ionian, between Messina, Catania and Syracuse; the central Sicilian, in the interior, between Palermo and Catania via Caltanissetta and Enna completes the picture. The inland transversal between Palermo and Agrigento is being upgraded and speeded up, and
398:
when, especially with the so-called Scalfaro decree, the disposal of some lines that were deemed too costly in terms of the ratio of revenue to yield began despite the fact that they served, sometimes as the only link, the local populations of inland areas. A second wave of disposals in more recent
81:, but the routes have, by and large, remained original and circuitous, and modernization works during the 20th century have been very limited. It was only in the first decade of the 21st century that route modifications were planned and in some cases initiated to adapt them to transportation needs.
1605:
Rail link: the construction site was opened on 22 February 2008 with the intention of doubling the track, burying part of the line and creating 9 new stops: Roccella, Brancaccio residential, Guadagna, Palazzo di Giustizia, Lolli, Lazio-Restivo, Belgio, La Malfa, Sferracavallo the completion of the
718:
and on RFI's procurement portal for a base bid amount of 220 million euros. The tender is expected to be concluded by the end of 2017. The intervention consists of the construction of the double-track line between Bicocca and Catenanuova (about 37 km); part of the route runs alongside the existing
663:
when the line was still among the most important in Sicily. After the long Misericordia Tunnel, the line reaches Enna Station, a passenger stop of a certain importance, after which the line descends again toward the Dittaino Valley to the 280 m above sea level of Dittaino Station, which serves the
650:
Trains from Palermo, having arrived at Roccapalumba for the most part go toward Agrigento, while some continue to Caltanissetta and Catania through a long series of sparsely man-made valleys and hills and the long Marianopoli Tunnel that heralds the arrival at the Caltanissetta Xirbi Station. From
992:
were greatly reduced during the first decade of the 2000s. Overall long-distance passenger traffic, which had been intense from the 1960s onward, gradually declined to extremely modest levels. Only commuter traffic around larger urban areas has some consistency. The busiest routes are the coastal
1004:
The most important rail installations, namely those of Palermo, Messina and Catania have suffered a steady decline in long-distance passenger traffic since the last years of the last century. The gradual corporate disengagement of the FS group, which has consistently decreased the supply of rail
462:
before finally reaching Messina. The line slavishly follows the Tyrrhenian coast for most of the route as a result of the difficult topography of the area, in many cases with a steep coastline and overhanging into the sea, without penetrating inland except in a few cases. Doubling has been under
126:
and had undertaken negotiations with Belgian and Dutch investors for the possible establishment of a railway company that would build the routes afferent to the two ports most useful for the purpose, the Palermo-Bagheria (for the embarkation at the port of Palermo of sulfur from Lercara) and the
1089:
Alongside the projects, however, the shortcomings of the island's rail system also remain evident, which appears, especially in its internal lines, to be obsolete and uncompetitive in its infrastructure, forcing convoys to move very often at average speeds below 100 km/h. Most of the lines are,
1646:
and Partanna, for a total of 20.77 km and 23 stations. In the first five years of the 2010s the project seemed to fade away, however in 2017 a resolution of the city council announced the conclusion of the preliminary design process approved by MIT. In May 2019, the municipality announces its
283:
From the capital, at the beginning the first radiating hub of Sicilian railroads, it was not until 1880 that the first sections of the line to Trapani began to open by the Western Sicilian Railway Company, which was joined six years later by the longer Castelvetrano route. In 1892 the line to
1066:
The Palermo-Catania section of the only planned high-capacity line, whose preliminary design dates back to the early 1990s, at the time of the establishment of the Ente FS in the original plans, would have retained the current route as the basis for the Catania-Catenanuova route, albeit with
202:, strongly advocated to attract goods to the port of Aretusa, was, however, quite late compared to the others and classified among the complementary lines to be built only with the contribution of local authorities. This was because the major interest of the mining entrepreneurs was to get
463:
construction for many years with very significant costs given the need for considerable artwork with moving the route further inland. The line, which measures 213 km, is still largely single-track with rather low track speeds for much of the route. Until the 1990s, in order to pass the
695:
The railroad has modest commuter traffic between Enna and Caltanissetta, and between them and Catania, and despite modernizations and the use of modern circulation systems it records low standards of utilization in place, with little supply of passenger trains and few freight trains.
1025:
in Sicily even though there have been widespread, on several occasions, design assumptions by the FS regarding the construction of a high-speed line in Sicily; almost as a continuation of an equivalent HS/HC Battipaglia-Reggio Calabria line framed within the European program of a
483:
in 1955. During the following years the sections near the two cities were doubled and finally with the activation of the Peloritan Tunnel eliminated the push service to heavy trains. In the past the line had an increase in freight traffic to support the industrial activities of
1757:
Between the late nineteenth and early twentieth centuries, a number of extra-urban tramway lines were also built in Sicily to connect the larger cities and the surrounding area; they lost their viability as a result of the development of road transport from the 1930s onward.
1034:
has been largely buried, freeing up large areas on the surface, and was reopened to rail traffic in October 2018, after 3 years since its closure, for its renovation and track doubling, with the construction of new underground stops. This enabled the optimization of the
579:
All categories of trains run on the Ionian line, except for high-speed ones, and at one time also many agency trains of a tourist nature. However, traffic is affected by the presence of the long single-track section in the central part. The line begins double-track from
1795:
Other tramway lines were built for mining transport in central and southwestern Sicily. In the Sicilian hinterland, the Raddusa-Miniera di Sant'Agostino was created, attested at the Raddusa-Agira station of the Catania-Palermo railway intended to serve the numerous
758:
The other line, the Syracuse-Ragusa-Vizzini Railroad, which ran through the Anapo Valley, was closed and dismantled in the late 1950s despite representing, if upgraded, the shortest link between Ragusa and Catania and a valuable means of tourist transportation to
1791:
with a total length of 74 km: the Messina-Granatari-Barcellona Pozzo di Gotto tramway, which ran northward from the Peloritan capital and was inaugurated in 1890, and the Messina-Giampilieri tramway heading south, both promoted by a Belgian-owned company.
687:
and the Enna area (including the important ones of Floristella and Grottacalda) to the embarkation ports. The importance of the line for freight traffic waned until the 1970s following the systematic closure of the mines and especially the opening of the
714:, resulted in the tendering of the doubling and speeding of the Bicocca - Catenanuova lot. The track design calls for a maximum commercial speed of up to 200 km/h. The call for tenders for the executive design and construction work was published in the
654:
The railroad continues to the Villarosa Station, once an important sulfur depot and since 8 December 1995 the site of an interesting Railway Museum, of mining art and rural culture, set up entirely aboard vintage wagons. Then begins the hard climb to
1668:
was inaugurated on 27 June 1999, and went into service on 11 July that year. Initially planned as a landfill of the urban-crossing line of the Circumetnea Railway during the planning process, it was redesigned as a full-fledged metro managed by the
904:
type in place of antiquated rolling stock. Thereafter, however, there has often been only a recycling of rolling stock, much of it from north-central railways, where it was redundant due to the arrival of the latest generation high-speed vehicles.
1055:. Other projects include the joining of the island's rail network with the planned Catania Bicocca Interport and, on the Messina-Siracusa, track doubling between Giampilieri and Fiumefreddo and speeding up the route between Catania and Syracuse.
1576:
The short route consists of a single underground track from Notarbartolo to Federico; the rest is in trenches. The line operates from 6:40 a.m. to 8:40 p.m., weekdays only. The frequency of service is one run every 30 minutes in the urban area.
630:
Xirbi). The construction period of more than 20 years can be explained by the topographical difficulties of the stretches of land crossed, as well as by the length of the line, about 240 km, which passes through the inland provincial capitals,
1481:
From Palermo Centrale to Palazzo Reale Orleans it is above ground and single track, which becomes underground as far as France and then re-emerges outside the city. From here on, it passes through the main centers of the western district,
263:
section of the line was also opened for operation. And two years later, in 1893 the Terranova di Sicilia - Comiso section and the Comiso-Modica, which completed the Syracuse-Licata railway, were inaugurated on June 18 of the same year.
140:(with predominantly French capital); nevertheless, the railways in Sicily were built late and slowly given the gradual insolvency and financial collapse in which the said company soon found itself. Even in the early 1870s, the mayor of
65:
of the region. Many lines were decommissioned and generally dismantled, particularly in the 1960s (but even up to almost the threshold of the 1990s, decommissioning took place), mainly because they were uncompetitive in comparison with
755:, which has shown constant vitality and despite experiencing periods of great difficulty has been moving, since the threshold of the 2000s, toward adaptation to metropolitan and tourist traffic with further network expansion projects.
