953:
original one as part of or in compliance with the plan of a particular transmission project associated with the power line whether that part of a project's plan was planned by NAPOCOR/NPC, TransCo, and NGCP) of each structures or facilities which are steel poles, lattice towers, and portal towers from pedestal or foundation to top segment can take 1–2 days, while the completion of a right-of-way (ROW) or portion of a transmission line which involves structures are all installed or placed on lands already acquired and designated where they are located on that ROW depends on the power line portion's amount of structures, length, and how long do the structures or components part of that ROW arrive or be delivered which can range from days to years. First, on a land where the steel pole will be located, the precast concrete foundation laid underground and a cement is added to create the pole's pedestal. Second, the pedestal laid ground, then backfill up some of remaining holes between the gap. Third, the poles were laid in three to six segments, the butt segment (the lowermost), mid segment which are between the butt and top segments, and the top segment. The second to the last segment to the top and the top segment are where the insulators are placed and a steel
1510:
1450:
252:
1535:
1470:
1426:
1523:
1438:
1196:
a three-leveled lowercase letter "T" or a cross. Some newer anchor steel poles can have polymer composite dead-end insulator. Irregular variant has 3 horizontal dead-end insulators on a steel crossarm and another 3 arranged in a vertical pattern, has vertical insulator mounted on one side of a crossarm, at the center are 1-2 insulators, and on the pole's top segment is another steel crossarm used to support the overhead ground wire (OHGW) where it is used near the
Balintawak and Araneta substations. Newer anchor poles with flag design have 3 horizontal made of 22 porcelain discs and vertical insulators with 21 discs mounted on steel crossarms, with a crossarm at the top segment to support the OHGW.
1482:
949:
lines and used as spacer placing). In case of Sucat-Paco-Araneta-Balintawak transmission line, the method is to using spacer cart of NAPOCOR/NPC since the line was higher and hard to reach up (later TransCo from March 1, 2003 to
January 15, 2009 and NGCP since January 15, 2009). During its final stringing of conductors, the spacer placing took place. There are 6 spacer carts per line span. If there was a broken spacer (like snapping), it will replaced with the new spacer damper or springed spacer. Most portions of a transmission line use moving-joint spacers and weighed damper (spacer), used in relocated segments of the line.
1260:) are operated, maintained, and owned by NGCP, while those that were placed or built, acquired, and designated from July 2000 to January 14, 2009 are owned by TransCo and operated and maintained by NGCP, as one mandate of the former is to handle all existing cases, including right-of-way and claims which accrued prior to the transfer of power grid operations and maintenance to the latter on January 15, 2009. Below is the table showing the ownership information on each lands where the structures and their respective foundations and pedestals stand, and right-of-way.
973:), Ike2 (flag anchor steel pole), Cabadbaran1 (flag suspension steel pole), Cabadbaran2 (flag suspension steel pole with custom braced line post insulators attachment to conductor, it is used on Paco–Araneta segment), Gabbie (flag anchor steel pole with crossarms also used on Paco–Araneta segment similar to Ike1 but having narrower steel crossarm to support the overhead ground wire (OHGW) and uses normal steel pole), and PTVR (anchor irregular design steel monopole). Ike1, Cabadbaran2, and Gabbie were introduced by NGCP due to the construction of Skyway Stage 3.
1256:
and grid and the efficient operation and maintenance of the subtransmission systems which have not yet been disposed by TransCo where NGCP acts as the temporary owner of these assets and facilities and they will be transferred to TransCo once the 50-year NGCP concession period ends on
December 1, 2058, lands where the transmission structures stand and their pedestals or foundations and right-of-way or portions of a power line acquired and designated, and facilities built or placed from January 15, 2009 (new steel poles built due to the construction of
1494:
1509:
66:
930:(Meralco) Paco Substation in October 2012, it was a two-part power line. Due to the construction of the line's cut-in connection to Meralco Paco Substation, two new steel poles were added between poles 143 and 144 of the Sucat–Araneta segment of the line. This cut-in connection to the said substation also made the transmission line from being a two-part to three-part power line.
168:
25:
1449:
919:) totaling to 246 transmission structures. Steel poles have flag tower design (suspension and anchor variants), while lattice towers have incomplete tower design. Portal towers are used on portions of the line where it intersects with another power line. It has a length of 34 kilometers (21 mi) and is a single-circuit, double-bundle power line.
