Knowledge (XXG)

Railway network of Sicily

Source đź“ť

1846:," was studied to meet the mobility needs of the city of Palermo; commissioned by Italconsult S.p.A. and Groupe Scetauroute, it underwent a revision in 1998. Responsible for the revision and executive design was engineer Vinicio Brandani. The system included three lines: one from the Roccella industrial area to the Central Station, one from the Borgo Nuovo district to the Notarbartolo railway station, and one from the San Giovanni Apostolo district (former Cep) to the Notarbartolo station, passing through Sicilian Region Avenue to the Corso Calatafimi interchange. The project included numerous ancillary works such as three pedestrian overpasses along the Sicilian Region avenue between Einstein Square and Corso Calatafimi; roadway improvements; two rolling stock depots with adjoining workshops, in the Roccella industrial area and on Via Castellana; and the routes on protected lanes entirely separate from the roadways. The planned in-service trains: 17 bi-directional 250-seat trainsets (of which 62 seated), with 6 accesses on each side and equipped with information systems with screens and internal audio. Commercial speed was expected to be about 20 km/h. The overall development of the system of just over 15 km, with 40 stops (almost every 400 meters) had a total cost of about 192 million euros. It was planned to be completed within 5 years from the start of construction (October 2006) with the three lines completed approximately 44, 48, and 52 months from the start date. On 30 December 2005 the contract was awarded to a temporary association of companies consisting of the Turin-based "Sis" consortium, the Rome-based firms "Bombardier Transportation Italy" and "Mosco & Associati," Messina-based "Edil Scavi," Milan-based "Amec Spie Rail," and the Berlin-based, "Seib Ingenieur-Consult," IngenieurbĂĽro Wosnitza e Knappe" and "ETC Transport Consultants." The construction sites opened in October 2006 and began work in June 2007. 378:. Such a route was expected to drastically cut down the connection time between the two metropolitan cities but triggered controversy from Enna and Caltanissetta institutions that preferred a line that would penetrate as far as both cities by retracing a merely modernized version of the current route. The two cities at the time of the railroad's construction were joined mainly because of the richness of their sulfur basins; following the abandonment of ore mining since the late 1960s, rail freight became marginal, both because of market crises and, since the late 1980s, as a result of the FS's decision to abandon small batch transport in favor of full train. Diverting the route planned for the A.V. line with stops in the two cities, however, would totally nullify its construction given that stops below 100 km would drastically lower the commercial speed. 1079:. Variants have been proposed over the years that, while crossing the territories of central Sicily, would involve increases in travel time and require less financial resources. The "institutional contract" of 28 February 2013, partly accepted what had previously been proposed, elaborating on the contested aspects regarding the central section of the line, on which a decision will still have to be made in a rather short time frame; regarding this section, the point of detachment from the old route has been modified, taking it from Catenanuova to Raddusa/Agira. The contract seems to have laid the groundwork for a start on the modernization of the important route, so much so that the government the following year earmarked more than 800 million for the Palermo-Messina-Catania rail axis to carry out part of the work. 740: 1832: 284:
Caltagirone from the Etnean capital was also completed, however, it was not until 1931 that this locality was connected to the station of Dittaino, near Enna, (but on a narrow gauge) and it was necessary to wait a good half century, that is, until 1979, for the continuation of the line to Gela to come into operation, which would probably never have been connected to the Catania-Caltagirone line without the emergence of the Gela petrochemical hub. Instead, the direct connection between Caltagirone and Canicattì, which would have shortened the distance between Catania and Agrigento, remained unfinished, although much of the work had already been completed.
1440: 916:, clearly visible to those who travel the network of state and provincial roads where they cause severe unevenness of the road surface to be traveled at walking pace. On the railroad network, whose road surface is, in many cases, still that of the last century with embankments in poor condition and never resolved ballast drainage problems, such events often cause traffic disruptions or in less severe cases slowdowns that disrupt the regularity of train travel. (The heavy costs of ongoing rehabilitation work, eventually globally outweighing those of any modernization, contributed to the decision to close the extensive FS narrow-gauge network.) 276: 1094:
Trapani - Palermo via Milo sections, closed since 8 May 2011 and 25 February 2013 respectively, for a total of more than 130 km in total, are unusable due to structural failure or landslides. Added to this is the fact that many areas, especially inland, lack rail links altogether, despite the precarious condition of the road system and the tourism potential they express: reference can usefully be made to the southern coast of Agrigento and the inland areas of the province of Enna, which were traversed by narrow-gauge railways that were closed in the second half of the 20th century.
1824: 98: 1494:, it is a double-track section, with considerable commuter and tourist traffic between the air terminal and the Sicilian capital. The line operates from 4:45 a.m. to 10 p.m. in the direction of the Airport and from 5:30 a.m. to 11 p.m. in the direction of the Central Station every day of the week, with reduced number of runs on holidays. The frequency is one run every 30 minutes in the urban area from Central Station to Tommaso Natale and every 60 minutes for the Trinacria Express service to the airport. These stations are: 1647:
participation in the ministry's notice on "Submission of applications for access to resources earmarked for Mass Rapid Transit with Fixed Installations," with a deadline of 31 December 2019, in order to obtain at least funding for the first functional Oreto-Notarbartolo lot, about 6 kilometers long with 8 stations, whose costs are around 850 million euros. On 6 August 2020 it was announced that the City of Palermo had submitted the funding application for the design adjustment of the work, with a total amount of €300000.
1657: 1718: 1745:, the so-called Metroferrovia came into operation on 15 June 2009, to connect the city center to the southern suburbs with a dedicated train service, making use of the double-track route of the Messina-Catania railway, for a total of 16 km in the urban section of Messina; 11 stops were established. The service is operated by RFI through a service contract and uses a Minuetto electric train shuttling round trips daily. The service was suspended from 1 October 2009 due to the 845:. However, plans dated back to the 1920s and some of the work had already been done before the war. Many works executed or started were finally abandoned in the 1950s such as the continuation towards Palermo of the Regalbuto - Nicosia section or the Canicattì - Caltagirone. At present, the regional network would need a profound redesign of the routes according to new mobility needs, and the connection with, and between, airports and intermodal freight transport. 403: 268: 85: 127:
Caltanissetta-Licata (for the embarkation at the port of Licata from that of Caltanissetta). A short time later the Institute for the Promotion of Agriculture, Arts and Crafts in Palermo announced a competition for the study of a rail network of Sicily; in this context a project that set as a priority the construction of the Palermo-Girgenti railroad with a branch line to Caltanissetta and Licata arose. With the proclamation of
1878: 614: 973: 399:
times occurred as a result of the so-called stately decree. In 2008, the network was paradoxically configured to resemble that of the early 20th century, with slightly less extension, but in 2010 additional rail routes were suspended and uncertainty remains about the fate of important lines such as the Syracuse-Gela-Canicattì and the Alcamo-Castelvetrano-Trapani.
885: 731:, developed as an extension and complement to two main lines: the north-south transversal Palermo-Corleone-San Carlo and the longitudinal coastal Castelvetrano-Porto Empedocle. Most of the others stood at intermediate or terminal stations of the first two. Exceptions were the lines in the central hinterland that arose in support of the Palermo-Catania. 299:, which instead remained without railroads. By the time the picturesque Catania-Motta Sant'Anastasia-Regalbuto railway was finally completed in the 1950s, it was too late for the purposes for which it had been designed, but nevertheless it was intensively used until the 1970s to transport oranges from Leto, Mandarano, Carcaci (in the territory of 589:
entrance of Catania; the Acireale section is, since the 1980s, almost entirely in tunnels following the construction of the double track. The section of the line through Catania is currently being buried with work scheduled for completion in 2016. From Catania's Acquicella station it runs alongside the double-track
908:
As of 22 November 2009, between Messina and Patti on the Palermo-Messina, speeds of up to 220 km/h can be reached, while 150 km/h maximum speeds remain attainable only on two short sections of the Messina-Catania and near Palermo. On the rest of the lines, the maximum speeds that can be reached, only
772:
of lines since the 1950s has not resulted in the design and construction of new tracks, leaving the areas of central and southwestern Sicily without rail connections: the southern area of the province of Enna, of great tourist-archaeological interest, and the coast from Castelvetrano to Agrigento and
771:
The Sicilian railways, while still quite extensive are, except for a few newly built sections near the areas of the three largest Sicilian cities, generally of obsolete design and layout and therefore inadequate to the changing economic needs of the Sicilian territory. The closure of more than 700 km
588:
it passes through densely inhabited areas and alternates between sections in the open and in tunnels; the line penetrates further, continuing on Giarre (where there is a connection with the FCE) and Acireale becoming double-track again shortly after the station of Fiumefreddo di Sicilia and up to the
531:
The Ionian is the second major line in the region. It is 182 km long from central Messina to Syracuse. It was the first line in the region to be built in its entirety between 1867 and 1871, with the present layout except for the modern double-track variant sections between Fiumefreddo and Catania and
1705:
The Catania rail link is being built, of which the urban section between Cannizzaro, Ognina and Catania Centrale is already active, while the one between Catania and Bicocca (whose station will be underground) is still in the executive design phase, as is the entire RFI track of the affected section
1062:
to the Peloritan capital completed, construction has begun on the doubling of the section between Fiumetorto and CefalĂą Ogliastrillo. The intermediate Patti-Castelbuono section has remained single-track, but there is a feasibility study as well as a preliminary project for doubling between Patti and
621:
The central Sicilian backbone that began in 1863 with the Palermo-Bagheria was completed in 1885, with the opening of the Marianopoli tunnel that allowed direct trains between Palermo and Catania to take the so-called Vallelunga line, avoiding the long round trip of the one, opened in 1881, that ran
1093:
Moreover, the lines cross areas that are geologically unstable, which undermine the delicate rail and road structure of Sicily, further penalizing rail transport, given the long times and high costs required to restore the damaged sections: suffice it to say that to date, the Caltagirone - Gela and
414:
and to Trapani is attached westward; and the Ionian, between Messina, Catania and Syracuse; the central Sicilian, in the interior, between Palermo and Catania via Caltanissetta and Enna completes the picture. The inland transversal between Palermo and Agrigento is being upgraded and speeded up, and
398:
when, especially with the so-called Scalfaro decree, the disposal of some lines that were deemed too costly in terms of the ratio of revenue to yield began despite the fact that they served, sometimes as the only link, the local populations of inland areas. A second wave of disposals in more recent
81:, but the routes have, by and large, remained original and circuitous, and modernization works during the 20th century have been very limited. It was only in the first decade of the 21st century that route modifications were planned and in some cases initiated to adapt them to transportation needs. 1605:
Rail link: the construction site was opened on 22 February 2008 with the intention of doubling the track, burying part of the line and creating 9 new stops: Roccella, Brancaccio residential, Guadagna, Palazzo di Giustizia, Lolli, Lazio-Restivo, Belgio, La Malfa, Sferracavallo the completion of the
718:
and on RFI's procurement portal for a base bid amount of 220 million euros. The tender is expected to be concluded by the end of 2017. The intervention consists of the construction of the double-track line between Bicocca and Catenanuova (about 37 km); part of the route runs alongside the existing
663:
when the line was still among the most important in Sicily. After the long Misericordia Tunnel, the line reaches Enna Station, a passenger stop of a certain importance, after which the line descends again toward the Dittaino Valley to the 280 m above sea level of Dittaino Station, which serves the
650:
Trains from Palermo, having arrived at Roccapalumba for the most part go toward Agrigento, while some continue to Caltanissetta and Catania through a long series of sparsely man-made valleys and hills and the long Marianopoli Tunnel that heralds the arrival at the Caltanissetta Xirbi Station. From
992:
were greatly reduced during the first decade of the 2000s. Overall long-distance passenger traffic, which had been intense from the 1960s onward, gradually declined to extremely modest levels. Only commuter traffic around larger urban areas has some consistency. The busiest routes are the coastal
1004:
The most important rail installations, namely those of Palermo, Messina and Catania have suffered a steady decline in long-distance passenger traffic since the last years of the last century. The gradual corporate disengagement of the FS group, which has consistently decreased the supply of rail
462:
before finally reaching Messina. The line slavishly follows the Tyrrhenian coast for most of the route as a result of the difficult topography of the area, in many cases with a steep coastline and overhanging into the sea, without penetrating inland except in a few cases. Doubling has been under
126:
and had undertaken negotiations with Belgian and Dutch investors for the possible establishment of a railway company that would build the routes afferent to the two ports most useful for the purpose, the Palermo-Bagheria (for the embarkation at the port of Palermo of sulfur from Lercara) and the
1089:
Alongside the projects, however, the shortcomings of the island's rail system also remain evident, which appears, especially in its internal lines, to be obsolete and uncompetitive in its infrastructure, forcing convoys to move very often at average speeds below 100 km/h. Most of the lines are,
1646:
and Partanna, for a total of 20.77 km and 23 stations. In the first five years of the 2010s the project seemed to fade away, however in 2017 a resolution of the city council announced the conclusion of the preliminary design process approved by MIT. In May 2019, the municipality announces its
283:
From the capital, at the beginning the first radiating hub of Sicilian railroads, it was not until 1880 that the first sections of the line to Trapani began to open by the Western Sicilian Railway Company, which was joined six years later by the longer Castelvetrano route. In 1892 the line to
1066:
The Palermo-Catania section of the only planned high-capacity line, whose preliminary design dates back to the early 1990s, at the time of the establishment of the Ente FS in the original plans, would have retained the current route as the basis for the Catania-Catenanuova route, albeit with
202:, strongly advocated to attract goods to the port of Aretusa, was, however, quite late compared to the others and classified among the complementary lines to be built only with the contribution of local authorities. This was because the major interest of the mining entrepreneurs was to get 463:
construction for many years with very significant costs given the need for considerable artwork with moving the route further inland. The line, which measures 213 km, is still largely single-track with rather low track speeds for much of the route. Until the 1990s, in order to pass the
695:
The railroad has modest commuter traffic between Enna and Caltanissetta, and between them and Catania, and despite modernizations and the use of modern circulation systems it records low standards of utilization in place, with little supply of passenger trains and few freight trains.
1025:
in Sicily even though there have been widespread, on several occasions, design assumptions by the FS regarding the construction of a high-speed line in Sicily; almost as a continuation of an equivalent HS/HC Battipaglia-Reggio Calabria line framed within the European program of a
483:
in 1955. During the following years the sections near the two cities were doubled and finally with the activation of the Peloritan Tunnel eliminated the push service to heavy trains. In the past the line had an increase in freight traffic to support the industrial activities of
1757:
Between the late nineteenth and early twentieth centuries, a number of extra-urban tramway lines were also built in Sicily to connect the larger cities and the surrounding area; they lost their viability as a result of the development of road transport from the 1930s onward.
1034:
has been largely buried, freeing up large areas on the surface, and was reopened to rail traffic in October 2018, after 3 years since its closure, for its renovation and track doubling, with the construction of new underground stops. This enabled the optimization of the
579:
All categories of trains run on the Ionian line, except for high-speed ones, and at one time also many agency trains of a tourist nature. However, traffic is affected by the presence of the long single-track section in the central part. The line begins double-track from
1795:
Other tramway lines were built for mining transport in central and southwestern Sicily. In the Sicilian hinterland, the Raddusa-Miniera di Sant'Agostino was created, attested at the Raddusa-Agira station of the Catania-Palermo railway intended to serve the numerous
758:
The other line, the Syracuse-Ragusa-Vizzini Railroad, which ran through the Anapo Valley, was closed and dismantled in the late 1950s despite representing, if upgraded, the shortest link between Ragusa and Catania and a valuable means of tourist transportation to
1791:
with a total length of 74 km: the Messina-Granatari-Barcellona Pozzo di Gotto tramway, which ran northward from the Peloritan capital and was inaugurated in 1890, and the Messina-Giampilieri tramway heading south, both promoted by a Belgian-owned company.
687:
and the Enna area (including the important ones of Floristella and Grottacalda) to the embarkation ports. The importance of the line for freight traffic waned until the 1970s following the systematic closure of the mines and especially the opening of the
714:, resulted in the tendering of the doubling and speeding of the Bicocca - Catenanuova lot. The track design calls for a maximum commercial speed of up to 200 km/h. The call for tenders for the executive design and construction work was published in the 654:
The railroad continues to the Villarosa Station, once an important sulfur depot and since 8 December 1995 the site of an interesting Railway Museum, of mining art and rural culture, set up entirely aboard vintage wagons. Then begins the hard climb to
1668:
was inaugurated on 27 June 1999, and went into service on 11 July that year. Initially planned as a landfill of the urban-crossing line of the Circumetnea Railway during the planning process, it was redesigned as a full-fledged metro managed by the
904:
type in place of antiquated rolling stock. Thereafter, however, there has often been only a recycling of rolling stock, much of it from north-central railways, where it was redundant due to the arrival of the latest generation high-speed vehicles.
1055:. Other projects include the joining of the island's rail network with the planned Catania Bicocca Interport and, on the Messina-Siracusa, track doubling between Giampilieri and Fiumefreddo and speeding up the route between Catania and Syracuse. 1576:
The short route consists of a single underground track from Notarbartolo to Federico; the rest is in trenches. The line operates from 6:40 a.m. to 8:40 p.m., weekdays only. The frequency of service is one run every 30 minutes in the urban area.
630:
Xirbi). The construction period of more than 20 years can be explained by the topographical difficulties of the stretches of land crossed, as well as by the length of the line, about 240 km, which passes through the inland provincial capitals,
1481:
From Palermo Centrale to Palazzo Reale Orleans it is above ground and single track, which becomes underground as far as France and then re-emerges outside the city. From here on, it passes through the main centers of the western district,
263:
section of the line was also opened for operation. And two years later, in 1893 the Terranova di Sicilia - Comiso section and the Comiso-Modica, which completed the Syracuse-Licata railway, were inaugurated on June 18 of the same year.
140:(with predominantly French capital); nevertheless, the railways in Sicily were built late and slowly given the gradual insolvency and financial collapse in which the said company soon found itself. Even in the early 1870s, the mayor of 65:
of the region. Many lines were decommissioned and generally dismantled, particularly in the 1960s (but even up to almost the threshold of the 1990s, decommissioning took place), mainly because they were uncompetitive in comparison with
755:, which has shown constant vitality and despite experiencing periods of great difficulty has been moving, since the threshold of the 2000s, toward adaptation to metropolitan and tourist traffic with further network expansion projects. 837:, and between Targia and Syracuse. Modernizations of the nodes around the island's two largest cities have been built slowly and still seem far from being completed. The last railway line to be built and completed, in 1979, was the 1897:
The streetcars make 18 stops and make it possible to reach the Polyclinic, the southern bus terminus (at the Gazzi end of the line), and the cemetery; they run through the city center along San Martino Avenue and Cairoli Square.
1889:
came into operation in Messina on 3 April 2003 after a long gestation and construction period and more than half a century after the decommissioning of the previous urban network whose last line had been discontinued in 1951; 15
1673:
itself. Its construction, albeit with some phases of work slowdown, has continued by progressively activating other sections of the urban service but with the aim of extending the connection to the Piedmontese Etna centers of
707:. The Palermo-Catania-Messina railway axis is included in the works envisaged by the Sblocca Italia decree, which allocated 816 million out of the 8,000 million needed for the entire work according to government estimates. 131:
Provisional Dictatorial Government all this fervor had immediate effect, and on 25 September 1860 a Convention was signed with the Adami and Lemmi Company formed by the bankers Pietro Augusto Adami and Adriano Lemmi of
331:, which reached as much as 32 per thousand; the line, on the other hand, was designed with a maximum gradient of 21 per thousand. This time the projects were not completed either (despite the fact that the route up to 307:; from the early 1970s, however, citrus fruits were gradually transported in other ways, and the line was decommissioned after a few decades. Preliminary plans, again, envisioned the continuation of the line as far as 354:/high-capacity carrier axis using part of the historic Catania-Palermo route, (with the necessary adjustments and doubled), from Catania Bicocca Station to Catenanuova-Centuripe Station, then pointing towards the 121:
had long since been undertaken. There were numerous instances from the various agricultural and industrial business sectors; in 1859 the Palermo entrepreneur Gaspare Ciprì had even founded a newspaper entitled
1697:
single-track overground branch line is temporarily closed for maintenance. The network has 11 stations, 10 of which are underground. The above-ground track runs along the coastal area flanked by FS tracks at
2574: 824:
rule, such as the Motta Sant'Anastasia-Regalbuto and the Alcantara-Randazzo, have undergone few and limited upgrading works and some have been abandoned to their own devices, condemning them to irreversible
327:, so that the Ennese area, with its large sulfur basins in Catania and Palermo, could be more quickly connected, and above all to reduce the problem of the excessive gradient of the Misericordia pass in 2660: 2524: 475:, that is, until the 1950s, this caused quite a few health problems for the tail-end drivers because of the smoke that accumulated in the tunnel. In May 1951, electric traction operation began on the 496:
even though it was penalized by the single track and the amount of crossings and headways due to the coexisting passenger traffic. The general crisis of the 2000s drastically reduced this traffic.
