337:
Central
Electricity Generating Board's policy of preservation of amenities, a better solution was sought. Consideration was given to 400 kV and 500 kV schemes: both gave a sufficient margin for future expansion. The decision in favour of a 400 kV system was made for two main reasons. Firstly the majority of the 275 kV lines could be uprated to 400 kV, and secondly it was envisaged that operation at 400 kV could begin in 1965 compared with 1968 for a 500 kV scheme. Design work was started and in order to meet the programme for 1965 it was necessary for the contract engineering for the first projects to run concurrently with the design. One of these projects was the West Burton 400 kV Indoor Substation, the first section of which was commissioned in June 1965. From 1965, the grid was partly upgraded to 400 kV, beginning with a 150-mile (240 km) line from
197:
281:– linking the 122 most efficient power stations. The first "grid tower" was erected near Edinburgh on 14 July 1928, and work was completed in September 1933, ahead of schedule and on budget. It began operating in 1933 as a series of regional grids with auxiliary interconnections for emergency use. Following the unauthorised but successful short term parallelling of all regional grids by the night-time engineers on 29 October 1937, by 1938 the grid was operating as a national system. The growth by then in the number of electricity users was the fastest in the world, rising from three quarters of a million in 1920 to nine million in 1938. The grid proved its worth during the
929:
404:
42:
412:
267:
5644:
6223:
1117:
144:
5457:
949:'Triad demand' is a metric of demand which reports retrospectively three numbers about peak demand between November and February (inclusive) each winter. In order to encourage usage of the National Grid to be less 'peaky', the triad is used as the basis for extra charges paid by the users (the licensed electricity suppliers) to the National Grid: the users pay less if they can
666:
441:
429:
1270:
frequency drop, and over the next few hours
National Grid ordered the distribution networks to reduce voltage in order to reduce demand. At least 500,000 customers lost power. Within 40 minutes, distribution networks were allowed to reconnect all customers, although voltage control continued in some areas until 18:07.
1182:
by at least ten clear working days. The TNUoS charges for a HH customer are simply their average demand during the triad periods multiplied by the tariff for their zone. Therefore, (as of 2007) a customer in London with a 1 MW average demand during the three triad periods would pay £19,430 in TNUoS charges.
1273:
The incident was described as a "gigantic coincidence" and was not attributed to lack of investment. Nonetheless, a number of issues were exposed by the event. The behaviour of generation protection during sudden frequency changes caused a number of generators to disconnect from the grid incorrectly.
1181:
The TNUoS charges for a HH metered customer are based on their demand during three half-hour periods of greatest demand between
November and February, known as the Triad. Due to the nature of electricity demand in the UK, the three Triad periods always fall in the early evening, and must be separated
1177:
Consumers of electricity are split into two categories: half-hourly metered (HH) and non-half-hourly metered (NHH). Customers whose peak demand is sufficiently high are obliged to have a HH meter, which, in effect, takes a meter reading every 30 minutes. The rates at which charges are levied on these
1079:
However, Bernard Quigg notes: "According to the 06/07 annual accounts for NGC UK transmission, NGC carried 350TW⋅h for an income of £2012m in 2007, i. e. NGC receives 0.66p per kW hour. With two years inflation to 2008/9, say 0.71p per kW⋅h.", but this also includes generators' connection fees.
956:
For each year's calculation, historic system demand metrics are analysed to determine three half-hour periods of high average demand; the three periods are known as triads. The periods are (a) the period of peak system demand, and (b) two other periods of highest demand which are separated from peak
1291:
tripped within seconds of each other, removing 1.378 GW of generation, which was in excess of the 1 GW of backup power (the size of the largest single expected loss) that the operator was maintaining at the time. The grid frequency fell to 48.8 Hz before automatic load-shedding disconnected 5%
960:
For power stations, the chargeable demand is only the net site demand (per CUSC rule 14.17.10), so when the site is net exporting (i.e. total metered generation at that site exceeds total separately metered station demand), that separately metered station demand shall not be liable for demand TNUoS
312:
Considered in the study, together with the increased demand, was the effect on the transmission system of the rapid advances in generator design resulting in projected power stations of 2,000–3,000 MW installed capacity. These new stations were mostly to be sited where advantage could be taken
1269:
The system frequency immediately dropped to 49.2 Hz, and subsequent additional trips of generation due to automatic protection caused the frequency to fall further to a low of 48.8 Hz. This caused the distribution networks to automatically disconnect some customers in order to arrest the
656:
Because of the power loss associated with this north to south flow, the effectiveness and efficiency of new generation capacity is significantly affected by its location. For example, new generating capacity on the south coast has about 12% greater effectiveness due to reduced transmission system
639:
Generated power entering the grid is metered at the high-voltage side of the generator transformer. Any power losses in the generator transformer are therefore accounted to the generating company, not to the grid system. The power loss in the generator transformer does not contribute to the grid
574:
or offsetting would be needed as is the case with 'net zero'). In 2020 about 40% of the grid's energy came from burning natural gas, and it is not expected that anywhere close to sufficient green power will be available to run the grid on zero carbon in 2025, except perhaps on the very windiest
336:
Continued reinforcement and extension of the 275 kV systems was examined as a possible solution. However, in addition to the technical problem of high fault levels, many more lines would have been required to obtain the estimated transfers at 275 kV. As this was not consistent with the
1236:
An oil leak had been left untreated, except for top-ups, for many months, pending a proper fix. This caused an alarm which was misinterpreted by the
National Grid control room. While switching the presumed faulty equipment out, an incorrectly sized protection relay installed several years prior
1088:
In order to be allowed to supply electricity to the transmission system, generators must be licensed (by BEIS) and enter into a connection agreement with NGET which also grants
Transmission Entry Capacity (TEC). Generators contribute to the costs of running the system by paying for TEC, at the
1075:
If the total TNUoS or Triad receipts (say £15,000/MW·year × 50,000 MW = £750 million/year) is divided by the total number of units delivered by the UK generating system in a year (the total number of units sold – say 360 terawatt-hours (1.3 EJ).), then a crude estimate can be made of
1194:
Constraint payments are payments to generators above a certain size, where the
National Grid gives them dispatch instructions that they are unable to take the electricity that the generators would normally provide. This can be due to a lack of transmission capacity, a shortfall in demand, or
1245:
A week after the London blackout, on 5 September 2003, an incident occurred at Hams Hall substation which affected supply to 201,000 customers in east
Birmingham. Affected customers included Network Rail, Birmingham International Airport, and the National Exhibition Centre, with a total of
1063:
This is the main source of income which
National Grid uses to cover its costs for high-voltage long-distance transmission (lower voltage distribution is charged separately). The grid also charges an annual fee to cover the cost of generators, distribution networks and large industrial users
936:
The costs of operating the
National Grid System are recouped by National Grid Electricity System Operator (NGESO) through levying of Transmission Network Use of System (TNUoS) charges on the users of the system. The costs are split between the generators and the users of electricity.
940:
Tariffs are set annually by NGESO, and the country is divided into zones, each with a different tariff for generation and consumption. In general, tariffs are higher for generators in the north and consumers in the south since there is generally a north–south flow of electricity.
565:
or negative by 2033, well ahead of the UK's national target to achieve this by 2050. It also aims to have the capability to be 'zero carbon' as early as 2025, meaning that if energy suppliers are able to produce sufficient green power, the grid could theoretically run without any
823:
National Grid is responsible for contracting short term generating provision to cover demand prediction errors and sudden failures at power stations. This covers a few hours of operation giving time for market contracts to be established to cover longer term balancing.
1265:
in
Suffolk, disconnected from the grid ("tripped") within minutes of each other. The total combined loss of generation caused by these trips was at least 1714 MW — larger than the maximum loss of 1260 MW which the grid was required to support that day.
2894:
1350:
On 4 November 2015 National Grid issued an emergency notice asking for voluntary power cuts because of "multiple plant breakdowns". No power cuts occurred but wholesale electricity prices rose dramatically, with the grid paying up to £2,500 per megawatt-hour.
1282:
The third event occurred on 9 August 2019, when around a million customers across Great Britain found themselves without power. Lightning struck a transmission line at 4:52 pm, causing the loss of 500 MW embedded (mostly solar) generation. Almost immediately,
648:
In 2009–10 there was an average power flow of about 11 GW from the north of the UK, particularly from Scotland and northern England, to the south of the UK across the grid. This flow was anticipated to grow to about 12 GW by 2014. Completion of the
1089:
generation TNUoS tariffs set by NGET. This is charged on a maximum-capacity basis. In other words, a generator with 100 MW of TEC who only generated at a maximum rate of 75 MW during the year would still be charged for the full 100 MW of TEC.
3063:
304:
At its inception in 1950, the 275 kV Transmission System was designed to form part of a national supply system with an anticipated total demand of 30,000 MW by 1970. The predicted demand was already exceeded by 1960. This rapid growth led the
1714:
635:
to the consumer, causing a total distribution loss of about 7.7%. Losses differ significantly for customers connected at different voltages; connected at high voltage the total losses are about 2.6%, at medium voltage 6.4% and at low voltage 12.2%.
325:, is an example. These developments shifted the emphasis on the transmission system from interconnection to bulk power transfers from the generation areas to the load centres, such as the anticipated transfer in 1970 of some 6,000 MW from the
587:
is progressing rapidly with only 1.6% of the UK's electricity coming from coal in 2020, compared with about 25% in 2015. 2020 saw the UK go more than two months without needing to burn any coal for electricity, the longest period since the
2132:
1608:
2883:
1203:
Power cuts due to faults in the national grid, or lack of generation to supply it with sufficient power, are very rare. The overall performance of the system is published on National Grid's website and includes a simple
805:. As of May 2021, 1.3 GW of battery storage was operating in the United Kingdom, with 16 GW of projects in the pipeline potentially deployable over the next few years. A 100 MW power Chinese-financed plant at
575:
days. Analysts such as Hartree Solutions considered in 2020 that getting to 'net zero' by 2050 would be challenging, even more so to reach 'net zero' by 2033. There has, however, been sustained progress towards
1211:
In 2020–21, issues affecting the low voltage distribution networks – for which National Grid is not responsible – caused almost all the 60 minutes or so per year, on average, of unplanned domestic power cuts.
848:
Fast Start: generation units that start from a standstill and deliver power within five minutes automatically, or within seven minutes of a manual instruction, with generation maintained for a minimum of four
72:, and ensuring that electricity generated anywhere on the grid can be used to satisfy demand elsewhere. The network serves the majority of Great Britain and some of the surrounding islands. It does not cover
1703:
1185:
TNUoS charges levied on NHH metered customers are much simpler. A supplier is charged for the sum of their total consumption between 16:00 and 19:00 every day over a year, multiplied by the relevant tariff.
5134:
1612:
4823:
2801:
2698:
584:
1448:
1274:
The Low Frequency Demand Disconnection and voltage control schemes also did not deliver as much demand reduction as they were intended to, but this did not have a significant impact on the outage.
1306:
trains to fail. Half were restarted by the drivers but the others required a technician to come out to the train to restart it. This led to substantial travel disruption for several hours on the
4941:
3225:
3064:"Commercial Opportunities for Back-Up Generation and Load Reduction via National Grid, the National Electricity Transmission System Operator (NETSO) for England, Scotland, Wales and Offshore"
6254:
240:. This opened in 1901, and by 1912 had developed into the largest integrated power system in Europe. The rest of the country, however, continued to use a patchwork of small supply networks.
1812:
4798:
1965:
4923:
4540:
2399:
2362:
4853:
4848:
4079:
2772:
2124:
1616:
3737:
3525:
855:
Short Term Operating Reserve (STOR): generation of at least 3 MW, from a single or aggregation of sites, within four hours of instruction and maintained for at least two hours.
2989:
4890:
4745:
2734:
1428:
3831:
1993:
809:, Wiltshire was reported to be the largest in Europe when it opened in July 2021; when a 50 MW extension is completed, the site's storage capacity will be 266 MWh.
6259:
5069:
4550:
2565:
2097:
5401:
4991:
4818:
1325:
concluded in January 2020. It found that Little Barford and Hornsea One had failed to remain connected to the grid following the lightning strike, and their operators –
1940:
1292:
of the local distribution networks (1.1 million customers) for 15 to 20 minutes; this action stabilised the remaining 95% of the system and prevented a wider blackout.
1067:
Triad charges encourage users to cut load at peak periods; this is often achieved by using diesel generators. Such generators are also routinely used by National Grid.