1469:
1534:
1374:
after failed negotiations. Responding to the petition filed by the residents, the
Supreme Court ruled in 2006 that the safety issue of the lines was "evidentiary in nature," although they took note of the potential health risks due to EMF radiation exposure with regards to the scientific studies. The
957:
is placed for a top segment of suspension steel poles with flag design. Fourth, the insulators were attached. Steel poles of the
Araneta–Balintawak segment use square piles, while the Sucat–Paco and Paco–Araneta segments have a concrete over a square pile. Poles of the relocated segments of the line,
948:
The spacers are crucial part of any power transmission lines. They help to maintain bundle spacing and prevents from arcing each other, which can cause power outages. The placing of spacers was carried from the bucket truck or spacer cart (a cart is used on EHV transmission lines and UHV transmission
1350:
The SLEx (Makati) – Bonifacio
Heights (Taguig) segment of Sucat–Paco–Araneta–Balintawak Transmission Line was criticized by the residents living along the Tamarind Road in Dasmariñas Village, Makati, who claimed the transmission line pose health risks. The said segment is located within 10 meters of
1255:
As a result of the turnover from TransCo to NGCP, and
Republic Act (RA) 9511 and concession agreement between both parties which authorized the latter to exercise the right of eminent domain necessary for the construction, expansion, and efficient maintenance and operation of the transmission system
1195:
Horizontal dead-end insulators made of 17-22 porcelain discs with 3 horizontal pole-mounted porcelain insulator at the center. When viewed sidewards for the flag variant of the anchor steel pole, the horizontal pole-mounted porcelain insulators resemble the letter "E" while its front side looks like
922:
The highest elevation segment are the Paco-Araneta and
Araneta-Balintawak segments, utilizing the Skyway Stage 3 and steel poles are 60-70m tall and they use anchor flag design poles. The segments are half Chinese design (most of the steel poles imported from China, and owned by TransCo and operated
1398:
billion. Former TransCo president Alan Ortiz noted the transmission line as a crucial line, and said claims of electromagnetic radiation associated with high-voltage transmission lines like this "have yet to be 100-percent scientifically established." TransCo submitted a motion to the
Supreme Court
1186:
3 braced line post insulators made of 17 porcelain discs facing in one direction and forming the pole a flag shape, and a steel crossarm used to support the overhead ground wire (OHGW) at the steel pole's top segment. Some newer suspension steel poles can have polymer composite dead-end insulator.
715:
to cover the increasing demand for electricity and a contribution was to be made to ensuring a continuous supply of electricity and to the macroeconomic objectives of growth and employment, and to address the Luzon power crisis from 1991 to 1993. It is one of the shortest transmission lines in the
952:
The steel poles are made of galvanized steel and they have a height of 30-70m tall. It is installed on base or foundation of the steel pole (pedestal). The installation or erection and re-erection (for secondhand structures now being used with a new function or purpose and ignoring the older or
251:
710:
The Sucat–Paco–Araneta–Balintawak
Transmission Line began construction in 1996 and went into service in July 2000 which took four years to complete because there is a right of way (ROW) or alignment constraints. The line was constructed to increase the transmission output in the urban grid in
914:
The transmission line consists of 219 steel poles (53 on the Balintawak–Araneta segment (1–53) and 167 on the Araneta–Paco and Paco–Sucat segments (1–8, 30-149, 150A, 150B, and 155–185)), 26 lattice towers (9-29, 150, and 151–154), and 1 portal tower located between steel poles 49 and 50
989:(NGCP) on the line were stored on various substations for those unused for a while. Most people know that the unused retired structures are stored in a structure's graveyard but it is not. They are stored in various substations for future other uses with their new ownership.
905:
The line continues paralleling Araneta Avenue and Skyway Stage 3 until it passes to Valentin Ventura Street, Tuktukan Street, and Kaingin Road before it crosses to EDSA. It turns left and after a few meters is the transmission line's terminus which is Balintawak Substation.
812:. The Sucat–Paco and Paco–Araneta segments are under NGCP's South Luzon Operations and Maintenance (SLOM) District 1 (South Western Tagalog) while the Araneta–Balintawak segment is under North Luzon Operations and Maintenance (NLOM) District 7 (National Capital Region).
1437:
1399:
asking that they be granted until January 31, 2009 to carry out activities and coordination works in alleviating the impact of the impending shutdown, but was refused and instead supported the Makati RTC's decision in shutting the transmission line down.
868:
transmission steel poles and one belonging to Sucat–Paco–Araneta–Balintawak line itself anchoring it before entering Paco Substation. The cut-in connection to Meralco Paco substation is located in this district, where the line's Sucat–Paco section ends.
724:
ROW. The electrical current heads south because the Hermosa–Duhat–Balintawak transmission line connects to Balintawak substation making the power line third of five lines forming the transmission network from Bataan Combined Cycle Power Plant (BCCPP) in
1413:
In its February 5, 2013 order, the Makati RTC approved the request of the petitioners, referring the case back to another branch following the failure of the judicial dispute resolution. The case is still pending at its pre-trial stage.