1030:. The work includes significant upgrades along a number of lines in the Sicilian network, including the Palermo-Agrigento railway. The section of the line to Trapani that runs through the city of 144:
Tenerelli, a financier and entrepreneur in the sulfur industry, denounced the delay in the construction of the Palermo-Catania railway as the main reason for the crippling of the sulfur industry.
2498: 820:
Sicily's railroads, all or most of which were designed or date back to the second half of the nineteenth century, of which some were even built or started only during the twenty-year period of
155:, fully activated in 1871, and completed in a much shorter time than the Palermo-Messina. The Palermo-Catania railroad opened in the same period made use of the original first section between 335:
had already been built) due to the lesser interest in developing rail transport in the region, as the investment of high financial resources for crossing mountainous territories such as the
2074:
Felice Ippolito, Amici e Maestri:lo Stato e le ferrovie, Bari, edizioni Dedalo, 1988. Note 4 on p. 85: cites Carteggio Cavour-Nigra, La liberazione del Mezzogiorno, Vol. IV, pp. 328 and 378
679:
The line had relevance from its inception because it connected the three major urban centers of Palermo, Catania and Messina. Also because it was functional for mining transport from the
415:
to a lesser extent the one between Catania and Gela. However, there are also lines of more limitedly local and commuter function such as the Alcamo-Castelvetrano-Trapani and the southern
1063:
Capo D'Orlando. Construction sites for the Castelbuono-Fiumetorto section were opened on 15 September 2008; in October 2017, the section from Campofelice to Ogliastrillo was opened.
2686: 647:
to the ports of Palermo or Porto Empedocle. Only later did the opportunity to connect the aforementioned line more concretely to the one already built coming from Catania emerge.
924:
The harsh terrain of Sicily meant that many lines were built with steep inclines to keep costs down. The maximum slope reaches a level of 31 per thousand on the ramps leading to
1082:
Other interventions have recently been set on the Canicattì-Siracusa section between Comiso and Canicattì, with a view to strengthening and shortening connections with the new
218:
had been connected since 24 September 1876, and later the connecting section up to Aragona Caldare joined the Palermo line (which crossed the other important mining basins of
175:); this was the route that most interested sulfur industrialists because of the extensive mining basin of Grottacalda, Floristella and Sant'Agostino. Later, work extended to 136:
for the realization of the island's railroad network. Shortly afterwards, the newly formed Savoy government revoked the convention and transferred the concession deed to the
699:
Since the beginning of the 2000s, an upgrading project with relevant structural changes to the line has been slowly materializing, starting with the first section Bicocca -
2554: 1106:. In the past, the most important passenger trains were identified in this way, but for some time now only some domestic suburban or tourist routes have received a name. 147:
The first short section of a railway in Sicily was built in 1863 by engineer Francesco Durante Scimone, when tracks were laid between the capital and the nearby town of
2446: 2420: 2367: 1051:, where the Catania junction is being upgraded. It also includes the construction of the Catania Aeroporto Fontanarossa station, opening on 14 March 2021 to serve the 1067:
appropriate adjustments. Instead, an entirely new route would have been built for the Erei-Madonie-CefalĂą-Palermo route: the new railway would have involved a long
2299: 2047: 251: 1090:
moreover, single track. This combination of factors makes it unlikely that the gap with "continental" infrastructure can be closed in the medium to short term.
1009:, whose most important terminals are the Bicocca station, in the area of which the Bicocca interport is being built, and the stations, home to freight hubs, of 1622:: an automatic light rail line has been planned since 2006: when fully operational, the project envisages that the line will connect the southern area of the 2532: 416: 199: 2507: 593:, which, however, ends as early as Bicocca; it becomes single-track again, crossing almost uninterrupted citrus groves and coastal stretches as far as 419:
which, although they pass through many important areas and production centers, do not seem to be given much consideration. Notable among these is the
2736: 1269: 812:(1146 km), and 791 km of it has been electrified. The extent of electrified double-track lines is 223 km. The thermal traction lines total 578 km. 2794: 447:
on the northern side of the region. The union of the two lines Palermo-Messina and Palermo-Trapani entirely covers the Tyrrhenian side of Sicily.
909:
on a few occasions, exceed 120 km/h; they remain, for the most part, within and below 100 km/h, with long internal stretches at only 75/80 km/h.
450:
The Tyrrhenian Palermo-Messina was fully inaugurated in 1895, replacing the very long previous route that, from Palermo, passed through Aragona,
1461:
to Giachery. It has become important in the Sicilian transportation network both in terms of extension and passenger traffic. It is operated by
295:
at its base, was completed in 1898; however, In the initial plans it had been clamored for the line to reach even the towns to the north of the
2635: 715: 2472: 3050: 1860: 1639: 1584: 1515: 1470: 1450: 1444: 1413: 1071:
section to avoid the high gradients and unstable terrain of inland Sicily and speed up the line. This project met with objections from the
1036: 179:
and Santa Caterina Xirbi, joined in the summer of 1876, which were also affected by the railroad mainly because of the importance of the
1702:, single-track for 1815 m (between Galatea and Porto). The metro is served by "M.88" and "CT0" series electric trains, built by Firema. 1233: 2725:
SocietĂ  Italiana Docenti di Trasporti, XIV Convegno nazionale, Area Metropolitana di Catania e trasporto ferroviario. Feb. 19-21, 2007
1915: 985: 2385: 3144: 3125: 3106: 3069: 2985: 2966: 2871: 2194:
Presidential Decree No. 1505 of 11 December 1961, on " Abolition of the Palermo Acqua dei Corsari-Burgio narrow-gauge railway line."
1746: 989: 1811:
Beginning in the late 1930s and after World War II, the Sicilian tramway lines were discontinued one after another and replaced by
1711: 1683: 1614:: works include the construction of 4 new stops (Porto, Politeama, Malaspina-Catania, Lazio-LibertĂ ) and the extension of the line. 1052: 590: 410:
The most important lines in the present-day network are: the Tyrrhenian, between Messina and Palermo to which the extension on the
2560: 3235: 1854: 1849:
Palermo's tramway network, consisting of four urban tramway lines was inaugurated on December 30, 2015 with the following lines:
1699: 1631: 1498: 1458: 1428: 1370: 1163: 581: 533: 1842:
At the end of the 20th century, a project, called "P. & C.M. Service, for the design and construction of 3 tramway lines in
1027: 3240: 2760:
Royal Decree No. 1469 of 30 November 1911, published in the Official Gazette of the Kingdom of Italy No. 24 of 30 January 1912.
1203: 159:
and Bagheria and then penetrated into inland Sicily, stopping, however, at the station of Roccapalumba near the sulfur area of
829:. Since the 1980s, only a few rail sections afferent to the island's major cities have been built, such as the branch line to 864: 2899:
Coletti, Giovanni (1972). "Il passaggio delle ferrovie dall'amministrazione privata all'amministrazione pubblica nel 1905".
2450: 2424: 2371: 499:
The backbone is supplemented by the 125-km-long Palermo-Trapani, from which branches off the important branch (of 14 km) to
88:
The rail network in operation in Sicily at the beginning of the 21st century. In red the RFI lines, in purple the FCE line.
1920: 1409: 897: 719:
line, and part is a variant. It is scheduled for completion in 2022. One of the two new tracks will be activated in 2020.
51: 1707: 1424: 1044: 626:
to Aragona-Caldare (on the outskirts of Agrigento, then Girgenti) and then up to Canicattì and Caltanissetta Xirbi (then
152: 3245: 1215: 1157: 573: 2203:
Presidential Decree No. 1555 of 11 December 1961, on "Abolition of the San Carlo-Salaparuta narrow-gauge railway line."
467:
Pass near Messina, it was necessary for trains of higher composition to be pushed to the rear with a decoupleable mesh
2106: 1564: 1466: 854: 187:
mines of Villarosa and Imera in inland Sicily; the Leonforte-Villarosa section in fact was built under subcontract by
106: 1207: 110: 2610: 1491: 1374: 1040: 830: 500: 411: 2930:
D'Addio, Michele; Casucci, Aristide (1970). "Il potenziamento e il nuovo sistema della linea Lentini d.ne-Gela".
1635: 1185: 872: 711: 627: 347: 33: 739: 2334: 1831: 1520: 1274: 1212: 1039:, which has been in operation since 2001, linking the regional capital and its surrounding municipalities with 602: 2410:
Carta delle Ferrovie d'Italia-Mappa della ferrovia che cambia, a cura delle Relazioni aziendali FS, Roma, 1988
617:
Catania Centrale station, seen in 2004 from the FS stop of the Catania Metro, which was discontinued in 2016.