4996:
4933:
3759:
3505:
UK Electricity Networks: The nature of UK electricity transmission and distribution networks in an intermittent renewable and embedded electricity generation future
4570:
5495:
5428:
5317:
5119:
4803:
4697:
4560:
3669:
1443:
1138:
161:
4858:
4692:
3771:
3511:
1630:
2805:
2709:
6168:
5281:
5064:
5381:
4770:
4582:
3730:
917:
2540:
1866:
1337:£1.5M for beginning to reconnect customers before being cleared to do so, although this breach of procedure did not affect the recovery of the system.
5370:
4986:
4956:
4843:
4545:
1249:
This was attributed to an error made by National Grid when commissioning protection systems after upgrading components in the substation that August.
3236:
2511:
2496:
251:
industrialist, to solve the problem of Britain's inefficient and fragmented electricity supply industry. Weir consulted Merz, and the result was the
5433:
4592:
2592:
2442:
2335:
1377:
2205:
1103:
market. "Dynamic Containment" started in October 2020, initially priced at £17 per MW per hour, and Dynamic Regulation (DR) started in April 2022.
5184:
4635:
3553:
3356:
Interim Report into the Low Frequency Demand Disconnection (LFDD) following Generator Trips and Frequency Excursion on 9 Aug 2019 - 16 August 2019
1819:
358:, the Supergrid is defined as those parts of the British electricity transmission system that are connected at voltages in excess of 200 kV.
196:
2916:
897:
The English and Welsh parts of the National Grid are controlled from the National Grid Control Centre which is located in St Catherine's Lodge,
87:
operating at 50 hertz. Most of the physical HV parts of the grid consists of 400 kV lines as well as some 275 kV lines that collectively form a
6249:
5179:
4915:
4873:
4760:
3794:
3390:
3113:
1976:
1550:
1096:
over the course of the year. This represents the reduction in costs caused by having a generator close to the centre of demand of the country.
713:
526:
30:
This article is about the power grid in Great Britain. For the UK Ordnance Survey National Grid for mapping co-ordinates in Great Britain, see
3226:"Report of the National Grid Investigation into the Frequency Deviation and Automatic Demand Disconnection that occurred on the 27th May 2008"
2958:
2396:
2359:
5460:
5084:
4655:
3723:
838:, except in exceptional circumstances. These are used on a second by second basis to either lower the demand or to provide extra generation.
695:
2776:
2618:
6264:
6226:
5411:
5386:
5301:
5271:
4682:
4600:
3659:
1295:
Although power was maintained at all times to the railway network (but not to the signalling system), the reduction in frequency caused 60
306:
107:
3278:
2179:
6065:
5094:
4905:
4793:
4707:
4630:
2990:"What is the cost per kWh of bulk transmission / National Grid in the UK (note this excludes distribution costs) | Claverton Group"
2750:
6173:
5643:
5488:
4555:
4476:
3415:
2830:
2309:
845:
Fast Reserve: rapid delivery (within two minutes) of increased generation or reduced demand, sustainable for a minimum of 15 minutes.
313:
of a surplus of cheap low-grade fuel and adequate supplies of cooling water, but these sites did not coincide with the load centres.
5793:
5240:
4966:
4735:
4565:
4527:
3469:
2744:
1371:
1164:
183:
2004:
2281:
657:
power losses compared to new generating capacity in north England, and about 20% greater effectiveness than in northern Scotland.
5104:
4978:
3689:
1472:
875:
1582:
1333:
respectively – agreed to each pay £4.5 million to Ofgem's redress fund. Additionally, Ofgem fined distribution network operator
5956:
5881:
5752:
5421:
5235:
4493:
Companies with headquarters and/or registered office in the UK but no applicable energy operations within the country shown in
3611:
2569:
2039:
1397:
1311:
1092:
In some cases, there are negative TNUoS tariffs. These generators are paid an amount based on their peak net supply over three
775:
3171:
549:
in the UK grid is around 300–360 TWh (1.1–1.3 EJ), with an average load factor of 72% (i.e. 3.6×10/(8,760 × 57×10).
5149:
4833:
3586:
2286:
1745:
1663:
1142:
719:
As of 2024, the total capacity of these connectors is over 9 GW. They include direct-current cables to northern France (2 GW
165:
6128:
6060:
6050:
5926:
5826:
5481:
5337:
5322:
5159:
5114:
5001:
4882:
4750:
4675:
4625:
4289:
3684:
3664:
3197:
1433:
1366:
818:
802:
298:
252:
77:
31:
4610:
2060:
752:
5981:
5941:
5518:
5129:
4813:
4720:
4670:
4414:
4256:
3746:
1438:
1284:
1229:
In the early evening of 28 August 2003, a power cut affected 476,000 customers in the south London area, as well as the
928:
221:
127:
2486:
6208:
6203:
5921:
5896:
5886:
5862:
5857:
5563:
5438:
4730:
4715:
4640:
4377:
4280:
3546:
3433:
Stacey, Kiran; Adams, Christopher (5 November 2015). "National Grid in emergency plea for heavy users to power down".
1656:
Electricity supply in the United Kingdom : a chronology – from the beginnings of the industry to 31 December 1985
1402:
217:
123:
54:
4497:
Ultimate parent company is not UK-based Integrated in the United States, no generation or supply activities in the UK
2884:"Power struggle: The National Grid was created to provide energy for all – but that's when the problems really began"
1704:"Power struggle: The National Grid was created to provide energy for all – but that's when the problems really began"
1127:
3454:
Electricity Before Nationalisation, A Study in the Development of the Electricity Supply Industry in Britain to 1948
6123:
5841:
5811:
5588:
5396:
5164:
5139:
4322:
4151:
2145:
1922:
1418:
1382:
827:
571:
432:
403:
342:
314:
233:
213:
84:
3503:
3088:
2499:
1146:
1131:
1076:
transmission costs, and one gets the figure of around 0.2p/kW⋅h. Other estimates also give a figure of 0.2p/kW⋅h.
154:
6178:
5667:
5628:
5347:
5286:
4363:
260:
2079:
905:
in Berkshire. It is sometimes described as being a 'secret' location. As of 2015 the system is under consistent
41:
6153:
5961:
5901:
5558:
5327:
5174:
5059:
4740:
2021:
795:
687:
Some of these HVDC lines transfer power from renewable sources such as hydro and wind. For names, see also the
632:
567:
2156:
1767:
6092:
6082:
6072:
5391:
5342:
5109:
4788:
4645:
4109:
3815:
3627:
3606:
3591:
912:
Although the transmission network in Scotland is owned by separate companies – SP Transmission plc (part of
538:
530:
411:
286:
17:
3198:"Report on support investigations into recent blackouts in London and West Midlands Volume 1 - Main report"
852:
Demand Management: reduction in demand of at least 25 MW from large power users, for at least an hour.
6013:
5876:
5659:
5548:
5245:
5006:
4900:
4297:
3977:
3581:
3539:
1303:
1299:
1215:
Since 1990, there have been a small number of prominent power outages which were linked to National Grid:
791:
787:
3519:
3491:
2933:
2450:
1237:
caused a circuit breaker to trip, resulting in the loss of supply to two major south London substations.
6148:
5916:
5911:
5891:
4863:
4348:
4156:
3699:
3576:
1423:
706:
688:
589:
69:
2483:
2233:
301:. In 1949, the British Electricity Authority decided to upgrade the grid by adding 275 kV links.
5742:
5504:
4838:
4808:
4660:
3643:
3457:
3371:
2471:
2101:
1307:
1224:
748:
631:
Although overall losses in the National Grid are low, there are significant further losses in onward
294:
290:
244:
92:
3023:
1557:
263:, which set up the UK's first synchronised, nationwide AC grid, running at 132 kV, 50 Hz.
6113:
5946:
5846:
5821:
5774:
5583:
5573:
5538:
5416:
5124:
5074:
4575:
4353:
4246:
4030:
3461:
2856:
2491:
1330:
831:
366:
278:
237:
1893:
1195:
unexpected excess generation. A constraint payment is recompense for the reduction in generation.
5987:
5598:
5250:
5079:
4650:
4302:
3780:
3616:
3303:
1230:
879:
720:
271:
57:
3130:
2834:
229:
1844:
1233:
and some rail services, for approximately 40 minutes. A total of 724 MW of load was lost.
6138:
6018:
5623:
5291:
5169:
4422:
4394:
4317:
4266:
4236:
4172:
3944:
3930:
3679:
3465:
3288:
3257:
2740:
2254:
1787:
1741:
1669:
1659:
1334:
1288:
1205:
650:
576:
362:
111:
35:
3036:
6087:
6028:
5732:
5727:
5704:
5613:
5553:
5276:
5154:
4456:
3937:
3901:
3884:
3134:
1779:
1315:
699:
611:
580:
546:
100:
73:
3353:
3146:
6118:
6077:
6055:
5936:
5906:
5871:
5831:
5633:
5144:
4045:
4009:
3970:
3621:
2889:
2403:
2366:
2266:
1899:
1709:
1413:
1361:
950:
392:
381:
318:
266:
256:
2541:"Siemens Energy and Sumitomo Electric awarded EPC contract for Ireland-UK interconnector"
3049:
6143:
6133:
5931:
5543:
5255:
4951:
4946:
4687:
4535:
4261:
4226:
4196:
3924:
3908:
3895:
2643:
2210:
1524:
920:) in the north – overall control rests with National Grid Electricity System Operator.
744:
732:
562:
542:
377:
369:
grid link within Great Britain, although interconnectors to foreign grids already used
2733:
Gross, R; Heptonstall, P; Anderson, D; Green, T; Leach, M & Skea, J (March 2006).
1867:"National Grid builds UK's first T-pylon in East Huntspill as Hinkley work progresses"
841:
Reserve services are a group of services each acting within different response times:
653:
in 2018 added capacity for a flow of 2.2 GW between Western Scotland and North Wales.
6243:
6163:
5951:
5836:
5816:
5747:
5737:
5694:
5578:
5533:
4828:
4404:
4358:
4343:
4307:
4216:
4183:
4166:
4114:
3963:
3801:
3674:
3601:
1586:
1100:
913:
604:
534:
509:
469:
453:
330:
115:
65:
61:
3367:
122:
in the north. Infrastructure connecting offshore wind farms to the grid is owned by
6183:
6158:
6023:
5992:
5806:
5608:
5225:
5049:
4783:
4778:
4466:
4251:
4201:
3951:
3919:
3262:
1407:
558:
376:
In 2021 a new non-lattice design of electricity pylon, the T-pylon, was built near
225:
209:
103:, the Republic of Ireland, France, Belgium, the Netherlands, Norway, and Denmark.
1178:
customers' electricity suppliers therefore varies 17,520 times a (non-leap) year.
365:
from Scotland to North Wales was built in 2013–2018. This was the first major non-
2593:"Moroccan solar-plus-wind to be linked to GB in 'ground-breaking' Xlinks project"
505:
Capacity (2005/6): 79.9 GW (or 80 GW per the 2008 Seven Year Statement)
6008:
5976:
5769:
5757:
5677:
5603:
5593:
5523:
5296:
5230:
4231:
4221:
4065:
4040:
4025:
3983:
2416:
1116:
906:
874:
The largest credible single generation failure event, which is currently either
756:
477:
322:
224:
in the United States. The first use of this system in the United Kingdom was by
143:
96:
3715:
2080:"National Grid connection 'vital' for Scottish islands' renewables development"
1314:
was also disrupted, and a weakness was exposed in backup power arrangements at
766:) is scheduled for 2024. Further potential schemes include links with Germany (
5971:
5966:
5779:
5762:
5618:
4755:
4620:
4471:
4338:
4241:
4206:
4146:
4138:
4104:
4060:
3988:
2706:
Operating the Electricity Transmission Networks in 2020 – Initial Consultation
1326:
1296:
1262:
898:
767:
346:
277:
The grid was created with 6,400 kilometres (4,000 mi) of cables – mostly
3391:"Blackout investigation: Power firms fined as Ofgem 'accelerates' ESO review"
1791:
309:(created in 1958) to carry out a study in 1960 of future transmission needs.
5687:
5682:
5568:
5528:
4615:
4451:
4211:
4004:
3853:
3704:
3513:
The electricity supply industry and the Central Electricity Generating Board
3283:
1673:
1497:
1387:
1258:
902:
763:
736:
716:(off-island transmission capacity relative to production capacity) was 6%.
615:
502:
Annual electrical energy used in the UK is around 360 TWh (1.3 EJ)
385:
354:
282:
88:
3114:"National Grid ESO's newest frequency service Dynamic Regulation goes live"
2482:
COM/2015/082 final: "Achieving the 10% electricity interconnection target"
2180:"National Grid: UK's electricity system could go carbon-negative from 2033"
1783:
1257:
On 27 May 2008 starting at 11:34, two of Britain's largest power stations,
2917:
U.K. Power Grid is Under Attack From Hackers Every Minute, Says Parliament
2336:"Carbon in UK Power – Part 2: Is It Time to Prioritise Carbon Over Price?"