760:
With the construction of the Skyway Stage 3, several steel poles are being replaced by newer ones specifically those along the Araneta segment and also added new poles on certain portions of the line. The newer steel poles were made of
83:
38:
1806:
422:
1834:
382:
342:
1481:
302:
1425:
44:
1522:
1493:
1515:
Poles 118 (foreground) and 119 (behind it) of the transmission line, with anchor designs, beside PNR and SLEx. Also seen is pole 120, having replaced an older structure to give way to the Skyway Stage 3
784:(NGCP) new reflective reference tag (Araneta–Balintawak) and NAPOCOR/NPC steel pole and lattice tower numbers with NGCP's reference tags since 2015 on the Sucat–Paco and Araneta–Balintawak segments.
1375:
Court also added that long-term human safety should be of paramount importance as opposed to the presumption of economic benefits. Citing the said ruling, the Makati RTC in October 2008 obliged the
820:
The transmission line starts at Sucat Substation where it parallels Manuel L. Quezon Avenue and Laguna Lake Highway before it turns left. It then passes to Diego Silang Village and parallels with
1475:
Steel pole 13 (of suspension or flag design, in the foreground) and 14 (of anchor or flag design, in the background) of the transmission line along the east side of the Gregorio Araneta Avenue
130:
102:
1571:
NGCP abbreviation of the line's Balintawak–Araneta segment. (Introduced by NGCP and putting stickers (the yellow and black one) along Balintawak-Araneta segment, example: 123.)
109:
757:, and its frequency is 60.14 Hz (every transmission line in Philippines have 60 hertz). There are no loads measured but the information, was not publicly available.
1865:
116:
1850:
1580:
NGCP abbreviation of the line's Araneta–Paco segment.. (Introduced by NGCP and putting stickers (the yellow and black one) along Araneta-Paco segment, example: 123.)
1248:(TransCo) on March 1, 2003 where it operated and maintained the line until January 15, 2009. The line's operations and maintenance was transferred to privately-owned
1463:. Note that the lowest insulator on the left in which it connects to a support steel pole instead of directly connecting to pole 162 like the rest of its insulators.
1860:
98:
1382:
TransCo vice president for operations Carlito Claudio warned in November 2008 that complete retirement of the transmission line could trigger "hours-long rotating
1855:
1589:
NGCP abbreviation of the line's Paco–Sucat segment. (Introduced by NGCP and putting stickers (the yellow and black one) along Paco-Sucat segment, example: 123.)
780:
As of 2016, the base of the transmission line segment of Sucat–Paco, Paco–Araneta, and Araneta–Balintawak segment have a large and tall circular pile with the
1318:
1249:
986:
781:
720:
with its 34 kilometer span. The transmission line has four substations to connect but the ROW needs to be flexible which is the reason why the line uses the
687:
1244:(NAPOCOR/NPC) from July 2000 to March 1, 2003. Operations, maintenance, and ownership of the line then transferred to another government corporation
123:
1750:
1443:
Lattice towers 150 and 151, and new steel poles 150A and 150B (of anchor or flag design) along the Tomas Claudio Street/Skyway Stage 3 segment
923:
and maintained by NGCP for existing segments and poles while relocated portions and their poles are owned, operated and maintained by NGCP).
1697:
961:
The transmission structure types are: steel monopole (used on relocated steel poles of Araneta-Balintawak and Paco-Araneta segments along
742:
1407:
1376:
1292:
1245:
229:
211:
149:
52:
1387:
1371:
586:
985:(NAPOCOR/NPC)-era transmission structures that were retired from original use and ownership because of various projects made by
295:
178:
87:
882:
261:
1386:, just like during the power crisis in the 1990s," that might adversely impact the country's leading economic hubs of
1641:
1613:
1403:
1241:
982:
1779:
825:
193:
1499:
Steel pole 49 anchoring the line to a portal tower, located along Upper McKinley Road, Bonifacio Global City,
1370:
A case was filed in Makati Regional and Metropolitan Trial Court (Makati RTC) in 2000, but was raised to the
954:
927:
890:
766:
189:
76:
1352:
833:
829:
821:
485:
965:, and on poles with irregular design), normal steel pole, lattice tower, and portal tower (located near
894:
853:
746:
878:
257:
1725:
1367:. They also took note of no consultation with regards to the construction of the transmission line.
1784:
1618:
1456:
1257:
1084:
1037:
970:
886:
770:
721:
678:
from July 2000 to October 2012, is a 230,000 volt, single-circuit, three-part transmission line in
576:
1218:
3 dead-end horizontal insulators made with 15 porcelain discs and 6 vertical porcelain insulator.