837:, and between Targia and Syracuse. Modernizations of the nodes around the island's two largest cities have been built slowly and still seem far from being completed. The last railway line to be built and completed, in 1979, was the
1897:
The streetcars make 18 stops and make it possible to reach the Polyclinic, the southern bus terminus (at the Gazzi end of the line), and the cemetery; they run through the city center along San Martino Avenue and Cairoli Square.
1889:
came into operation in Messina on 3 April 2003 after a long gestation and construction period and more than half a century after the decommissioning of the previous urban network whose last line had been discontinued in 1951; 15
1673:
itself. Its construction, albeit with some phases of work slowdown, has continued by progressively activating other sections of the urban service but with the aim of extending the connection to the Piedmontese Etna centers of
707:. The Palermo-Catania-Messina railway axis is included in the works envisaged by the Sblocca Italia decree, which allocated 816 million out of the 8,000 million needed for the entire work according to government estimates.
131:
Provisional Dictatorial Government all this fervor had immediate effect, and on 25 September 1860 a Convention was signed with the Adami and Lemmi Company formed by the bankers Pietro Augusto Adami and Adriano Lemmi of
331:, which reached as much as 32 per thousand; the line, on the other hand, was designed with a maximum gradient of 21 per thousand. This time the projects were not completed either (despite the fact that the route up to
307:; from the early 1970s, however, citrus fruits were gradually transported in other ways, and the line was decommissioned after a few decades. Preliminary plans, again, envisioned the continuation of the line as far as
354:/high-capacity carrier axis using part of the historic Catania-Palermo route, (with the necessary adjustments and doubled), from Catania Bicocca Station to Catenanuova-Centuripe Station, then pointing towards the
121:
had long since been undertaken. There were numerous instances from the various agricultural and industrial business sectors; in 1859 the Palermo entrepreneur Gaspare Ciprì had even founded a newspaper entitled
1697:
single-track overground branch line is temporarily closed for maintenance. The network has 11 stations, 10 of which are underground. The above-ground track runs along the coastal area flanked by FS tracks at
2574:
824:
rule, such as the Motta Sant'Anastasia-Regalbuto and the Alcantara-Randazzo, have undergone few and limited upgrading works and some have been abandoned to their own devices, condemning them to irreversible
327:, so that the Ennese area, with its large sulfur basins in Catania and Palermo, could be more quickly connected, and above all to reduce the problem of the excessive gradient of the Misericordia pass in
2660:
2524:
475:, that is, until the 1950s, this caused quite a few health problems for the tail-end drivers because of the smoke that accumulated in the tunnel. In May 1951, electric traction operation began on the
496:
even though it was penalized by the single track and the amount of crossings and headways due to the coexisting passenger traffic. The general crisis of the 2000s drastically reduced this traffic.
1030:. The work includes significant upgrades along a number of lines in the Sicilian network, including the Palermo-Agrigento railway. The section of the line to Trapani that runs through the city of
144:
Tenerelli, a financier and entrepreneur in the sulfur industry, denounced the delay in the construction of the Palermo-Catania railway as the main reason for the crippling of the sulfur industry.
2498:
820:
Sicily's railroads, all or most of which were designed or date back to the second half of the nineteenth century, of which some were even built or started only during the twenty-year period of
155:, fully activated in 1871, and completed in a much shorter time than the Palermo-Messina. The Palermo-Catania railroad opened in the same period made use of the original first section between
335:
had already been built) due to the lesser interest in developing rail transport in the region, as the investment of high financial resources for crossing mountainous territories such as the
2074:
Felice Ippolito, Amici e Maestri:lo Stato e le ferrovie, Bari, edizioni Dedalo, 1988. Note 4 on p. 85: cites Carteggio Cavour-Nigra, La liberazione del Mezzogiorno, Vol. IV, pp. 328 and 378
679:
The line had relevance from its inception because it connected the three major urban centers of Palermo, Catania and Messina. Also because it was functional for mining transport from the
415:
to a lesser extent the one between Catania and Gela. However, there are also lines of more limitedly local and commuter function such as the Alcamo-Castelvetrano-Trapani and the southern
1063:
Capo D'Orlando. Construction sites for the Castelbuono-Fiumetorto section were opened on 15 September 2008; in October 2017, the section from Campofelice to Ogliastrillo was opened.
2686:
647:
to the ports of Palermo or Porto Empedocle. Only later did the opportunity to connect the aforementioned line more concretely to the one already built coming from Catania emerge.
924:
The harsh terrain of Sicily meant that many lines were built with steep inclines to keep costs down. The maximum slope reaches a level of 31 per thousand on the ramps leading to
1082:
Other interventions have recently been set on the Canicattì-Siracusa section between Comiso and Canicattì, with a view to strengthening and shortening connections with the new
218:
had been connected since 24 September 1876, and later the connecting section up to Aragona Caldare joined the Palermo line (which crossed the other important mining basins of
175:); this was the route that most interested sulfur industrialists because of the extensive mining basin of Grottacalda, Floristella and Sant'Agostino. Later, work extended to
136:
for the realization of the island's railroad network. Shortly afterwards, the newly formed Savoy government revoked the convention and transferred the concession deed to the
699:
Since the beginning of the 2000s, an upgrading project with relevant structural changes to the line has been slowly materializing, starting with the first section Bicocca -
2554:
1106:. In the past, the most important passenger trains were identified in this way, but for some time now only some domestic suburban or tourist routes have received a name.
147:
The first short section of a railway in Sicily was built in 1863 by engineer Francesco Durante Scimone, when tracks were laid between the capital and the nearby town of
2446:
2420:
2367:
1051:, where the Catania junction is being upgraded. It also includes the construction of the Catania Aeroporto Fontanarossa station, opening on 14 March 2021 to serve the
1067:
appropriate adjustments. Instead, an entirely new route would have been built for the Erei-Madonie-CefalĂą-Palermo route: the new railway would have involved a long
2299:
2047:
251:
1090:
moreover, single track. This combination of factors makes it unlikely that the gap with "continental" infrastructure can be closed in the medium to short term.
1009:, whose most important terminals are the Bicocca station, in the area of which the Bicocca interport is being built, and the stations, home to freight hubs, of
1622:: an automatic light rail line has been planned since 2006: when fully operational, the project envisages that the line will connect the southern area of the
2532:
416:
199:
2507:
593:, which, however, ends as early as Bicocca; it becomes single-track again, crossing almost uninterrupted citrus groves and coastal stretches as far as
419:
which, although they pass through many important areas and production centers, do not seem to be given much consideration. Notable among these is the
2736:
1269:
812:(1146 km), and 791 km of it has been electrified. The extent of electrified double-track lines is 223 km. The thermal traction lines total 578 km.
2794:
447:
on the northern side of the region. The union of the two lines Palermo-Messina and Palermo-Trapani entirely covers the Tyrrhenian side of Sicily.
909:
on a few occasions, exceed 120 km/h; they remain, for the most part, within and below 100 km/h, with long internal stretches at only 75/80 km/h.
450:
The Tyrrhenian Palermo-Messina was fully inaugurated in 1895, replacing the very long previous route that, from Palermo, passed through Aragona,
1461:
to Giachery. It has become important in the Sicilian transportation network both in terms of extension and passenger traffic. It is operated by
295:
at its base, was completed in 1898; however, In the initial plans it had been clamored for the line to reach even the towns to the north of the
2635:
715:
2472:
3050:
1860:
1639:
1584:
1515:
1470:
1450:
1444:
1413:
1071:
section to avoid the high gradients and unstable terrain of inland Sicily and speed up the line. This project met with objections from the
1036:
179:
and Santa Caterina Xirbi, joined in the summer of 1876, which were also affected by the railroad mainly because of the importance of the
1702:, single-track for 1815 m (between Galatea and Porto). The metro is served by "M.88" and "CT0" series electric trains, built by Firema.
1233:
2725:
SocietĂ Italiana Docenti di Trasporti, XIV Convegno nazionale, Area Metropolitana di Catania e trasporto ferroviario. Feb. 19-21, 2007
1915:
985:
2385:
3144:
3125:
3106:
3069:
2985:
2966:
2871:
2194:
Presidential Decree No. 1505 of 11 December 1961, on " Abolition of the Palermo Acqua dei Corsari-Burgio narrow-gauge railway line."
1746:
989:
1811:
Beginning in the late 1930s and after World War II, the Sicilian tramway lines were discontinued one after another and replaced by
1711:
1683:
1614:: works include the construction of 4 new stops (Porto, Politeama, Malaspina-Catania, Lazio-LibertĂ ) and the extension of the line.
1052:
590:
410:
The most important lines in the present-day network are: the Tyrrhenian, between Messina and Palermo to which the extension on the
2560:
3235:
1854:
1849:
Palermo's tramway network, consisting of four urban tramway lines was inaugurated on December 30, 2015 with the following lines:
1699:
1631:
1498:
1458:
1428:
1370:
1163:
581:
533:
1842:
At the end of the 20th century, a project, called "P. & C.M. Service, for the design and construction of 3 tramway lines in
1027:
3240:
2760:
Royal Decree No. 1469 of 30 November 1911, published in the Official Gazette of the Kingdom of Italy No. 24 of 30 January 1912.
