Knowledge

West Springfield Generating Station

Source 📝

131: 467:
the substation via generator step-up transformers (GSU). The plant could be started with no off-site power available and with only the on-site emergency diesel generator providing electricity to plant systems. As a result, the West Springfield plant was capable of starting and supplying power to local loads in the event of a complete grid failure or in the event that the utility substation through which it transmits power is isolated from the rest of the grid, known as "black start" capability.
393:, Inc. By that time, the plant had become a reserve facility only used at times of very high system load. In 2002, Con Edison converted the plant into a peaking facility by replacing the original boiler Units 1 and 2 with the current combustion turbines. The facility did not operate often and was primarily used to maintain grid reliability in the area. Due to the current New England market conditions, none of the plant's units fared well, revenue-wise, but in 2005 it was determined by 455:
up to 6 million gallons per day of water when operating. Units 1, 2, and 10 rejected all of their waste heat from combustion to the atmosphere via the exhaust stacks. However, Units 1 and 2 required a small amount of cooling water to remove heat from the lubricating oil system for the turbines. A small service water system operating at 730 gpm continuously provided cooling water for that purpose. Unit 10 did not require any cooling water at all.
25: 466:
owned substation located directly behind the plant. All four units generated power at 13.8 kilovolts (kV). Units 1 and 10 supplied power directly via the 13.8 kV local distribution system fed out of the substation. Unit 3, and since 2002 unit 2, supplied power to the 115 kV transmission switchyard at
454:
from its condenser to a water source. A once-through cooling system utilizing water from the river removed waste heat from Unit 3's condenser. The circulating water pumps are located in the plant's pump house across the highway from the facility directly on the Connecticut River. Unit 3 could require
421:
Steam Units 1 and 2 are permanently retired as of December 31, 2000 (last used in 1999) and the boilers are currently being decommissioned. During the decommissioning of Units 1 and 2 and installation of CTG-1 and CTG-2, the plant's coal chute located on the outside of the boiler hall was removed and
401:
agreements in 2005 from ISO New England for the station's units. In RMR agreements, the electricity market agrees to subsidize the costs of operating units which are deemed necessary but are unable to make enough revenue to pay operational costs. Generally these are paid for by increasing electricity
434:
of 98 MW were installed and began operating June 5, 2002. Gas turbines are capable of starting up and responding much faster to changing electricity demand than steam units, thus the CTGs are much more desirable as peaking units than the original boilers. In addition, the CTGs emit far less air
458:
Units 1 and 2 had an operational constraint of 4800 hours/year based on the Massachusetts Department of Environmental Protection (MA DEP) Air Quality Plan Approval. The MA DEP has recently granted approval to NAEA to operate the units an additional 720 hours per year using distillate fuel oil.
385:). The original station consisted of two simple-cycle steam units (Units 1 and 2) which burned both oil and coal at different periods of their existence. Unit 3 was added in 1957 and the jet turbine was added in 1969. In 1999 the Station was acquired by 360:
The plant was shut down in June 2022 and is scheduled to be demolished. The generators have been sold and dismantling had begun in the summer of 2022 with the jet turbine disconnected and removed from the site by August 2022.
776: 771: 353:
generators (Units 1 and 2) fueled by natural gas or ultra low-sulphur diesel fuel, one 18 MW jet turbine (Unit 10) that was fueled by kerosene, and one 107 MW simple-cycle steam
42: 357:
unit (Unit 3) burning no. 6 fuel oil, ULSD or natural gas. The station also had a small auxiliary boiler for process and building heat and an emergency back-up generator.
766: 170: 761: 756: 751: 786: 306: 781: 89: 61: 378: 711: 68: 682: 75: 470:
Owned by Cogentrix Energy, the West Springfield Generating Station is located at 15 Agawam Ave. in West Springfield, Massachusetts.