255:, the new concessionary company, on 5 April 1886. It still waited until 1891 for Licata to be connected with 948:
on the Messina-Siracusa. The Dittaino-Piazza Armerina-Caltagirone railroad, no longer in existence had many
760: 644: 203: 164: 137: 118: 71: 1729:
and Stesicoro-Palestro, and an extension to the airport is at an advanced planning stage. The Misterbianco-
2135:, in Annuario d. Soc. dei licenziati della Regia scuola mineraria di Caltanissetta, 1887-1888, pp. 156-157 1006: 900:
replaced most of the steam locomotives with modern diesel locomotives and also introduced railcars of the
689: 28: 1784:
at about 300 m above sea level. It had a strong tourist value because of the panoramic views on the way.
1967: 1805: 1690: 2265:
Ferrovie dello Stato, fascicolo circolazione linee della unitĂ  periferica di Palermo, 1995, pp. 16-171
1439: 2687:"Metropolitana Automatica Leggera di Palermo, il Comune chiede i fondi per l'adeguamento progettuale" 1910: 1670: 1611: 1010: 961: 953: 809: 752: 728: 420: 387: 288: 192: 46: 41: 38: 1894:'s Cityway model 5-element articulated streetcars were put into operation to carry out the service. 2908:
Crisafulli, Alessandro (2000). "Il sistema ferroviario siciliano e l'inchiesta Borsani-Bonfadini".
1694: 1540: 1454: 710:
In 2017, the approval of the final project, signed by Maurizio Gentile, CEO and general manager of
747:, of the Circumetnea Railway, restored for the provision of tourist and amateur trains on request. 2293: 2041: 976:
A "Minuetto" train (in service on some Sicilian lines), stopping at the Catania Locomotive Depot.
744: 128: 2316:"RFI, Linea Palermo - Catania: pubblicato il bando di gara per i lavori Bicocca - Catenanuova". 2107:"Prospetto cronologico dei tratti di ferrovia aperti all'esercizio dal 1839 al 31 dicembre 1926" 275: 3005: 2941:
La linea di Vallelunga. La tormentata genesi del collegamento ferroviario fra Palermo e Catania
2921:
Cruciani, Marcello; Zanotti, Roberto (2002). "Pubblico e privato nella storia delle ferrovie".
2846:
Le linee delle FS a scartamento ridotto a cremagliera in Scilia in Si viaggia anche in dentiera
2589: 2019:
Il primo progetto per la costruzione delle ferrovie in Sicilia-Nuovi quaderni del Meridione III
572:. The line also saw the presence of ALe 601s, which operated the "Peloritano" express train to 97: 3140: 3121: 3102: 3065: 3046: 2981: 2962: 2867: 981: 789: 78: 1749:
and restored from 27 September 2010. However, the service is not regular and is hardly used.
1886: 1710:
with the creation of 4 additional stops. The construction of a "Fontanarossa" stop near the
1316: 1072: 952:
sections to deal with the very steep gradients, up to 75 per thousand between Mulinello and
945: 901: 889: 669: 664:
Enna Industrial Hub. The line continues downhill through arable fields and citrus groves to
660: 549: 512: 504: 472: 391: 296: 242: 188: 3194:. Palermo: UniversitĂ  degli Studi di Palermo. FacoltĂ  di Ingegneria. Istituto di trasporti. 3185:. Palermo: UniversitĂ  degli Studi di Palermo. FacoltĂ  di Ingegneria. Istituto di trasporti. 2105:
Ufficio Centrale di Statistica delle Ferrovie dello Stato (1927). Tuzza, Alessandro (ed.).
1733:
suburban extension, 11.5 km long and with 7 stations to be built, is still to be financed.
912:
It must be considered that the hydrogeological disruption conditions of Sicily often cause
896:
The vehicles running on Sicily's railways underwent some renewal during the 1970s when the
151:. In 1866, however, construction of the second line (the busiest in the region) began: the 2389: 1835: 1022: 957: 949: 928:
and 30 per thousand from lower Agrigento to Aragona, and on the ramps of the line between
797: 692:, which was more competitive for passenger connections between the two extreme locations. 594: 493: 443:
to be reached; it is called Tyrrhenian because it faithfully follows the coastline of the
355: 351: 336: 320: 207: 2711: 519:. The line speed is around 80-90 km/h, with considerable gradients (19 per mille) around 833:
and some doubling of the main single-track network, such as the one between Messina and
751:
Of the Sicilian railways in concession only one has survived the cuts and closures; the
1198: 1083: 994: 933: 781: 704: 598: 569: 565: 561: 557: 444: 324: 227: 160: 67: 703:
with a view to future upgrading and development of the railway network in central and
3229: 2661:"Metropolitana a Palermo, l'assessore Catania: "A settembre rilanceremo il progetto"" 1823: 1665: 1643: 1398: 1394: 1176: 1059: 937: 834: 793: 636: 516: 451: 386:
The Sicilian railroad network, which was largely created in the 70 years between the
223: 211: 74:
extracted in large quantities in the mines in the center of the region, had ceased.
2225: 1988: 1766: 1761:
These included the Catania-Acireale tramway, which connected the Etna capital with
1726: 1679: 1419:
A suburban rail service (the so-called "metroferrovia") has also been activated in
980:
Sicily's rail network has a predominantly local significance; connections, via the
826: 623: 545: 541: 537: 564:
locomotives and Ale 840 railcars arrived, supplemented from the mid-1970s also by
215: 1656: 1102:
As in the rest of the Italian railway network, named trains have been running in
1717: 853:
According to official RFI data, as of 2017, traffic remote control systems (SCC/
838: 700: 665: 439:
around which the major commuter traffic takes place and also allows the city of
371: 3217:
Tiberi, Gianfranco (1989). "Gli investimenti ferroviari:150 anni di altalena".
3210:
ViabilitĂ  antica in Sicilia. Dalla colonizzazione greca all'unificazione (1860)
1457:
was less extensive than the current one and consisted of only the section from
540:
locomotives and some of Italy's most impressive steam locomotives, such as the
77:
The Sicilian network constitutes the most extensive island rail network in the
1812: 1770: 1730: 1675: 1619: 1462: 998: 468: 464: 304: 292: 2737:"Fermata FS Catania Aeroporto, al via i lavori: sarĂ  fruibile da giugno 2020" 2473:"Doppio binario tra Palermo e CefalĂą: inaugurata la Campofelice-Ogliastrillo" 676:
is made tangible by the sight of the industrial settlements and the airport.
70:, or because the needs for which they were created, such as the transport of 3034:
Ferrovie siciliane in abbandono, in iTreni, n. 356, febbraio 2013, pp. 20-26
2816: 2611:"Quel sogno chiamato "metro" leggera, ci siamo: "Così Palermo cambia volto"" 2110: 1777: 936:. The other lines have smaller gradients, ranging from 22 per thousand near 913: 777: 684: 640: 639:. Initially, when it was built it was a connection on Lercara and later for 520: 359: 308: 300: 172: 584:
to Giampilieri from where it becomes single-track; from here and as far as
402: 375: 267: 84: 3192:
Le ferrovie in Sicilia. Analisi economica del traffico viaggiatori e merci
2175:"rfi/notizie e documenti/periodici e pubblicazioni/argomenti/ numero4.pdf" 2796:
Tram a Palermo, parte la prima corsa Folla di curiosi per l'inaugurazione
1781: 1762: 1627: 1623: 585: 553: 395: 219: 148: 62: 2890:
Cirillo, Mario (1969). "Vicende ed evoluzione delle ferrovie italiane".
2636:"Metropolitana automatica, il Comune richiederĂ  finanziamento al M.I.T." 503:. The line enters the Trapani plain, cutting sharply through the tip of 1843: 1788: 1742: 1420: 1405: 1320: 1296: 1292: 1048: 1031: 941: 821: 785: 673: 508: 485: 480: 476: 459: 440: 436: 432: 367: 340: 332: 316: 312: 168: 156: 141: 133: 58: 259:, at that time Terranova di Sicilia, and on 23 December 1891 the Noto- 101:
One of the earliest urban rail crossings in Catania: the Marina Arches
1891: 1797: 1556: 1550: 1545: 1487: 1483: 1238: 1103: 1068: 1013:, Termini Imerese, Priolo and Cannizzaro, are also in steep decline. 929: 773: 680: 605:, which has been transformed into a head station for some years now. 363: 260: 231: 210:
and Licata, seaports for the embarkation of the ore; the area around
184: 180: 114: 19: 1689:
Since 2017, the Nesima-Stesicoro section has been in operation; the
279:
The Circumetnea Railway, opened in 1898 on the slopes of Mount Etna.
1721:
The future layout of metropolitan and suburban transport in Catania
171:
and Bicocca opened and by mid-1870 it was active as far as Pirato (
1877: 1876: 1830: 1822: 1716: 1655: 1438: 1354: 1337: 1312: 971: 883: 738: 612: 401: 346:
The old idea was taken up, in principle, in the early 2000s by an
274: 266: 235: 96: 83: 1181: 2853:
Barni, Enrico (1990). "Profili di storia ferroviaria italiana".
1801: 1076: 997:
lines, on the sections afferent to Palermo and Messina, and the
925: 842: 656: 632: 613: 489: 455: 328: 256: 246: 176: 2064:. Vol. 2. Naples: Stabilimento tipografico Perrotti. 1862. 1043:. A similar project is being carried out on the section of the 651:
Xirbi, the railway route for Canicattì and Agrigento detaches.
2500:
Min.Coesione Territoriale; Contratto istituzionale di sviluppo
1193:
Intercity-Night; Currently Express "Bellini" and "Gattopardo"
972: 892:
series railcars: a constant presence on Sicily's inland lines.
597:; after the long, almost straight section passing through the 350:
project for the construction of a new Messina-Catania-Palermo
1939: 1838:, used for the tram network in Palermo, via Leonardo da Vinci 776:, in which there are important archaeological areas, such as 370:
Mountains until reaching the Messina-Palermo coastal line at
366:
for a total of 39 km, and crossing the last offshoots of the
3201:
Produzione e commercio dello zolfo in Sicilia nel secolo XIX
3088:
Marini, Renzo (1969). "La nuova ferrovia Caltagirone-Gela".
1427:, which connects the suburbs of the city's territory to the 1362:
Express, currently Intercity-Night with beds and couchettes
884: 3172:
Sergi, Giuseppe (1980). "Nuova ferrovia Caltagirone-Gela".