1203:
159:
and Bagheria and then penetrated into inland Sicily, stopping, however, at the station of Roccapalumba near the sulfur area of
829:. Since the 1980s, only a few rail sections afferent to the island's major cities have been built, such as the branch line to
864:
2899:
Coletti, Giovanni (1972). "Il passaggio delle ferrovie dall'amministrazione privata all'amministrazione pubblica nel 1905".
2450:
2424:
2371:
499:
The backbone is supplemented by the 125-km-long Palermo-Trapani, from which branches off the important branch (of 14 km) to
88:
The rail network in operation in Sicily at the beginning of the 21st century. In red the RFI lines, in purple the FCE line.
1920:
1409:
897:
719:
line, and part is a variant. It is scheduled for completion in 2022. One of the two new tracks will be activated in 2020.
51:
1707:
1424:
1044:
626:
to Aragona-Caldare (on the outskirts of Agrigento, then Girgenti) and then up to Canicattì and Caltanissetta Xirbi (then
152:
3245:
1215:
1157:
573:
2203:
Presidential Decree No. 1555 of 11 December 1961, on "Abolition of the San Carlo-Salaparuta narrow-gauge railway line."
467:
Pass near Messina, it was necessary for trains of higher composition to be pushed to the rear with a decoupleable mesh
2106:
1564:
1466:
854:
187:
mines of Villarosa and Imera in inland Sicily; the Leonforte-Villarosa section in fact was built under subcontract by
106:
1207:
110:
2610:
1491:
1374:
1040:
830:
500:
411:
2930:
D'Addio, Michele; Casucci, Aristide (1970). "Il potenziamento e il nuovo sistema della linea Lentini d.ne-Gela".
1635:
1185:
872:
711:
627:
347:
33:
739:
2334:
1831:
1520:
1274:
1212:
1039:, which has been in operation since 2001, linking the regional capital and its surrounding municipalities with
602:
2410:
Carta delle Ferrovie d'Italia-Mappa della ferrovia che cambia, a cura delle Relazioni aziendali FS, Roma, 1988
617:
Catania Centrale station, seen in 2004 from the FS stop of the Catania Metro, which was discontinued in 2016.
255:, the new concessionary company, on 5 April 1886. It still waited until 1891 for Licata to be connected with
948:
on the Messina-Siracusa. The Dittaino-Piazza Armerina-Caltagirone railroad, no longer in existence had many
760:
644:
203:
164:
137:
118:
71:
1729:
and Stesicoro-Palestro, and an extension to the airport is at an advanced planning stage. The Misterbianco-
2135:, in Annuario d. Soc. dei licenziati della Regia scuola mineraria di Caltanissetta, 1887-1888, pp. 156-157
1006:
900:
replaced most of the steam locomotives with modern diesel locomotives and also introduced railcars of the
689:
28:
1784:
at about 300 m above sea level. It had a strong tourist value because of the panoramic views on the way.
1967:
1805:
1690:
2265:
Ferrovie dello Stato, fascicolo circolazione linee della unitĂ periferica di Palermo, 1995, pp. 16-171
1439:
2687:"Metropolitana Automatica Leggera di Palermo, il Comune chiede i fondi per l'adeguamento progettuale"
1910:
1670:
1611:
1010:
961:
953:
809:
752:
728:
420:
387:
288:
192:
46:
41:
38:
1894:'s Cityway model 5-element articulated streetcars were put into operation to carry out the service.
2908:
Crisafulli, Alessandro (2000). "Il sistema ferroviario siciliano e l'inchiesta Borsani-Bonfadini".
1694:
1540:
1454:
710:
In 2017, the approval of the final project, signed by Maurizio Gentile, CEO and general manager of
747:, of the Circumetnea Railway, restored for the provision of tourist and amateur trains on request.
2293:
2041:
976:
A "Minuetto" train (in service on some Sicilian lines), stopping at the Catania Locomotive Depot.
744:
128:
2316:"RFI, Linea Palermo - Catania: pubblicato il bando di gara per i lavori Bicocca - Catenanuova".
2107:"Prospetto cronologico dei tratti di ferrovia aperti all'esercizio dal 1839 al 31 dicembre 1926"
275:
3005:
2941:
La linea di Vallelunga. La tormentata genesi del collegamento ferroviario fra Palermo e Catania
2921:
Cruciani, Marcello; Zanotti, Roberto (2002). "Pubblico e privato nella storia delle ferrovie".
2846:
Le linee delle FS a scartamento ridotto a cremagliera in Scilia in Si viaggia anche in dentiera
2589:
2019:
Il primo progetto per la costruzione delle ferrovie in Sicilia-Nuovi quaderni del Meridione III
572:. The line also saw the presence of ALe 601s, which operated the "Peloritano" express train to
97:
3140:
3121:
3102:
3065:
3046:
2981:
2962:
2867:
981:
789:
78:
1749:
and restored from 27 September 2010. However, the service is not regular and is hardly used.
1886:
1710:
with the creation of 4 additional stops. The construction of a "Fontanarossa" stop near the
1316:
1072:
952:
sections to deal with the very steep gradients, up to 75 per thousand between Mulinello and
945:
901:
889:
669:
664:
Enna Industrial Hub. The line continues downhill through arable fields and citrus groves to
660:
549:
512:
504:
472:
391:
296:
242:
188:
3194:. Palermo: UniversitĂ degli Studi di Palermo. FacoltĂ di Ingegneria. Istituto di trasporti.
3185:. Palermo: UniversitĂ degli Studi di Palermo. FacoltĂ di Ingegneria. Istituto di trasporti.
2105:
Ufficio Centrale di Statistica delle Ferrovie dello Stato (1927). Tuzza, Alessandro (ed.).
1733:
suburban extension, 11.5 km long and with 7 stations to be built, is still to be financed.
912:
It must be considered that the hydrogeological disruption conditions of Sicily often cause
896:
The vehicles running on Sicily's railways underwent some renewal during the 1970s when the
151:. In 1866, however, construction of the second line (the busiest in the region) began: the
2389:
1835:
1022:
957:
949:
928:
and 30 per thousand from lower Agrigento to Aragona, and on the ramps of the line between
797:
692:, which was more competitive for passenger connections between the two extreme locations.
594:
493:
443:
to be reached; it is called Tyrrhenian because it faithfully follows the coastline of the
355:
351:
336:
320:
207:
2711:
519:. The line speed is around 80-90 km/h, with considerable gradients (19 per mille) around
833:
and some doubling of the main single-track network, such as the one between Messina and
751:
Of the Sicilian railways in concession only one has survived the cuts and closures; the
1198:
1083:
994:
933:
781:
704:
598:
569:
565:
561:
557:
444:
324:
227:
160:
67:
703:
with a view to future upgrading and development of the railway network in central and
3229:
2661:"Metropolitana a Palermo, l'assessore Catania: "A settembre rilanceremo il progetto""
1823:
1665:
1643:
1398:
1394:
1176:
1059:
937:
834:
793:
636:
516:
451:
386:
The Sicilian railroad network, which was largely created in the 70 years between the
223:
211:
74:
extracted in large quantities in the mines in the center of the region, had ceased.
2225:
1988:
1766:
1761:
These included the Catania-Acireale tramway, which connected the Etna capital with
1726:
1679:
1419:
A suburban rail service (the so-called "metroferrovia") has also been activated in
980:
Sicily's rail network has a predominantly local significance; connections, via the
826:
623:
545:
541:
537:
564:
locomotives and Ale 840 railcars arrived, supplemented from the mid-1970s also by
215:
1656:
1102:
As in the rest of the Italian railway network, named trains have been running in
1717:
853:
According to official RFI data, as of 2017, traffic remote control systems (SCC/
838:
700:
665:
439:
around which the major commuter traffic takes place and also allows the city of
371:
3217:
Tiberi, Gianfranco (1989). "Gli investimenti ferroviari:150 anni di altalena".
3210:
ViabilitĂ antica in Sicilia. Dalla colonizzazione greca all'unificazione (1860)
1457:
was less extensive than the current one and consisted of only the section from
540:
locomotives and some of Italy's most impressive steam locomotives, such as the
77:
The Sicilian network constitutes the most extensive island rail network in the
1812:
1770:
1730:
1675:
1619:
1462:
998:
468:
464:
304:
292:
2737:"Fermata FS Catania Aeroporto, al via i lavori: sarĂ fruibile da giugno 2020"
2473:"Doppio binario tra Palermo e CefalĂą: inaugurata la Campofelice-Ogliastrillo"
676:
is made tangible by the sight of the industrial settlements and the airport.