969:). The name of these structures are: Ike1 (tall anchor steel monopole, used on Araneta Avenue and
857:
1351:
Tamarind Road in the said village. The residents, led by Atty. Eduardo F. Hernandez, blamed the
852:
are 7 new steel poles that were used for the relocation of the line due to the construction of
1394:, and added the unfeasibility of building an alternate underground cable line that would cost
837:
754:
1240:
The transmission line was originally operated, maintained, and owned by the government-owned
849:
734:
1252:(NGCP) on January 15, 2009 where it now operates and maintains the power line since then.
1541:
1391:
1088:
1041:
962:
841:
1844:
1544:
in Paco, using new steel pole 144, as a result of the construction of Skyway Stage 3.
966:
938:
726:
1807:"Preliminary Information Statement for Annual Stockholders' Meeting on May 26, 2020"
1487:
Replacement pole for the pole 28 along the west side of the Gregorio Araneta Avenue
1410:(TransCo) right-of-ways need to be reheighted to address a controversy since 2008.
1383:
861:
712:
679:
288:
245:
Sucat–Paco–Araneta–Balintawak Transmission Line (The 2nd Tallest Transmission Line)
1210:
3 double-bundle vertical suspension insulators consisting of 34 porcelain discs.
792:
The Sucat–Paco–Araneta–Balintawak Transmission Line passes through the cities of
1379:(TransCo) to "de-energize" the Sucat–Paco–Araneta–Balintawak Transmission Line.
1364:
809:
750:
717:
691:
683:
476:
278:
65:
793:
438:
424:
398:
384:
358:
344:
318:
304:
762:
1670:"Operations - National Grid Corporation of the Philippines: Business Scope"
993:
Electrical Information of Sucat–Paco–Araneta–Balintawak Transmission Line
1755:
1702:
1360:
1264:
Ownership Information of Sucat–Paco–Araneta–Balintawak Transmission Line
738:
1669:
1648:
926:
From July 2000 until the completion of the line's cut-in connection to
865:
774:
773:, the newer design is flag design with the deadend insulators (made of
695:
520:
509:
480:
1500:
1460:
1356:
942:
805:
801:
797:
730:
699:
977:
Storage space for structures retired from original use and ownership
690:(NGCP), with line segment termination at NGCP Araneta substation in
196:. Statements consisting only of original research should be removed.
1355:(EMF) emanated by the 230-kV power lines for such health issues as
897:, and the line's Paco–Araneta section ends at Araneta Substation.
264:
in Pandacan, Manila, with the lattice tower 154 at the foreground.
1083:
Relocated and added steel poles segments due to construction of
1036:
Relocated and added steel poles segments due to construction of
845:
933:
In 2018, a portal tower located between steel poles 53 and 54 (
161:
59:
18:
848:(EDSA). It continues on a straight route and after crossing
937:) was removed and retired to give way for the widening of
1298:
196 (169 steel poles, 26 lattice towers, 1 portal tower)
609:(219 steel poles, 26 lattice towers, and 1 portal tower)
185:
1562:
Abbreviation used on the line's Sucat–Araneta segment.
672:
Muntinlupa–Manila–Doña Imelda–Quezon Transmission Line
1642:"Empowering Partnerships: Meralco 2009 Annual Report"
1751:"Removal of power line to cut RP's competitiveness"
1284:Percentage (by number of right-of-way or portions)
765:discs (15) and 3 horizontal pole-mounted porcelain
633:
622:
614:
600:
592:
582:
572:
567:
549:
531:
526:
515:
504:
499:
491:
470:
462:
294:
284:
274:
269:
244:
90:. Unsourced material may be challenged and removed.
1698:"3-hour brownouts loom over Metro Manila, Bulacan"
1431:The transmission line near Arnaiz Avenue in Makati
1236:Ownership, operations, and maintenance information
686:that connects Sucat and Balintawak substations of
521:Ownership, operations, and maintenance information
510:Ownership, operations, and maintenance information
1608:
1606:
1540:Rerouting of the transmission line segment along
99:"Sucat–Paco–Araneta–Balintawak Transmission Line"
1692:
1690:
1528:The transmission line along EDSA–Roosevelt area
1281:Percentage (by number of lands and structures)
1069:Sucat–Paco–Araneta–Balintawak (other segments)
648:Sucat–Paco–Araneta–Balintawak Transmission Line
824:. It goes to the left again, passing through
16:230 kV overhead power line in the Philippines
8:
1778:Gatdula, Donnabelle L. (November 28, 2008).