2226:"Decreto del Ministro delle infrastrutture e dei trasporti" 1989:"Decreto del Ministro delle infrastrutture e dei trasporti" 727:
The network, which can be defined as minor because of its
167:
to the port of Palermo; in 1869 the first section between
291:, which with its tracks encircles the enormous massif of 1465:
and consists of 2 lines, connecting Palermo Centrale to
423:, a rail line with suburban and metropolitan functions. 394:'s government, underwent little change since then until 117:
despite the fact that the exploitation of the island's
2590:"Comune di Palermo - Metropolitana automatica Leggera" 2525:"Rfi: investimento da 35 mln in Sicilia per Canicatti" 1776:
Another extra-urban line was the tramway, of electric
1725:
Other metro "sections" are under construction: Nesima-
1058:
With the doubling of the Palermo-Messina section from
816:
Obsolescence and failure to upgrade the Sicilian lines
743:
The railcar ALn 56.06 (series ALn 56.01-06), built by
659:
that required double or triple pulling in the days of
2174: 1642:
station and the northern suburbs of San Lorenzo, the
2950:
Tuttotreno Tema 14, Lo scartamento ridotto in Italia
2421:"Palermo - Agrigento - Palermo-Agrigento - Italferr" 1804:
area and the Porto Empedocle-Lucia for those in the
601:, it becomes double-track again at Targia as far as 406:
Extension of the Sicilian railway network as of 1950
940:on the Palermo-Trapani, to 16 per thousand between 643:because the primary interest was mainly in getting 2447:"Messina - Siracusa - Messina-Siracusa - Italferr" 1787:Extensive extra-urban tramway lines were built in 1827:Map of the 4 lines of the Palermo tramway network 1416:, sometimes improperly referred to as a "metro." 984:, ferrying rolling stock between the stations of 54:network in operation covers a length of 1369 km. 3163:Ogliari, Francesco (1977). "Dilettoso viaggio". 867:, for train running control installed on 901 km; 2781: 2769: 2251:Notizie flash, in Itreni 1 (2002), n. 233, p. 6 507:to reach Trapani from which it can continue to 3118:La rete FS a scartamento ridotto della Sicilia 860:Traffic safety is ensured by the presence of: 552:, among others, ran on this line. In the late 3190:Sergio Cannarozzo, Salvatore Amoroso (1984). 3181:Sergio Cannarozzo, Salvatore Amoroso (1979). 2997:Lo Stato e le ferrovie in Sicilia (1860-1895) 8: 2957:Formigari, Vittorio; Romano, Giulio (2001). 2261: 2259: 2257: 1451:Palermo's first metropolitan railway service 956:and 35 per thousand between Caltagirone and 3004:Giuliani, Paolo; Sirolli, Raffaele (2004). 2133:Cenni sulla storia delle solfare in Sicilia 1149:Rapid, later discontinued in Sicilian sec. 875:, for guidance support operating on 468 km. 271:Sicilian railways in the early 20th century 252:SocietĂ  per le Strade Ferrate della Sicilia 2298:: CS1 maint: location missing publisher ( 2046:: CS1 maint: location missing publisher ( 1431:as far as Giampilieri, south of the city. 1340:Porta Nuova - Palermo Centrale - Siracusa 857:+DPC) are operated on a total of 1340 km. 319:Mountains, disgorging in the direction of 42:Catania-Randazzo-Linguaglossa-Riposto line 31:lines since 1986, is operated entirely by 2939:Ettore Caliri, Salvatore Amoroso (1986). 2083: 2004:Storia della Sicilia medioevale e moderna 1773:; opened in 1915, it was closed in 1934. 1453:activated in 1990 on the occasion of the 2212: 1868:Corso Calatafimi - Stazione Notarbartolo 1630:, passing through the historic center, ( 1389:Suburban and metropolitan rail transport 1108: 431:The line involves the two urban hubs of 343:Mountains was not considered justified. 200:coastal line between Licata and Syracuse 3156:Le ferrovie della Sicilia sud-orientale 3135:Molino, Nico; Sinchetto, Beppe (1985). 3097:Molino, Nico; Pautasso, Sergio (1983). 3043:Amici e Maestri: lo Stato e le ferrovie 2735:Tartaglia, Andrea (February 18, 2019). 1931: 1357:Centrale – Palermo Centrale - Siracusa 1241:S. Lucia - Palermo Centrale - Siracusa 645:sulfur from the inland basins of Sicily 163:with the specific purpose of conveying 3099:Le automotrici della prima generazione 3064:. Newton Abbott, David & Charles. 2354: 2291: 2144: 2039: 880:Vehicles in operation and travel speed 716:Official Journal of the European Union 61:consist of 8 lines, spanning all nine 3083:. Palermo: Tipografia Michele Amenta. 2329: 2327: 2311: 2309: 2169: 2167: 2165: 2156: 2100: 2098: 2096: 2094: 2092: 1962: 1960: 1958: 1956: 1423:by adapting part of the route of the 1129:Agrigento Centrale - Porto Empedocle 7: 3060:Kalla-Bishop, Peter Michael (1970). 2335:"Sblocca Italia – L'elenco completo" 1445:Palermo metropolitan railway service 1001:lines, on the Messina-Catania line. 230:). By 1881 with the continuation on 195:) also a major sulfur entrepreneur. 113:in Italy, this was not the case for 3137:Linee ferroviarie. La Paola-Cosenza 2240:Spinta in coda con sgancio in corsa 1940:"Azienda: la storia della ferrovia" 1222:Discontinued between 2009 and 2010 964:, gradients reach 40 per thousand. 479:; electrification work reached the 3079:Maggiore Perni, Francesco (1861). 3006:"L'impegno di RFI nel Mezzogiorno" 2999:. Caltanissetta: Sciascia Editore. 2284:Maggiore Perni, Francesco (1861). 2274:CIPE resolution dated May 27, 2005 2242:, in iTreni oggi n. 66/1986, p. 24 2032:Maggiore Perni, Francesco (1861). 2006:. Bari: LaTerza. pp. 510–511. 1916:History of rail transport in Italy 1765:following a 14.3-km route through 1572:Palermo Notarbartolo-Giachery line 804:Electrification and track doubling 784:and Agrigento, and cities such as 14: 1477:Palermo Centrale-Punta Raisi line 1346:Express with beds and couchettes 849:Control and security technologies 1881:A tramway of the Messina tramway 1256:Roma Termini - Palermo Centrale 1086:, with a 35-million investment. 1005:services, has also contributed. 315:, from where it would cross the 153:Messina-Catania-Siracusa railway 3081:Delle strade ferrate in Sicilia 2883:Gela 15 anni dopo,in Itreni-150 2286:Delle strade ferrate in Sicilia 2034:Delle strade ferrate in Sicilia 1780:type, which ran up the hill of 1264:Intercity, then Intercity Plus 1075:because it did not include its 1017:Fast lines and ongoing projects 808:The majority of the network is 339:and the even more inaccessible 2952:. Albignasego: Duegi Editrice. 2576:Articolo sul "treno dei Mille" 2368:"Sito Italferr, archivio news" 1968:"RFI La rete oggi in: Sicilia" 1236:- Siracusa - Palermo Centrale 609:The backbone of central Sicily 556:period, with electrification, 417:Syracuse-Ragusa-Gela-Canicattì 1: 3165:Storia dei Trasporti Italiani 3062:Mediterranean island railways 2925:(223 ed.). Edizioni Etr. 2848:. Milan: Arcipelago edizioni. 2556:Articolo sull'Akragas Express 1921:Ferrovie dello Stato Italiane 206:to the coastal refineries of 37:; an exception is the 111-km 3208:Tesoriere, Giuseppe (1994). 3199:Squarzina, Federico (1963). 2995:Giuffrida, Romualdo (1967). 2976:Giarrizzo, Giuseppe (1986). 2770:Formigari & Romano (2001 2017:Brancato, Francesco (1965). 1414:metropolitan railway service 1393:In Sicily there is only one 1053:Catania-Fontanarossa Airport 1037:metropolitan railway service 548:, ALn 56 Fiat railcars, and 109:had the pride of having the 3167:. 31–33. Milan: Cavallotti. 3032:Inzerilli, Massimo (2013). 