70:, or because the needs for which they were created, such as the transport of
3034:
Ferrovie siciliane in abbandono, in iTreni, n. 356, febbraio 2013, pp. 20-26
2816:
2611:"Quel sogno chiamato "metro" leggera, ci siamo: "Così Palermo cambia volto""
2110:
1777:
936:. The other lines have smaller gradients, ranging from 22 per thousand near
913:
777:
684:
640:
639:. Initially, when it was built it was a connection on Lercara and later for
520:
359:
308:
300:
172:
584:
to Giampilieri from where it becomes single-track; from here and as far as
402:
375:
267:
84:
3192:
Le ferrovie in Sicilia. Analisi economica del traffico viaggiatori e merci
2175:"rfi/notizie e documenti/periodici e pubblicazioni/argomenti/ numero4.pdf"
2796:
Tram a Palermo, parte la prima corsa Folla di curiosi per l'inaugurazione
1781:
1762:
1627:
1623:
585:
553:
395:
219:
148:
62:
2890:
Cirillo, Mario (1969). "Vicende ed evoluzione delle ferrovie italiane".
2636:"Metropolitana automatica, il Comune richiederĂ finanziamento al M.I.T."
503:. The line enters the Trapani plain, cutting sharply through the tip of
1843:
1788:
1742:
1420:
1405:
1320:
1296:
1292:
1048:
1031:
941:
821:
785:
673:
508:
485:
480:
476:
459:
440:
436:
432:
367:
340:
332:
316:
312:
168:
156:
141:
133:
58:
259:, at that time Terranova di Sicilia, and on 23 December 1891 the Noto-
101:
One of the earliest urban rail crossings in Catania: the Marina Arches
1891:
1797:
1556:
1550:
1545:
1487:
1483:
1238:
1103:
1068:
1013:, Termini Imerese, Priolo and Cannizzaro, are also in steep decline.
929:
773:
680:
605:, which has been transformed into a head station for some years now.
363:
260:
231:
210:
and Licata, seaports for the embarkation of the ore; the area around
184:
180:
114:
19:
1689:
Since 2017, the Nesima-Stesicoro section has been in operation; the
279:
The Circumetnea Railway, opened in 1898 on the slopes of Mount Etna.
1721:
The future layout of metropolitan and suburban transport in Catania
171:
and Bicocca opened and by mid-1870 it was active as far as Pirato (
1877:
1876:
1830:
1822:
1716:
1655:
1438:
1354:
1337:
1312:
971:
883:
738:
612:
401:
346:
The old idea was taken up, in principle, in the early 2000s by an
274:
266:
235:
96:
83:
1181:
2853:
Barni, Enrico (1990). "Profili di storia ferroviaria italiana".
1801:
1076:
997:
lines, on the sections afferent to Palermo and Messina, and the
925:
842:
656:
632:
613:
489:
455:
328:
256:
246:
176:
2064:. Vol. 2. Naples: Stabilimento tipografico Perrotti. 1862.
1043:. A similar project is being carried out on the section of the
651:
Xirbi, the railway route for Canicattì and Agrigento detaches.
2500:
Min.Coesione Territoriale; Contratto istituzionale di sviluppo
1193:
Intercity-Night; Currently Express "Bellini" and "Gattopardo"
972:
892:
series railcars: a constant presence on Sicily's inland lines.
597:; after the long, almost straight section passing through the
350:
project for the construction of a new Messina-Catania-Palermo
1939:
1838:, used for the tram network in Palermo, via Leonardo da Vinci
776:, in which there are important archaeological areas, such as
370:
Mountains until reaching the Messina-Palermo coastal line at
366:
for a total of 39 km, and crossing the last offshoots of the
3201:
Produzione e commercio dello zolfo in Sicilia nel secolo XIX
3088:
Marini, Renzo (1969). "La nuova ferrovia Caltagirone-Gela".
1427:, which connects the suburbs of the city's territory to the
1362:
Express, currently Intercity-Night with beds and couchettes
884:
3172:
Sergi, Giuseppe (1980). "Nuova ferrovia Caltagirone-Gela".
2226:"Decreto del Ministro delle infrastrutture e dei trasporti"
1989:"Decreto del Ministro delle infrastrutture e dei trasporti"
727:
The network, which can be defined as minor because of its
167:
to the port of Palermo; in 1869 the first section between
291:, which with its tracks encircles the enormous massif of
1465:
and consists of 2 lines, connecting Palermo Centrale to
423:, a rail line with suburban and metropolitan functions.
394:'s government, underwent little change since then until
117:
despite the fact that the exploitation of the island's
2590:"Comune di Palermo - Metropolitana automatica Leggera"
2525:"Rfi: investimento da 35 mln in Sicilia per Canicatti"
1776:
Another extra-urban line was the tramway, of electric
1725:
Other metro "sections" are under construction: Nesima-
1058:
With the doubling of the Palermo-Messina section from
816:
Obsolescence and failure to upgrade the Sicilian lines
743:
The railcar ALn 56.06 (series ALn 56.01-06), built by
659:
that required double or triple pulling in the days of
2174:
1642:
station and the northern suburbs of San Lorenzo, the
2950:
Tuttotreno Tema 14, Lo scartamento ridotto in Italia
2421:"Palermo - Agrigento - Palermo-Agrigento - Italferr"
1804:
area and the Porto Empedocle-Lucia for those in the
601:, it becomes double-track again at Targia as far as
406:
Extension of the Sicilian railway network as of 1950
940:on the Palermo-Trapani, to 16 per thousand between
643:because the primary interest was mainly in getting
2447:"Messina - Siracusa - Messina-Siracusa - Italferr"
1787:Extensive extra-urban tramway lines were built in
1827:Map of the 4 lines of the Palermo tramway network
1416:, sometimes improperly referred to as a "metro."
984:, ferrying rolling stock between the stations of
54:network in operation covers a length of 1369 km.
3163:Ogliari, Francesco (1977). "Dilettoso viaggio".
867:, for train running control installed on 901 km;
2781:
2769:
2251:Notizie flash, in Itreni 1 (2002), n. 233, p. 6
507:to reach Trapani from which it can continue to
3118:La rete FS a scartamento ridotto della Sicilia
860:Traffic safety is ensured by the presence of:
552:, among others, ran on this line. In the late
3190:Sergio Cannarozzo, Salvatore Amoroso (1984).
3181:Sergio Cannarozzo, Salvatore Amoroso (1979).
2997:Lo Stato e le ferrovie in Sicilia (1860-1895)
8:
2957:Formigari, Vittorio; Romano, Giulio (2001).
2261:
2259:
2257:
1451:Palermo's first metropolitan railway service
956:and 35 per thousand between Caltagirone and
3004:Giuliani, Paolo; Sirolli, Raffaele (2004).
2133:Cenni sulla storia delle solfare in Sicilia
1149:Rapid, later discontinued in Sicilian sec.
875:, for guidance support operating on 468 km.
271:Sicilian railways in the early 20th century
252:SocietĂ per le Strade Ferrate della Sicilia
2298:: CS1 maint: location missing publisher (
2046:: CS1 maint: location missing publisher (
1431:as far as Giampilieri, south of the city.
1340:Porta Nuova - Palermo Centrale - Siracusa
857:+DPC) are operated on a total of 1340 km.
319:Mountains, disgorging in the direction of
42:Catania-Randazzo-Linguaglossa-Riposto line
31:lines since 1986, is operated entirely by
2939:Ettore Caliri, Salvatore Amoroso (1986).
2083:
2004:Storia della Sicilia medioevale e moderna
1773:; opened in 1915, it was closed in 1934.
1453:activated in 1990 on the occasion of the
2212:
1868:Corso Calatafimi - Stazione Notarbartolo
1630:, passing through the historic center, (
1389:Suburban and metropolitan rail transport
1108:
431:The line involves the two urban hubs of
343:Mountains was not considered justified.
200:coastal line between Licata and Syracuse
3156:Le ferrovie della Sicilia sud-orientale
3135:Molino, Nico; Sinchetto, Beppe (1985).
3097:Molino, Nico; Pautasso, Sergio (1983).
3043:Amici e Maestri: lo Stato e le ferrovie
2735:Tartaglia, Andrea (February 18, 2019).
1931:
1357:Centrale – Palermo Centrale - Siracusa
1241:S. Lucia - Palermo Centrale - Siracusa
645:sulfur from the inland basins of Sicily
163:with the specific purpose of conveying
3099:Le automotrici della prima generazione
3064:. Newton Abbott, David & Charles.
2354:
2291:
2144:
2039:
880:Vehicles in operation and travel speed
716:Official Journal of the European Union
61:consist of 8 lines, spanning all nine
3083:. Palermo: Tipografia Michele Amenta.