108: 57: 423: 374: 370: 334: 157: 46: 130: 444: 436: 411: 390: 403: 418:. In 2019, the plant did not receive a contract to supply peak power and the owners decided to decommission it. 82: 450:
The plant used the Connecticut River as its source of cooling water. Unit 3, as a steam unit, had to reject
35: 427: 210: 414:. Essential Power was subsequently acquired by Cogentrix Energy, under ownership of funds managed by 398: 338: 350: 288: 276: 407: 463: 415: 382: 431: 394: 459:
According to the plant management, Unit 3 could operate at about 10–20% of its capacity.
329:, also known by its corporate name EP Energy Massachusetts, LLC, was a fossil-fuel-fired 440: 745: 377:. The power plant and the adjacent West Springfield Substation were built in 1949 by 342: 330: 262: 258: 24: 451: 422:
the original brick exhaust stacks were replaced with metallic stacks. The two
386: 185: 172: 435:
pollution and require far less cooling water. Each exhaust housing contains
406:, Inc. now known as Essential Power LLC, which is a joint venture owned by 397:
that the station was needed for reliability purposes and CEEMI was awarded
346: 266: 315: 354: 712:"State funds will help determine future of closed power plant" 18: 683:"West Springfield explores redevelopment of old power plant" 439:(SCR) and an oxidation catalyst system for the control of 578:
No. 6 Fuel Oil / N. gas / ultra low-sulfur diesel (ULSD)
402:
rates to customers. In 2008, Con Edison sold CEEMI to
341:" facility, meaning that it primarily operates during 462:
Electricity was supplied to the grid at the adjacent
777:
Industrial buildings and structures in Massachusetts
430:
combustion turbine generators (CTGs) having a total
302: 297: 287: 282: 272: 254: 249: 241: 226: 209: 201: 164: 152: 144: 123: 49:. Unsourced material may be challenged and removed. 772:Natural gas-fired power stations in Massachusetts 705: 703: 619:Pratt & Whitney FT4a-8LF combustion turbine 603:Pratt & Whitney FT4a-8LF Combustion turbine 586:Pratt & Whitney FT4a-8LF Combustion turbine 8: 381:, a subsidiary of Northeast Utilities (now 135:West Springfield Generating Station in 2011 735:EPA response to NPDES Permit No. MA0004707 120: 767:Oil-fired power stations in Massachusetts 109:Learn how and when to remove this message 561:N. gas / ultra low-sulfur diesel (ULSD) 544:N. gas / ultra low-sulfur diesel (ULSD) 477: 762:Energy infrastructure completed in 1969 757:Energy infrastructure completed in 1957 752:Energy infrastructure completed in 1949 673: 307:Related media on Commons 389:and the plant's corporate name became 379:Western Massachusetts Electric Company 443:(NOx). The company did not install a 58:"West Springfield Generating Station" 7: 787:1949 establishments in Massachusetts 369:The station is located south of the 47:adding citations to reliable sources 345:. The facility consisted of two 49- 327:West Springfield Generating Station 124:West Springfield Generating Station 681:Munford, Aprell May (2023-04-24). 16:Power plant in Massachusetts, U.S. 14: 627:ultra low-sulfur kerosene (ULSK) 611:ultra low-sulfur kerosene (ULSK) 595:ultra low-sulfur kerosene (ULSK) 710:Dobbs, G. Michael (2022-12-07). 250:Thermal power station 129: 23: 782:West Springfield, Massachusetts 391:Con Edison Energy Massachusetts 375:West Springfield, Massachusetts 335:West Springfield, Massachusetts 158:West Springfield, Massachusetts 34:needs additional citations for 404:North American Energy Alliance 1: 635:Cleaver Brooks Package boiler 569:Combustion Engineering Boiler 518:Combustion Engineering Boiler 501:Combustion Engineering Boiler 445:heat recovery steam generator 437:selective catalytic reduction 689:. The Springfield Republican 803: 312: 140: 128: 638:14MM BTU/hr (heat only) 289:Nameplate capacity 273:Turbine technology 186:42.095667°N 72.595694°W 343:peak electrical demand 227:Decommission date 337:. The station was a " 283:Power generation 191:42.095667; -72.595694 652:Reiner Generator set 399:Reliability Must Run 211:Commission date 205:Being decommissioned 43:improve this article 649:Emergency Generator 474:Installed equipment 298:External links 182: /  552:Combustion turbine 535:Combustion turbine 447:with these units. 