2782:Molino & Sinchetto 1985 1865:CEP - Stazione Notarbartolo 1028:Berlin–Palermo railway axis 501:Palermo-Punta Raisi Airport 107:Kingdom of the Two Sicilies 3262: 3120:. Turin: Edizioni Elledi. 2959:123 anni di tram a Messina 2948:Federici, Antonio (1999). 2866:. Rome: Donzelli Editore. 2002:Mack Smith, Denis (1973). 1836:Bombardier Flexity Outlook 1606:work was expected by 2012. 599:Priolo petrochemical plant 477:Peloritan side of the city 471:; when traction was still 249:was only activated by the 27:, which has included only 3154:Muscolino, Piero (2006). 3045:. Bari: edizioni Dedalo. 3041:Ippolito, Felice (1988). 2980:. Bari: Laterza editore. 2862:Barone, Giuseppe (2002). 2386:"l'interporto di catania" 1682:and to reach Librino and 1664:The first section of the 1580:The line has 4 stations: 1490:, and from the latter to 712:Rete Ferroviaria Italiana 536:and Giampilieri. Elegant 34:Rete Ferroviaria Italiana 16:Railway network in Sicily 3219:La Tecnica Professionale 2932:La Tecnica Professionale 2901:La Tecnica Professionale 2892:La tecnica professionale 2817:"Messina risale in tram" 2713:Metropolitana Di Catania 1714:began in February 2019. 1700:Catania Centrale station 1429:Messina Centrale station 1343:discontinued since 2011 1326:discontinued since 2007 1283:Touristic (summer only) 1258:Roma Termini - Siracusa 1143:Roma Termini - Siracusa 683:mines of Caltanissetta, 390:and the first decade of 198:The construction of the 3236:Railway lines in Sicily 3212:. Palermo: Zedi Italia. 2881:Caliri, Ettore (1994). 2844:Abate, Ogliari (2008). 1885:The 7.7-kilometer-long 1425:railway line to Catania 1132:periodical, since 2010 1098:Sicilian trains by name 767:Network characteristics 672:; the proximity to the 668:and beyond through the 427:The Tyrrhenian backbone 238:had finally been made. 138:Victor Emmanuel Railway 44:, which is operated by 3241:Railway lines in Italy 3183:Le ferrovie in Sicilia 3090:Ingegneria Ferroviaria 2910:Ingegneria Ferroviaria 2864:Le vie del Mezzogiorno 2803:Giornale di Sicilia.it 1882: 1839: 1828: 1722: 1661: 1447: 1280:periodical since 2005 1047:that runs through the 977: 893: 748: 618: 407: 280: 272: 234:the connection to the 102: 89: 3116:Molino, Nico (1985). 2885:. Salò: Edizioni ETR. 2392:on September 26, 2009 1880: 1861:Stazione Notarbartolo 1834: 1826: 1720: 1660:Subway map of Catania 1659: 1509:Palazzo Reale-Orleans 1442: 1245:discontinued in 2011 1230:Freccia della Laguna 1218:- Agrigento Centrale 1190:discontinued in 2007 975: 887: 742: 616: 405: 362:and with a series of 287:Also in Catania, the 278: 270: 100: 87: 3176:(1). Desenzano: ETR. 2961:. Cortona: Calosci. 2741:MobilitĂ .org.Catania 2691:Filodiretto Monreale 2374:on November 8, 2013. 1911:Ferrovia Circumetnea 1819:Palermo tram network 1712:Fontanarossa airport 1684:Fontanarossa airport 1471:Palermo Notarbartolo 1007:Rail freight traffic 954:Valguarnera Caropepe 753:Ferrovia Circumetnea 591:Fontanarossa airport 388:Unification of Italy 358:in the direction of 193:Ferrovia Circumetnea 191:(the builder of the 129:Giuseppe Garibaldi's 47:Ferrovia Circumetnea 3246:Transport in Sicily 2805:, December 30, 2015 2665:Giornale di Sicilia 2477:Giornale di Sicilia 2147:, pp. 132–135) 1747:2009 Messina floods 1678:, Piano Tavola and 1541:Isola delle Femmine 1492:Punta Raisi Airport 1455:1990 FIFA World Cup 1304:Touristic (May 11) 1041:Punta Raisi Airport 962:Circumetnea Railway 831:Punta Raisi airport 735:Lines in concession 527:The Ionian backbone 421:Circumetnea railway 412:Punta Raisi Airport 289:Circumetnea railway 3158:. Ragusa: EdiARGO. 3139:. Torino: Elledi. 2943:. Palermo: Aracne. 2799:, 30 December 2015 2535:on August 16, 2015 2479:. October 16, 2017 1883: 1873:Tramway of Messina 1840: 1829: 1723: 1662: 1600:Planned expansions 1448: 1367:Trinacria Express 1211:Milano Centrale - 1208:Agrigento Centrale 986:Villa San Giovanni 978: 894: 749: 723:Minor inland lines 619: 408: 396:after World War II 281: 273: 183:activities of the 124:Le ferrovie sicule 103: 90: 50:. As of 2018, the 3101:. Turin: ElleDi. 3092:(11). Rome: CIFI. 3052:978-88-220-6076-1 2815:Russo, Giovanni. 2320:. April 14, 2017. 2062:Vita di Garibaldi 1855:Stazione Centrale 1636:Politeama Theater 1525:San Lorenzo Colli 1386: 1385: 1270:Treno del Barocco 990:Messina Marittima 382:Network extension 241:The section from 3253: 3222: 3213: 3204: 3195: 3186: 3177: 3168: 3159: 3150: 3131: 3112: 3093: 3084: 3075: 3056: 3037: 3028: 3026: 3024: 3010: 3000: 2991: 2972: 2953: 2944: 2935: 2926: 2917: 2904: 2895: 2886: 2877: 2858: 2855:Amm. Ferroviaria 2849: 2832: 2831: 2829: 2827: 2812: 2806: 2800: 2791: 2785: 2779: 2773: 2767: 2761: 2758: 2752: 2751: 2749: 2747: 2732: 2726: 2723: 2717: 2716: 2708: 2702: 2701: 2699: 2697: 2683: 2677: 2676: 2674: 2672: 2657: 2651: 2650: 2648: 2646: 2639:Mobilita Palermo 2632: 2626: 2625: 2623: 2621: 2607: 2601: 2600: 2598: 2596: 2586: 2580: 2579: 2571: 2565: 2564: 2559:, archived from 2551: 2545: 2544: 2542: 2540: 2531:. Archived from 2521: 2515: 2514: 2512: 2506:, archived from 2505: 2495: 2489: 2488: 2486: 2484: 2469: 2463: 2462: 2460: 2458: 2453:on July 25, 2015 2449:. Archived from 2443: 2437: 2436: 2434: 2432: 2427:on July 25, 2015 2423:. Archived from 2417: 2411: 2408: 2402: 2401: 2399: 2397: 2388:. Archived from 2382: 2376: 2375: 2370:. Archived from 2364: 2358: 2352: 2346: 2345: 2343: 2341: 2331: 2322: 2321: 2313: 2304: 2303: 2297: 2289: 2281: 2275: 2272: 2266: 2263: 2252: 2249: 2243: 2236: 2230: 2229: 2222: 2216: 2210: 2204: 2201: 2195: 2192: 2186: 2185: 2183: 2181: 2171: 2160: 2154: 2148: 2142: 2136: 2129: 2123: 2122: 2120: 2118: 2109:. Archived from 2102: 2087: 2081: 2075: 2072: 2066: 2065: 2058: 2052: 2051: 2045: 2037: 2029: 2023: 2022: 2014: 2008: 2007: 1999: 1993: 1992: 1985: 1979: 1978: 1976: 1974: 1964: 1951: 1950: 1948: 1946: 1936: 1459:Palermo Centrale 1371:Palermo Centrale 1309:Treno dell'Etna 1288:Treno dei Mille 1234:Venezia S. Lucia 1186:Palermo Centrale 1164:Palermo Centrale 1126:Akragas Express 1109: 1073:province of Enna 1023:high-speed lines 745:Fiat Ferroviaria 670:Plain of Catania 513:Mazara del Vallo 505:San Vito Lo Capo 481:Sicilian capital 303:) Schettino and 297:province of Enna 189:Robert Trewhella 3261: 3260: 3256: 3255: 3254: 3252: 3251: 3250: 3226: 3225: 3216: 3207: 3198: 3189: 3180: 3171: 3162: 3153: 3147: 3134: 3128: 3115: 3109: 3096: 3087: 3078: 3072: 3059: 3053: 3040: 3031: 3022: 3020: 3008: 3003: 2994: 2988: 2975: 2969: 2956: 2947: 2938: 2929: 2920: 2907: 2898: 2889: 2880: 2874: 2861: 2852: 2843: 2840: 2835: 2825: 2823: 2814: 2813: 2809: 2793: 2792: 2788: 2780: 2776: 2768: 2764: 2759: 2755: 2745: 2743: 2734: 2733: 2729: 2724: 2720: 2710: 2709: 2705: 2695: 2693: 2685: 2684: 2680: 2670: 2668: 2659: 2658: 2654: 2644: 2642: 2634: 2633: 2629: 2619: 2617: 2609: 2608: 2604: 2594: 2592: 2588: 2587: 2583: 2573: 2572: 2568: 2563:on May 26, 2010 2553: 2552: 2548: 2538: 2536: 2523: 2522: 2518: 2513:on July 2, 2013 2510: 2503: 2497: 2496: 2492: 2482: 2480: 2471: 2470: 2466: 2456: 2454: 2445: 2444: 2440: 2430: 2428: 2419: 2418: 2414: 2409: 2405: 2395: 2393: 2384: 2383: 2379: 2366: 2365: 2361: 2353: 2349: 2339: 2337: 2333: 2332: 2325: 2315: 2314: 2307: 2290: 2283: 2282: 2278: 2273: 2269: 2264: 2255: 2250: 2246: 2238:Ettore Caliri, 2237: 