2003:. Department of Energy & Climate Change. 27 March 2014. Archived from
1975:. Department of Energy & Climate Change. 31 March 2016. Archived from
5801:
5406:
4191:
4161:
4094:
4050:
3890:
3808:
1894:"National Grid drops Beijing-backed supplier over UK power network fears"
728:
493:
457:
326:
2857:"National Grid Control Centre Visit | Royal Meteorological Society"
665:
5722:
5712:
5473:
4605:
4481:
4461:
4446:
4399:
4312:
4119:
4099:
3957:
3914:
3821:
3596:
3375:
3325:
2516:
2238:
858:
BM Start-Up: mainstream major generation units maintained in either an
771:
740:
248:
168: in this section. Unsourced material may be challenged and removed.
119:
3147:"National Electricity Transmission System Performance Report, 2021-22"
916:) in the south, and Scottish Hydro Electric Transmission plc (part of
5717:
4725:
1392:
806:
461:
338:
201:
2369:, Simon Minett, director, DELTA Energy and Environment, October 2005
2234:"Britain sees greenest year for electricity in 2020 – National Grid"
488:
The following figures are taken from the 2005 Seven Year Statement.
5332:
5054:
4895:
4055:
4035:
3872:
3694:
3205:
2619:"Top ten UK battery storage projects forecast for 2021 completion"
2472:
https://www.ssen-transmission.co.uk/projects/project-map/shetland/
1322:
927:
835:
724:
705:
The UK grid is connected to adjacent European electrical grids by
664:
473:
410:
402:
352:
In the 2010 issue of the code that governs the National Grid, the
265:
195:
40:
5135:
Decarbonisation measures in proposed UK electricity market reform
2512:"ElecLink: IGC approves start of tests at the converter stations"
2125:"UK electricity demand close to record low Sunday: National Grid"
391:
In 2023, the National Grid began removing equipment from China's
27:
High-voltage electric power transmission network in Great Britain
5672:
3531:
2644:"Biggest storage battery in Europe built near Wiltshire village"
786:
The UK grid has access to large pumped storage systems, notably
465:
370:
5477:
5368:
5205:
5031:
4515:
3757:
3719:
3535:
3878:
3787:
2669:
1766:
Booth, E.S.; Clark, D.; Egginton, J.L.; Forrest, J.S. (1962).
1110:
521:
Length of 132 kV (or lower) grid; 5,250 km (circuit)
452:
The contiguous synchronous grid covers England (including the
285:, when South Wales provided power to replace lost output from
137:
3497:
3131:
http://ireland2050.ie/questions/what-are-constraint-payments/
1449:
List of high-voltage transmission links in the United Kingdom
885:
The general anticipated availability of all generation plants
3485:
2282:"Britain goes two months without burning coal amid lockdown"
2206:"U.K. Power Grid Heads for Greenest Year as Renewables Grow"
444:
110:
in 1990, the National Grid in England and Wales is owned by
3848:
2693:
2691:
2310:"Carbon in UK Power – Part 1: Lower Costs or Least Carbon?"
1631:"Electricity Act 1926 | Electricity System | IESIS Energy"
1206:
high-level figure for the transmission system availability
762:
A further 500 MW link with the Republic of Ireland (
525:
Total generating capacity is supplied roughly equally by
3354:
https://www.nationalgrideso.com/document/151081/download
957:
system demand and from each other by at least ten days.
790:
which can provide 1.7 GW for 5–6 hours, and the smaller
778:(3.6 GW from new battery-backed solar generation).
3522:, BBC News, map revised by Deloitte & Touche (2003)
3172:"RIIO-1 Electricity Distribution Annual Report 2020-21"
1686:
The Secret Life of the National Grid: Wiring the Nation
1393:
2007 switching station flood at Walham, Gloucestershire
270:
National Grid helicopter inspecting overhead cables in
600:
Figures are again from the 2005 Seven Year Statement.
3416:"Companies pay £10.5 million over 9 August power cut"
1429:
List of high voltage underground and submarine cables
870:
These reserves are sized according to three factors:
259:" supply system be created. The 1926 Act created the
2983:
2981:
2979:
2959:"Transmission Network Use of System (TNUoS) Charges"
961:
charges in relation to the station demand at triad.
627:
Total losses: 1,423.5 MW (2.29% of peak demand)
621:
Substation transformer heating losses: 142.4 MW
515:
Length of 400 kV grid: 11,500 km (circuit)
6192:
6102:
6039:
6001:
5855:
5792:
5703:
5658:
5651:
5511:
5310:
5264:
5216:
5093:
5042:
4977:
4965:
4932:
4914:
4881:
4872:
4769:
4706:
4591:
4526:
4439:
4413:
4385:
4376:
4331:
4288:
4279:
4182:
4137:
4128:
4087:
4078:
4018:
3997:
3862:
3841:
3830:
3770:
3652:
3636:
3569:
3220:
3218:
3216:
1498:"Nikola Tesla: Father of Our Modern Energy Systems"
624:
Generator transformer heating losses: 157.3 MW
518:
Length of 275 kV grid: 9,800 km (circuit)
421:
5402:Double Glazing & Conservatory Ombudsman Scheme
5070:Department for Environment, Food and Rural Affairs
2882:
1892:
1772:Proceedings of the IEE - Part A: Power Engineering
1702:
694:There is a 40 MW AC cable to the Isle of Man, the
6255:Electric power transmission in the United Kingdom
3326:"Major power failure affects homes and transport"
3052:, published 29 March 2021, accessed 30 April 2021
3037:History repeats itself: trends are hard to change
293:power stations. The grid was nationalised by the
3039:, published 26 March 2018, accessed 3 April 2018
3026:, published 29 March 2017, accessed 3 April 2018
460:(including some of the Scottish islands such as
3368:"GB : Frequency drops off the chart to..."
3251:
3249:
3013:Inenco, 2015/16 Triads, published 31 March 2016
2010:on 8 October 2016 – via Internet Archive.
618:; can be 100 MW higher in adverse weather)
5318:Centre for Renewable Energy Systems Technology
5120:Climate Change and Sustainable Energy Act 2006
3670:High-voltage substations in the United Kingdom
3349:
3347:
3345:
3343:
2699:"Appendix D Description of Balancing Services"
1768:"The 400 kV grid system for England and Wales"
1444:High-voltage substations in the United Kingdom
583:falling by 53% in the five years to 2020. The
5489:
3731:
3547:
3528:, National Grid's Seven Year Statement (2008)
3256:Milner, Mark; Wearden, Graeme (28 May 2008).
2923:, 9 January 2015. Retrieved: 20 January 2015.
2568:. National Grid. 12 July 2016. Archived from
1585:. North Northumberland Online. Archived from
407:UK electricity production by source 1985–2020
99:, and DC connectors to Northern Ireland, the
8:
3279:"Blackouts hit thousands as generators fail"
1982:on 3 July 2016 – via Internet Archive.
1556:. Royal Society of Edinburgh. Archived from
18:Control of the National Grid (Great Britain)
5065:Department for Energy Security and Net Zero
4698:Timeline of the electricity supply industry
3277:Ahmed, Murad; Hawkes, Steve (28 May 2008).
1696:
1694:
1692:
1145:. Unsourced material may be challenged and
5655:
5496:
5482:
5474:
5382:Association for the Conservation of Energy
5365:
5213:
5202:
5039:
5028:
4878:
4523:
4512:
4382:
4285:
4134:
4084:
3838:
3767:
3754:
3738:
3724:
3716:
3554:
3540:
3532:
3520:Map of GB power stations and national grid
3492:Carbon-intensity variations in the GB grid
2708:, National Grid, June 2009, archived from
2406:, 2009 Seven Year Statement, National Grid
1966:"UK Energy Statistics, 2015 & Q4 2015"
1057:Wednesday 10 February 2021, 18:00 - 18:30
918:Scottish and Southern Electricity Networks
6260:1933 establishments in the United Kingdom
3695:Record of Inter System Safety Precautions
1473:"The GB electricity transmission network"
1165:Learn how and when to remove this message
1071:Estimating costs per kW⋅h of transmission
987:Wednesday 25 November 2015, 17:00 – 17:30
317:'s 4 × 500 MW machines, in the
200:Electricity pylons in a suburban area of
184:Learn how and when to remove this message
3089:"Grid Operations | Claverton Group"
2378:Metering Code of Practice 1 (Elexon Ltd)
1761:
1759:
1757:
1378:Energy security and renewable technology
966:
751:); the Republic of Ireland (500 MW HVDC
5185:United Kingdom Climate Change Programme
1941:"International Energy Statistics – EIA"
1551:"Kelvin to Weir, and on to GB SYS 2005"
1523:Massachusetts Institute of Technology.
1461:
1310:and Thameslink services. The supply to
813:Reserve services and frequency response
610:Fixed losses: 266 MW (consists of
499:Minimum demand (2020 May): 15.3 GW
4761:United Kingdom Atomic Energy Authority
3516:, Competition Commission Report (1987)
2736:The Costs and Impacts of Intermittency
2262:
2252:
1054:Thursday 7 January 2021, 17:30 - 18:00
1015:Monday 11 December 2017, 17:30 – 18:00
1007:Monday 23 January 2017, 17:00 – 17:30
1004:Thursday 5 January 2017, 17:00 – 17:30
418:
243:In 1925, the British government asked
5085:Office of Gas and Electricity Markets
4656:Isle of Man to England Interconnector
2123:Edwardes-Evans, Henry (11 May 2020).
1051:Monday 7 December 2020, 17:00 - 17:30
1001:Monday 5 December 2016, 17:00 – 17:30
993:Monday 15 February 2016, 18:00–18:30
696:Isle of Man to England Interconnector
255:, which recommended that a "national
7:
5412:Energy efficiency in British housing
5387:British Energy Efficiency Federation
5302:Utilities Intermediaries Association
5272:Association for Decentralised Energy
4683:New Electricity Trading Arrangements
4601:Association of Electricity Producers
4400:Scottish Hydro Electric Transmission
3660:Central Electricity Generating Board
2617:McCorkindale, Mollie (19 May 2021).
2539:Stanford, Anna (21 September 2021).
1847:. National Grid & Scottish Power
1467:
1465:
1208:. For 2021–22, this was 99.999612%.
1143:adding citations to reliable sources
1021:Monday 5 February 2018, 18:00–18:30
1018:Monday 26 February 2018, 18:30–19:00
990:Tuesday 19 January 2016, 17:00–17:30
888:Anticipated demand prediction errors
878:(1,260 MW) or one cable of the
698:and a 260km 600MW HVDC cable to the
415:Electricity supplied (net) 1920–2014
307:Central Electricity Generating Board
166:adding citations to reliable sources
108:Central Electricity Generating Board
4906:Renewable Transport Fuel Obligation
2591:Grundy, Alice (25 September 2021).
2360:Time to Take a Fresh Look at CHP...
2204:Rachel Morison (29 December 2020).
114:. In Scotland the grid is owned by
6174:Renewable energy commercialization
4556:Confederation of UK Coal Producers
4477:United Downs Deep Geothermal Power
3050:Winter 20-21 TRIAD dates announced
2135:from the original on 3 March 2021.
1923:"Electricity production by source"
1701:Gerard Gilbert (22 October 2010).
964:Triad dates in recent years were:
472:which have limited connectivity),
25:
5241:Centre for Alternative Technology
4736:Nuclear Decommissioning Authority
3498:Real-time electricity market data
2897:from the original on 18 June 2022
2802:"NETA Despatch Instruction Guide"
2232:Reuters Staff (11 January 2021).
2078:McCulloch, Scott (8 March 2016).
1717:from the original on 18 June 2022
1658:. The Electricity Council. 1987.
1410:– calculating the cost of back-up
1372:Economics of nuclear power plants
747:); Northern Ireland (500 MW HVDC
714:electricity interconnection level
492:Maximum demand (2005/6): 63
395:over national security concerns.
6222:
6221:
5642:
5455:
5105:Carbon Emission Reduction Target
4824:Natural gas-fired power stations
3690:Niagara Mohawk Power Corporation
1115:
876:Sizewell B nuclear power station
834:frequency within ±1% of 50
439:
427:
208:At the end of the 19th century,
142:
5422:Energy Saving Trust Recommended
5236:Campaign against Climate Change
3612:Huddersfield Narrow Canal Pylon
3389:Stoker, Liam (3 January 2020).
3235:. February 2009. Archived from
3024:2016/17 Triad Periods Confirmed
2449:. National Grid. Archived from
2334:Adam Lewis (22 December 2020).