2329:
2327:
2311:
2309:
2169:
2167:
2165:
2156:
2100:
2098:
2096:
2094:
2092:
1962:
1960:
1958:
1956:
1423:by adapting part of the route of the
1129:Agrigento Centrale - Porto Empedocle
7:
3060:Kalla-Bishop, Peter Michael (1970).
2335:"Sblocca Italia – L'elenco completo"
1445:Palermo metropolitan railway service
1001:lines, on the Messina-Catania line.
230:). By 1881 with the continuation on
195:) also a major sulfur entrepreneur.
113:in Italy, this was not the case for
3137:Linee ferroviarie. La Paola-Cosenza
2240:Spinta in coda con sgancio in corsa
1940:"Azienda: la storia della ferrovia"
1222:Discontinued between 2009 and 2010
964:, gradients reach 40 per thousand.
479:; electrification work reached the
3079:Maggiore Perni, Francesco (1861).
3006:"L'impegno di RFI nel Mezzogiorno"
2999:. Caltanissetta: Sciascia Editore.
2284:Maggiore Perni, Francesco (1861).
2274:CIPE resolution dated May 27, 2005
2242:, in iTreni oggi n. 66/1986, p. 24
2032:Maggiore Perni, Francesco (1861).
2006:. Bari: LaTerza. pp. 510–511.
1916:History of rail transport in Italy
1765:following a 14.3-km route through
1572:Palermo Notarbartolo-Giachery line
804:Electrification and track doubling
784:and Agrigento, and cities such as
14:
1477:Palermo Centrale-Punta Raisi line
1346:Express with beds and couchettes
849:Control and security technologies
1881:A tramway of the Messina tramway
1256:Roma Termini - Palermo Centrale
1086:, with a 35-million investment.
1005:services, has also contributed.
315:, from where it would cross the
153:Messina-Catania-Siracusa railway
3081:Delle strade ferrate in Sicilia
2883:Gela 15 anni dopo,in Itreni-150
2286:Delle strade ferrate in Sicilia
2034:Delle strade ferrate in Sicilia
1780:type, which ran up the hill of
1264:Intercity, then Intercity Plus
1075:because it did not include its
1017:Fast lines and ongoing projects
808:The majority of the network is
339:and the even more inaccessible
2952:. Albignasego: Duegi Editrice.
2576:Articolo sul "treno dei Mille"
2368:"Sito Italferr, archivio news"
1968:"RFI La rete oggi in: Sicilia"
1236:- Siracusa - Palermo Centrale
609:The backbone of central Sicily
556:period, with electrification,
417:Syracuse-Ragusa-Gela-Canicattì
1:
3165:Storia dei Trasporti Italiani
3062:Mediterranean island railways
2925:(223 ed.). Edizioni Etr.
2848:. Milan: Arcipelago edizioni.
2556:Articolo sull'Akragas Express
1921:Ferrovie dello Stato Italiane
206:to the coastal refineries of
37:; an exception is the 111-km
3208:Tesoriere, Giuseppe (1994).
3199:Squarzina, Federico (1963).
2995:Giuffrida, Romualdo (1967).
2976:Giarrizzo, Giuseppe (1986).
2770:Formigari & Romano (2001
2017:Brancato, Francesco (1965).
1414:metropolitan railway service
1393:In Sicily there is only one
1053:Catania-Fontanarossa Airport
1037:metropolitan railway service
548:, ALn 56 Fiat railcars, and
109:had the pride of having the
3167:. 31–33. Milan: Cavallotti.
3032:Inzerilli, Massimo (2013).
2782:Molino & Sinchetto 1985
1865:CEP - Stazione Notarbartolo
1028:Berlin–Palermo railway axis
501:Palermo-Punta Raisi Airport
107:Kingdom of the Two Sicilies
3262:
3120:. Turin: Edizioni Elledi.
2959:123 anni di tram a Messina
2948:Federici, Antonio (1999).
2866:. Rome: Donzelli Editore.
2002:Mack Smith, Denis (1973).
1836:Bombardier Flexity Outlook
1606:work was expected by 2012.
599:Priolo petrochemical plant
477:Peloritan side of the city
471:; when traction was still
249:was only activated by the
27:, which has included only
3154:Muscolino, Piero (2006).
3045:. Bari: edizioni Dedalo.
3041:Ippolito, Felice (1988).
2980:. Bari: Laterza editore.
2862:Barone, Giuseppe (2002).
2386:"l'interporto di catania"
1682:and to reach Librino and
1664:The first section of the
1580:The line has 4 stations:
1490:, and from the latter to
712:Rete Ferroviaria Italiana
536:and Giampilieri. Elegant
34:Rete Ferroviaria Italiana
16:Railway network in Sicily
3219:La Tecnica Professionale
2932:La Tecnica Professionale
2901:La Tecnica Professionale
2892:La tecnica professionale
2817:"Messina risale in tram"
2713:Metropolitana Di Catania
1714:began in February 2019.
1700:Catania Centrale station
1429:Messina Centrale station
1343:discontinued since 2011
1326:discontinued since 2007
1283:Touristic (summer only)
1258:Roma Termini - Siracusa
1143:Roma Termini - Siracusa
683:mines of Caltanissetta,
390:and the first decade of
198:The construction of the
3236:Railway lines in Sicily
3212:. Palermo: Zedi Italia.
2881:Caliri, Ettore (1994).
2844:Abate, Ogliari (2008).
1885:The 7.7-kilometer-long
1425:railway line to Catania
1132:periodical, since 2010
1098:Sicilian trains by name
767:Network characteristics
672:; the proximity to the
668:and beyond through the
427:The Tyrrhenian backbone
238:had finally been made.
138:Victor Emmanuel Railway
44:, which is operated by
3241:Railway lines in Italy
3183:Le ferrovie in Sicilia
3090:Ingegneria Ferroviaria
2910:Ingegneria Ferroviaria
2864:Le vie del Mezzogiorno
2803:Giornale di Sicilia.it
1882:
1839:
1828:
1722:
1661:
1447:
1280:periodical since 2005
1047:that runs through the
977:
893:
748:
618:
407:
280:
272:
234:the connection to the
102:
89:
3116:Molino, Nico (1985).
2885:. Salò: Edizioni ETR.
2392:on September 26, 2009
1880:
1861:Stazione Notarbartolo
1834:
1826:
1720:
1660:Subway map of Catania
1659:
1509:Palazzo Reale-Orleans
1442:
1245:discontinued in 2011
1230:Freccia della Laguna
1218:- Agrigento Centrale
1190:discontinued in 2007
975:
887:
742:
616:
405:
362:and with a series of
287:Also in Catania, the
278:
270:
100:
87:
3176:(1). Desenzano: ETR.
2961:. Cortona: Calosci.
2741:MobilitĂ .org.Catania
2691:Filodiretto Monreale
2374:on November 8, 2013.
1911:Ferrovia Circumetnea
1819:Palermo tram network
1712:Fontanarossa airport
1684:Fontanarossa airport
1471:Palermo Notarbartolo
1007:Rail freight traffic
954:Valguarnera Caropepe
753:Ferrovia Circumetnea
591:Fontanarossa airport
388:Unification of Italy
358:in the direction of
193:Ferrovia Circumetnea
191:(the builder of the
129:Giuseppe Garibaldi's
47:Ferrovia Circumetnea
3246:Transport in Sicily
2805:, December 30, 2015
2665:Giornale di Sicilia
2477:Giornale di Sicilia
2147:, pp. 132–135)
1747:2009 Messina floods
1678:, Piano Tavola and
1541:Isola delle Femmine
1492:Punta Raisi Airport
1455:1990 FIFA World Cup
1304:Touristic (May 11)
1041:Punta Raisi Airport
962:Circumetnea Railway
831:Punta Raisi airport
735:Lines in concession
527:The Ionian backbone
421:Circumetnea railway
412:Punta Raisi Airport
289:Circumetnea railway
3158:. Ragusa: EdiARGO.
3139:. Torino: Elledi.
2943:. Palermo: Aracne.
2799:, 30 December 2015
2535:on August 16, 2015
2479:. October 16, 2017
1883:
1873:Tramway of Messina
1840:
1829:
1723:
1662:
1600:Planned expansions
1448:
1367:Trinacria Express
1211:Milano Centrale -
1208:Agrigento Centrale
986:Villa San Giovanni
978:
894:
749:
723:Minor inland lines
619:
408:
396:after World War II
281:
273:
183:activities of the
124:Le ferrovie sicule
103:
90:
50:. As of 2018, the
3101:. Turin: ElleDi.
3092:(11). Rome: CIFI.
3052:978-88-220-6076-1
2815:Russo, Giovanni.
2320:. April 14, 2017.