2233: 2224: 2223: 2219: 2211: 2207: 2202: 2198: 2193: 2189: 2179: 2177: 2173: 2172: 2163: 2155: 2151: 2143: 2139: 2130: 2126: 2116: 2114: 2113:on May 22, 2021 2104: 2103: 2090: 2084:Giarrizzo (1986 2082: 2078: 2073: 2069: 2060: 2059: 2055: 2038: 2031: 2030: 2026: 2016: 2015: 2011: 2001: 2000: 1996: 1987: 1986: 1982: 1972: 1970: 1966: 1965: 1954: 1944: 1942: 1938: 1937: 1933: 1929: 1907: 1901: 1887:Messina tramway 1875: 1821: 1755: 1739: 1708:Messina-Catania 1654: 1632:Central station 1602: 1574: 1479: 1437: 1391: 1334:Treno del Sole 1204:Milano Centrale 1199:Freccia del Sud 1162:Roma Termini - 1100: 1019: 970: 958:Piazza Armerina 950:rack and pinion 922: 882: 851: 818: 806: 798:Porto Empedocle 769: 737: 725: 611: 582:central Messina 534:central Messina 529: 494:Termini Imerese 429: 384: 356:Erean Mountains 337:Erean Mountains 321:Termini Imerese 208:Porto Empedocle 95: 17: 12: 11: 5: 3259: 3257: 3249: 3248: 3243: 3238: 3228: 3227: 3224: 3223: 3214: 3205: 3196: 3187: 3178: 3169: 3160: 3151: 3145: 3132: 3126: 3113: 3107: 3094: 3085: 3076: 3070: 3057: 3051: 3038: 3029: 3001: 2992: 2986: 2973: 2967: 2954: 2945: 2936: 2927: 2918: 2905: 2896: 2887: 2878: 2872: 2859: 2850: 2839: 2836: 2834: 2833: 2807: 2786: 2774: 2762: 2753: 2727: 2718: 2703: 2678: 2652: 2641:. May 27, 2019 2627: 2602: 2581: 2566: 2546: 2516: 2490: 2464: 2438: 2412: 2403: 2377: 2359: 2347: 2323: 2305: 2276: 2267: 2253: 2244: 2231: 2217: 2213:Federici (1999 2205: 2196: 2187: 2161: 2149: 2137: 2124: 2088: 2076: 2067: 2053: 2024: 2009: 1994: 1980: 1952: 1930: 1928: 1925: 1924: 1923: 1918: 1913: 1906: 1903: 1874: 1871: 1870: 1869: 1866: 1863: 1859:Borgo Nuovo - 1857: 1820: 1817: 1815:or bus lines. 1754: 1751: 1738: 1735: 1653: 1650: 1649: 1648: 1624:Oreto-Guadagna 1616: 1615: 1608: 1607: 1601: 1598: 1597: 1596: 1593: 1590: 1587: 1573: 1570: 1569: 1568: 1562: 1559: 1554: 1548: 1543: 1538: 1535: 1534:Tommaso Natale 1532: 1529: 1526: 1523: 1518: 1513: 1510: 1507: 1504: 1501: 1478: 1475: 1436: 1433: 1410:State Railways 1390: 1387: 1384: 1383: 1380: 1377: 1368: 1364: 1363: 1360: 1358: 1352: 1348: 1347: 1344: 1341: 1335: 1331: 1330: 1327: 1324: 1315:Porta Nuova - 1310: 1306: 1305: 1302: 1299: 1289: 1285: 1284: 1281: 1278: 1272: 1266: 1265: 1262: 1260: 1254: 1250: 1249: 1246: 1243: 1231: 1227: 1226: 1223: 1220: 1201: 1195: 1194: 1191: 1188: 1179: 1173: 1172: 1169: 1167: 1155: 1151: 1150: 1147: 1144: 1141: 1137: 1136: 1133: 1130: 1127: 1123: 1122: 1119: 1116: 1113: 1099: 1096: 1084:Comiso Airport 1049:Etnean capital 1045:Ionian railway 1018: 1015: 969: 966: 921: 918: 898:State Railways 881: 878: 877: 876: 869: 868: 850: 847: 817: 814: 805: 802: 768: 765: 736: 733: 724: 721: 705:eastern Sicily 674:Etnean capital 628:Santa Caterina 610: 607: 528: 525: 445:Tyrrhenian Sea 428: 425: 383: 380: 374:, just before 325:Tyrrhenian Sea 161:Lercara Friddi 111:first railroad 94: 91: 68:road transport 29:standard-gauge 15: 13: 10: 9: 6: 4: 3: 2: 3258: 3247: 3244: 3242: 3239: 3237: 3234: 3233: 3231: 3221:. Rome: CIFI. 3220: 3215: 3211: 3206: 3202: 3197: 3193: 3188: 3184: 3179: 3175: 3170: 3166: 3161: 3157: 3152: 3148: 3146:88-7649-032-9 3142: 3138: 3133: 3129: 3127:88-7649-037-X 3123: 3119: 3114: 3110: 3108:88-7649-016-7 3104: 3100: 3095: 3091: 3086: 3082: 3077: 3073: 3071:0-7153-4761-6 3067: 3063: 3058: 3054: 3048: 3044: 3039: 3035: 3030: 3018: 3014: 3013:RFI Argomenti 3007: 3002: 2998: 2993: 2989: 2987:88-420-2786-3 2983: 2979: 2974: 2970: 2968:88-7785-175-9 2964: 2960: 2955: 2951: 2946: 2942: 2937: 2934:. Rome: CIFI. 2933: 2928: 2924: 2919: 2916:(7): 461–472. 2915: 2911: 2906: 2903:. Rome: CIFI. 2902: 2897: 2894:. Rome: CIFI. 2893: 2888: 2884: 2879: 2875: 2873:88-7989-684-9 2869: 2865: 2860: 2856: 2851: 2847: 2842: 2841: 2837: 2826:September 18, 2822: 2818: 2811: 2808: 2804: 2798: 2797: 2790: 2787: 2783: 2778: 2775: 2772:, p. 23) 2771: 2766: 2763: 2757: 2754: 2742: 2738: 2731: 2728: 2722: 2719: 2715: 2714: 2707: 2704: 2692: 2688: 2682: 2679: 2667:. 27 May 2019 2666: 2662: 2656: 2653: 2640: 2637: 2631: 2628: 2616: 2612: 2606: 2603: 2591: 2585: 2582: 2578: 2577: 2570: 2567: 2562: 2558: 2557: 2550: 2547: 2539:September 13, 2534: 2530: 2526: 2520: 2517: 2509: 2502: 2501: 2494: 2491: 2478: 2474: 2468: 2465: 2457:September 14, 2452: 2448: 2442: 2439: 2431:September 14, 2426: 2422: 2416: 2413: 2407: 2404: 2391: 2387: 2381: 2378: 2373: 2369: 2363: 2360: 2357:, p. 16) 2356: 2351: 2348: 2340:September 13, 2336: 2330: 2328: 2324: 2319: 2312: 2310: 2306: 2301: 2295: 2287: 2280: 2277: 2271: 2268: 2262: 2260: 2258: 2254: 2248: 2245: 2241: 2235: 2232: 2227: 2221: 2218: 2215:, p. 67) 2214: 2209: 2206: 2200: 2197: 2191: 2188: 2176: 2170: 2168: 2166: 2162: 2159:, p. 15) 2158: 2153: 2150: 2146: 2141: 2138: 2134: 2128: 2125: 2112: 2108: 2101: 2099: 2097: 2095: 2093: 2089: 2086:, p. 60) 2085: 2080: 2077: 2071: 2068: 2063: 2057: 2054: 2049: 2043: 2035: 2028: 2025: 2021:. p. 11. 2020: 2013: 2010: 2005: 1998: 1995: 1990: 1984: 1981: 1973:September 26, 1969: 1963: 1961: 1959: 1957: 1953: 1941: 1935: 1932: 1926: 1922: 1919: 1917: 1914: 1912: 1909: 1908: 1904: 1902: 1899: 1895: 1893: 1888: 1879: 1872: 1867: 1864: 1862: 1858: 1856: 1852: 1851: 1850: 1847: 1845: 1837: 1833: 1825: 1818: 1816: 1814: 1809: 1807: 1803: 1800:mines in the 1799: 1793: 1790: 1785: 1783: 1779: 1774: 1772: 1768: 1764: 1759: 1752: 1750: 1748: 1744: 1736: 1734: 1732: 1728: 1719: 1715: 1713: 1709: 1703: 1701: 1696: 1692: 1687: 1685: 1681: 1677: 1672: 1667: 1666:Catania metro 1658: 1651: 1645: 1641: 1637: 1633: 1629: 1625: 1621: 1618: 1617: 1613: 1610: 1609: 1604: 1603: 1599: 1594: 1591: 1588: 1586: 1583: 1582: 1581: 1578: 1571: 1566: 1563: 1560: 1558: 1555: 1553:Torre Ciachea 1552: 1549: 1547: 1544: 1542: 1539: 1537:Sferracavallo 1536: 1533: 1530: 1527: 1524: 1522: 1519: 1517: 1514: 1511: 1508: 1505: 1502: 1500: 1497: 1496: 1495: 1493: 1489: 1485: 1476: 1474: 1473:to Giachery. 1472: 1468: 1464: 1460: 1456: 1452: 1446: 1441: 1434: 1432: 1430: 1426: 1422: 1417: 1415: 1411: 1407: 1402: 1400: 1399:Catania metro 1396: 1388: 1381: 1378: 1376: 1372: 1369: 1366: 1365: 1361: 1359: 1356: 1353: 1350: 1349: 1345: 1342: 1339: 1336: 1333: 1332: 1328: 1325: 1322: 1318: 1314: 1311: 1308: 1307: 1303: 1300: 1298: 1294: 1290: 1287: 1286: 1282: 1279: 1276: 1273: 1271: 1268: 1267: 1263: 1261: 1259: 1255: 1252: 1251: 1247: 1244: 1242: 1240: 1235: 1232: 1229: 1228: 1224: 1221: 1219: 1217: 1214: 1209: 1205: 1202: 1200: 1197: 1196: 1192: 1189: 1187: 1183: 1180: 1178: 1175: 1174: 1170: 1168: 1166: 1165: 1159: 1156: 1153: 1152: 1148: 1145: 1142: 1139: 1138: 1134: 1131: 1128: 1125: 1124: 1120: 1117: 1114: 1111: 1110: 1107: 1105: 1097: 1095: 1091: 1087: 1085: 1080: 1078: 1074: 1070: 1064: 1061: 1056: 1054: 1050: 1046: 1042: 1038: 1033: 1029: 1024: 1021:There are no 1016: 1014: 1012: 1008: 1002: 1000: 996: 991: 987: 983: 974: 967: 965: 963: 959: 955: 951: 947: 943: 939: 938:Castelvetrano 935: 931: 927: 919: 917: 915: 910: 906: 903: 899: 891: 886: 879: 874: 871: 870: 866: 863: 862: 861: 858: 856: 848: 846: 844: 840: 836: 832: 828: 823: 815: 813: 811: 803: 801: 799: 795: 794:Castelvetrano 791: 787: 783: 782:Eraclea Minoa 779: 775: 766: 764: 762: 756: 754: 746: 741: 734: 732: 730: 722: 720: 717: 713: 708: 706: 702: 697: 693: 691: 686: 682: 677: 675: 671: 667: 662: 658: 652: 648: 646: 642: 