1319:National Grid Corporation of the Philippines
1250:National Grid Corporation of the Philippines
987:National Grid Corporation of the Philippines
828:and Bonifacio Heights before paralleling to
782:National Grid Corporation of the Philippines
688:National Grid Corporation of the Philippines
844:. At Magallanes Interchange, it crosses to
53:Learn how and when to remove these messages
893:and run parallel with the said avenue and
676:Sucat–Araneta–Balintawak Transmission Line
250:
1275:Number of right-of-way or portions owned
1148:149 (128 steel poles, 21 lattice towers)
256:A segment of the transmission line along
230:Learn how and when to remove this message
212:Learn how and when to remove this message
150:Learn how and when to remove this message
1866:Buildings and structures in Metro Manila
1837:- 2007 evaluation by Entwicklungsbank.de
1321:(NGCP; owned, operated, and maintained)
1262:
1156:
1105:
1048:
991:
864:. Near Paco Substation, the two broader
1851:Energy infrastructure completed in 2000
1602:
1555:
1421:
1192:Anchor steel pole (flag and irregular)
1861:2000 establishments in the Philippines
1137:44 (39 steel poles, 5 lattice towers)
241:
1856:Transmission lines in the Philippines
1835:Philippines_Sucat_Balintawak_2007.pdf
1272:Number of lands and structures owned
7:
1163:Type of steel pole or lattice tower
88:adding citations to reliable sources
698:(Meralco) Paco substation in Paco,
1614:"'Silent killer' at Tamarind Road"
14:
1408:National Transmission Corporation
1402:The transmission towers stand on
1377:National Transmission Corporation
1293:National Transmission Corporation
1246:National Transmission Corporation
34:This article has multiple issues.
1533:
1521:
1508:
1492:
1480:
1468:
1448:
1436:
1424:
166:
64:
23:
1229:Same as anchor lattice towers.
840:from Magallanes Interchange to
832:(SLEx) from Maricaban Creek to
75:needs additional citations for
42:or discuss these issues on the
743:Mak–Ban Geothermal Power Plant
634:
623:
601:
1:
1455:Steel pole 163 located along
1177:Suspension steel pole (flag)
958:however, use circular piles.
1780:"Transco warns of blackouts"
885:Metro Commuter railroad and
846:Epifanio delos Santos Avenue
769:. Since the construction of
881:(or Paco–Santa Mesa Road),
537:; 28 years ago
192:the claims made and adding
1882:
1404:National Power Corporation
1242:National Power Corporation
1201:Suspension lattice towers
983:National Power Corporation
577:Overhead transmission line
1206:
1203:
1182:
1179:
1020:
1017:
1014:
733:to Calaca Power Plant in
249:
1812:. PDS Group. p. 143
1055:Bundle type and segment
826:Manila American Cemetery
674:, and formerly known as
527:Construction information
1287:Percentage (by length)
928:Manila Electric Company
891:Gregorio Araneta Avenue
856:Stage 3. It crosses to
822:Carlos P. Garcia Avenue
696:Manila Electric Company
596:34 km (21 mi)
1353:electromagnetic fields
1215:Anchor lattice towers
1158:Insulator information
1107:Components and length
877:The line parallels to
834:Magallanes Interchange
830:South Luzon Expressway
604:of transmission towers
555:; 24 years ago
486:Magallanes Interchange
439:14.66056°N 121.01222°E
399:14.61833°N 121.01556°E
359:14.58056°N 120.99833°E
319:14.44444°N 121.05250°E
1115:Number of structures
910:Technical description
749:also in Batangas and
568:Technical information
500:Ownership information
495:Balintawak Substation
450:Balintawak Substation
879:Tomas Claudio Street
532:Construction started