2022:"Energy Trends: UK electricity"
1549:Alan Shaw (29 September 2005).
1398:List of energy storage projects
380:, Somerset for the new 35 mile
232:consulting partnership, at his
153:needs additional citations for
106:Since the privatisation of the
78:Irish single electricity market
5207:Non-governmental organisations
5150:Energy performance certificate
4834:North Sea Transition Authority
3587:Aust Severn Powerline Crossing
3133:What are constraint payments?
2308:Adam Lewis (8 December 2020).
2287:Natural History Museum, London
882:interconnector (1,000 MW)
739:); the Netherlands (1 GW HVDC
496:(approx.) (81.39% of capacity)
212:established the principles of
1:
6250:National Grid (Great Britain)
6169:Renewable Energy Certificates
6129:Cost of electricity by source
6051:Arc-fault circuit interrupter
5927:High-voltage shore connection
5338:Oil Depletion Analysis Centre
5323:Energy Technologies Institute
5160:Low Carbon Building Programme
5002:North Seas Energy Cooperation
4751:Office for Nuclear Regulation
4257:TotalEnergies Gas & Power
3685:National Grid Reserve Service
3665:Electricity (Supply) Act 1926
2739:. UK Energy Research Centre.
2040:"Historical electricity data"
1434:National Grid Reserve Service
1367:Cost of electricity by source
932:400 kV power line in Cheshire
819:National Grid Reserve Service
299:British Electricity Authority
253:Electricity (Supply) Act 1926
32:Ordnance Survey National Grid
6184:Spark/Dark/Quark/Bark spread
5982:Transmission system operator
5942:Mains electricity by country
5519:Automatic generation control
5130:CRC Energy Efficiency Scheme
4942:Hydroelectric power stations
4814:National Transmission System
4721:Franco-British Nuclear Forum
3747:Energy in the United Kingdom
3456:. London & Basingstoke:
3302:George South (28 May 2008).
2831:"Wind Turbine Price List Uk"
2447:National Grid – UK – Library
2441:PLC, National Grid Company.
2280:Katie Pavid (15 June 2020).
2178:Sarah Green (27 July 2020).
2098:"National Grid - SYS 2005 -"
1439:Energy in the United Kingdom
1285:Little Barford Power Station
755:), and Denmark (1.4 GW
128:transmission system operator
124:offshore transmission owners
6265:Wide area synchronous grids
6209:List of electricity sectors
6204:Electric energy consumption
5922:High-voltage direct current
5897:Electric power transmission
5887:Electric power distribution
5564:Energy return on investment
5439:National Home Energy Rating
5282:Energy Networks Association
4992:List of offshore wind farms
4731:National Nuclear Laboratory
4716:Advanced Gas-cooled Reactor
4641:Grid Trade Master Agreement
3486:National Grid data overview
3366:@enappsys (9 August 2019).
3258:"Q&A: Blackout Britain"
2443:"2002 Seven Year Statement"
2387:Metering Code of Practice 2
1403:List of major power outages
1246:301 MW of load lost.
828:Frequency-response reserves
445:Current grid status, charts
399:Characteristics of the grid
218:electric power distribution
126:. National Grid plc is the
55:electric power transmission
6281:
6124:Carbon offsets and credits
5842:Three-phase electric power
5397:Code for Sustainable Homes
5165:Non-Fossil Fuel Obligation
5140:Display Energy Certificate
4997:List of onshore wind farms
4364:Wales & West Utilities
4323:Western Power Distribution
4152:Engie Energy International
2934:"Our Transmission Network"
2566:"Interconnectors: Iceland"
1419:Three-phase electric power
1383:Intermittent energy source
1222:
816:
234:Neptune Bank Power Station
116:ScottishPower Transmission
85:wide area synchronous grid
29:
6217:
6179:Renewable Energy Payments
5668:Fossil fuel power station
5640:
5451:
5377:
5364:
5348:UK Energy Research Centre
5287:Energy Retail Association
5212:
5201:
5038:
5033:Government and regulation
5027:
4924:Geothermal power stations
4631:Energy switching services
4541:Coal-fired power stations
4522:
4511:
4490:
3766:
3753:
2421:www.westernhvdclink.co.uk
2397:Effect on Power Transfers
1609:"Lighting by electricity"
830:act to keep the system's
770:, 1.4 GW); Iceland (
438:
433:Current grid status, maps
426:
361:The 2.2 GW undersea
297:, which also created the
261:Central Electricity Board
220:while he was working for
95:: an AC connector to the
5962:Single-wire earth return
5902:Electrical busbar system
5559:Energy demand management
5429:Greenhouse gas emissions
5328:Met Office Hadley Centre
5175:Renewable Heat Incentive
5115:Climate Change Agreement
5060:Climate Change Committee
4849:Oil-fired power stations
4804:Greenhouse gas emissions
4741:Nuclear Liabilities Fund
4611:East–West Interconnector
4561:Greenhouse gas emissions
3304:"iPM: Blackout Britain?"
2365:27 February 2008 at the
2061:"Over the hills to Skye"
1583:"Survey of Belford 1995"
953:so as to be less peaky.
774:, around 1 GW) and
753:East–West Interconnector
679: Under construction
633:electricity distribution
607:in cables: 857.8 MW
568:greenhouse gas emissions
557:The National Grid has a
93:undersea interconnectors
45:Map of the National Grid
6093:Residual-current device
6083:Power system protection
6073:Generator interlock kit
5392:Close the Door campaign
5343:Sunbury Research Centre
5110:Climate Change Act 2008
4789:Forties pipeline system
4646:Gridlink Interconnector
3628:Severn-Wye Cable Tunnel
3607:Gridlink Interconnector
3592:Blackhillock Substation
3526:The Transmission System
3452:Hannah, Leslie (1979).
2157:"Zero-carbon explained"
1813:"the British Grid Code"
743:); Norway (1.4 GW HDVC
130:for the whole GB grid.
83:The National Grid is a
76:, which is part of the
34:. For the company, see
5877:Distributed generation
5549:Electric power quality
5246:National Energy Action
5007:Wind power in Scotland
4901:Renewable Fuels Agency
4891:Biofuel power stations
4746:Nuclear power stations
4313:SSE Power Distribution
4298:Electricity North West
3978:Rockhopper Exploration
3582:400 kV Thames Crossing
3437:. pp. front page.
2417:"Western Link project"
2065:Over the hills to Skye
1994:"UK Energy Statistics"
1784:10.1049/pi-a.1962.0143
1736:Cochrane, Rob (1985).
1374:– for cost comparisons
933:
788:Dinorwig Power Station
735:); Belgium (1 GW HVDC
707:submarine power cables
691:
416:
408:
274:
205:
46:
6149:Fossil fuel phase-out
5917:Electricity retailing
5912:Electrical substation
5892:Electric power system
5180:Renewables Obligation
4864:Petroleum Revenue Tax
4349:Northern Gas Networks
4157:Horizon Nuclear Power
3700:Registered power zone
3577:275 kV Forth Crossing
3508:, Scott Butler (2001)
1424:List of HVDC projects
1099:National Grid uses a
931:
668:
590:Industrial Revolution
414:
406:
269:
199:
118:in the south, and by
44:
5505:Electricity delivery
4839:Offshore Energies UK
4809:Hydrocarbon Oil Duty
4661:Moyle Interconnector
4583:Open-pit coal mining
3644:2003 London blackout
3458:Macmillan Publishers
3328:. BBC. 9 August 2019
3093:Claverton-energy.com
3068:Claverton-energy.com
2994:Claverton-energy.com
2773:"Agenda 22 May 2007"
2495:, 25 February 2015.
2402:28 July 2012 at the
1321:An investigation by
1308:East Coast Main Line
1225:2003 London blackout
1139:improve this section
801:There are also some
749:Moyle Interconnector
673: Existing links
512:connected to it: 181
295:Electricity Act 1947
162:improve this article
53:is the high-voltage
6114:Availability factor
6066:Sulfur hexafluoride
5947:Overhead power line
5847:Virtual power plant
5822:Induction generator
5775:Sustainable biofuel
5584:Home energy storage
5574:Grid energy storage
5539:Droop speed control
5417:Energy Saving Trust
5371:Energy conservation
5125:Climate Change Levy
5075:Energy Saving Trust
4987:Offshore wind power
4626:Electricity billing
4576:National Coal Board
4551:Coal mining regions
4354:Phoenix Natural Gas
4247:Phoenix Natural Gas
4031:Amec Foster Wheeler
3462:Electricity Council
3022:Trident Utilities,
2863:. 24 September 2012
2715:on 23 December 2011
2492:European Commission
2453:on 19 December 2005
2104:on 8 September 2012
2028:. 30 November 2023.
1873:. 14 September 2021
1738:Power to the People
1635:www.iesisenergy.org
1190:Constraint payments
893:Control of the grid
367:alternating current
321:coalfield near the
238:Newcastle upon Tyne
230:Merz & McLellan
5988:Transmission tower
5599:Nameplate capacity
5251:Stop Climate Chaos
5080:Environment Agency
4854:Oil infrastructure
4819:Natural gas fields
4799:Gas infrastructure
4651:HVDC Cross-Channel
4405:SP Energy Networks
4308:SP Energy Networks
4303:Northern Powergrid
3617:HVDC Cross-Channel
3242:on 4 January 2010.
2837:on 3 November 2010
2623:Solar Power Portal
2265:has generic name (
1903:. 17 December 2023
1871:Burnham-On-Sea.com
1613:The National Trust
1231:London Underground
1084:Generation charges
951:manage their usage
934:
924:Transmission costs
880:HVDC Cross-Channel
721:HVDC Cross-Channel
712:In 2014, the UK's
692:
689:annotated version.
547:energy transmitted
417:
409:
275:
272:Greater Manchester
206:
47:
6235:
6234:
6139:Environmental tax
6019:Cascading failure
5788:
5787:
5624:Utility frequency
5471:
5470:
5447:
5446:
5360:
5359:
5356:
5355:
5292:Green Power Forum
5197:
5196:
5193:
5192:
5170:Planning Act 2008
5023:
5022:
5019:
5018:
5015:
5014:
4636:Green electricity
4507:
4506:
4503:
4502:
4498:
4435:
4434:
4431:
4430:
4372:
4371:
4318:UK Power Networks
4275:
4274:
4267:Utility Warehouse
4237:Outfox the Market
4173:Vedanta Resources
4074:
4073:
3945:Melrose Resources
3938:JKX Oil & Gas
3931:Hardy Oil and Gas
3713:
3712:
3680:National Grid plc
3422:. 3 January 2020.
3291:on 9 August 2011.