638: 637:Caltanissetta 634: 629: 625: 615: 608: 606: 604: 600: 596: 592: 587: 583: 577: 575: 571: 567: 563: 559: 555: 551: 547: 543: 539: 535: 526: 524: 522: 518: 517:Castelvetrano 514: 510: 506: 502: 497: 495: 491: 487: 482: 478: 474: 473:steam-powered 470: 466: 461: 457: 453: 452:Caltanissetta 448: 446: 442: 438: 434: 426: 424: 422: 418: 413: 404: 400: 397: 393: 389: 381: 379: 377: 373: 369: 365: 361: 357: 353: 349: 344: 342: 338: 334: 330: 326: 322: 318: 314: 310: 306: 302: 298: 294: 290: 285: 277: 269: 265: 262: 258: 254: 253: 248: 244: 239: 237: 233: 229: 225: 224:Casteltermini 221: 217: 213: 212:Caltanissetta 209: 205: 201: 196: 194: 190: 186: 182: 178: 174: 170: 166: 162: 158: 154: 150: 145: 143: 139: 135: 130: 125: 120: 116: 112: 108: 99: 92: 86: 82: 80: 79:Mediterranean 75: 73: 69: 64: 60: 57:The Sicilian 55: 53: 49: 48: 43: 40: 36: 35: 30: 26: 23: 22: 3218: 3209: 3200: 3191: 3182: 3173: 3164: 3155: 3136: 3117: 3098: 3089: 3080: 3061: 3042: 3036:. Salò: ETR. 3033: 3021:. Retrieved 3016: 3012: 2996: 2977: 2958: 2949: 2940: 2931: 2922: 2913: 2909: 2900: 2891: 2882: 2863: 2854: 2845: 2838:Bibliography 2824:. Retrieved 2820: 2810: 2802: 2795: 2789: 2784:, p. 9. 2777: 2765: 2756: 2746:February 24, 2744:. Retrieved 2740: 2730: 2721: 2712: 2706: 2694:. Retrieved 2690: 2681: 2669:. Retrieved 2664: 2655: 2643:. Retrieved 2638: 2630: 2618:. Retrieved 2615:PalermoToday 2614: 2605: 2593:. Retrieved 2584: 2575: 2569: 2561:the original 2555: 2549: 2537:. Retrieved 2533:the original 2528: 2519: 2508:the original 2499: 2493: 2481:. Retrieved 2476: 2467: 2455:. Retrieved 2451:the original 2441: 2429:. Retrieved 2425:the original 2415: 2406: 2394:. Retrieved 2390:the original 2380: 2372:the original 2362: 2355:Molino (1985 2350: 2338:. Retrieved 2317: 2285: 2279: 2270: 2247: 2239: 2234: 2220: 2208: 2199: 2190: 2178:. Retrieved 2152: 2145:Barone (2002 2140: 2132: 2127: 2117:September 4, 2115:. Retrieved 2111:the original 2079: 2070: 2061: 2056: 2033: 2027: 2018: 2012: 2003: 1997: 1983: 1971:. Retrieved 1943:. Retrieved 1934: 1900: 1896: 1884: 1848: 1841: 1810: 1794: 1786: 1775: 1767:Aci Castello 1760: 1756: 1740: 1727:Misterbianco 1724: 1704: 1688: 1680:Misterbianco 1663: 1640:Notarbartolo 1634:, ex-Borsa, 1612:Railway ring 1585:Notarbartolo 1579: 1575: 1531:Cardillo-Zen 1516:Notarbartolo 1480: 1449: 1418: 1403: 1392: 1257: 1237: 1216:Roma Termini 1210: 1161: 1158:Roma Termini 1101: 1092: 1088: 1081: 1065: 1057: 1020: 1003: 979: 923: 911: 907: 895: 859: 852: 827:obsolescence 819: 810:single-track 807: 770: 757: 750: 729:narrow gauge 726: 709: 698: 694: 678: 653: 649: 624:Roccapalumba 620: 578: 574:Roma Termini 530: 498: 449: 430: 409: 385: 345: 286: 282: 250: 240: 197: 146: 123: 104: 76: 56: 45: 39:narrow-gauge 32: 25:rail network 24: 20: 18: 2483:October 17, 2396:November 9, 2180:November 6, 2157:Sergi (1980 1945:November 7, 1853:Roccella - 1565:Punta Raisi 1467:Punta Raisi 1379:since 2001 1375:Punta Raisi 1301:since 2009 1291:Calatafimi/ 1253:Peloritano 1177:Conca d'Oro 1171:Intercity. 1160:- Siracusa 839:Caltagirone 701:Catenanuova 690:A19 highway 666:Catenanuova 372:Castelbuono 3230:Categories 3019:(4): 6–101 2821:Mondo Tram 2696:August 26, 2671:August 27, 2645:August 27, 2620:August 27, 2595:August 27, 2288:. Palermo. 2131:M. Gatto, 2036:. Palermo. 1927:References 1813:trolleybus 1771:Aci Trezza 1620:Light rail 1567:(airport). 1463:Trenitalia 1412:operate a 1351:Trinacria 1184:Termini - 1154:Archimede 1135:Touristic 995:Tyrrhenian 914:landslides 888:A pair of 568:and later 469:locomotive 465:Peloritani 352:high-speed 293:Mount Etna 2294:cite book 2042:cite book 1806:Agrigento 1778:funicular 1626:UPL with 1561:Piraineto 1382:Regional 1323:Centrale 1277:- Ragusa 960:. On the 778:Selinunte 761:Pantalica 685:Villarosa 521:Partinico 492:plant in 392:Mussolini 360:Regalbuto 323:, on the 309:Leonforte 301:Centuripe 216:Canicattì 173:Leonforte 165:mined ore 63:provinces 1905:See also 1782:Monreale 1763:Acireale 1753:Tramways 1628:Mondello 1595:Giachery 1589:Federico 1528:La Malfa 1503:Guadagna 1499:Centrale 1329:Express 1317:Siracusa 1275:Siracusa 1248:Express 1225:Express 1213:Siracusa 946:Syracuse 641:Girgenti 603:Siracusa 586:Taormina 532:between 488:and the 243:Syracuse 220:Comitini 149:Bagheria 59:railways 21:Sicily's 3203:. ILTE. 3023:May 14, 2978:Catania 2923:I Treni 2318:FS News 1844:Palermo 1789:Messina 1743:Messina 1737:Messina 1731:Paternò 1706:of the 1691:Galatea 1676:Paternò 1652:Catania 1521:Francia 1443:Map of 1435:Palermo 1421:Messina 1406:Palermo 1321:Palermo 1297:Marsala 1293:Segesta 1239:Venezia 1140:Aurora 1118:Period 1077:capital 1032:Palermo 968:Traffic 942:Lentini 902:ALn 668 890:ALn 668 822:Fascist 786:Sciacca 595:Augusta 554:postwar 550:ALn 772 509:Marsala 486:Palermo 460:Catania 441:Trapani 437:Messina 433:Palermo 368:Nebrodi 364:tunnels 348:RFI SpA 341:Madonie 333:Nicosia 317:Madonie 313:Nicosia 305:Paternò 228:Lercara 169:Catania 157:Palermo 142:Catania 134:Livorno 105:If the 93:History 3174:ITreni 3143:  3124:  3105:  3068:  3049:  2984:  2965:  2870:  2529:AGI.it 1892:Alstom 1808:area. 1802:Ennese 1798:sulfur 1557:Carini 1551:Carini 1546:Capaci 1506:Vespri 1488:Carini 1484:Capaci 1408:, the 1397:, the 1355:Milano 1338:Torino 1313:Torino 1115:Route 1104:Sicily 1069:tunnel 999:Ionian 982:strait 934:Ragusa 930:Modica 920:Slopes 790:Ribera 774:Licata 681:sulfur 458:, and 376:CefalĂą 261:Modica 232:Licata 204:sulfur 185:sulfur 181:mining 119:sulfur 115:Sicily 72:sulfur 3009:(PDF) 2511:(PDF) 2504:(PDF) 1695:Porto 1592:Fiera 1512:Lolli 1395:metro 1146:1974 1121:Note 1112:Name 1060:Patti 835:Patti 661:steam 622:from 570:E.656 566:E.646 562:E.626 558:E.636 236:coast 3141:ISBN 3122:ISBN 3103:ISBN 3066:ISBN 3047:ISBN 3025:2013 2982:ISBN 2963:ISBN 2868:ISBN 2828:2014 2748:2019 2698:2020 2673:2019 2647:2019 2622:2019 2597:2019 2541:2015 2485:2017 2459:2015 2433:2015 2398:2009 2342:2015 2300:link 2182:2009 2119:2021 2048:link 1975:2018 1947:2009 1769:and 1486:and 1469:and 1182:Roma 1011:Gela 988:and 944:and 932:and 926:Enna 865:SCMT 843:Gela 796:and 657:Enna 635:and 633:Enna 544:and 515:and 490:FIAT 456:Enna 435:and 329:Enna 311:and 257:Gela 247:Noto 226:and 214:and 177:Enna 1741:In 1671:FCE 1644:ZEN 1638:), 1404:In 873:SSC 855:CTC 546:480 542:746 538:625 245:to 3232:: 3015:. 3011:. 2914:55 2912:. 2819:. 2801:, 2739:. 2689:. 2663:. 2613:. 2527:. 2475:. 2326:^ 2308:^ 2296:}} 2292:{{ 2256:^ 2164:^ 2091:^ 2044:}} 2040:{{ 1955:^ 1686:. 1401:. 1373:– 1319:- 1295:- 1206:- 841:- 800:. 792:, 788:, 780:, 763:. 576:. 560:, 523:. 511:, 454:, 222:, 52:FS 3149:. 3130:. 3111:. 3074:. 3055:. 3027:. 3017:2 2990:. 2971:. 2876:. 2857:. 2830:. 2750:. 2700:. 2675:. 2649:. 2624:. 2599:. 2543:. 2487:. 2461:. 2435:. 2400:. 2344:. 2302:) 2228:. 2184:. 2121:. 2050:) 1991:. 1977:. 1949:. 1693:-

Index

Sicily's
standard-gauge
Rete Ferroviaria Italiana
narrow-gauge
Catania-Randazzo-Linguaglossa-Riposto line
Ferrovia Circumetnea
FS
railways
provinces
road transport
sulfur
Mediterranean


Kingdom of the Two Sicilies
first railroad
Sicily
sulfur
Giuseppe Garibaldi's
Livorno
Victor Emmanuel Railway
Catania
Bagheria
Messina-Catania-Siracusa railway
Palermo
Lercara Friddi
mined ore
Catania
Leonforte
Enna

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.

↑