258:Tomas Claudio Street
84:improve this article
1759:. November 28, 2008
1706:. November 27, 2008
1457:Magsaysay Boulevard
1265:
1159:
1123:Araneta–Balintawak
1108:
1051:
1050:Bundle information
1031:Araneta–Balintawak
994:
887:Magsaysay Boulevard
444:14.66056; 121.01222
434: /
404:14.61833; 121.01556
394: /
364:14.58056; 120.99833
354: /
324:14.44444; 121.05250
314: /
1622:. January 27, 2015
1406:(NAPOCOR/NPC) and
1346:Health controversy
1263:
1157:
1106:
1049:
992:
901:Araneta–Balintawak
474:Araneta Substation
410:Araneta Substation
177:possibly contains
1726:"G.R. No. 145328"
1343:
1342:
1233:
1232:
1155:
1154:
1104:
1103:
1047:
1046:
788:Route description
644:
643:
610:
240:
239:
232:
222:
221:
214:
179:original research
160:
159:
152:
134:
57:
1873:
1822:
1821:
1819:
1817:
1811:
1803:
1797:
1796:
1794:
1792:
1775:
1769:
1768:
1766:
1764:
1747:
1741:
1740:
1738:
1736:
1722:
1716:
1715:
1713:
1711:
1694:
1685:
1684:
1682:
1680:
1666:
1660:
1659:
1657:
1655:
1646:
1638:
1632:
1631:
1629:
1627:
1610:
1590:
1587:
1581:
1578:
1572:
1569:
1563:
1560:
1537:
1525:
1512:
1496:
1484:
1472:
1452:
1440:
1428:
1397:
1266:
1160:
1109:
1052:
995:
889:, turns left to
858:San Andres Bukid
850:Gil Puyat Avenue
670:) also known as
650:(abbreviated as
636:
625:
608:
603:
563:
561:
556:
545:
543:
538:
466:Sucat Substation
458:
457:
455:
454:
453:
451:
446:
445:
440:
435:
432:
431:
430:
427:
418:
417:
415:
414:
413:
411:
406:
405:
400:
395:
392:
391:
390:
387:
378:
377:
375:
374:
373:
371:
366:
365:
360:
355:
352:
351:
350:
347:
338:
337:
335:
334:
333:
331:
330:Sucat Substation
326:
325:
320:
315:
312:
311:
310:
307:
254:
242:
235:
228:
217:
210:
206:
203:
197:
194:inline citations
170:
169:
162:
155:
148:
144:
141:
135:
133:
92:
68:
60:
49:
27:
26:
19:
1881:
1880:
1876:
1875:
1874:
1872:
1871:
1870:
1841:
1840:
1831:
1826:
1825:
1815:
1813:
1809:
1805:
1804:
1800:
1790:
1788:
1777:
1776:
1772:
1762:
1760:
1749:
1748:
1744:
1734:
1732:
1724:
1723:
1719:
1709:
1707:
1696:
1695:
1688:
1678:
1676:
1668:
1667:
1663:
1653:
1651:
1644:
1640:
1639:
1635:
1625:
1623:
1612:
1611:
1604:
1599:
1594:
1593:
1588:
1584:
1579:
1575:
1570:
1566:
1561:
1557:
1552:
1545:
1538:
1529:
1526:
1517:
1513:
1504:
1497:
1488:
1485:
1476:
1473:
1464:
1453:
1444:
1441:
1432:
1429:
1420:
1395:
1348:
1324:50 steel poles
1238:
1207:no calculation
1126:53 steel poles
1064:Broken spacers
979:
935:(8LI1MNA-MUN)92
917:(8LI1MNA-MUN)97
912:
903:
875:
818:
790:
708:
583:Type of current
559:
557:
554:
541:
539:
536:
484:
483:Paco Substation
479:
475:
449:
447:
443:
441:
437:
436:
433:
428:
425:
423:
421:
420:
419:
409:
407:
403:
401:
397:
396:
393:
388:
385:
383:
381:
380:
379:
370:Paco Substation
369:
367:
363:
361:
357:
356:
353:
348:
345:
343:
341:
340:
339:
329:
327:
323:
321:
317:
316:
313:
308:
305:
303:
301:
300:
265:
236:
225:
224:
223:
218:
207:
201:
198:
183:
171:
167:
156:
145:
139:
136:
93:
91:
81:
69:
28:
24:
17:
12:
11:
5:
1879:
1877:
1869:
1868:
1863:
1858:
1853:
1843:
1842:
1839:
1838:
1830:
1829:External links
1827:
1824:
1823:
1798:
1770:
1742:
1717:
1686:
1661:
1633:
1601:
1600:
1598:
1595:
1592:
1591:
1582:
1573:
1564:
1554:
1553:
1551:
1548:
1547:
1546:
1542:Quirino Avenue
1539:
1532:
1530:
1527:
1520:
1518:
1514:
1507:
1505:
1498:
1491:
1489:
1486:
1479:
1477:
1474:
1467:
1465:
1454:
1447:
1445:
1442:
1435:
1433:
1430:
1423:
1419:
1416:
1347:
1344:
1341:
1340:
1337:
1334:
1331:
1328:
1325:
1322:
1315:
1314:
1311:
1308:
1305:
1304:28.29 km
1302:
1299:
1296:
1289:
1288:
1285:
1282:
1279:
1276:
1273:
1270:
1258:Skyway Stage 3
1237:
1234:
1231:
1230:
1227:
1224:
1223:Portal towers
1220:
1219:
1216:
1212:
1211:
1208:
1205:
1202:
1198:
1197:
1193:
1189:
1188:
1184:
1181:
1178:
1174:
1173:
1170:
1167:
1164:
1153:
1152:
1151:22.24 km
1149:
1146:
1142:
1141:
1138:
1135:
1131:
1130:
1127:
1124:
1120:
1119:
1116:
1113:
1102:
1101:
1098:
1095:
1092:
1089:NLEX Connector
1085:Skyway Stage 3
1080:
1079:
1076:
1073:
1070:
1066:
1065:
1062:
1059:
1056:
1045:
1044:
1042:NLEX Connector
1038:Skyway Stage 3
1033:
1032:
1028:
1027:
1023:
1022:
1019:
1016:
1013:
1009:
1008:
1005:
1002:
999:
978:
975:
971:Skyway Stage 3
963:Araneta Avenue
911:
908:
902:
899:
895:Skyway Stage 3
874:
871:
842:Quirino Avenue
838:Osmeña Highway
817:
814:
789:
786:
771:Skyway Stage 3
722:Skyway Stage 3
707:
704:
642:
641:
638:
631:
630:
627:
620:
619:
616:
612:
611:
605:
598:
597:
594:
590:
589:
584:
580:
579:
574:
570:
569:
565:
564:
551:
547:
546:
533:
529:
528:
524:
523:
517:
513:
512:
506:
502:
501:
497:
496:
493:
489:
488:
472:
471:Passes through
468:
467:
464:
460:
459:
298:
292:
291:
286:
282:
281:
276:
272:
271:
267:
266:
255:
247:
246:
238:
237:
220:
219:
174:
172:
165:
158:
157:
140:September 2019
72:
70:
63:
58:
32:
31:
29:
22:
15:
13:
10:
9:
6:
4:
3:
2:
1878:
1867:
1864:
1862:
1859:
1857:
1854:
1852:
1849:
1848:
1846:
1836:
1833:
1832:
1828:
1808:
1802:
1799:
1787:
1786:
1781:
1774:
1771:
1758:
1757:
1752:
1746:
1743:
1735:September 21,
1731:
1727:
1721:
1718:
1705:
1704:
1699:
1693:
1691:
1687:
1675:
1671:
1665:
1662:
1650:
1643:
1637:
1634:
1626:September 21,
1621:
1620:
1615:
1609:
1607:
1603:
1596:
1586:
1583:
1577:
1574:
1568:
1565:
1559:
1556:
1549:
1543:
1536:
1531:
1524:
1519:
1511:
1506:
1502:
1495:
1490:
1483:
1478:
1471:
1466:
1462:
1458:
1451:
1446:
1439:
1434:
1427:
1422:
1417:
1415:
1411:
1409:
1405:
1400:
1393:
1389:
1385:
1380:
1378:
1373:
1372:Supreme Court
1368:
1366:
1362:
1358:
1354:
1345:
1338:
1335:
1332:
1330:5.94 km
1329:
1326:
1323:
1320:
1317:
1316:
1312:
1309:
1306:
1303:
1300:
1297:
1294:
1291:
1290:
1286:
1283:
1280:
1277:
1274:
1271:
1268:
1267:
1261:
1259:
1253:
1251:
1247:
1243:
1235:
1228:
1225:
1222:
1221:
1217:
1214:
1213:
1209:
1200:
1199:
1194:
1191:
1190:
1185:
1176:
1175:
1171:
1168:
1165:
1162:
1161:
1150:
1147:
1144:
1143:
1140:5.92 km
1139:
1136:
1134:Paco–Araneta
1133:
1132:
1129:5.67 km
1128:
1125:
1122:
1121:
1117:
1114:
1111:
1110:
1099:
1097:not measured
1096:
1093:
1090:
1086:
1082:
1081:
1077:
1075:not measured
1074:
1071:
1068:
1067:
1063:
1060:
1057:
1054:
1053:
1043:
1039:
1035:
1034:
1030:
1029:
1026:Paco–Araneta
1025:
1024:
1015:not measured
1011:
1010:
1006:
1003:
1000:
997:
996:
990:
988:
984:
976:
974:
972:
968:
967:Lawton Avenue
964:
959:
956:
950:
946:
944:
940:
939:Lawton Avenue
936:
931:
929:
924:
920:
918:
909:
907:
900:
898:
896:
892:
888:
884:
880:
872:
870:
867:
863:
859:
855:
851:
847:
843:
839:
835:
831:
827:
823:
815:
813:
811:
807:
803:
799:
795:
787:
785:
783:
778:
776:
772:
768:
764:
758:
756:
752:
748:
744:
740:
736:
732:
728:
723:
719:
714:
705:
703:
701:
697:
693:
689:
685:
681:
677:
673:
669:
665:
661:
657:
653:
649:
639:
632:
628:
621:
617:
613:
606:
599:
595:
591:
588:
585:
581:
578:
575:
571:
566:
552:
548:
534:
530:
525:
522:
518:
514:
511:
507:
503:
498:
494:
490:
487:
482:
478:
473:
469:
465:
461:
456:
416:
376:
336:
299:
297:
293:
290:
287:
283:
280:
277:
273:
268:
263:
259:
253:
248:
243:
234:
231:
216:
213:
205:
195:
191:
187:
181:
180:
175:This article
173:
164:
163:
154:
151:
143:
132:
129:
125:
122:
118:
115:
111:
108:
104:
101: –
100:
96:
95:Find sources:
89:
85:
79:
78:
73:This article
71:
67:
62:
61:
56:
54:
47:
46:
41:
40:
35:
30:
21:
20:
1814:. Retrieved
1801:
1789:. Retrieved
1785:Philstar.com
1783:
1773:
1761:. Retrieved
1754:
1745:
1733:. Retrieved
1729:
1720:
1708:. Retrieved
1701:
1677:. Retrieved
1673:
1664:
1654:December 11,
1652:. Retrieved
1636:
1624:. Retrieved
1619:PhilStar.com
1617:
1585:
1576:
1567:
1558:
1412:
1401:
1381:
1369:
1349:
1254:
1239:
1180:30-70m tall
980:
960:
951:
947:
934:
932:
925:
921:
916:
913:
904:
876:
873:Paco–Araneta
819:
791:
779:
777:/porcelain)
759:
713:Metro Manila
709:
680:Metro Manila
675:
671:
667:
663:
659:
655:
651:
647:
645:
593:Total length
550:Commissioned
289:Metro Manila
226:
208:
199:
176:
146:
137:
127:
120:
113:
106:
94:
82:Please help
77:verification
74:
50:
43:
37:
36:Please help
33:
1816:January 11,
1730:Lawphil.net
1365:miscarriage
1145:Sucat–Paco
1012:Sucat–Paco
810:Quezon City
747:Santo Tomas
741:and six to
718:Philippines
692:Quezon City
684:Philippines
664:8LI1MNA-MUN
660:8LI1DIM-MNA
656:8LI1QUE-DIM
637:of circuits
618:230 kV
477:Pasig River
442: /
402: /
362: /
349:120°59′54″E
322: /
296:Coordinates
279:Philippines
1845:Categories
1763:August 25,
1710:August 25,
1597:References
1295:(TransCo)
1172:Insulator
816:Sucat–Paco
794:Muntinlupa
615:AC voltage
448: (
429:121°0′44″E
426:14°39′38″N
408: (
389:121°0′56″E
368: (
346:14°34′50″N
328: (
306:14°26′40″N
202:April 2021
186:improve it
110:newspapers
39:improve it
1791:April 23,
1679:April 12,
1384:blackouts
767:insulator
763:porcelain
560:July 2000
553:July 2000
386:14°37′6″N
309:121°3′9″E
190:verifying
45:talk page
1756:GMA News
1703:GMA News
1516:project.
1361:leukemia
1183:7+ tons
1112:Segment
1058:Spacers
1018:230,000
1007:Heading
1001:Current
998:Segment
955:crossarm
739:Batangas
626:of poles
516:Operator
285:Province
270:Location
1674:ngcp.ph
1649:Meralco
1418:Gallery
1392:Ortigas
1339:17.47%
1336:44.44%
1333:20.33%
1313:83.21%
1310:55.56%
1307:79.67%
1278:Length
1169:Weight
1166:Height
1118:Length
866:Meralco
775:polymer
706:History
558: (
540: (
481:Meralco
275:Country
184:Please
124:scholar
1501:Taguig
1461:Manila
1388:Makati
1363:, and
1357:cancer
1269:Owner
1094:300 +
1072:500 +
1021:South
1004:Volts
943:Taguig
854:Skyway
808:, and
806:Manila
802:Makati
798:Taguig
755:Laguna
735:Calaca
731:Bataan
700:Manila
668:SPABTL
126:
119:
112:
105:
97:
1810:(PDF)
1645:(PDF)
1550:Notes
1061:Amps
727:Limay
505:Owner
131:JSTOR
117:books
1818:2021
1793:2020
1765:2020
1737:2019
1712:2020
1681:2021
1656:2023
1628:2019
1390:and
1226:10m
1204:70m
1087:and
1040:and
981:The
862:Paco
860:and
836:and
694:and
646:The
607:246
587:HVAC
573:Type
542:1996
535:1996
519:see
508:see
463:From
103:news
1301:10
941:in
883:PNR
753:in
751:Bay
745:in
635:No.
629:219
624:No.
602:No.
262:PNR
188:by
86:by
1847::
1782:.
1753:.
1728:.
1700:.
1689:^
1672:.
1647:.
1616:.
1605:^
1459:,
1396:₱1
1359:,
1327:8
1100:0
1091:)
1078:0
945:.
804:,
800:,
796:,
737:,
729:,
702:.
682:,
666:,
662:,
658:,
654:,
652:SA
492:To
48:.
1820:.
1795:.
1767:.
1739:.
1714:.
1683:.
1658:.
1630:.
1503:.
915:(
640:1
562:)
544:)
452:)
412:)
372:)
332:)
260:/
233:)
227:(
215:)
209:(
204:)
200:(
182:.
153:)
147:(
142:)
138:(
128:·
121:·
114:·
107:·
80:.
55:)
51:(
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.