2062:Vita di Garibaldi
1855:Stazione Centrale
1636:Politeama Theater
1525:San Lorenzo Colli
1386:
1385:
1270:Treno del Barocco
990:Messina Marittima
382:Network extension
241:The section from
3253:
3222:
3213:
3204:
3195:
3186:
3177:
3168:
3159:
3150:
3131:
3112:
3093:
3084:
3075:
3056:
3037:
3028:
3026:
3024:
3010:
3000:
2991:
2972:
2953:
2944:
2935:
2926:
2917:
2904:
2895:
2886:
2877:
2858:
2855:Amm. Ferroviaria
2849:
2832:
2831:
2829:
2827:
2812:
2806:
2800:
2791:
2785:
2779:
2773:
2767:
2761:
2758:
2752:
2751:
2749:
2747:
2732:
2726:
2723:
2717:
2716:
2708:
2702:
2701:
2699:
2697:
2683:
2677:
2676:
2674:
2672:
2657:
2651:
2650:
2648:
2646:
2639:Mobilita Palermo
2632:
2626:
2625:
2623:
2621:
2607:
2601:
2600:
2598:
2596:
2586:
2580:
2579:
2571:
2565:
2564:
2559:, archived from
2551:
2545:
2544:
2542:
2540:
2531:. Archived from
2521:
2515:
2514:
2512:
2506:, archived from
2505:
2495:
2489:
2488:
2486:
2484:
2469:
2463:
2462:
2460:
2458:
2453:on July 25, 2015
2449:. Archived from
2443:
2437:
2436:
2434:
2432:
2427:on July 25, 2015
2423:. Archived from
2417:
2411:
2408:
2402:
2401:
2399:
2397:
2388:. Archived from
2382:
2376:
2375:
2370:. Archived from
2364:
2358:
2352:
2346:
2345:
2343:
2341:
2331:
2322:
2321:
2313:
2304:
2303:
2297:
2289:
2281:
2275:
2272:
2266:
2263:
2252:
2249:
2243:
2236:
2230:
2229:
2222:
2216:
2210:
2204:
2201:
2195:
2192:
2186:
2185:
2183:
2181:
2171:
2160:
2154:
2148:
2142:
2136:
2129:
2123:
2122:
2120:
2118:
2109:. Archived from
2102:
2087:
2081:
2075:
2072:
2066:
2065:
2058:
2052:
2051:
2045:
2037:
2029:
2023:
2022:
2014:
2008:
2007:
1999:
1993:
1992:
1985:
1979:
1978:
1976:
1974:
1964:
1951:
1950:
1948:
1946:
1936:
1459:Palermo Centrale
1371:Palermo Centrale
1309:Treno dell'Etna
1288:Treno dei Mille
1234:Venezia S. Lucia
1186:Palermo Centrale
1164:Palermo Centrale
1126:Akragas Express
1109:
1073:province of Enna
1023:high-speed lines
745:Fiat Ferroviaria
670:Plain of Catania
513:Mazara del Vallo
505:San Vito Lo Capo
481:Sicilian capital
303:) Schettino and
297:province of Enna
189:Robert Trewhella
3261:
3260:
3256:
3255:
3254:
3252:
3251:
3250:
3226:
3225:
3216:
3207:
3198:
3189:
3180:
3171:
3162:
3153:
3147:
3134:
3128:
3115:
3109:
3096:
3087:
3078:
3072:
3059:
3053:
3040:
3031:
3022:
3020:
3008:
3003:
2994:
2988:
2975:
2969:
2956:
2947:
2938:
2929:
2920:
2907:
2898:
2889:
2880:
2874:
2861:
2852:
2843:
2840:
2835:
2825:
2823:
2814:
2813:
2809:
2793:
2792:
2788:
2780:
2776:
2768:
2764:
2759:
2755:
2745:
2743:
2734:
2733:
2729:
2724:
2720:
2710:
2709:
2705:
2695:
2693:
2685:
2684:
2680:
2670:
2668:
2659:
2658:
2654:
2644:
2642:
2634:
2633:
2629:
2619:
2617:
2609:
2608:
2604:
2594:
2592:
2588:
2587:
2583:
2573:
2572:
2568:
2563:on May 26, 2010
2553:
2552:
2548:
2538:
2536:
2523:
2522:
2518:
2513:on July 2, 2013
2510:
2503:
2497:
2496:
2492:
2482:
2480:
2471:
2470:
2466:
2456:
2454:
2445:
2444:
2440:
2430:
2428:
2419:
2418:
2414:
2409:
2405:
2395:
2393:
2384:
2383:
2379:
2366:
2365:
2361:
2353:
2349:
2339:
2337:
2333:
2332:
2325:
2315:
2314:
2307:
2290:
2283:
2282:
2278:
2273:
2269:
2264:
2255:
2250:
2246:
2238:Ettore Caliri,
2237:
2233:
2224:
2223:
2219:
2211:
2207:
2202:
2198:
2193:
2189:
2179:
2177:
2173:
2172:
2163:
2155:
2151:
2143:
2139:
2130:
2126:
2116:
2114:
2113:on May 22, 2021
2104:
2103:
2090:
2084:Giarrizzo (1986
2082:
2078:
2073:
2069:
2060:
2059:
2055:
2038:
2031:
2030:
2026:
2016:
2015:
2011:
2001:
2000:
1996:
1987:
1986:
1982:
1972:
1970:
1966:
1965:
1954:
1944:
1942:
1938:
1937:
1933:
1929:
1907:
1901:
1887:Messina tramway
1875:
1821:
1755:
1739:
1708:Messina-Catania
1654:
1632:Central station
1602:
1574:
1479:
1437:
1391:
1334:Treno del Sole
1204:Milano Centrale
1199:Freccia del Sud
1162:Roma Termini -
1100:
1019:
970:
958:Piazza Armerina
950:rack and pinion
922:
882:
851:
818:
806:
798:Porto Empedocle
769:
737:
725:
611:
582:central Messina
534:central Messina
529:
494:Termini Imerese
429:
384:
356:Erean Mountains
337:Erean Mountains
321:Termini Imerese
208:Porto Empedocle
95:
17:
12:
11:
5:
3259:
3257:
3249:
3248:
3243:
3238:
3228:
3227:
3224:
3223:
3214:
3205:
3196:
3187:
3178:
3169:
3160:
3151:
3145:
3132:
3126:
3113:
3107:
3094:
3085:
3076:
3070:
3057:
3051:
3038:
3029:
3001:
2992:
2986:
2973:
2967:
2954:
2945:
2936:
2927:
2918:
2905:
2896:
2887:
2878:
2872:
2859:
2850:
2839:
2836:
2834:
2833:
2807:
2786:
2774:
2762:
2753:
2727:
2718:
2703:
2678:
2652:
2641:. May 27, 2019
2627:
2602:
2581:
2566:
2546:
2516:
2490:
2464:
2438:
2412:
2403:
2377:
2359:
2347:
2323:
2305:
2276:
2267:
2253:
2244:
2231:
2217:
2213:Federici (1999
2205:
2196:
2187:
2161:
2149:
2137:
2124:
2088:
2076:
2067:
2053:
2024:
2009:
1994:
1980:
1952:
1930:
1928:
1925:
1924:
1923:
1918:
1913:
1906:
1903:
1874:
1871:
1870:
1869:
1866:
1863:
1859:Borgo Nuovo -
1857:
1820:
1817:
1815:or bus lines.
1754:
1751:
1738:
1735:
1653:
1650:
1649:
1648:
1624:Oreto-Guadagna
1616:
1615:
1608:
1607:
1601:
1598:
1597:
1596:
1593:
1590:
1587:
1573:
1570:
1569:
1568:
1562:
1559:
1554:
1548:
1543:
1538:
1535:
1534:Tommaso Natale
1532:
1529:
1526:
1523:
1518:
1513:
1510:
1507:
1504:
1501:
1478:
1475:
1436:
1433:
1410:State Railways
1390:
1387:
1384:
1383:
1380:
1377:
1368:
1364:
1363:
1360:
1358:
1352:
1348:
1347:
1344:
1341:
1335:
1331:
1330:
1327:
1324:
1315:Porta Nuova -
1310:
1306:
1305:
1302:
1299:
1289:
1285:
1284:
1281:
1278:
1272:
1266:
1265:
1262:
1260:
1254:
1250:
1249:
1246:
1243:
1231:
1227:
1226:
1223:
1220:
1201:
1195:
1194:
1191:
1188:
1179:
1173:
1172:
1169:
1167:
1155:
1151:
1150:
1147:
1144:
1141:
1137:
1136:
1133:
1130:
1127:
1123:
1122:
1119:
1116:
1113:
1099:
1096:
1084:Comiso Airport
1049:Etnean capital
1045:Ionian railway
1018:
1015:
969:
966:
921:
918:
898:State Railways
881:
878:
877:
876:
869:
868:
850:
847:
817:
814:
805:
802:
768:
765:
736:
733:
724:
721:
705:eastern Sicily
674:Etnean capital
628:Santa Caterina
610:
607:
528:
525:
445:Tyrrhenian Sea
428:
425:
383:
380:
374:, just before
325:Tyrrhenian Sea
161:Lercara Friddi
111:first railroad
94:
91:
68:road transport
29:standard-gauge
15:
13:
10:
9:
6:
4:
3:
2:
3258:
3247:
3244:
3242:
3239:
3237:
3234:
3233:
3231:
3221:. Rome: CIFI.