3151:National Grid ESO
3048:Now Then Energy,
2963:National Grid ESO
2520:. 15 October 2020
2340:Hartree Solutions
2314:Hartree Solutions
1927:Our World in Data
1335:UK Power Networks
1312:Newcastle Airport
1289:Hornsea Wind Farm
1175:
1174:
1167:
1061:
1060:
651:Western HVDC Link
585:phase out of coal
577:carbon neutrality
450:
449:
363:Western HVDC Link
194:
193:
186:
112:National Grid plc
91:. It has several
36:National Grid plc
16:(Redirected from
6272:
6225:
6224:
6134:Energy subsidies
6088:Protective relay
6029:Rolling blackout
5656:
5646:
5614:Power-flow study
5554:Electrical fault
5498:
5491:
5484:
5475:
5459:
5458:
5366:
5277:Energy Institute
5214:
5203:
5155:Fossil Fuel Levy
5040:
5029:
4934:Hydroelectricity
4879:
4524:
4513:
4492:
4457:Aquamarine Power
4383:
4286:
4135:
4085:
3902:Desire Petroleum
3885:Capricorn Energy
3839:
3768:
3755:
3740:
3733:
3726:
3717:
3556:
3549:
3542:
3533:
3475:
3439:
3438:
3430:
3424:
3423:
3412:
3406:
3405:
3403:
3401:
3386:
3380:
3379:
3363:
3357:
3351:
3338:
3337:
3335:
3333:
3322:
3316:
3315:
3313:
3311:
3299:
3293:
3292:
3287:. Archived from
3274:
3268:
3267:
3253:
3244:
3243:
3241:
3230:
3222:
3211:
3210:
3202:
3194:
3188:
3187:
3185:
3183:
3168:
3162:
3161:
3159:
3157:
3143:
3137:
3135:Energy Institute
3128:
3122:
3121:
3110:
3104:
3103:
3101:
3099:
3085:
3079:
3078:
3076:
3074:
3059:
3053:
3046:
3040:
3033:
3027:
3020:
3014:
3011:
3005:
3004:
3002:
3000:
2985:
2974:
2973:
2971:
2969:
2955:
2949:
2948:
2946:
2944:
2938:SPEnergyNetworks
2930:
2924:
2915:Ward, Jillian. "
2913:
2907:
2906:
2904:
2902:
2886:
2879:
2873:
2872:
2870:
2868:
2853:
2847:
2846:
2844:
2842:
2833:. Archived from
2827:
2821:
2820:
2818:
2816:
2810:
2804:. Archived from
2798:
2792:
2791:
2789:
2787:
2781:
2775:. Archived from
2769:
2763:
2762:
2760:
2758:
2749:. Archived from
2730:
2724:
2723:
2722:
2720:
2714:
2703:
2695:
2686:
2685:
2683:
2681:
2666:
2660:
2659:
2657:
2655:
2640:
2634:
2633:
2631:
2629:
2614:
2608:
2607:
2605:
2603:
2588:
2582:
2581:
2579:
2577:
2562:
2556:
2555:
2553:
2551:
2536:
2530:
2529:
2527:
2525:
2508:
2502:
2480:
2474:
2469:
2463:
2462:
2460:
2458:
2438:
2432:
2431:
2429:
2427:
2413:
2407:
2394:
2388:
2385:
2379:
2376:
2370:
2357:
2351:
2350:
2348:
2346:
2331:
2325:
2324:
2322:
2320:
2305:
2299:
2298:
2296:
2294:
2277:
2271:
2270:
2264:
2260:
2258:
2250:
2248:
2246:
2229:
2223:
2222:
2220:
2218:
2201:
2195:
2194:
2192:
2190:
2175:
2169:
2168:
2166:
2164:
2153:
2147:
2143:
2137:
2136:
2129:www.spglobal.com
2120:
2114:
2113:
2111:
2109:
2100:. Archived from
2094:
2088:
2087:
2075:
2069:
2068:
2057:
2051:
2050:
2048:
2046:
2036:
2030:
2029:
2018:
2012:
2011:
2009:
1998:
1990:
1984:
1983:
1981:
1970:
1962:
1956:
1955:
1953:
1951:
1937:
1931:
1930:
1919:
1913:
1912:
1910:
1908:
1896:
1889:
1883:
1882:
1880:
1878:
1863:
1857:
1856:
1854:
1852:
1841:
1835:
1834:
1832:
1830:
1825:on 22 March 2011
1824:
1818:. Archived from
1817:
1809:
1803:
1802:
1800:
1798:
1763:
1752:
1751:
1733:
1727:
1726:
1724:
1722:
1706:
1698:
1687:
1684:
1678:
1677:
1652:
1646:
1645:
1643:
1641:
1627:
1621:
1620:
1619:on 29 June 2011.
1615:. Archived from
1605:
1599:
1598:
1596:
1594:
1589:on 12 April 2016
1579:
1573:
1572:
1570:
1568:
1562:
1555:
1546:
1540:
1539:
1537:
1535:
1520:
1514:
1513:
1511:
1509:
1494:
1488:
1487:
1485:
1483:
1469:
1316:Ipswich Hospital
1170:
1163:
1159:
1156:
1150:
1119:
1111:
967:
860:energy readiness
700:Shetland Islands
684:
678:
672:
581:carbon intensity
570:at all (i.e. no
508:Number of large
443:
442:
431:
430:
419:
345:, to become the
204:, West Yorkshire
189:
182:
178:
175:
169:
146:
138:
101:Shetland Islands
74:Northern Ireland
21:
6280:
6279:
6275:
6274:
6273:
6271:
6270:
6269:
6240:
6239:
6236:
6231:
6213:
6197:
6195:
6188:
6119:Capacity factor
6107:
6105:
6098:
6078:Numerical relay
6056:Circuit breaker
6044:
6042:
6035:
5997:
5937:Load management
5907:Electrical grid
5872:Demand response
5865:
5860:
5851:
5832:Microgeneration
5784:
5699:
5647:
5638:
5634:Vehicle-to-grid
5507:
5502:
5472:
5467:
5456:
5443:
5373:
5352:
5306:
5265:Industry bodies
5260:
5219:pressure groups
5218:
5208:
5189:
5145:Energy Act 2013
5096:
5095:Legislation and
5089:
5034:
5011:
4973:
4961:
4928:
4910:
4868:
4765:
4702:
4676:Reserve Service
4587:
4518:
4499:
4486:
4427:
4409:
4368:
4327:
4271:
4178:
4130:
4124:
4070:
4046:John Wood Group
4014:
4010:Murco Petroleum
3993:
3971:Regal Petroleum
3864:
3858:
3833:
3826:
3762:
3749:
3744:
3714:
3709:
3648:
3632:
3622:HVDC Kingsnorth
3565:
3560:
3482:
3472:
3451:
3448:
3446:Further reading
3443:
3442:
3435:Financial Times
3432:
3431:
3427:
3414:
3413:
3409:
3399:
3397:
3388:
3387:
3383:
3365:
3364:
3360:
3352:
3341:
3331:
3329:
3324:
3323:
3319:
3309:
3307:
3301:
3300:
3296:
3276:
3275:
3271:
3255:
3254:
3247:
3239:
3228:
3224:
3223:
3214:
3209:. 25 June 2004.
3200:
3196:
3195:
3191:
3181:
3179:
3170:
3169:
3165:
3155:
3153:
3145:
3144:
3140:
3129:
3125:
3120:. 8 April 2022.
3112:
3111:
3107:
3097:
3095:
3087:
3086:
3082:
3072:
3070:
3062:Andrews, Dave.
3061:
3060:
3056:
3047:
3043:
3034:
3030:
3021:
3017:
3012:
3008:
2998:
2996:
2988:Andrews, Dave.
2987:
2986:
2977:
2967:
2965:
2957:
2956:
2952:
2942:
2940:
2932:
2931:
2927:
2914:
2910:
2900:
2898:
2890:The Independent
2881:
2880:
2876:
2866:
2864:
2855:
2854:
2850:
2840:
2838:
2829:
2828:
2824:
2814:
2812:
2811:on 14 July 2011
2808:
2800:
2799:
2795:
2785:
2783:
2782:on 14 July 2011
2779:
2771:
2770:
2766:
2756:
2754:
2753:on 21 June 2008
2747:
2732:
2731:
2727:
2718:
2716:
2712:
2701:
2697:
2696:
2689:
2679:
2677:
2668:
2667:
2663:
2653:
2651:
2642:
2641:
2637:
2627:
2625:
2616:
2615:
2611:
2601:
2599:
2590:
2589:
2585:
2575:
2573:
2572:on 21 July 2016
2564:
2563:
2559:
2549:
2547:
2538:
2537:
2533:
2523:
2521:
2510:
2509:
2505:
2481:
2477:
2470:
2466:
2456:
2454:
2440:
2439:
2435:
2425:
2423:
2415:
2414:
2410:
2404:Wayback Machine
2395:
2391:
2386:
2382:
2377:
2373:
2367:Wayback Machine
2358:
2354:
2344:
2342:
2333:
2332:
2328:
2318:
2316:
2307:
2306:
2302:
2292:
2290:
2279:
2278:
2274:
2261:
2251:
2244:
2242:
2231:
2230:
2226:
2216:
2214:
2203:
2202:
2198:
2188:
2186:
2177:
2176:
2172:
2162:
2160:
2155:
2154:
2150:
2144:
2140:
2122:
2121:
2117:
2107:
2105:
2096:
2095:
2091:
2084:businessInsider
2077:
2076:
2072:
2059:
2058:
2054:
2044:
2042:
2038:
2037:
2033:
2020:
2019:
2015:
2007:
1996:
1992:
1991:
1987:
1979:
1968:
1964:
1963:
1959:
1949:
1947:
1939:
1938:
1934:
1921:
1920:
1916:
1906:
1904:
1900:Financial Times
1891:
1890:
1886:
1876:
1874:
1865:
1864:
1860:
1850:
1848:
1843:
1842:
1838:
1828:
1826:
1822:
1815:
1811:
1810:
1806:
1796:
1794:
1765:
1764:
1755:
1748:
1735:
1734:
1730:
1720:
1718:
1710:The Independent
1700:
1699:
1690:
1685:
1681:
1666:
1654:
1653:
1649:
1639:
1637:
1629:
1628:
1624:
1607:
1606:
1602:
1592:
1590:
1581:
1580:
1576:
1566:
1564:
1563:on 4 March 2009
1560:
1553:
1548:
1547:
1543:
1533:
1531:
1522:
1521:
1517:
1507:
1505:
1504:. 30 March 2022
1496:
1495:
1491:
1481:
1479:
1471:
1470:
1463:
1458:
1453:
1414:Load management
1362:Demand response
1357:
1348:
1343:
1341:Minor incidents
1280:
1255:
1243:
1227:
1221:
1201:
1199:Major incidents
1192:
1171:
1160:
1154:
1151:
1136:
1120:
1109:
1086:
1073:
947:
926:
895:
821:
815:
784:
686:
682:
680:
676:
674:
670:
663:
661:Interconnectors
646:
598:
555:
553:Decarbonisation
486:
440:
428:
422:External images
401:
393:NARI Technology
382:Hinkley Point C
319:Nottinghamshire
190:
179:
173:
170:
159:
147:
136:
39:
28:
23:
22:
15:
12:
11:
5:
6278:
6276:
6268:
6267:
6262:
6257:
6252:
6242:
6241:
6233:
6232:
6230:
6229:
6218:
6215:
6214:
6212:
6211:
6206:
6200:
6198:
6194:Statistics and
6193:
6190:
6189:
6187:
6186:
6181:
6176:
6171:
6166:
6161:
6156:
6151:
6146:
6144:Feed-in tariff
6141:
6136:
6131:
6126:
6121:
6116:
6110:
6108:
6103:
6100:
6099:
6097:
6096:
6090:
6085:
6080:
6075:
6070:
6069:
6068:
6063:
6053:
6047:
6045:
6040:
6037:
6036:
6034:
6033:
6032:
6031:
6021:
6016:
6011:
6005:
6003:
5999:
5998:
5996:
5995:
5990:
5985:
5979:
5974:
5969:
5964:
5959:
5954:
5949:
5944:
5939:
5934:
5932:Interconnector
5929:
5924:
5919:
5914:
5909:
5904:
5899:
5894:
5889:
5884:
5882:Dynamic demand
5879:
5874:
5868:
5866:
5856:
5853:
5852:
5850:
5849:
5844:
5839:
5834:
5829:
5824:
5819:
5814:
5812:Combined cycle
5809:
5804:
5798:
5796:
5790:
5789:
5786:
5785:
5783:
5782:
5777:
5772:
5767:
5766:
5765:
5760:
5755:
5750:
5745:
5735:
5730:
5725:
5720:
5715:
5709:
5707:
5701:
5700:
5698:
5697:
5692:
5691:
5690:
5685:
5680:
5675:
5664:
5662:
5653:
5649:
5648:
5641:
5639:
5637:
5636:
5631:
5626:
5621:
5616:
5611:
5606:
5601:
5596:
5591:
5589:Load-following
5586:
5581:
5576:
5571:
5566:
5561:
5556:
5551:
5546:
5544:Electric power
5541:
5536:
5531:
5526:
5521:
5515:
5513:
5509:
5508:
5503:
5501:
5500:
5493:
5486:
5478:
5469:
5468:
5466:
5465:
5452:
5449:
5448:
5445:
5444:
5442:
5441:
5436:
5431:
5426:
5425:
5424:
5414:
5409:
5404:
5399:
5394:
5389:
5384:
5378:
5375:
5374:
5369:
5362:
5361:
5358:
5357:
5354:
5353:
5351:
5350:
5345:
5340:
5335:
5330:
5325:
5320:
5314:
5312:
5308:
5307:
5305:
5304:
5299:
5294:
5289:
5284:
5279:
5274:
5268:
5266:
5262:
5261:
5259:
5258:
5256:Tyndall Centre
5253:
5248:
5243:
5238:
5233:
5228:
5222:
5220:
5210:
5209:
5206:
5199:
5198:
5195:
5194:
5191:
5190:
5188:
5187:
5182:
5177:
5172:
5167:
5162:
5157:
5152:
5147:
5142:
5137:
5132:
5127:
5122:
5117:
5112:
5107:
5101:
5099:
5091:
5090:
5088:
5087:
5082:
5077:
5072:
5067:
5062:
5057:
5052:
5046:
5044:
5036:
5035:
5032:
5025:
5024:
5021:
5020:
5017:
5016:
5013:
5012:
5010:
5009:
5004:
4999:
4994:
4989:
4983:
4981:
4975:
4974:
4971:
4969:
4963:
4962:
4960:
4959:
4954:
4952:Severn Barrage
4949:
4947:Mersey Barrage
4944:
4938:
4936:
4930:
4929:
4927:
4926:
4920:
4918:
4912:
4911:
4909:
4908:
4903:
4898:
4893:
4887:
4885:
4876:
4870:
4869:
4867:
4866:
4861:
4859:Oil refineries
4856:
4851:
4846:
4841:
4836:
4831:
4826:
4821:
4816:
4811:
4806:
4801:
4796:
4791:
4786:
4781:
4775:
4773:
4767:
4766:
4764:
4763:
4758:
4753:
4748:
4743:
4738:
4733:
4728:
4723:
4718:
4712:
4710:
4704:
4703:
4701:
4700:
4695:
4693:Power stations
4690:
4688:North Sea Link
4685:
4680:
4679:
4678:
4673:
4663:
4658:
4653:
4648:
4643:
4638:
4633:
4628:
4623:
4618:
4613:
4608:
4603:
4597:
4595:
4589:
4588:
4586:
4585:
4580:
4579:
4578:
4573:
4571:miners' strike
4563:
4558:
4553:
4548:
4543:
4538:
4536:Coal Authority
4532:
4530:
4520:
4519:
4517:Energy sources
4516:
4509:
4508:
4505:
4504:
4501:
4500:
4491:
4488:
4487:
4485:
4484:
4479:
4474:
4469:
4464:
4459:
4454:
4449:
4443:
4441:
4437:
4436:
4433:
4432:
4429:
4428:
4426:
4425:
4419:
4417:
4411:
4410:
4408:
4407:
4402:
4397:
4391:
4389:
4380:
4374:
4373:
4370:
4369:
4367:
4366:
4361:
4356:
4351:
4346:
4341:
4335:
4333:
4329:
4328:
4326:
4325:
4320:
4315:
4310:
4305:
4300:
4294:
4292:
4283:
4277:
4276:
4273:
4272:
4270:
4269:
4264:
4262:Utilita Energy
4259:
4254:
4249:
4244:
4239:
4234:
4229:
4227:Octopus Energy
4224:
4219:
4214:
4209:
4204:
4199:
4197:Bristol Energy
4194:
4188:
4186:
4180:
4179:
4177:
4176:
4169:
4164:
4159:
4154:
4149:
4143:
4141:
4132:
4126:
4125:
4123:
4122:
4117:
4112:
4107:
4102:
4097:
4091:
4089:
4082:
4076:
4075:
4072:
4071:
4069:
4068:
4063:
4058:
4053:
4048:
4043:
4038:
4033:
4028:
4022:
4020:
4016:
4015:
4013:
4012:
4007:
4001:
3999:
3995:
3994:
3992:
3991:
3986:
3981:
3974:
3967:
3960:
3955:
3948:
3941:
3934:
3927:
3925:Harbour Energy
3922:
3917:
3912:
3909:Emerald Energy
3905:
3898:
3896:Dana Petroleum
3893:
3888:
3881:
3876:
3868:
3866:
3865:and production
3860:
3859:
3857:
3856:
3851:
3845:
3843:
3836:
3828:
3827:
3825:
3824:
3819:
3812:
3805:
3798:
3791:
3784:
3781:Anglo American
3776:
3774:
3764:
3763:
3758:
3751:
3750:
3745:
3743:
3742:
3735:
3728:
3720:
3711:
3710:
3708:
3707:
3702:
3697:
3692:
3687:
3682:
3677:
3672:
3667:
3662:
3656:
3654:
3650:
3649:
3647:
3646:
3640:
3638:
3634:
3633:
3631:
3630:
3625:
3619:
3614:
3609:
3604:
3599:
3594:
3589:
3584:
3579:
3573:
3571:
3567:
3566:
3561:
3559:
3558:
3551:
3544:
3536:
3530:
3529:
3523:
3517:
3509:
3501:
3495:
3494:, earth.org.uk
3489:
3481:
3480:External links
3478:
3477:
3476:
3470:
3447:
3444:
3441:
3440:
3425:
3407:
3381:
3374:) – via
3358:
3339:
3317:
3294:
3269:
3245:
3212:
3189:
3178:. 8 March 2022
3163:
3138:
3123:
3105:
3080:
3054:
3041:
3028:
3015:
3006:
2975:
2950:
2925:
2908:
2874:
2848:
2822:
2793:
2764:
2745:
2725:
2687:
2661:
2650:. 15 July 2021
2635:
2609:
2583:
2557:
2531:
2503:
2475:
2464:
2433:
2408:
2389:
2380:
2371:
2352:
2326:
2300:
2272:
2224:
2196:
2170:
2148:
2138:
2115:
2089:
2070:
2052:
2031:
2013:
1985:
1957:
1932:
1914:
1884:
1858:
1845:"Western Link"
1836:
1804:
1753:
1746:
1728:
1688:
1679:
1664:
1647:
1622:
1600:
1574:
1541:
1525:"NIKOLA TESLA"
1515:
1489:
1460:
1459:
1457:
1454:
1452:
1451:
1446:
1441:
1436:
1431:
1426:
1421:
1416:
1411:
1405:
1400:
1395:
1390:
1385:
1380:
1375:
1369:
1364:
1358:
1356:
1353:
1347:
1344:
1342:
1339:
1279:
1276:
1254:
1251:
1242:
1241:September 2003
1239:
1223:Main article:
1220:
1217:
1200:
1197:
1191:
1188:
1173:
1172:
1123:
1121:
1114:
1108:
1107:Demand charges
1105:
1085:
1082:
1072:
1069:
1059:
1058:
1055:
1052:
1049:
1045:
1044:
1042:
1040:
1038:
1034:
1033:
1031:
1029:
1027:
1023:
1022:
1019:
1016:
1013:
1009:
1008:
1005:
1002:
999:
995:
994:
991:
988:
985:
981:
980:
977:
974:
971:
946:
943:
925:
922:
894:
891:
890:
889:
886:
883:
868:
867:
856:
853:
850:
846:
817:Main article:
814:
811:
803:grid batteries
783:
780:
745:North Sea Link
733:Channel Tunnel
685: Proposed
681:
675:
669:
662:
659:
645:
642:
629:
628:
625:
622:
619:
608:
597:
594:
572:carbon capture
563:carbon neutral
559:stretch target
554:
551:
543:power stations
523:
522:
519:
516:
513:
510:power stations
506:
503:
500:
497:
485:
482:
448:
447:
436:
435:
424:
423:
400:
397:
378:East Huntspill
192:
191:
150:
148:
141:
135:
132:
66:power stations
26:
24:
14:
13:
10:
9:
6:
4:
3:
2:
6277:
6266:
6263:
6261:
6258:
6256:
6253:
6251:
6248:
6247:
6245:
6238:
6228:
6220:
6219:
6216:
6210:
6207:
6205:
6202:
6201:
6199:
6191:
6185:
6182:
6180:
6177:
6175:
6172:
6170:
6167:
6165:
6164:Pigouvian tax
6162:
6160:
6157:
6155:
6152:
6150:
6147:
6145:
6142:
6140:
6137:
6135:
6132:
6130:
6127:
6125:
6122:
6120:
6117:
6115:
6112:
6111:
6109:
6101:
6094:
6091:
6089:
6086:
6084:
6081:
6079:
6076:
6074:
6071:
6067:
6064:
6062:
6061:Earth-leakage
6059:
6058:
6057:
6054:
6052:
6049:
6048:
6046:
6038:
6030:
6027:
6026:
6025:
6022:
6020:
6017:
6015:
6012:
6010:
6007:
6006:
6004:
6002:Failure modes
6000:
5994:
5991:
5989:
5986:
5983:
5980:
5978:
5975:
5973:
5970:
5968:
5965:
5963:
5960:
5958:
5955:
5953:
5952:Power station
5950:
5948:
5945:
5943:
5940:
5938:
5935:
5933:
5930:
5928:
5925:
5923:
5920:
5918:
5915:
5913:
5910:
5908:
5905:
5903:
5900:
5898:
5895:
5893:
5890:
5888:
5885:
5883:
5880:
5878:
5875:
5873:
5870:
5869:
5867:
5864:
5859:
5854:
5848:
5845:
5843:
5840:
5838:
5837:Rankine cycle
5835:
5833:
5830:
5828:
5825:
5823:
5820:
5818:
5817:Cooling tower
5815:
5813:
5810:
5808:
5805:
5803:
5800:
5799:
5797:
5795:
5791:
5781:
5778:
5776:
5773:
5771:
5768:
5764:
5761:
5759:
5756:
5754:
5751:
5749:
5746:
5744:
5741:
5740:
5739:
5736:
5734:
5731:
5729:
5726:
5724:
5721:
5719:
5716:
5714:
5711:
5710:
5708:
5706:
5702:
5696:
5693:
5689:
5686:
5684:
5681:
5679:
5676:
5674:
5671:
5670:
5669:
5666:
5665:
5663:
5661:
5660:Non-renewable
5657:
5654:
5650:
5645:
5635:
5632:
5630:
5627:
5625:
5622:
5620:
5617:
5615:
5612:
5610:
5607:
5605:
5602:
5600:
5597:
5595:
5592:
5590:
5587:
5585:
5582:
5580:
5579:Grid strength
5577:
5575:
5572:
5570:
5567:
5565:
5562:
5560:
5557:
5555:
5552:
5550:
5547:
5545:
5542:
5540:
5537:
5535:
5534:Demand factor
5532:
5530:
5527:
5525:
5522:
5520:
5517:
5516:
5514:
5510:
5506:
5499:
5494:
5492:
5487:
5485:
5480:
5479:
5476:
5464:
5463:
5454:
5453:
5450:
5440:
5437:
5435:
5432:
5430:
5427:
5423:
5420:
5419:
5418:
5415:
5413:
5410:
5408:
5405:
5403:
5400:
5398:
5395:
5393:
5390:
5388:
5385:
5383:
5380:
5379:
5376:
5372:
5367:
5363:
5349:
5346:
5344:
5341:
5339:
5336:
5334:
5331:
5329:
5326:
5324:
5321:
5319:
5316:
5315:
5313:
5309:
5303:
5300:
5298:
5295:
5293:
5290:
5288:
5285:
5283:
5280:
5278:
5275:
5273:
5270:
5269:
5267:
5263:
5257:
5254:
5252:
5249:
5247:
5244:
5242:
5239:
5237:
5234:
5232:
5229:
5227:
5224:
5223:
5221:
5217:Charities and
5215:
5211:
5204:
5200:
5186:
5183:
5181:
5178:
5176:
5173:
5171:
5168:
5166:
5163:
5161:
5158:
5156:
5153:
5151:
5148:
5146:
5143:
5141:
5138:
5136:
5133:
5131:
5128:
5126:
5123:
5121:
5118:
5116:
5113:
5111:
5108:
5106:
5103:
5102:
5100:
5098:
5092:
5086:
5083:
5081:
5078:
5076:
5073:
5071:
5068:
5066:
5063:
5061:
5058:
5056:
5053:
5051:
5048:
5047:
5045:
5043:Organisations
5041:
5037:
5030:
5026:
5008:
5005:
5003:
5000:
4998:
4995:
4993:
4990:
4988:
4985:
4984:
4982:
4980:
4976:
4970:
4968:
4964:
4958:
4955:
4953:
4950:
4948:
4945:
4943:
4940:
4939:
4937:
4935:
4931:
4925:
4922:
4921:
4919:
4917:
4913:
4907:
4904:
4902:
4899:
4897:
4894:
4892:
4889:
4888:
4886:
4884:
4880:
4877:
4875:
4871:
4865:
4862:
4860:
4857:
4855:
4852:
4850:
4847:
4845:
4842:
4840:
4837:
4835:
4832:
4830:
4829:North Sea oil
4827:
4825:
4822:
4820:
4817:
4815:
4812:
4810:
4807:
4805:
4802:
4800:
4797:
4795:
4794:Fuel protests
4792:
4790:
4787:
4785:
4782:
4780:
4777:
4776:
4774:
4772:
4768:
4762:
4759:
4757:
4754:
4752:
4749:
4747:
4744:
4742:
4739:
4737:
4734:
4732:
4729:
4727:
4724:
4722:
4719:
4717:
4714:
4713:
4711:
4709:
4705:
4699:
4696:
4694:
4691:
4689:
4686:
4684:
4681:
4677:
4674:
4672:
4669:
4668:
4667:
4666:National Grid
4664:
4662:
4659:
4657:
4654:
4652:
4649:
4647:
4644:
4642:
4639:
4637:
4634:
4632:
4629:
4627:
4624:
4622:
4619:
4617:
4614:
4612:
4609:
4607:
4604:
4602:
4599:
4598:
4596:
4594:
4590:
4584:
4581:
4577:
4574:
4572:
4569:
4568:
4567:
4564:
4562:
4559:
4557:
4554:
4552:
4549:
4547:
4544:
4542:
4539:
4537:
4534:
4533:
4531:
4529:
4525:
4521:
4514:
4510:
4496:
4489:
4483:
4480:
4478:
4475:
4473:
4470:
4468:
4465:
4463:
4460:
4458:
4455:
4453:
4450:
4448:
4445:
4444:
4442:
4438:
4424:
4423:National Grid
4421:
4420:
4418:
4416:
4412:
4406:
4403:
4401:
4398:
4396:
4395:National Grid
4393:
4392:
4390:
4388:
4384:
4381:
4379:
4375:
4365:
4362:
4360:
4357:
4355:
4352:
4350:
4347:
4345:
4344:Firmus Energy
4342:
4340:
4337:
4336:
4334:
4330:
4324:
4321:
4319:
4316:
4314:
4311:
4309:
4306:
4304:
4301:
4299:
4296:
4295:
4293:
4291:
4287:
4284:
4282:
4278:
4268:
4265:
4263:
4260:
4258:
4255:
4253:
4250:
4248:
4245:
4243:
4240:
4238:
4235:
4233:
4230:
4228:
4225:
4223:
4220:
4218:
4217:Firmus Energy
4215:
4213:
4210:
4208:
4205:
4203:
4200:
4198:
4195:
4193:
4190:
4189:
4187:
4185:
4181:
4175:
4174:
4170:
4168:
4167:Vattenfall UK
4165:
4163:
4160:
4158:
4155:
4153:
4150:
4148:
4145:
4144:
4142:
4140:
4136:
4133:
4127:
4121:
4118:
4116:
4115:ScottishPower
4113:
4111:
4108:
4106:
4103:
4101:
4098:
4096:
4093:
4092:
4090:
4086:
4083:
4081:
4077:
4067:
4064:
4062:
4059:
4057:
4054:
4052:
4049:
4047:
4044:
4042:
4039:
4037:
4034:
4032:
4029:
4027:
4024:
4023:
4021:
4017:
4011:
4008:
4006:
4003:
4002:
4000:
3996:
3990:
3987:
3985:
3982:
3980:
3979:
3975:
3973:
3972:
3968:
3966:
3965:
3964:Pharos Energy
3961:
3959:
3956:
3954:
3953:
3949:
3947:
3946:
3942:
3940:
3939:
3935:
3933:
3932:
3928:
3926:
3923:
3921:
3918:
3916:
3913:
3911:
3910:
3906:
3904:
3903:
3899:
3897:
3894:
3892:
3889:
3887:
3886:
3882:
3880:
3877:
3875:
3874:
3870:
3869:
3867:
3861:
3855:
3852:
3850:
3847:
3846:
3844:
3840:
3837:
3835:
3829:
3823:
3820:
3818:
3817:
3813:
3811:
3810:
3806:
3804:
3803:
3802:GCM Resources
3799:
3797:
3796:
3792:
3790:
3789:
3785:
3783:
3782:
3778:
3777:
3775:
3773:
3769:
3765:
3761:
3756:
3752:
3748:
3741:
3736:
3734:
3729:
3727:
3722:
3721:
3718:
3706:
3703:
3701:
3698:
3696:
3693:
3691:
3688:
3686:
3683:
3681:
3678:
3676:
3675:Lattice Group
3673:
3671:
3668:
3666:
3663:
3661:
3658:
3657:
3655:
3651:
3645:
3642:
3641:
3639:
3635:
3629:
3626:
3623:
3620:
3618:
3615:
3613:
3610:
3608:
3605:
3603:
3602:Fawley Tunnel
3600:
3598:
3595:
3593:
3590:
3588:
3585:
3583:
3580:
3578:
3575:
3574:
3572:
3568:
3564:
3563:National Grid
3557:
3552:
3550:
3545:
3543:
3538:
3537:
3534:
3527:
3524:
3521:
3518:
3515:
3514:
3510:
3507:
3506:
3502:
3499:
3496:
3493:
3490:
3488:, iamkate.com
3487:
3484:
3483:
3479:
3473:
3471:0-8018-2145-2
3467:
3463:
3459:
3455:
3450:
3449:
3445:
3436:
3429:
3426:
3421:
3417:
3411:
3408:
3396:
3392:
3385:
3382:
3377:
3373:
3369:
3362:
3359:
3355:
3350:
3348:
3346:
3344:
3340:
3327:
3321:
3318:
3305:
3298:
3295:
3290:
3286:
3285:
3280:
3273:
3270:
3265:
3264:
3259:
3252:
3250:
3246:
3238:
3234:
3233:National Grid
3227:
3221:
3219:
3217:
3213:
3208:
3207:
3199:
3193:
3190:
3177:
3173:
3167:
3164:
3152:
3148:
3142:
3139:
3136:
3132:
3127:
3124:
3119:
3115:
3109:
3106:
3094:
3090:
3084:
3081:
3069:
3065:
3058:
3055:
3051:
3045:
3042:
3038:
3032:
3029:
3025:
3019:
3016:
3010:
3007:
2995:
2991:
2984:
2982:
2980:
2976:
2964:
2960:
2954:
2951:
2939:
2935:
2929:
2926:
2922:
2918:
2912:
2909:
2896:
2892:
2891:
2885:
2878:
2875:
2862:
2858:
2852:
2849:
2836:
2832:
2826:
2823:
2807:
2803:
2797:
2794:
2778:
2774:
2768:
2765:
2752:
2748:
2746:1-903144-04-3
2742:
2738:
2737:
2729:
2726:
2711:
2707:
2700:
2694:
2692:
2688:
2675:
2671:
2665:
2662:
2649:
2645:
2639:
2636:
2624:
2620:
2613:
2610:
2598:
2594:
2587:
2584:
2571:
2567:
2561:
2558:
2546:
2542:
2535:
2532:
2519:
2518:
2513:
2507:
2504:
2501:
2498:
2494:
2493:
2488:
2485:
2479:
2476:
2473:
2468:
2465:
2452:
2448:
2444:
2437:
2434:
2422:
2418:
2412:
2409:
2405:
2401:
2398:
2393:
2390:
2384:
2381:
2375:
2372:
2368:
2364:
2361:
2356:
2353:
2341:
2337:
2330:
2327:
2315:
2311:
2304:
2301:
2289:
2288:
2283:
2276:
2273:
2268:
2263:|author=
2256:
2241:
2240:
2235:
2228:
2225:
2213:
2212:
2207:
2200:
2197:
2185:
2181:
2174:
2171:
2158:
2152:
2149:
2146:
2142:
2139:
2134:
2130:
2126:
2119:
2116:
2103:
2099:
2093:
2090:
2085:
2081:
2074:
2071:
2066:
2062:
2056:
2053:
2041:
2035:
2032:
2027:
2023:
2017:
2014:
2006:
2002:
1995:
1989:
1986:
1978:
1974:
1967:
1961:
1958:
1946:
1942:
1936:
1933:
1928:
1924:
1918:
1915:
1902:
1901:
1895:
1888:
1885:
1872:
1868:
1862:
1859:
1846:
1840:
1837:
1821:
1814:
1808:
1805:
1793:
1789:
1785:
1781:
1777:
1773:
1769:
1762:
1760:
1758:
1754:
1749:
1743:
1739:
1732:
1729:
1716:
1712:
1711:
1705:
1697:
1695:
1693:
1689:
1683:
1680:
1675:
1671:
1667:
1661:
1657:
1651:
1648:
1636:
1632:
1626:
1623:
1618:
1614:
1610:
1604:
1601:
1588:
1584:
1578:
1575:
1559:
1552:
1545:
1542:
1530:
1526:
1519:
1516:
1503:
1499:
1493:
1490:
1478:
1474:
1468:
1466:
1462:
1455:
1450:
1447:
1445:
1442:
1440:
1437:
1435:
1432:
1430:
1427:
1425:
1422:
1420:
1417:
1415:
1412:
1409:
1406:
1404:
1401:
1399:
1396:
1394:
1391:
1389:
1386:
1384:
1381:
1379:
1376:
1373:
1370:
1368:
1365:
1363:
1360:
1359:
1354:
1352:
1346:November 2015
1345:
1340:
1338:
1336:
1332:
1328:
1324:
1319:
1317:
1313:
1309:
1305:
1301:
1298:
1293:
1290:
1286:
1277:
1275:
1271:
1267:
1264:
1260:
1252:
1250:
1247:
1240:
1238:
1234:
1232:
1226:
1218:
1216:
1213:
1209:
1207:
1198:
1196:
1189:
1187:
1183:
1179:
1169:
1166:
1158:
1155:November 2014
1148:
1144:
1140:
1134:
1133:
1129:
1124:This section
1122:
1118:
1113:
1112:
1106:
1104:
1102:
1101:grid services
1097:
1095:
1090:
1083:
1081:
1077:
1070:
1068:
1065:
1056:
1053:
1050:
1047:
1046:
1043:
1041:
1039:
1036:
1035:
1032:
1030:
1028:
1025:
1024:
1020:
1017:
1014:
1011:
1010:
1006:
1003:
1000:
997:
996:
992:
989:
986:
983:
982:
978:
975:
972:
969:
968:
965:
962:
958:
954:
952:
944:
942:
938:
930:
923:
921:
919:
915:
914:ScottishPower
910:
908:
904:
900:
892:
887:
884:
881:
877:
873:
872:
871:
865:
861:
857:
854:
851:
847:
844:
843:
842:
839:
837:
833:
829:
825:
820:
812:
810:
808:
804:
799:
797:
793:
789:
781:
779:
777:
773:
769:
765:
760:
758:
754:
750:
746:
742:
738:
734:
730:
726:
722:
717:
715:
710:
708:
703:
701:
697:
690:
667:
660:
658:
654:
652:
643:
641:
637:
634:
626:
623:
620:
617:
613:
609:
606:
605:Joule heating
603:
602:
601:
595:
593:
591:
586:
582:
578:
573:
569:
564:
560:
552:
550:
548:
544:
540:
536:
532:
528:
520:
517:
514:
511:
507:
504:
501:
498:
495:
491:
490:
489:
483:
481:
479:
475:
471:
470:Western Isles
467:
463:
459:
455:
454:Isle of Wight
446:
437:
434:
425:
420:
413:
405:
398:
396:
394:
389:
387:
383:
379:
374:
372:
368:
364:
359:
357:
356:
350:
348:
344:
340:
334:
332:
331:home counties
328:
324:
320:
316:
310:
308:
302:
300:
296:
292:
288:
284:
280:
273:
268:
264:
262:
258:
254:
250:
246:
241:
239:
235:
231:
227:
223:
219:
216:high-voltage
215:
211:
203:
198:
188:
185:
177:
174:February 2019
167:
163:
157:
156:
151:This section
149:
145:
140:
139:
133:
131:
129:
125:
121:
117:
113:
109:
104:
102:
98:
94:
90:
86:
81:
79:
75:
71:
67:
64:, connecting
63:
62:Great Britain
59:
56:
52:
51:National Grid
43:
37:
33:
19:
6237:
6159:Net metering
6106:and policies
6024:Power outage
5993:Utility pole
5957:Pumped hydro
5863:distribution
5858:Transmission
5807:Cogeneration
5609:Power factor
5461:
5226:Ashden Award
5050:Carbon Trust
4784:Dash for Gas
4779:BBL Pipeline
4665:
4494:
4467:Hi-Gen Power
4386:
4378:Transmission
4281:Distribution
4252:Shell Energy
4202:Co-op Energy
4171:
3976:
3969:
3962:
3952:Ophir Energy
3950:
3943:
3936:
3929:
3920:Essar Energy
3907:
3900:
3883:
3871:
3814:
3807:
3800:
3793:
3786:
3779:
3624:(dismantled)
3562:
3512:
3504:
3453:
3434:
3428:
3419:
3410:
3398:. Retrieved
3395:Current News
3394:
3384:
3361:
3330:. Retrieved
3320:
3308:. Retrieved
3297:
3289:the original
3282:
3272:
3263:The Guardian
3261:
3237:the original
3232:
3204:
3192:
3180:. Retrieved
3175:
3166:
3154:. Retrieved
3150:
3141:
3126:
3117:
3108:
3096:. Retrieved
3092:
3083:
3071:. Retrieved
3067:
3057:
3044:
3031:
3018:
3009:
2997:. Retrieved
2993:
2966:. Retrieved
2962:
2953:
2941:. Retrieved
2937:
2928:
2920:
2911:
2899:. Retrieved
2888:
2877:
2865:. Retrieved
2860:
2851:
2839:. Retrieved
2835:the original
2825:
2813:. Retrieved
2806:the original
2796:
2784:. Retrieved
2777:the original
2767:
2755:. Retrieved
2751:the original
2735:
2728:
2717:, retrieved
2710:the original
2705:
2680:27 September
2678:. Retrieved
2673:
2664:
2654:29 September
2652:. Retrieved
2647:
2638:
2628:27 September
2626:. Retrieved
2622:
2612:
2602:29 September
2600:. Retrieved
2596:
2586:
2574:. Retrieved
2570:the original
2560:
2550:23 September
2548:. Retrieved
2544:
2534:
2522:. Retrieved
2515:
2506:
2490:
2478:
2467:
2455:. Retrieved
2451:the original
2446:
2436:
2424:. Retrieved
2420:
2411:
2392:
2383:
2374:
2355:
2343:. Retrieved
2339:
2329:
2317:. Retrieved
2313:
2303:
2291:. Retrieved
2285:
2275:
2243:. Retrieved
2237:
2227:
2215:. Retrieved
2209:
2199:
2187:. Retrieved
2183:
2173:
2161:. Retrieved
2159:. April 2020
2151:
2141:
2128:
2118:
2106:. Retrieved
2102:the original
2092:
2083:
2073:
2064:
2055:
2043:. Retrieved
2034:
2025:
2016:
2005:the original
2000:
1988:
1977:the original
1972:
1960:
1948:. Retrieved
1944:
1935:
1926:
1917:
1905:. Retrieved
1898:
1887:
1877:16 September
1875:. Retrieved
1870:
1861:
1849:. Retrieved
1839:
1827:. Retrieved
1820:the original
1807:
1795:. Retrieved
1775:
1771:
1737:
1731:
1719:. Retrieved
1708:
1682:
1655:
1650:
1638:. Retrieved
1634:
1625:
1617:the original
1603:
1591:. Retrieved
1587:the original
1577:
1565:. Retrieved
1558:the original
1544:
1532:. Retrieved
1528:
1518:
1506:. Retrieved
1501:
1492:
1480:. Retrieved
1476:
1408:Spark spread
1349:
1320:
1294:
1281:
1272:
1268:
1261:in Fife and
1256:
1248:
1244:
1235:
1228:
1214:
1210:
1202:
1193:
1184:
1180:
1176:
1161:
1152:
1137:Please help
1125:
1098:
1094:proving runs
1093:
1091:
1087:
1078:
1074:
1066:
1064:connecting.