351:combustion turbine 277:Combustion turbine 665: 664: 464:Eversource Energy 416:The Carlyle Group 383:Eversource Energy 323: 322: 255:Primary fuel 119: 118: 111: 93: 794: 736: 733: 727: 726: 724: 723: 707: 698: 697: 695: 694: 678: 478: 432:nominal capacity 316:edit on Wikidata 245:Cogentrix Energy 237: 235: 222: 220: 197: 196: 194: 193: 192: 187: 183: 180: 179: 178: 175: 156:5 Agawam Avenue 133: 121: 114: 107: 103: 100: 94: 92: 51: 27: 19: 802: 801: 797: 796: 795: 793: 792: 791: 742: 741: 740: 739: 734: 730: 721: 719: 716:thereminder.com 709: 708: 701: 692: 690: 680: 679: 675: 670: 644:No. 2 Fuel oil 527:No. 6 Fuel oil 510:No. 6 Fuel oil 476: 441:nitrogen oxides 395:ISO New England 371:Memorial Bridge 367: 319: 233: 231: 218: 216: 190: 188: 184: 181: 176: 173: 171: 169: 168: 136: 115: 104: 98: 95: 52: 50: 40: 28: 17: 12: 11: 5: 800: 798: 790: 789: 784: 779: 774: 769: 764: 759: 754: 744: 743: 738: 737: 728: 718:. The Reminder 699: 672: 671: 669: 666: 663: 662: 659: 656: 653: 650: 646: 645: 642: 639: 636: 633: 629: 628: 625: 623: 620: 617: 613: 612: 609: 607: 604: 601: 597: 596: 593: 590: 587: 584: 580: 579: 576: 573: 570: 567: 563: 562: 559: 556: 553: 550: 546: 545: 542: 539: 536: 533: 529: 528: 525: 524:Decommissioned 522: 519: 516: 512: 511: 508: 507:Decommissioned 505: 502: 499: 495: 494: 491: 488: 485: 482: 475: 472: 366: 363: 321: 320: 313: 310: 309: 304: 300: 299: 295: 294: 291: 285: 284: 280: 279: 274: 270: 269: 256: 252: 251: 247: 246: 243: 239: 238: 228: 224: 223: 213: 207: 206: 203: 199: 198: 166: 162: 161: 154: 150: 149: 146: 142: 141: 138: 137: 134: 126: 125: 117: 116: 31: 29: 22: 15: 13: 10: 9: 6: 4: 3: 2: 799: 788: 785: 783: 780: 778: 775: 773: 770: 768: 765: 763: 760: 758: 755: 753: 750: 749: 747: 732: 729: 717: 713: 706: 704: 700: 688: 684: 677: 674: 667: 660: 657: 654: 651: 648: 647: 643: 640: 637: 634: 631: 630: 626: 624: 621: 618: 616:Woodland Road 615: 614: 610: 608: 605: 602: 600:Doreen Street 599: 598: 594: 591: 588: 585: 582: 581: 577: 574: 571: 568: 565: 564: 560: 557: 554: 551: 548: 547: 543: 540: 537: 534: 531: 530: 526: 523: 520: 517: 514: 513: 509: 506: 503: 500: 497: 496: 492: 489: 486: 483: 480: 479: 473: 471: 468: 465: 460: 456: 453: 448: 446: 442: 438: 433: 429: 425: 419: 417: 413: 409: 405: 400: 396: 392: 388: 384: 380: 376: 372: 364: 362: 358: 356: 352: 348: 344: 340: 336: 332: 328: 317: 311: 308: 305: 301: 296: 293:259 megawatts 292: 290: 286: 281: 278: 275: 271: 268: 264: 260: 257: 253: 248: 244: 240: 229: 225: 214: 212: 208: 204: 200: 195: 167: 163: 159: 155: 151: 148:United States 147: 143: 139: 132: 127: 122: 113: 110: 102: 91: 88: 84: 81: 77: 74: 70: 67: 63: 60: –  59: 55: 54:Find sources: 48: 44: 38: 37: 32:This article 30: 26: 21: 20: 731: 720:. Retrieved 715: 691:. Retrieved 687:masslive.com 686: 676: 661:Natural gas 469: 461: 457: 449: 424:simple-cycle 420: 368: 359: 326: 324: 177:72°35′44.5″W 105: 96: 86: 79: 72: 65: 53: 41:Please help 36:verification 33: 632:Aux. Boiler 484:Description 365:Information 333:located in 331:power plant 263:diesel fuel 259:Natural gas 189: / 174:42°5′44.4″N 165:Coordinates 99:August 2010 746:Categories 722:2023-06-17 693:2023-06-17 668:References 490:Start date 452:waste heat 408:AllCapital 387:Con Edison 69:newspapers 428:gas-fired 487:Capacity 481:Unit No. 347:megawatt 267:kerosene 242:Owner(s) 153:Location 339:peaking 303:Commons 232: ( 217: ( 145:Country 83:scholar 572:107 MW 355:boiler 202:Status 85:  78:  71:  64:  56:  622:18 MW 606:18 MW 589:18 MW 555:49 MW 538:49 MW 521:48 MW 504:48 MW 493:Fuel 349:(MW) 314:[ 90:JSTOR 76:books 658:1955 655:5 KW 641:1994 592:1969 575:1957 558:2002 549:CT-2 541:2002 532:CT-1 410:and 325:The 234:2022 230:2022 219:1949 215:1949 160:1089 62:news 412:IFM 373:in 45:by 748:: 714:. 702:^ 685:. 583:10 426:, 725:. 696:. 566:3 515:2 498:1 318:] 265:/ 261:/ 236:) 221:) 112:) 106:( 101:) 97:( 87:· 80:· 73:· 66:· 39:.

Index


verification
improve this article
adding citations to reliable sources
"West Springfield Generating Station"
news
newspapers
books
scholar
JSTOR
Learn how and when to remove this message

West Springfield, Massachusetts
42°5′44.4″N 72°35′44.5″W / 42.095667°N 72.595694°W / 42.095667; -72.595694
Commission date
Natural gas
diesel fuel
kerosene
Combustion turbine
Nameplate capacity
Related media on Commons
edit on Wikidata
power plant
West Springfield, Massachusetts
peaking
peak electrical demand
megawatt
combustion turbine
boiler
Memorial Bridge

Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.