3220:
3215:
3211:
3206:
3202:
3197:
3193:
3188:
3184:
3179:
3175:
3170:
3166:
3161:
3157:
3152:
3148:
3146:88-7649-032-9
3142:
3138:
3133:
3129:
3127:88-7649-037-X
3123:
3119:
3114:
3110:
3108:88-7649-016-7
3104:
3100:
3095:
3091:
3086:
3082:
3077:
3073:
3071:0-7153-4761-6
3067:
3063:
3058:
3054:
3048:
3044:
3039:
3035:
3030:
3018:
3014:
3013:RFI Argomenti
3007:
3002:
2998:
2993:
2989:
2987:88-420-2786-3
2983:
2979:
2974:
2970:
2968:88-7785-175-9
2964:
2960:
2955:
2951:
2946:
2942:
2937:
2934:. Rome: CIFI.
2933:
2928:
2924:
2919:
2916:(7): 461–472.
2915:
2911:
2906:
2903:. Rome: CIFI.
2902:
2897:
2894:. Rome: CIFI.
2893:
2888:
2884:
2879:
2875:
2873:88-7989-684-9
2869:
2865:
2860:
2856:
2851:
2847:
2842:
2841:
2837:
2826:September 18,
2822:
2818:
2811:
2808:
2804:
2798:
2797:
2790:
2787:
2783:
2778:
2775:
2772:, p. 23)
2771:
2766:
2763:
2757:
2754:
2742:
2738:
2731:
2728:
2722:
2719:
2715:
2714:
2707:
2704:
2692:
2688:
2682:
2679:
2667:. 27 May 2019
2666:
2662:
2656:
2653:
2640:
2637:
2631:
2628:
2616:
2612:
2606:
2603:
2591:
2585:
2582:
2578:
2577:
2570:
2567:
2562:
2558:
2557:
2550:
2547:
2539:September 13,
2534:
2530:
2526:
2520:
2517:
2509:
2502:
2501:
2494:
2491:
2478:
2474:
2468:
2465:
2457:September 14,
2452:
2448:
2442:
2439:
2431:September 14,
2426:
2422:
2416:
2413:
2407:
2404:
2391:
2387:
2381:
2378:
2373:
2369:
2363:
2360:
2357:, p. 16)
2356:
2351:
2348:
2340:September 13,
2336:
2330:
2328:
2324:
2319:
2312:
2310:
2306:
2301:
2295:
2287:
2280:
2277:
2271:
2268:
2262:
2260:
2258:
2254:
2248:
2245:
2241:
2235:
2232:
2227:
2221:
2218:
2215:, p. 67)
2214:
2209:
2206:
2200:
2197:
2191:
2188:
2176:
2170:
2168:
2166:
2162:
2159:, p. 15)
2158:
2153:
2150:
2146:
2141:
2138:
2134:
2128:
2125:
2112:
2108:
2101:
2099:
2097:
2095:
2093:
2089:
2086:, p. 60)
2085:
2080:
2077:
2071:
2068:
2063:
2057:
2054:
2049:
2043:
2035:
2028:
2025:
2021:. p. 11.
2020:
2013:
2010:
2005:
1998:
1995:
1990:
1984:
1981:
1973:September 26,
1969:
1963:
1961:
1959:
1957:
1953:
1941:
1935:
1932:
1926:
1922:
1919:
1917:
1914:
1912:
1909:
1908:
1904:
1902:
1899:
1895:
1893:
1888:
1879:
1872:
1867:
1864:
1862:
1858:
1856:
1852:
1851:
1850:
1847:
1845:
1837:
1833:
1825:
1818:
1816:
1814:
1809:
1807:
1803:
1800:mines in the
1799:
1793:
1790:
1785:
1783:
1779:
1774:
1772:
1768:
1764:
1759:
1752:
1750:
1748:
1744:
1736:
1734:
1732:
1728:
1719:
1715:
1713:
1709:
1703:
1701:
1696:
1692:
1687:
1685:
1681:
1677:
1672:
1667:
1666:Catania metro
1658:
1651:
1645:
1641:
1637:
1633:
1629:
1625:
1621:
1618:
1617:
1613:
1610:
1609:
1604:
1603:
1599:
1594:
1591:
1588:
1586:
1583:
1582:
1581:
1578:
1571:
1566:
1563:
1560:
1558:
1555:
1553:Torre Ciachea
1552:
1549:
1547:
1544:
1542:
1539:
1537:Sferracavallo
1536:
1533:
1530:
1527:
1524:
1522:
1519:
1517:
1514:
1511:
1508:
1505:
1502:
1500:
1497:
1496:
1495:
1493:
1489:
1485:
1476:
1474:
1473:to Giachery.
1472:
1468:
1464:
1460:
1456:
1452:
1446:
1441:
1434:
1432:
1430:
1426:
1422:
1417:
1415:
1411:
1407:
1402:
1400:
1399:Catania metro
1396:
1388:
1381:
1378:
1376:
1372:
1369:
1366:
1365:
1361:
1359:
1356:
1353:
1350:
1349:
1345:
1342:
1339:
1336:
1333:
1332:
1328:
1325:
1322:
1318:
1314:
1311:
1308:
1307:
1303:
1300:
1298:
1294:
1290:
1287:
1286:
1282:
1279:
1276:
1273:
1271:
1268:
1267:
1263:
1261:
1259:
1255:
1252:
1251:
1247:
1244:
1242:
1240:
1235:
1232:
1229:
1228:
1224:
1221:
1219:
1217:
1214:
1209:
1205:
1202:
1200:
1197:
1196:
1192:
1189:
1187:
1183:
1180:
1178:
1175:
1174:
1170:
1168:
1166:
1165:
1159:
1156:
1153:
1152:
1148:
1145:
1142:
1139:
1138:
1134:
1131:
1128:
1125:
1124:
1120:
1117:
1114:
1111:
1110:
1107:
1105:
1097:
1095:
1091:
1087:
1085:
1080:
1078:
1074:
1070:
1064:
1061:
1056:
1054:
1050:
1046:
1042:
1038:
1033:
1029:
1024:
1021:There are no
1016:
1014:
1012:
1008:
1002:
1000:
996:
991:
987:
983:
974:
967:
965:
963:
959:
955:
951:
947:
943:
939:
938:Castelvetrano
935:
931:
927:
919:
917:
915:
910:
906:
903:
899:
891:
886:
879:
874:
871:
870:
866:
863:
862:
861:
858:
856:
848:
846:
844:
840:
836:
832:
828:
823:
815:
813:
811:
803:
801:
799:
795:
794:Castelvetrano
791:
787:
783:
782:Eraclea Minoa
779:
775:
766:
764:
762:
756:
754:
746:
741:
734:
732:
730:
722:
720:
717:
713:
708:
706:
702:
697:
693:
691:
686:
682:
677:
675:
671:
667:
662:
658:
652:
648:
646:
642:
638:
637:Caltanissetta
634:
629:
625:
615:
608:
606:
604:
600:
596:
592:
587:
583:
577:
575:
571:
567:
563:
559:
555:
551:
547:
543:
539:
535:
526:
524:
522:
518:
517:Castelvetrano
514:
510:
506:
502:
497:
495:
491:
487:
482:
478:
474:
473:steam-powered
470:
466:
461:
457:
453:
452:Caltanissetta
448:
446:
442:
438:
434:
426:
424:
422:
418:
413:
404:
400:
397:
393:
389:
381:
379:
377:
373:
369:
365:
361:
357:
353:
349:
344:
342:
338:
334:
330:
326:
322:
318:
314:
310:
306:
302:
298:
294:
290:
285:
277:
269:
265:
262:
258:
254:
253:
248:
244:
239:
237:
233:
229:
225:
224:Casteltermini
221:
217:
213:
212:Caltanissetta
209:
205:
201:
196:
194:
190:
186:
182:
178:
174:
170:
166:
162:
158:
154:
150:
145:
143:
139:
135:
130:
125:
120:
116:
112:
108:
99:
92:
86:
82:
80:
79:Mediterranean
75:
73:
69:
64:
60:
57:The Sicilian
55:
53:
49:
48:
43:
40:
36:
35:
30:
26:
23:
22:
3218:
3209:
3200:
3191:
3182:
3173:
3164:
3155:
3136:
3117:
3098:
3089:
3080:
3061:
3042:
3036:. Salò: ETR.