1062:
963:
959:
955:
948:
945:Triad demand
939:
935:
911:
907:cyber attack
896:
869:
863:
859:
840:
826:
822:
800:
785:
782:Grid storage
761:
723:, 1 GW HVDC
718:
711:
704:
693:
655:
647:
638:
630:
599:
556:
524:
487:
484:Network size
451:
390:
388:connection.
375:
360:
353:
351:
335:
311:
303:
276:
242:
226:Charles Merz
222:Westinghouse
210:Nikola Tesla
207:
180:
171:
160:Please help
155:verification
152:
105:
82:
50:
48:
6154:Load factor
6009:Black start
5977:Transformer
5678:Natural gas
5629:Variability
5604:Peak demand
5594:Merit order
5524:Backfeeding
5297:RenewableUK
5231:Bioregional
5097:initiatives
4967:Solar power
4771:Oil and gas
4593:Electricity
4387:Electricity
4290:Electricity
4232:Opus Energy
4222:Good Energy
4066:WesternGeco
4026:Abbot Group
3984:Star Energy
3863:Exploration
2674:Penso Power
2524:9 September
2426:10 February
2345:17 February
2319:17 February
2293:11 February
2245:11 February
2217:11 February
2189:11 February
2163:11 February
1907:17 December
1778:(48): 493.
1567:12 November
1529:web.mit.edu
1502:Just Energy
1278:August 2019
1219:August 2003
864:hot standby
757:Viking Link
478:Isle of Man
343:West Burton
323:River Trent
315:West Burton
214:three-phase
97:Isle of Man
70:substations
6244:Categories
6196:production
6041:Protective
5972:Super grid
5967:Smart grid
5794:Generation
5728:Geothermal
5619:Repowering
4979:Wind power
4957:Wave farms
4916:Geothermal
4874:Renewables
4844:Oil fields
4756:Sellafield
4621:Economy 10
4546:Coal mines
4472:Mark Group
4339:Cadent Gas
4242:OVO Energy
4207:Ecotricity
4147:Drax Group
4139:Generation
4131:and supply
4129:Generation
4105:EDF Energy
4088:Integrated
4061:Weir Group
3989:Tullow Oil
3842:Integrated
3570:Facilities
3182:4 February
3156:4 February
2968:8 December
2943:24 January
2841:3 November
2815:3 November
2786:3 November
2489:page 2-5.
2457:8 November
1829:3 February
1797:4 February
1747:0600358755
1740:. Newnes.
1665:085188105X
1593:6 February
1534:29 January
1508:29 January
1456:References
1297:Thameslink
1263:Sizewell B
899:Sindlesham
796:Ffestiniog
768:NeuConnect
644:Power flow
476:, and the
249:Glaswegian
68:and major
6104:Economics
5827:Micro CHP
5705:Renewable
5688:Petroleum
5683:Oil shale
5569:Grid code
5529:Base load
4616:Economy 7
4452:APX Group
4212:ESB Group
4080:Utilities
4005:Greenergy
3816:Rio Tinto
3760:Companies
3705:TV pickup
3400:8 January
3310:21 August
3284:The Times
3098:21 August
3073:21 August
2999:21 August
2921:Bloomberg
2901:21 August
2867:21 August
2861:Rmets.org
2719:8 January
2576:21 August
2545:Greenlink
2211:bloomberg
2108:9 January
1950:21 August
1792:0369-8882
1721:21 August
1388:TV pickup
1300:Class 700
1259:Longannet
1126:does not
903:Wokingham
764:Greenlink
737:Nemo Link
616:iron loss
545:. Annual
527:renewable
386:Avonmouth
355:Grid Code
347:Supergrid
287:Battersea
245:Lord Weir
228:, of the
89:supergrid
6227:Category
6014:Brownout
5802:AC power
5512:Concepts
5462:Category
5407:EcoHomes
5311:Research
4883:Biofuels
4192:100Green
4162:Renantis
4095:Centrica
4051:Petrofac
3891:Centrica
3832:Oil and
3809:Glencore
3500:, Elexon
3460:for the
3332:9 August
2895:Archived
2648:BBC News
2400:Archived
2363:Archived
2255:cite web
2184:edie.net
2133:Archived
1715:Archived
1674:17343802
1355:See also
1253:May 2008
1048:2020/21
1012:2017/18
998:2016/17
984:2015/16
979:Triad 3
792:Cruachan
731:via the
729:ElecLink
640:losses.
468:and the
458:Scotland
327:Midlands
279:overhead
257:gridiron
60:serving
6043:devices
5753:Thermal
5748:Osmotic
5743:Current
5723:Biomass
5713:Biofuel
5695:Nuclear
5652:Sources
4708:Nuclear
4671:Control
4606:BritNed
4566:History
4495:italics
4482:Wavegen
4462:EnServe
4447:Aggreko
4100:E.ON UK
4041:Hunting
4019:Support
3958:Perenco
3915:EnQuest
3822:UK Coal
3653:Related
3597:BritNed
3376:Twitter
3118:Current
3035:Stark,
2757:15 July
2670:"About"
2597:Current
2517:Getlink
2497:Archive
2239:reuters
1945:Eia.gov
1851:18 June
1640:31 July
1482:25 June
1147:removed
1132:sources
1037:2019/20
1026:2018/19
976:Triad 2
973:Triad 1
776:Morocco
772:Icelink
741:BritNed
727:, 1 GW
579:, with
535:nuclear
533:fired,
329:to the
134:History
58:network
5738:Marine
5718:Biogas
4972:
4726:Magnox
4184:Supply
4110:Npower
3998:Supply
3637:Events
3468:
2743:
2676:. 2021
2500:Mirror
2045:14 May
2026:GOV.UK
2001:GOV.UK
1973:GOV.UK
1790:
1744:
1672:
1662:
1331:Ørsted
866:state.
849:hours.
807:Minety
683:
677:
671:
612:corona
596:Losses
561:to be
541:fired
462:Orkney
339:Sundon
291:Fulham
202:Pudsey
6095:(GFI)
5984:(TSO)
5770:Solar
5758:Tidal
5733:Hydro
5333:Narec
5055:Cenex
4896:NNFCC
4440:Other
4056:Qserv
4036:Expro
3873:Afren
3854:Shell
3420:Ofgem
3372:Tweet
3306:. BBC
3240:(PDF)
3229:(PDF)
3206:Ofgem
3201:(PDF)
3176:Ofgem
2809:(PDF)
2780:(PDF)
2713:(PDF)
2702:(PDF)
2008:(PDF)
1997:(PDF)
1980:(PDF)
1969:(PDF)
1823:(PDF)
1816:(PDF)
1561:(PDF)
1554:(PDF)
1477:Ofgem
1323:Ofgem
725:IFA-2
474:Wales
283:Blitz
236:near
5861:and
5780:Wind
5763:Wave
5673:Coal
4528:Coal
3795:ENRC
3772:Coal
3466:ISBN
3402:2020
3334:2019
3312:2016
3184:2023
3158:2023
3100:2016
3075:2016
3001:2016
2970:2021
2945:2020
2903:2016
2869:2016
2843:2010
2817:2010
2788:2010
2759:2008
2741:ISBN
2721:2011
2682:2021
2656:2021
2630:2021
2604:2021
2578:2016
2552:2021
2526:2021
2484:Text
2459:2013
2428:2019
2347:2021
2321:2021
2295:2021
2267:help
2247:2021
2219:2021
2191:2021
2165:2021
2110:2006
2047:2016
1952:2016
1909:2023
1879:2021
1853:2019
1831:2011
1799:2023
1788:ISSN
1742:ISBN
1723:2016
1670:OCLC
1660:ISBN
1642:2024
1595:2007
1569:2006
1536:2023
1510:2023
1484:2018
1329:and
1302:and
1287:and
1130:any
1128:cite
970:Year
794:and
759:).
614:and
539:coal
466:Skye
371:HVDC
289:and
247:, a
49:The
5434:HTB
4415:Gas
4359:SGN
4332:Gas
4120:SSE
3879:BHP
3834:gas
3788:BHP
2487:PDF
1780:doi
1776:109
1327:RWE
1304:717
1141:by
862:or
531:gas
456:),
384:to
341:to
164:by
120:SSE
6246::
3849:BP
3464:.
3418:.
3393:.
3342:^
3281:.
3260:.
3248:^
3231:.
3215:^
3203:.
3174:.
3149:.
3116:.
3091:.
3066:.
2992:.
2978:^
2961:.
2936:.
2919:"
2893:.
2887:.
2859:.
2704:,
2690:^
2672:.
2646:.
2621:.
2595:.
2543:.
2514:.
2445:.
2419:.
2338:.
2312:.
2284:.
2259::
2257:}}
2253:{{
2236:.
2208:.
2182:.
2131:.
2127:.
2082:.
2063:.
2024:.
1999:.
1971:.
1943:.
1925:.
1897:.
1869:.
1786:.
1774:.
1770:.
1756:^
1713:.
1707:.
1691:^
1668:.
1633:.
1611:.
1527:.
1500:.
1475:.
1464:^
1318:.
909:.
901:,
836:Hz
832:AC
798:.
709:.
702:.
592:.
537:,
529:,
494:GW
480:.
464:,
373:.
349:.
333:.
80:.
5497:e
5490:t
5483:v
3739:e
3732:t
3725:v
3555:e
3548:t
3541:v
3474:.
3404:.
3378:.
3370:(
3336:.
3314:.
3266:.
3186:.
3160:.
3102:.
3077:.
3003:.
2972:.
2947:.
2905:.
2871:.
2845:.
2819:.
2790:.
2761:.
2684:.
2658:.
2632:.
2606:.
2580:.
2554:.
2528:.
2461:.
2430:.
2349:.
2323:.
2297:.
2269:)
2249:.
2221:.
2193:.
2167:.
2112:.
2086:.
2067:.
2049:.
1954:.
1929:.
1911:.
1881:.
1855:.
1833:.
1801:.
1782::
1750:.
1725:.
1676:.
1644:.
1597:.
1571:.
1538:.
1512:.
1486:.
1168:)
1162:(
1157:)
1153:(
1149:.
1135:.
187:)
181:(
176:)
172:(
158:.
38:.
20:)
Text is available under the Creative Commons Attribution-ShareAlike License. Additional terms may apply.