3033:
3021:. Retrieved
3016:
3012:
2996:
2977:
2958:
2949:
2940:
2931:
2922:
2913:
2909:
2900:
2891:
2882:
2863:
2854:
2845:
2838:Bibliography
2824:. Retrieved
2820:
2810:
2802:
2795:
2789:
2784:, p. 9.
2777:
2765:
2756:
2746:February 24,
2744:. Retrieved
2740:
2730:
2721:
2712:
2706:
2694:. Retrieved
2690:
2681:
2669:. Retrieved
2664:
2655:
2643:. Retrieved
2638:
2630:
2618:. Retrieved
2615:PalermoToday
2614:
2605:
2593:. Retrieved
2584:
2575:
2569:
2561:the original
2555:
2549:
2537:. Retrieved
2533:the original
2528:
2519:
2508:the original
2499:
2493:
2481:. Retrieved
2476:
2467:
2455:. Retrieved
2451:the original
2441:
2429:. Retrieved
2425:the original
2415:
2406:
2394:. Retrieved
2390:the original
2380:
2372:the original
2362:
2355:Molino (1985
2350:
2338:. Retrieved
2317:
2285:
2279:
2270:
2247:
2239:
2234:
2220:
2208:
2199:
2190:
2178:. Retrieved
2152:
2145:Barone (2002
2140:
2132:
2127:
2117:September 4,
2115:. Retrieved
2111:the original
2079:
2070:
2061:
2056:
2033:
2027:
2018:
2012:
2003:
1997:
1983:
1971:. Retrieved
1943:. Retrieved
1934:
1900:
1896:
1884:
1848:
1841:
1810:
1794:
1786:
1775:
1767:Aci Castello
1760:
1756:
1740:
1727:Misterbianco
1724:
1704:
1688:
1680:Misterbianco
1663:
1640:Notarbartolo
1634:, ex-Borsa,
1612:Railway ring
1585:Notarbartolo
1579:
1575:
1531:Cardillo-Zen
1516:Notarbartolo
1480:
1449:
1418:
1403:
1392:
1257:
1237:
1216:Roma Termini
1210:
1161:
1158:Roma Termini
1101:
1092:
1088:
1081:
1065:
1057:
1020:
1003:
979:
923:
911:
907:
895:
859:
852:
827:obsolescence
819:
810:single-track
807:
770:
757:
750:
729:narrow gauge
726:
709:
698:
694:
678:
653:
649:
624:Roccapalumba
620:
578:
574:Roma Termini
530:
498:
449:
430:
409:
385:
345:
286:
282:
250:
240:
197:
146:
123:
104:
76:
56:
45:
39:narrow-gauge
32:
25:rail network
24:
20:
18:
2483:October 17,
2396:November 9,
2180:November 6,
2157:Sergi (1980
1945:November 7,
1853:Roccella -
1565:Punta Raisi
1467:Punta Raisi
1379:since 2001
1375:Punta Raisi
1301:since 2009
1291:Calatafimi/
1253:Peloritano
1177:Conca d'Oro
1171:Intercity.
1160:- Siracusa
839:Caltagirone
701:Catenanuova
690:A19 highway
666:Catenanuova
372:Castelbuono
3230:Categories
3019:(4): 6–101
2821:Mondo Tram
2696:August 26,
2671:August 27,
2645:August 27,
2620:August 27,
2595:August 27,
2288:. Palermo.
2131:M. Gatto,
2036:. Palermo.
1927:References
1813:trolleybus
1771:Aci Trezza
1620:Light rail
1567:(airport).
1463:Trenitalia
1412:operate a
1351:Trinacria
1184:Termini -
1154:Archimede
1135:Touristic
995:Tyrrhenian
914:landslides
888:A pair of
568:and later
469:locomotive
465:Peloritani
352:high-speed
293:Mount Etna
2294:cite book
2042:cite book
1806:Agrigento
1778:funicular
1626:UPL with
1561:Piraineto
1382:Regional
1323:Centrale
1277:- Ragusa
960:. On the
778:Selinunte
761:Pantalica
685:Villarosa
521:Partinico
492:plant in
392:Mussolini
360:Regalbuto
323:, on the
309:Leonforte
301:Centuripe
216:Canicattì
173:Leonforte
165:mined ore
63:provinces
1905:See also
1782:Monreale
1763:Acireale
1753:Tramways
1628:Mondello
1595:Giachery
1589:Federico
1528:La Malfa
1503:Guadagna
1499:Centrale
1329:Express
1317:Siracusa
1275:Siracusa
1248:Express
1225:Express
1213:Siracusa
946:Syracuse
641:Girgenti
603:Siracusa
586:Taormina
532:between
488:and the
243:Syracuse
220:Comitini
149:Bagheria
59:railways
21:Sicily's
3203:. ILTE.
3023:May 14,
2978:Catania
2923:I Treni
2318:FS News
1844:Palermo
1789:Messina
1743:Messina
1737:Messina
1731:Paternò
1706:of the
1691:Galatea
1676:Paternò
1652:Catania
1521:Francia
1443:Map of
1435:Palermo
1421:Messina
1406:Palermo
1321:Palermo
1297:Marsala
1293:Segesta
1239:Venezia
1140:Aurora
1118:Period
1077:capital
1032:Palermo
968:Traffic
942:Lentini
902:ALn 668
890:ALn 668
822:Fascist
786:Sciacca
595:Augusta
554:postwar
550:ALn 772
509:Marsala
486:Palermo
460:Catania
441:Trapani
437:Messina
433:Palermo
368:Nebrodi
364:tunnels
348:RFI SpA
341:Madonie
333:Nicosia
317:Madonie
313:Nicosia
305:Paternò
228:Lercara
169:Catania
157:Palermo
142:Catania
134:Livorno
105:If the
93:History
3174:ITreni
3143:
3124:
3105:
3068:
3049:
2984:
2965:
2870:
2529:AGI.it
1892:Alstom
1808:area.
1802:Ennese
1798:sulfur
1557:Carini
1551:Carini
1546:Capaci
1506:Vespri
1488:Carini
1484:Capaci
1408:, the
1397:, the
1355:Milano
1338:Torino
1313:Torino
1115:Route
1104:Sicily
1069:tunnel
999:Ionian
982:strait
934:Ragusa
930:Modica
920:Slopes
790:Ribera
774:Licata
681:sulfur
458:, and
376:CefalĂą
261:Modica
232:Licata
204:sulfur
185:sulfur
181:mining
119:sulfur
115:Sicily
72:sulfur
3009:(PDF)
2511:(PDF)
2504:(PDF)
1695:Porto
1592:Fiera
1512:Lolli
1395:metro
1146:1974
1121:Note
1112:Name
1060:Patti
835:Patti
661:steam
622:from
570:E.656
566:E.646
562:E.626
558:E.636
236:coast
3141:ISBN
3122:ISBN
3103:ISBN
3066:ISBN
3047:ISBN
3025:2013
2982:ISBN
2963:ISBN
2868:ISBN
2828:2014
2748:2019
2698:2020
2673:2019
2647:2019
2622:2019
2597:2019
2541:2015
2485:2017
2459:2015
2433:2015
2398:2009
2342:2015
2300:link
2182:2009
2119:2021
2048:link
1975:2018
1947:2009
1769:and
1486:and
1469:and
1182:Roma
1011:Gela
988:and
944:and
932:and
926:Enna
865:SCMT
843:Gela
796:and
657:Enna
635:and
633:Enna
544:and
515:and
490:FIAT
456:Enna
435:and
329:Enna
311:and
257:Gela
247:Noto
226:and
214:and
177:Enna
1741:In
1671:FCE
1644:ZEN
1638:),
1404:In
873:SSC
855:CTC
546:480
542:746
538:625
245:to
3232::
3015:.
3011:.
2914:55
2912:.
2819:.
2801:,
2739:.
2689:.
2663:.
2613:.
2527:.
2475:.
2326:^
2308:^
2296:}}
2292:{{
2256:^
2164:^
2091:^
2044:}}
2040:{{
1955:^
1686:.
1401:.
1373:–
1319:-
1295:-
1206:-
841:-
800:.
792:,
788:,
780:,
763:.
576:.
560:,
523:.
511:,
454:,
222:,
52:FS
3149:.
3130:.
3111:.
3074:.
3055:.
3027:.
3017:2
2990:.
2971:.
2876:.
2857:.
2830:.
2750:.
2700:.
2675:.
2649:.
2624:.
2599:.
2543:.
2487:.
2461:.
2435:.
2400:.
2344:.
2302:)
2228:.
2184:.
2121:.
2050:)
1991:.
1977:.
1949:.
1693:-
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.